Projected available balance from Horizontal plan ASCP

Which table and column stores the projected available balance details of ASCP horizontal plan
Details:
I can see the PAB (projected available balance) for a item in Horizontal plan in ASCP. which table and column stores this data.

Hi
Are you asking about start date (for each bucket ?) . Tools work dates>period start dates will give you that.
If its for the whole HP it will be system date-1 always.
Can you please elaborate on you qn ?
Best Regards
Partha

Similar Messages

  • Safety Stock field/table in ASCP Horizontal Plan?

    Hello,
    I need to get the safety stock data that is seen from the ASCP's Horizontal Plan. Whiat table and field is it? Can't find it from MSC_DEMANDS and MSC_SUPPLIES. Thanks

    Hello,
    in an ASCP plan safety stock results/output is always populated in MSC_SAFTEY_STOCKS and not in MSC_DEMANDS.
    MSC_DEMANDS is populated for SS only in IO Plans
    safety stock demands can be seen in msc_demands with origination_type = 31
    HTH
    Geert

  • ASCP Horizontal Plan - Snapshot data

    Hi All,
    We're planning to generate report based on Rolling Gross requirements as per (snapshot data on ASCP workbench).
    The Rolling Gross Requirements need to be shown for 12 weeks or 12 months as part of report.
    This is very challenging requirement, Can you please help me find (Any data points) how Oracle is currently retrieving snapshot dara for horizontal plan?
    We need to display (gross requirements) report data for 12 weeks (bucket) and 12 months (buckets) by each demand (Beginning on hand, purchase orders, requisitions, In Transit, In Receiving).
    I've reviewed package (MSC_HORIZONTAL_PLAN_SC) but It doesn't help me much in (understanding/getting) snapshot data.
    In MSC_HORIZONTAL_PLAN_SC package, there is a cursor (MRP_SNAPSHOT_ACTIVITY).
    The snapshot can be viewed on ASCP workbench in R12.1.3 with following steps
    1. Advanced Supply Chain Planner (ASCP) super user Responsibility
    2. Nav: Supply Chain Plan -> Workbench
    3. Select a Plan
    4. Go to Supply/Demand
    5. Select a record (Criteria:Supplier; Condition: equals ; From: <Supplier_Name>) and click Find button
    6. Right-click -> Horizontal Plan
    7. For each item, Rows shows [sales orders, Forecast, Dependent demand, Gross Requirements, Work orders, Purchase orders] and columns show [weekly and daily dates]
    Appreciate your help, Thanks in advance.
    Regards,
    Kal

    Hi,
    Are you having trouble in arranging a weekly/monthly pattern or having problem with Data.
    Weekly/Monthly pattern is possible to create.
    Chintamani

  • I am facing a problem while working in Muse... The issue is I cannot delete a page from my plan, when I am trying to delete it showing an error and the application shuts down. I am working on an emergency project which I got to submit it tomorrow I hope y

    I am facing a problem while working in Muse... The issue is I cannot delete a page from my plan, when I am trying to delete it showing an error and the application shuts down. I am working on an emergency project which I got to submit it tomorrow I hope you will find a solution for the same.Help with using Adobe Muse CC

    Thanks,
    I have tried with a new site it's working perfectly.
    See the screenshot of the error.
    Thanks for your support Rohit

  • How do I get my movies from iLife"09 into my imovie app on my phone and iPad. In the app it keeps saying "no projects available to copy from iTunes"

    How do I get my movies from iLife"09 into my imovie app on my phone and iPad. In the app it keeps saying "no projects available to copy from iTunes"

    First, you need to send the project to iTunes:
    http://support.apple.com/kb/PH2282?viewlocale=en_US
    From there, you can then sync it to your phone:
    http://support.apple.com/kb/PH2168

  • ASCP Horizontal Plan calculation

    Hi,
    Can anyone explain the arithmetic calculation of Horizontal Plan in ASCP?
    Thanks

    what do you mean by the arithmetic calculation?
    the HP can have many different rows of information depending upon what the user wants to see

  • Error validating business rules containing variable from another plan type.

    We have created few business rules in in plan type "Plan1" which we are using variable from plan type "Capex". This is how we are using it.
    "(@XREF(cpx,"Intangible Assets Finite, Gross","Unspecified","No Project","Information Technology (IT)","371064911-01"))"
    But when we validate this rule it gives the following error
    "An error occurred in: Rule:IFLJAN13.Plan1.B - Trail Balance - Capex
    A validation error was received from the Planning server 'http://hptstorg:8300/HyperionPlanning/servlet/HspAppManagerServlet?appname=IFLJAN13'.
    'Error:The member 'Unspecified' cannot be found.
    The member 'Unspecified' cannot be found.
    The member 'Intangible Assets' cannot be found.
    The member 'Unspecified' cannot be found.
    The member 'Unspecified' cannot be found. Rule IFLJAN13.Plan1.B - Trail Balance - Capex'."
    We have checked the location aliases using EAS Console and they are correct.

