Question is Related to customer projects.
Our Business Scenario:  Our Clientu2019s major revenue is based on Customer Projects i.e. supply and installation of  equipments at Customer site. For completion of these type of projects, it may take more than 1 one year. Once the Project completes, the Billing will happen with revenue and corresponding cost needs to be transferred to Cost of Projects. Till the time of completion of project, the material and the services utilized for the project will be shown as work in Progress in Books of Accounts.
To handle this scenario in SAP we have proposed the below Process.
Procuring the goods for Projects through normal GR (MIGO) with Mvmt. Type u2013 101 Q (Project stock)
1)        Accounting Doc: Inventory A/c Dr.
               To GR/IR Clearing A/c
Once the GR is made, issue the material to Projects through
movement type 281 (Q) by using  T Code - CNS0. Here the accounting doc is :
2)        WIP Project stock A/c (B/S account)
To Inventory Account Cr.
Once the project is completed, Settle and sell the project to Customer. While doing settlement, the balance in WIP account needs to be transferred to Cost of Projects account. The accounting entry will be :
3)        Cost of Projects (P&L) A/c Dr.
To WIP Project stock A/c (B/S account)
Now the problem we are facing is , when doing settlement, settlement is not happening properly and the required accounting entry is not posting i.e. as mentioned in serial no. 3 above.
Request your help in this regard at the earliest plz.,

Hi,
We need to assign the G/L account in WBSE of the Projects as cost recevier object for settlement of projects. In the transaction CJ02, select WBSE & settlement rule. Then in the category G/L has to be defined & in the settlement receiver the respective G/L account hasto be defined. This will transfer cost incured from WBSE into G/L after settlement.
Regards,
Rakesh Pradhan

Similar Messages

  • Error while attaching settlement rule for AuC asset

    Getting error "The share to be settled in rule 001 is not unique"  "Enter a unique number (001) (view: Actual settlement) "  when trying to attach a settlement receiver in transaction AIAB  - where to view the duplication of rules, and where to delete the rules ?

    Hello
    Check the transfer variant / receiving asset / transaction type.
    Check all rules again.
    Reg

  • Settling Rebate through free goods in R/3

    Client is producing halogen and CFL lights for home and office use. Client is making sales through dealers and distributors in market.
    Sales regions are: North, South, East, and West.
    Sales Sub regions: Delhi, UP, Maharashtra, Karnataka, West Bengal and so on.
    Promotional Schemes:
    1)     Monthly:
    a.      Quantity targets are given for month on achieving free goods are given
    b.     No Credit Memo
    c.     For example, on sale of 1000 pcs of 20W CFL in one month, 50 pcs of 15W CFL free.
    d.     Mostly product based schemes as  to promote particular line item
    e.     Different schemes for distributor and dealers (divided on basis of customer group)
    2)     Quarterly:
    a.     Similar to Monthly with difference in time frame which is of quarter
    3)     Secondary (On basis of points)
    a.     For each qualifying product, points are awarded. On accumulation of points free gifts or goods are provided for different level of points
    4)     Annual:
    a.     Annual discount on basis sales amount irrespective of which products sold.
    Key Points:
    1)     All calculations are done on excel sheet using sales report from SAP i.e. to find the qualifying customer.
    2)     Later scheme is settled by creating free of charge sales order in SAP of zero prices.
    3)     Same product can be part of two schemes one on distributor level and other on regional or national level.
    4)     No credit memo is issued to settle schemes.
    Question: Can we map this process through rebates or any way sales such that the schemes can be created and list of qualifying customer is calculated in system itself? Later, it can be settled through free goods rather then credit memo?

    Already solved. Item Catgory settings and Downloading R/3 customizing to CRM

  • Error " In case of evaluated receipt settlement, please maintain tax code", during VI01

    Dear Team
    We have a scenario in our environment where for a delivery made for STO Purchase Order, we are trying to post shipping cost document for Shipping document.
    When we try to save the document, the system returns the error " In case of evaluated receipt settlement, please maintain tax code".
    We have checked in the system. The vendor to whom the PO has been raised is not maintained for Evaluated Receipt Settlement, and as this is a STO , no vendor info record has been maintained for the same.
    The issue has started to come for a new plant and transportation route, for other routes and plants we are still able to proceed successfully for creation of shipment costs
    Can this be an issue of master data maintanence that we may have missed during plant creation or transportation route creation
    Else, Kindly guide.

    Hi Tarunveer,
    Which Vendor are you mentioning: Plant Vendor of STO or Forwarding Agent.
    I am suggesting to check in LFM2 for Forwarding Agent.
    Same way, in the case of Invoice Tab in PO, (Which PO are you mentioning: STO or PO for Forwarding Agent?)
    Regards,
    MJ.

