Project system: Purchase requisition coming from Networks

Dear Experts,
I have a tricky problem. I want to exclude a specific number range for purchase requisition coming from the Project system.
The current number range I have for the purchase requisition is let say: 10000000 - 19999999.
I want to use another number range (50000000-59999999) for the purchase requisitions as an impact of material components of an network activity.
What I've tried but it is not working properly:
1. TC: OMH7 - I created a new number range as I mentioned above
2. TC: OMEB - I've copied the document type NB to a new document type ZNB (NB = ZNB)
3. TC: OPTT - as last step I've assigned the document type ZNB to the order category 20 (network)
Please advice ASAP
Thanks a lot in advance

It should work as it works fine for me.
1. You create the Internal number range (50000000-59999999) first and number it with an ID.
2. Create the ZNB document type and assign the number range number (i.e., two-character ID)
3. Assign this ZNB in OPTT
If I've repeated what ever you've done/said, check the settings once again. It should work.
Regards
Sreenivas

Similar Messages

  • Project system: Purchase requisition coming from PS

    Dear Experts,
    I have a tricky problem. I want to exclude a specific number range for purchase requisition coming from the Project system.
    The current number range I have for the purchase requisition is let say: 10000000 - 19999999.
    I want to use another number range (50000000-59999999) for the purchase requisitions as an impact of material components of an network activity.
    What I've tried but it is not working properly:
    1. TC: OMH7 - I created a new number range as I mentioned above
    2. TC: OMEB - I've copied the document type NB to a new document type ZNB (NB = ZNB)
    3. TC: OPTT - as last step I've assigned the document type ZNB to the order category 20 (network)
    Please advice ASAP
    Thanks a lot in advance

    It should work as it works fine for me.
    1. You create the Internal number range (50000000-59999999) first and number it with an ID.
    2. Create the ZNB document type and assign the number range number (i.e., two-character ID)
    3. Assign this ZNB in OPTT
    If I've repeated what ever you've done/said, check the settings once again. It should work.
    Regards
    Sreenivas

  • Purchase Requisition Creation From Release

    Dear PM Gurus,
    For Manual material availability Check to work before release, the Purchase Requisition check is to be set to Immediately in SPRO-> Define Change Docs and Collective PR or Activating Pr from Now On from Maintenance Order. The issue is that I want to restrict the creation of Purchase Requisition to Release of Maintenance Order but what is happening is upon saving the Maintenance Order, the PRs for all non stock materials are created and I also want the manual availability check to work before release.
    Simplifying above details:
    I want Manual material availability check to work and PR generation from release both in my Maintenance Order to work..
    Regards..

    Hi DP Singh,
    I had seen the configuration settings that you are telling me but you see the Problem is:
    If in Define Change Docs, Collective Purc. Req. Indicator, Operation No. Interval, you define the Res/PReq Indicator as Immediately, then the Manual Material Availability Check would work accurately but upon saving the Order, System would generate the Purchase Requisition.
    and If in Define Change Docs, Collective Purc. Req. Indicator, Operation No. Interval, you define the Res/Preq Indicator as From Release, then the Manual Material Availability Check would not work as no material is as such MRP relevant till the time of releasing the Order but the Purchase Requisition would be created only when the Order is released.
    Now What I want is both the Manual Availability Check to work and Purchase Requisition Creation From Release, but this is not possible according to the Standard SAP System. A workaround could be that I configure the automatic material availability upon release and configure the Res/Preq indicator as From Release, that way the material availability would be checked when the order is released and Purchase Requisitions would also be created from Release but still the Manual Availability Check would not work.
    The Ideal Solution should have been configuring the Res/Purchase Requisition Indicator for all Non Stock Materials to be From Release and the Res/ Purchase Requisition Indicator for all Stock Materials to be Immediately. This way your manual availability Check would work for all Stock Materials and Purchase Requisition for all Non Stock materials would only be created upon Release. But this  But still this is an ideal solution not the actual solution for standard SAP does not give you the flexibility to do such a setting in customizing or using Enhancement.
    The Work Around Solution given by SAP is as follows: The system provides the following workaround:
    After you change the indicator for materials planning-relevance to
    "immediately" you can execute the availability check as required. You must
    not save the order or network.
    Regards,
    Muhammad  Usman Kahoot
    Edited by: Usman Kahoot on May 27, 2010 1:32 PM

  • Send a purchase requisition data From APO to SNC

    Hi ,
    Is it possible to send requisition data from APO  to SNC and any  internal integration is there.
    Any Standard way or method or FM  to send the Purchase requisition details from APO to SNC.
    Thanks.

