Project system : system status changes log?

Dear PS experts,
Kindly let me know where i can see the Project Definition ; system status changes done by users as & when required.
CRTD to REL
REL to TECO
TECO to REL (cancel)
so on
I wud like when the project status - system status changed by user thru any log report?
regards
srihari

Hi...
why don't you try the following:
in project builder CJ20N (project definition) use the I (informaton button) where the System/User status ism and then in the next screen use the menu Extras->Changed Documents ->All.
Next screen press button history...
(or even CN60 transaction)
i hope it helps
pan

Similar Messages

  • User Status Change Log for WBS Element

    Hi All,
    I have a requirement to capture the user and time when the user status has changed for WBS Element in TCODE CJ20N.
    How do I enhance the standard table to add these 2 fields and also which enhancement is used to populate these fields?
    Thanks
    David

    hi david,
    if your looking for status changes in WBS for CJ20N tcode then
    have changes documents tick marked in OPSA tcode for a particular project profile and then create project in CJ20N with that project profile and go to that respective WBS and click the blue icon and goto
    Extras->changedocuments->All---> here click on all changes or history ... here this should give you required data your looking for ...
    regards
    pushpa

  • WBS Report Showing Change logs - ex: system status

    Hi,
    I would like to know if there is any report that would show the change log for AVAC for WBS Elements (i.e. change data of system status).  I tried running CN60 but it does not give any results.
    Thanks!
    Vivian

    Hi Sarang,
    Thanks for your reply.
    Would you know if there is any specific report for this instead of having to look up individually?
    Also, in order to view the change document for both Project Definition and WBS Element, I understand there is some config that need to be done. Could you confirm if below are complete / correct?
    - project profile - tick on change document (OPSA)
    - Project Definition and WBS Element status profile (user status profile) - set business transaction to allow "create change document"
    Thanks!
    Vivian

  • Project definition system status change details

    Dear PS experts,
    Request, kindly let me know which report is available to show the system status change from
    crtd to rel
    rel to teco
    teco to clsd
    we would like to analyse which date or period the system status changed thru edit-status
    from crtd to rel
            rel to teco
            teco to clsd
    we don't use any user status.
    i have checked cn60 & all reports from cn41 to cn47, but i don't get any report states about the change details of system status.
    pl help
    srihari

    thanx,
    can u pl tell me about cn60 std report, does this use for system status change or any other purpose, pl let me what purpose this report is available for us.
    i wanted to know only the changes taken place in project definition with regard to crtd to rel or rel to teco or teco clsd, there should some report which will give this data without touching the tables.
    pl help
    regards
    Srihari

  • Can we change budget status through project setup system status window?

    Hi Experts,
    Can we change budget status through project statuses window?
    Thanks

    Hi
    Project statuses window will only deal with the status of the project, not the status of the budget.
    Dina

  • System Status Change for Project Definition

    Hi,
    I am working on a requirement to notify the Project Manager when the Project Status changes to REL.
    I couldn't find any user exits where I can add the code to send an e-mail notification at the time of status change of the Project Definition or the WBS elements within the Project.
    I checked for events in Business Objects BUS2054(WBS) and BUS2001(ProjectDefinition) which might get triggered at the time of status change. I couldn't find any events relevant to Status Change.
    Any ideas how to handle this requirement ?
    Regards
    Bhooma

    I found a solution to this issue.
    Regards
    Bhoooma

  • How to get the Change Log Table name of the ODS from the system table

    Hi,
    I have a list of ODSs in the system and I am interested in finding the corresponding Change Log Table and the number of records in that table.
    Can any one please tell me the name of the system table where this information is stored.
    I dont want to get in this information manully (from the Contents tab of the ODS maintenane).
    Regards,
    Harikiran Gunnala

    Hi
    Go to SE16
    Give the table name as "RSTSODS".
    For User application field give CHANGELOG as input
    and execute. You will get all the list of Changelog tables Along with below mentioned data
    PSA
    Version
    To
    Valid from
    Object Status
    Technical ODS name
    Program Name
    Maint  Program
    Object Name
    Last changed by
    UTC Time Stamp in Short Form
    Partition number
    Regards
    Raj