    Could you pls. check if you can see your BR in the location for the cube where you are unable to validate the rule?! (EAS console --> Administration --> Locations --> (right click) open)
    your user must be able to "validate or launch" the rule in this location (changeable with "Add Access Privileges") and the rule itself must be able to launch in this location (changeable with "Add rules").
    Kind regards
    André

  • Horizontal Plan Suggestions and Calculations

    Hi,
    I am facing an issue in understanding the ASCP Horizontal Plan calculations for EBS ver 12.1.3.
    I have made 1 FG Item, 1 RM Item and BOM of FG with component requirement 1 for 1 FG Item. Entered the Forecast of FG = 100 bucket type days.
    Made 1 resource allocated to single department and on routing available 24 Hrs without shifts with usage 1 and assigned units 1. Means 24 units can be made in 24 hrs.
    Now when i am launching the Resource constraint plan with no supplier constraint and wit no lead times option, the planner work bench is suggesting me batches with quantity 22 for 3 days and 21 for 1 day than 13 for 1 day. In horizontal plan the available hours are 24 but required hours shown are 22.
    Can any one tell me on what basis the suggested Qty for Job is 22 or 21 though the available resource hours are 24. I am also perplexed in understanding the calculations of Horizontal Plan for the following Available Hours, Required Hours, Net Hours Available, Capacity Load Ratio for current day and for the proceeding days.
    Also the Suggested Dates and Times shown are confusing.
    Thanks in Advance
    Regards,
    Farhan Ahmed

    Hi everyone,
    Kindly help me on this issue. Please reply to my post.
    Regards
    Farhan Ahmed

  • Exclusion of stock categories from SNP Planning

    HI All,
    I am trying to exclude specific stock categories from SNP Planning (Heuristics/CTM). These categories include 'CI' (Blocked stock) and 'CF' (Stock in Quality Inspection). According to note 487166, Blocked Stock is not relevant for planning and Quality Inspection stock is relevant for planning. Apparently this is hard coded. Still, the system seems to be taking both Blocked and Quality Stock into consideration when executing heuristics or CTM.
    I have also attempted to deselectu2019 Stock in Quality Inspection' and 'Blocked Stock' in the product master > Demand > Available Stock tab, but the system still considers them during planning.
    I have also read that the user exit APOCF011 can be used to change the stock category and change the Planning Relevance. However, the down side of this is that not all business unites want to use this same logic and this is a system wide change.
    I was hoping there was an easier way then the user exit (e.g. setting in product master > Demand tab), but there does not seem to be any other options? At the very least, I would expect Blocked Stock not to be considered as relevant to planning (according to OSS Note 487166). However, this does not seem to be the case in our system.
    Any assistance would be appreciated.
    Kind Regards,
    Paul

    Hi Paul,
    There is a way to exclude some stock categories in SNP Planning. You can create a ATP category group just with those stock elements that you want to consider and assignt this category group in location, SNP tab. I use this configuration for SNP optimizer, and it should work for SNP heuristics.
    I worked in few CTM projects, but if I were you I would create a order selection without some stock categories and assign this order seelction in planning scope/CTM profile.
    Noriaki Kimoto

  • Period O in Horizontal Plan

    Hello..
    We have set our bucket types to be all periods, days=0, weeks=0, periods=18.
    When pulling up a horizontal plan in ASCP, the first bucket is Period 0.. What is the purpose of Period 0, then following is the current date Period 1.. not all the information is listed in either one.
    The Period 0 has the forecast entries but not the beginning on hand while Period 1 does not have the forecast and has the beginning on hand.
    Please provide some insight on this .
    Thanks,
    Nadi

    Nadi,
    Period 0 is past due and will show past due forecast, sales orders, and supplies.
    On hand inventory is always available today, so it is displayed in period 1.
    Regards,
    Kevin

  • Horizontal Plan question

    Hello,
    I have a question regarding the behavior of the horizontal plan. I'm new to the ASCP module.
    I have current scheduled receipts let say a Purchase order of qty 20. If i drill down on it, there is
    an action of Reschedule Out but the "For Release" and "Firm" are still unchecked. So this scheduled
    receipts becomes part of the Projected On Hand for today. The same PO quantity appears under day bucket
    on which the suggested due date falls. Isn't this an overstatement?
    thanks.
    gregg