    Hi ,
    Is it possible to send requisition data from APO  to SNC and any  internal integration is there.
    Any Standard way or method or FM  to send the Purchase requisition details from APO to SNC.
    Thanks.

  • Purchase Requisition Transfers from SCM 5.0 APO to R/3

    I am working on SCM 5.0 -- transferring Purchase Requisitions from APO to R/3 from SNP heurristic run. I am wondering if there is any documented procedure of available options and the steps involved in setting up.
    Can you transfer only certain Purchase Requisitions instead of ALL?
    Can you setup approval workflow to allow the transfer of only approved PRs ?
    What steps involved to get PRs from the SNP Heuristic?
    I found the IMG Activity (SAP SCM – Implementation Guide  Advanced Planning and Optimization  Supply Chain Planning  Supply Network Planning (SNP)  Basic Settings  Configure Transfer to OLTP system).
    I shall greatly apprecaite if some one answers the questions and points me to some 'How to Guide or the steps involved in setting up'.
    Thanks

    Devendra,
    You actually need the SCM-APO-CIF  (Core Interface) Training for this. A Pre-requisite to that is the APO Overview.  Have you undergone it ?
    In Short i will tell you the answers you want ...  I hope you will reward me with Points if you feel it was helpful.
    To Transfer PRs from APO to R3 following setup is needed ..
    - Do Configuration of  STO (Stock Transfer) in R3.  Ensure Stock Transfer PRs and STOs between the 2 Plants can be created Manually in R3.  This will require you to do a Lot of MM & SD Configuration on IntraCompany STOs.
    A Key Part for APO is to set the STO Order Types for the
    Source and Destination Plant,  Assign Vendor to the Shipping Plant,  Customer to the Destination Plant .. etc. A Test of correct setup is your ability to create a PR and STO manually in R3 first before you do APO.
    - Setup of all APO Locations (Plants in SAP-R3), Products (Materials in SAP-R3).  These are done via the Location and Product Integration Models.  Make sure you have defined the Timezone in the Plant and set the Plant in SAP as DC or Production Plant (Refer CIF Training).
    -  Setup of  Transport Lanes in APO (done manually in APO).
    You define Transport Durations here.
    -  You have to have the Purchase Requisition Integration Model Active for those Product Locations.  To do the Integration Model all CIF Configuration including the one IMG you have described in your Question is to be done. Assuming that the Products are set to 'X0' MRP Type in R3 ... so they are set to Planning in APO.
    -  For Setup in "Configure Transfer to OLTP" it is best to select 'Periodic Transfer' so you can actually control the Product-Locations and Date Range of PRs APO has created.  The Planning Runs create 'Change Pointers' to send the PRs to R3.
    - Define in APO that you will be sending Purchase Requisitions at your Destination Location to R3.  You use 'Publish Change Pointers' - /sapapo/cp1 to do this.
    - The Change Pointers are created after APO Planning run which can be sent to R3 using /sapapo/c5.  You should send them periodically after you're satisfied with the planning results or in Night Batch runs after your Planning run.
    -  To Control some type of PRs you will have to use User Exits in APO for CIF that send External Procurement / PRs from APO to R3.  This is not Standard.  But I am not sure why you will  have different types of PRs for Stock Transfer between 2 Plants.  There is no need.  You can control PRs between 2 Locations to not go to R3, via the selection of locations in /sapapo/c5.
    Hope you find this usefull.
    Regards,
    Ambrish Mathur