  • System status change with delegated standard object

    Hi everybody,
    I delegated BUS2005 (production order) to ZBUS2005 and created a new event based upon the system status MANC (I0420). It works fine when I use my custom object ZBUS2005 in BSVZ and this event is successfully triggered. But when I change this object to the standard object BUS2005 in the same transaction BSVZ, the event is not triggered. BUS2005 has been already delegated to ZBUS2005.
    Can somebody kindly tell me how this can be fixed? I want to see the standard object, BUS2005 in the trace, instead of my custom object.
    Thanks,
    Max

    Thanks Nishant,
    Well, I have created many events for other objects and delegated the objects.
    In all these cases, I can see the standard objects in the trace, not the customized objects. But in these cases, I didnt go for status change management.
    So, why dont I see the same standard object in the trace in this case of BUS2005? Even the setting in BAVZ has been done according to BUS2005, not ZBUS2005. So, I am expecting BUS2005 in the trace. Trace comes only when I change this BUS2005 to ZBUS2005 in BSVZ.
    Please give your comments.
    Thanks,
    Max

  • Exit for CJ20N where system status changes can be captured

    Hi Experts,
    I need exit for CJ20N where system status changes can be captured
    for both the below cases
    1) When WBS Element is having Networks inside it
    2) when WBS Element is having no networks inside it
    EXIT_SAPLCOBT_001  --->>>   ZXCO1U01  , will work for 1) , but not for 2)
    i want an exit where status change gets captured for both cases 1 and 2 and
    will do further processing according to client needs based on status change
    Need to trigger IDOC on status change of  WBS element.
    If WBS is having network inside it  , then network status changes also with WBS status change
    and IDOC should trigger for WBS also.
    I just want suitable exit  / place for coding . Rest i can do.
    if no suitable exit / BADI , then what is the best possible place where i can go for Implicit Enhancement
    Best Regards,
    Gaurav
    Edited by: TheGaurav on Oct 25, 2011 7:08 AM
    Edited by: TheGaurav on Oct 25, 2011 7:12 AM

    I am kind of stuck in a similar issue. I need to perform custom validations on standard fields which cannot be done through OPSI or OPUC transactions. 0007 or 0002 User exits seem to assist on custom field creations/validations. However, I do see people posting the following BADIs which may be useful.
    CO_SRULE_CHECK
    PROJECTDEF_UPDATE
    WORKBREAKDOWN_UPDATE (which you already tried)
    WBS_FIELDS_FOR_ASSET
    CO_SRULE_CDOC
    Let me know if any of these worked out...
    AN

  • Compelete system change log

    Hello Experts,
    I want to see complete system change log, is there any option through which I can see the complete change log, or any query for viewing the change Log ?
    Thanks
    Help Required....

    Hi Muhammad
    Please try this query
    SELECT *  FROM ADOC T0 WHERE ObjType ='15'
    Regards,
    Syn Qin
    SAP Business One Forums Team

  • Sale Order Status Change after delivery of materials from projects

    have ETO sccenario which consists of all modules such as SD,PS.PP etc. Materials will be procured from external vendors & manufactured inhouse through project systems. After delivery of materials from project systems, billing & invoicing will be done at sales level.
    On delivery of materials from projects, sale order status remain open. Request you to look into the matter & suggest about status change of sale order after delivery / billing.
    Regards,
    Ranjan

    Hi,
    In sale order, WBSE is assigned. Delivery of materials are through cns0. then subsequently picking / packing / billing will happen at sales level. Billing is of delivery related. Please suggest to fix the issue.
    Thanks & Regards,
    Biplab Ranjan