    09-aug-10 | ....|...............................
    Current
    Scheduled
    Receipts 20 (action is Rescheduled out
    w/ future date like 02-FEB-11)
    Proj
    OnHand 20
    02-FEB-11|...
    PO 20 (drilling down the same po that are shown under sched receipts)
    It looks like this, there is a duplication the current schedule receipts are counted in the projected on hand, etc
    and then the rescheduled PO is counted once again.
    Edited by: Apps Devel on Aug 10, 2010 10:03 AM

  • Error in delta loading from a planning cube

    hi all,
    I am using a delta load from one planning cube to another.When the changed records are of a magnitude of 100 then it is successful but when the records are of magnitude of 100000 then it stays yellow with no data records sent and eventually fails.the packet size is 20000.
    any help is appreciated.

    Hello Ajay,
    Have you checked that your Request is closed in the planning cube? FM RSAPO_CLOSE_TRANS_REQUEST will do it
    It is a customizing issue to tell the infopackage to end "green" when it has no data.
    Transaction Spro ==> SAP Netweaver ==> SAP Business Information Warehouse ==> Automated Processes ==> Monitor Settings ==> Set Traffic Light Color. There you have to set the Traffic light on green if no data is available in the system.
    Hope that helps
    best regards
    Yannick

  • Transfer balance from one GL account to another, then restict posting

    Hi Gurus,
    We have an GL account (650045) showing balances ($ 4656)  and client wants to this balance to another GL account ( 650198) and close then 650045 and see that no postings are allowed in 650045.
    Can you please let me know how to do this transfer and then i need to close and resist postings to 650045.
    Thanks for your help, i will assign good points.
    Thanks
    Prashanth

    Dear Prashanth,
    You can use a transaction F-02 to transfer the balance. Follow the steps below:
    open a new GL account where th bal has to be transfered.
    take out the exact balance from old GL to be transfered
    Considering that u have a debit bal in old GL & have to transfer the same, the the entry u will pass thru F-02:
    'New GL' A/C   - Dr  - xxxx (posting key - 40)
       To 'Old GL' A/c          - xxxx (posting key - 50)
    This will pass on ur bal from one GL to another.
    Once done go to FS00, open the old GL. On the top right hand u have a symbol of 'lock'. click on to that. A screen will open with details as ... block for posting, block for creation, block for planning ...
    tick the option of block for posting in both chart of accounts & for company code.
    Hope this will solve ur pob.
    Regards,
    Ajay

  • Available balance in excise register

    Hi All
    I have captured and posted excise at the time of MIGO and Biling document.My PartII register is also showing entries against MIGO captured excise duty.
    I have posted FI JV for fund transfer to PLA on hold and then from J1iH transfered the same to PLA account as well.
    Now when I do monthly utilization J2iun, it is showing zero available balance against RG23A and RG23C and no PLA is showing here for utilization. And only billing invoices are coming for adjustment.
    Can someone suggest what is wrong here.
    Regards
    Mukta

    Hi Kishore
    GL account assignment exist for UTLZ for all the below RG23A and RG23C .
    RG23A BED               
    GL A/c for RG23A BED          
    RG23A SED          
    RG23C BED          
    RG23C AED          
    RG23C SED          
    Offset          
    Mod.Clear          
    GL A/c for PLA BED          
    GL A/c for PLA AED          
    GL A/c for PLA SED          
    GL A/c for PLA CESS          
    CENVAT OH          
    CENVAT sse          
    PLA On Hld          
    Reversal     
    GL account assignment not maintained for the below--
    G/L RG23AN     
    G/L RG23CN     
    G/L PLANCC     
    G/L RG23AE
    G/L RG23CE
    G/L PLAECS
    G/L 23AAT1
    G/L 23CAT1
    GL A/c for PLA AT1
    RG23AT2
    RG23CAT2
    G/L Acc for PLA AT2
    RG23AAT3
    RG23CAT3
    G/L Acc for PLA AT3
    Will this impact monthly utilization, or this is only for fortnightly utilization and any separate settings for monthly utilization?
    Also we have already extracted PLA after doing j1ih and the balance is coming in PLA Register when we see in J2i6.
    Regards
    Mukta

  • Field details of available balance in J2IUN

    dear all,
    In  J2IUN utilization transaction the column of available balaces are from either RG23 BALANCE and PLA.
    but can anybody reply how and from which tables the values are picked and calculated for the available balance field.
    Regards,
    Vimlesh

    .