  • Item category determination during Purchase Requisition creation from APO

    I’m creating a  SNP Purchase Requisition in APO and when it is  published to R/3, a Purchase Requisition document is created in R/3.
    When this PR is created in R/3, I want the Item Category to be determined based on the Material master Special Procurement Type. ( eg: I’d like the Item category to be ‘L’ if the Material master Special Procurement Type = 30 (Subcontracting) ). But by standard, this field is coming as ‘Blank’ and this field could only be populated during the creation from APO.
    I found a user exit ( CIFPUR02 :  Enhancement of Purchase Order Interface (Inbound) ) on R/3 where I tried to populate the Item Category, but  when I do this, all the purchase order related data is getting deleted and hence no PR’s are getting created in R/3.
    Could anyone please tell me if this could be resolved using configuration and if not any  tips to do this technically would be very helpful.
    Thanks,
    Harsha

    Hi Karun,
    This is the code i'm using...
    select single * from marc into lit_marc
    where  matnr = c_eban-matnr
    and    werks = c_eban-werks.
    append lit_marc.
    read table lit_marc with key matnr = c_eban-matnr
                                 werks = c_eban-werks
                                 sobsl = 30.
      if sy-subrc = 0.
      c_eban-pstyp = '3'.
      endif.
    Here sobsl = 30 is the Special procurement type
    But when i try to populate c_eban-pstyp = '3', during the creation of Purchase Requisitions in R/3, in the program SAPLEMPI -> LMEPIF01
    this condition is encountered which deletes all the data in the tables that is used to create Purchase requisitions.
    <i>* get rsnum in the case of subcontracting
          IF XEBAN-PSTYP EQ PSTYP-LOHN AND                      "RB240999
             EXITFLAG_ORDID IS INITIAL.                         "RB240999
    refresh all component tables
            CALL FUNCTION 'ME_COMPONENTS_REFRESH'
                 EXCEPTIONS
                      OTHERS = 1.</i>
    Could you please suggest me anything to get around this.
    Thanks,
    Harsha

  • IW31-Create Purchase Requisition automatically from PM order - Release 5.0

    Dear Experts,
    Currently we are working in the 4.6C Release but we are doing the migration for 5.0. In PM, in the 4.6C release when we
    create a PM Order in tcode IW31 we select a component and the system shows us the screen to inform the quantity and
    automatically the system shows us a  screen to Create Purchase Requisition where we can fill or select some fields.
    However, when we create a PM order in the  5.0 using the same tcode, the same material type, the system creates
    automatically the Purchase Requisition without to show us the screen to fill or select the fieds. I´ve checked the customizing
    comparing the systems but I couldn´t find something.
    I was wondering If you could help me with this issue?
    If my comments are not enough to understand me, please let me know...
    BR
    Valdevair

    Dear friend,
    Do check configuration node at
    plantmaintenance and custonmer service - maintenance and service processing -maintenance and service orders - functions and settings for order types - define change documents,collective pur.requisitionsindicator,operation no.interval
    here for your order type and plant  , check whether generation of PURCGHASE REQUISITION from maintenance order settings.
    there will be three options
    1) never
    2) from release
    3) immediatly.
    hipe this will help you.
    Regards,
    pardhu

  • Purchase requisition triggering from CRM

    Hi experts,
    We are struggling to create a purchase requisition in ecc from service order.
    Rightnow we are facing the error in which the system is tryig to create a purchase requisition but it is picking a default purchasing organisation 0001 from somewhere... and trying to check its assignement with the material plant. since it is finding it is finding an error.
    Is there somwhere we assign a default purchasing organization in CRM ECC integration... or where is it picking up this default purchasing organisation...
    Or can you please explain stepwise what are the settings for the same.
    I will award maximum points.
    Regards,
    Surendra More

    Hi Rekha,
    I am facing problems in creation of Purchase requisition for service order for service products.
    The scenario is we have service products in ECC with material type DIEN and it is attached to plant and purchase group.
    But when i save service order i am getting the below error.
    Enter a (default) purchasing group for material group SUB_MC (Notification E CRM_SRV_LOG_EXT_OLTP 002)
    I am not able to understand what i am missing.
    some clue please.
    Regards
    Raju