  • Credit status change through Sales order - change log

    Hi Friends,
      I'm currently facing a scenario were it was reported by the client that
      credit release is happening automatically.
      Brief details : 
       Order was created on 4th Of Oct and it was blocked (reaches the VKM1 bucket )
       since the customer reaches the credit limit.The same order on 5th Oct was not in VKM1
       bucket were the status of order in Sales document header states that it's  released.
      Initial check : (Sales order change log)
      1, I've checked the change log on 5th Oct were the  field VBUK - CMGST  "Overall status of credit checks changed"  from  B to A.
       ((  Status and details below
          A - Credit check was executed and document is OK.
          B - Credit check was exectued and Document is not OK (credit block).
          C - Credit check was executed document not OK, Partial release.
          D-  Document released by Sales representative. ))
    2, I tried to replicate the order status for block and release, But when I release through  VKM1 / VKM3
         the change logs are getting updated with Status - D .(ie from B to D) .
      I'm  wondering that  what could be the reason that causes the system to update in the table - VBUK  - CMGST from A to B
      or because of what change from the client in the sales document header level could impact this changes.
      Note - There is no payment which received from customer on that day.
      Please let me know in case if you are getting the clue...
      Thanks in Advance..
      - Pugal stalin

    Hi
    A simple credit check, as the name suggests, is very simple in nature. The functionality is limited and considers only open A/R items and open items from special G/L and sales orders for performing the credit checks. When you create/change a sales order that is relevant for a simple credit check, SAP calculates the payer/customeru2019s credit exposure by adding the open A/R balance for the customer, open item balances from the special G/L, and the net sales order value. This credit exposure is then compared against the customer credit limit maintained in the customeru2019s credit master. If the credit exposure is greater than the credit limit, the system sets the credit check status as u201Cfailu201D and shows a warning, generates an error message, or performs a delivery block
    Regards from Pakistan

  • Update overview log on status change in SM 4.0

    When processing support desk messages in CRM_DNO_MONITOR, we change the status to 'In process' and other values.  While these actions are recorded in the change documents, we are looking for a method of recording selected status changes with the date and user in the Overview log on the Transaction Data tab.  It would seem that this would be defined in SPPFCADM but none of the action definitions seem to match what we are trying to accomplish.  Any help provided will be appreciated, thanks in advance.

    I essentially need to figure out how to solve the following issue:
    Change requests cannot be displayed or created, because the RFC connection has errors, or is not maintained.
    Check whether the RFC connection to the Change Man agement system is under the key CHARM_DEST (APPLI field in the DESTINAT field), in the view BCOS_CUST. You need authorization for the cross-client view/table maintenance (S_TABU_DIS and S_TABU_CLI).
    Not sure how to check this!
    Check the RFC connection in the transaction SM59. If your SAP Solution Manager system is also your Change Manager system, the internal connection must be 'NONE'. You need authorization for the administration of RFC connections (S_RFC_ADM).
    My Solution Manager is my Change Manager system.
    You may have to dumb it down for me. 
    Thanks

  • Why dispute case "status" changing automatically and also not updating in log

    HI,
    I found something curious as you can see in the image below , I was process dispute case  "data complete" to "Partially Approved - SDC"  but system automatically changing status to data complete ... I did 2 times but system is automatically changing status  . We are unable to get the details in log also.
    Any one can help why system is automatically changing and log is not updating .

    Hi,
    It may be the case that some of the SharePoint timer jobs were not created when the PWA was provisioned.
    Try to re-provision the PWA instance and see if that would help (edit the PWA instance in SharePoint Central Admin without changing anything)
    Paul

  • Project Management System In Dreamweaver

    I'm looking to create project management system in Dreamweaver; similar to MS Outlook, only with an enhanced task hierarchy and detail section.
    Does anyone know of examples and / or books where I can see what I'm getting myself into?  Even better, does Dreamweaver have a template for this? (I haven't purchased the software yet)
    Thanks,,
    Mike

    I'm not looking for a full blown project management system; more like an activity (to-do) list in a subject lookup hierarchy, possible with email reminders of what's coming due. (something like expand-collapse subject areas with text, date, name and status fields).  I've done something similar in Visual Basic wtih an Access DB holding the information.  It doesn't look so great but does the job.

Maybe you are looking for