  • Release strategy & EBAN for project systems, purchasing

    Hi
    We have 2 different scenarios for which we use same account assignment category "Z".
    1) Purchase Requisitions for capital expenses (Account assignment category "Z") - this is part of project systems requisition attached to WBS elements
    2) Purchase Requisitions for expensed items (Account assignment category "Z")
    I have configured release strategy with classification with following characteristics
    1) plant
    2) cost centers
    3) total amount in PR
    4) account assignment category
    all 4 characteristics are same in both areas (capital and expensed)of purchase requisitions, account assignment category Z decides whether it is capital purchase or expense related purchases. Z uses order number that is internally tied to WBS element.
    my question is - if some one has similar scenario then what is the best solution to handle invocation of release strategy.
    how release strategy can be determine, do I need to use user exit and if yes what best user exit is available.
    EBAN fields, I have researched and I cant use fields like "requisitioner" for determining release strategy.
    I would like to invoke different release strategy for capital projects and different release strategy for expensed items in PR. there is a workflow attached to this later.
    Please reply
    Thanks and regards
    Umesh

    Umesh,
    Well, there needs to be some way to differentiate the 2 types of purchase requisitions for you to use 2 different release strategies.
    I am not sure if you have the option of using a different document type to differentiate the 2 requisitions. I would definitely look at this possibility and include the document type (CEBAN-BSART) as a characteristic in the release strategy.
    Other options would be to look at using the purchasing group (CEBAN-EKGRP) or the requirements tracking number (CEBAN-BEDNR) as characteristics in your release strategy.
    Hope this helps.
    H Narayan

  • Purchase Requisition transfer from ECC to SRM via XI

    Experts,
    Please let me know if you have any information on  the following issue:
    Environment : SRM 7.0,  ECC ep4,  Extended Classic scenario
    The purchase requisitions have been created in ECC and released. I believe in SRM 7.0  the PR's get automatically transferred to  SRM Sourcing cockpit via XI from ECC.
    One PR was pushed manually from SMQ1(Outbound queue ) in  ECC and this failed due to a login issue in XI.
    The XI was using the interface  PurchaseRequestERPSourcingRequest.
    My question is
    1. When the PR is released in ECC, where to check if the PR is pushed to XI. Do we need to schedule a job? When I checked SMQ1 (outbound queue, the queues are empty)
    2. Do we need to define the partner profile in ECC for XI in We20. If so, then what message types to use for the  IDocs going from ECC to XI.
    2. Do we need to configure the interface PurchaseRequestERPSourcingRequest in XI to map the incoming PR from ECC.
    3. In transaction SXMB_moni in XI  I am not able to pull the  XML messages. What options options do I need to
    set to pull the messages that errored out.
    Thanks,
    Scott.

    Hi All,
    Hope this helps you for XI configuration
       Importing Business Scenarios for Sourcing
    In this section, you transfer the business scenario Strategic Sourcing from the SAP Integration Repository, generate it, and activate it.
    Prerequisites
    You have:
    Defined the business systems for SAP Supplier Relationship Management (SAP SRM) and SAP ERP in the SAP System Landscape Directory. For more information about SAP NetWeaver Process Integration (SAP NetWeaver PI), see the SAP Marketplace
    Imported the SAP NetWeaver PI content for SAP SRM into the SAP Integration Repository.
    Procedure
    Log on to the SAP Netweaver PI system.
    Choose Integration Builder: Configuration.
    In the left pane, select the Objects tab.
    Choose  Service Without Partner  Business System .
    Right-click to display the context menu and choose  Business Systems  Assign Business System . This opens the wizard.
    Choose Continue. The wizard guides you through the required steps.
    Create the business system for both SAP SRM and ERP (you can bypass this step if the business system is already setup).
    Select a business system.
    You can create communication channels either manually or automatically. You can create them automatically here. In this case, the systems are applied from the SAP System Landscape Directory (SLD). Channels must be complete in terms of URLs and authentication information.
    Choose Finish, and then choose Close.
    11. On the main screen, choose  Tools  Transfer Integration Scenario from Integration Repository . This opens a wizard.
    Choose Name using input help SE_Sourcing_Enhancements
    Choose Continue. The scenario name is SE_Sourcing_Enhancements.
    Choose Finish and then choose Close. The Business Scenario Configurator opens automatically.
    Choose Component View.
    The Select Component View window opens.
    Choose Apply.
    Choose Assign Services. The Assign Services to Application Component window opens.
    Press F4 to retrieve the available services.
    Choose Assign.
    Select the related service and choose OK.
    Assign a business service to all roles.
    Choose Configure Connections.
    Select the connections from the Service Assignment tab.
    Press F4 in the Communication Channel field.
    Select a communication channel. This channel must be of type XI.
    Note
    If the systems are applied from the SAP Landscape Directory, the Integration Builder automatically creates the communication channels.
    If the systems are not applied from the SAP Landscape Directory, you create communication channels manually. To do this choose an existing service and then Communication Channel using context menu New. You must assign a communication channel for each connection.
    End of the note.
    Choose OK and then choose Apply.
    Choose Generate to open the Create Configuration Objects window.
    Choose Simulation, then Generate, then mark all in the list Scope of Generation.
    Choose Start to generate a log. Check the log for errors and save it if required.
    In the Close Integration Scenario screen, choose Apply.
    In the left pane, select the Scenarios tab; your scenario has been added.
    In the left pane, select the Change List tab.
    Expand the Standard Change List.
    Right click on the scenario name SE_Sourcing_Enhancements and choose Activate.
    Regards
    Sam

  • How to store the data coming from network analyser into a text or excel file

    Hii everyone
    I'm using Agilent 8719ET network analyser and wish to store the data coming from netowrk analyser into a text file/ excel file.
    Presently I'm able to get the data on Labview graph using GPIB . Can anyone suggest how to go ahead after collect data sub vi. How can the data be stored into a file apart from showing on the graph?
    Attached is the vi for kind consideration...
    Looking for help
    Regards
    Rohit
    Attachments:
    Agilent 87XX Series Exceed Max Meas.vi ‏43 KB

    First let me say that your code really looks pretty good. The data handling could be made more efficient by calculating the number of datapoints that are going to be in the completed dataset and preallocating the entire array -- but depending upon your answer to my questions, the logic in the lower shift register may be going away - so we won't worry about that right now.
    The thing I need to know before addressing the data storage question is: Each time you call "Collect and Display Data.vi", how many element are in the array? Are you reading single data points, or a group of data? (BTW: if the answer to that question is obvious based on the way the other VIs are setup, I don't have the drivers so I can't tell what the setup values are.) Second, how fast does the loop iterate? Are we talking msec per loop?, seconds? fortnights?
    The issues here are two-fold: how much data? and how fast is it coming? The answer to these will tell you how to save the data.
    Mike...
    Certified Professional Instructor
    Certified LabVIEW Architect
    LabVIEW Champion
    "... after all, He's not a tame lion..."
    Be thinking ahead and mark your dance card for NI Week 2015 now: TS 6139 - Object Oriented First Steps

  • How to Change delivery date of Purchase Requisition created from PM  module

    Hi all,
         We are creating service PR from PM module. There is a need that user should be able to change the
    Delivery Date of the PR. When we use ME52N , the field is grayed out.
    If the PR is created with same data manually with ME51N, we are able to change the delivery date.
    Please suggest how to do this.
    Thanks

    I´m sorry, but my english, is not better.
    Why in the Scheduling for External Procurement, the Purchase Requisition take (or picks up) as Delivery date, the Basic End Date of the Maintenance Order (PM). 
    What must I do in the customizing so that the Purchase Requisition takes (or picks up) the delivery date as the Basic End Date of the Maintenance Order.
    Please, helpme..
    Cristian Torres

  • Automatic purchase requisition created from routing needs to be have material no. information in it.

    Hello Experts,
    There are some operations in my routing where external service , from an outside vendor shall be required.
    We are doing this by using a particular control key PP02, for this routing, so that purchase requisition is created automatically, when the production order is created.
    Through customization, I have also been able to make the setting so that instead of single, collective requisition gets  created for the entire order.The requisition that is getting created is a service requisition and can be later converted to a Purchase order.
    Requirement :-  I need to enter material information in this requisition automatically. By material, I mean the material no. and preferably qty of the material,  which will have to be sent out to the external vendor for his services.
    How can I achieve this, in SAP?
    Regards
    P.R

    Hello Caetano,
    Right now we are not considering best practices , so not considering BADI implementation as such.
    So far I have done the following:
    I created a subcontracting purchasing info record for the material and a vendor.
    Then, I have created a routing for the material and the operation which expects to go for external processing, I have used control key YBP2 (tried with PP02) in it.
    I have assigned the subcontracting PIR under the external processing section of this operation in the routing.
    My Production version combines the BOM and routing in the material master.
    Now ,,when I try to create the production order, I get the following errors in succession:
    Control key YBP2: Maintain external processing data
    Message no. CO558
    Diagnosis
    The control key specifies that the operation is processed externally. However, not all data relevant to external processing has been maintained.
    respond by entering the material group where the cursor is.
    Then I get the following error.
    Material class differs from material class  from info record
    Message no. 06354
    Diagnosis
    The material class or material group of the info record differs from that of the item.
    I checked in the material master and the material group there is same as the material group in the info record . Field name is MATKL.
    What material class is it talking about?
    I cannot get past this error and therefore cannot complete the order creation.
    Regards
    P.R

  • Creating Purchase Requisition/Order from a CRM Service Order

    Hello,
    My client is using CRM 4.0 with Service Industry add-on.
    I am trying to kick out a purchase requisition from a service order, but does not go through.
    The Service Order is released in CRM and an internal order does get created in R/3. The material that I am using is a service product (defined in R/3 and used in CRM) and I trying to procure External services.
    All the requisite configuration in CRM and R/3 have been done.
    I get an error message E06 436 (In case of account assignment, please enter account assignment data for Item).
    Would appreciate any feedback in this regard.

    Hi,
    I am working on the some scenario. Based on the limited documentation, it appears that you have to create a service master in R/3 that is than replicated to CRM (object SERVICE_MASTER). I did this, and this works. However, I am facing the issue that there is no sales data assigned to the service product in CRM, while you do need this (service order is not complete).
    I hope that I will have an answer for this, and then I think that it should work.
    The PO that is created in R/3 will contain an item with item category D and account assignment F (in our case, as we work with internal orders as account assignment object).
    The receipt of the service provided will then be posted by means of a service entry sheet in R/3.

  • Backend exit in Purchase Requisition creation from SC in SRM

    Hello,
    could please someone tell me which exit can be called in R/3 backend system during the creation of a Purchase requisition created form a SC in SRM?
    Thanks a lot.
    Guido

    Hi Guido,
    It does exist in ECC60 !
    However, maybe your release backend does not have it....
    Kind regards,
    Yann

Maybe you are looking for

  • Problem in filling field catalog as table is dynamic

    Hi All,     I have to populate the data using the below function module and i am passing dynamic internal table <f_list> in place of list.    i have to populate the field catalog fc_hier which is getting field by standard program but i have to add ad

  • WINDOWS LOGO

    When I installed iTunes, it showed that it could not install the software for my CD/DVD drive because it didnt pass windows logo testing so it will not download this software. iTunes works fine but i still want to have importing and burning discs fea

  • Headphones aren't working:(

    Ever since I updated my iPad to IOS 7 none of my headphone worked does anyone have some ways for me to fix it?

  • Calling secured webservices from BPEL 10.1.3.5 (oc4j)

    Hi all, I'm trying to call a username/password secured service on a SAP system - it works perfectly with SoapUI. After some time I managed to get it working also in BPEL with <property name="basicHeaders">credentials</property> <property name="basicU

  • HT1879 i tried find music from the movie HOW THE WEST WAS WON?

    I am new to Itunes.  How can I search for music. There is so much stuff on the pages it is confusing.,  I want to be le to search for music and preview tghen buy