  • How to Make Settlement Rule Mandatory in Sales Order(In Acct Assigt Tab)

    Hi Gurus,
    I have a business requirement. For Free of charge 3rd party orders (yes they have FOC orders delivered by third party) the business wants to ensure that the Settlement rule should be mandatory. They enter cost center & receiver in the settlement rule.
    i.e the order should not save till Settlement rule is maintained in the line item in the Acct Assignment tab.
    Please let me know how this can be done.
    1: Applied my brains on incompletion procedure but does not seems like it can be done there.
    2: Is there something in CO where some setting can make it mandatory to enter settlement rule in Sales order?
    3: I s there any other way in user-exits or ABAP?
    4: Is there any setting in Item category(I could not locate any)?
    5: Can this be done via Requirement class.
    Please assist to resolve this one.

    Dear,
    It depends on settings in Requirement Class (OVZG) and Account Assignment Catg (AAC) in OME9
    If your AAC is E in Req Class, then your sales order is a CO object.
    Requirement Class in IMG can be checked - IMG > Controling > Prod Cost Planning > Cost Obj Controling > Prod Cost By Sales Order > Control of Requirement.
    Or any filed any you can Make mandatory through Transaction variant SHD0.

  • Automatic settlement to particular combination of cost centres and gl codes

    HI,
    A company uses Plant Maintenance for Engineering overhauls. MM is used for Engineering spares only (i.e. not for goods for resale etc).
    The requirement is to set up ongoing Plant Maintenance Orders, one for each item of plant (only 600). The plan is just to leave them open, as they are only used at a simple level.
    Anyway, for each PM order, the requirement will be to settle automatically, and to a particular GL code and a particular cost centre.
    So, for three different works orders:-
    Cost Centre -
    >   333     334     335
    GL code
    1234----
    >(X)
    1235----
    >(Y)
    1236----
    >(Z)
    1) What is the best way to achieve this? I am thinking that GL code will be specified by order type (therefore I will need about 10, corresponding to the GL codes) and cost centre will be specified by Work Centre in each order.
    2) How do I set up automatic settlement? Can this be at period end only or instantly when good are booked to the order by the stores.

    Hi ,
    For Plant Maintenance with FICO , you need Settlement rule & settlement profile. 
    The settlement rule determines what portions of a sender's costs are to be settled to which receiver(s).
    In thesettlement profile you determine to which objects orders of this order type can settle to. You can also assign an order type to a settlement profile at a later date. You can change the settlement profile in the order.
    After you create the settlement profile , you need to save the profile to particular order type.
    Inside the settlement profile , you will define the control parameter of how is the way to settle included which cost center to post.
    For automatic settlement , i think you need user exist - Please refer to userexit IWO10027 or COOM0003 with your abaper.
    Thank you.

  • PCtr in CWIP Settlement line items

    Hi all of you
    When I am doing CWIP settlement system is asking the PCtr as it is mandatory field in Document splitting. I have assigned one Internal order in the asset master and based on the order system is picking the PCtr in acquisitions,it is fine. But system is not picking the PCtr in CWIP Settlement.
    Please give me your valuable suggestions to resolve the issue.
    Thanks & Regards
    Ramki

    hi,
    At the time of settle the CWIP to Main asset there itself u can select additional aacount assignment button and enter ur PCA it is working ok becoz the same problem i had fece for the lost month ok.

  • Settlement of WBS element down payments to an asset under constructions

    The down payment (of the transactions tcode F-47 and tcode F-110), are
    always settlement wbs element (tcode CJ88), we do not want to post down
    payments to the receiving asset under construction (transaction type
    180 or 181).
    In the down payments are always taken into account in the settlement to
    an asset. The settlement of the down payment is the actual reason for
    the previous update of down payments in FI (Transaction type group
    15). Furthermore, the settlement of down payments to assets should
    not be capitalize.

    When you search on this forum try to put Date range "ALL" to get more results. Please read below threads and you will get the solution.
    MIRO:Transaction in area 15 contradicts the net book value rule
    Transaction in area 01 contradicts the NBV
    Looks like you have a negative balance in your WBS which you are trying to settle to FA.

  • About settlement, asset master data's amount column value

    Dear Experts,
    I  build an aseet master data :   A (the amount column's value is 0 in asset master data)
    Then, I build an asset purchase order  assign to A , after I  do GR,  A's amount column's value change to 1.
    But if as follows,
    I  build two asset master data :  B and C ,
    B's asset catalog is 167200(prepay for equipment) , c's asset catalog is 153100 (normal fixed asset)
    Then , I build an asset purchase order assign to B, then do GR , B has amount 1, and then ,
    I  do t-code: AIAB , settlement B to C , I found B's amount column's value still show 1 , and C is still 0 ,
    but the asset value certainly has transfer  from B to C......
    why B's amount column's value doesn't be changed?
    I can't figured out.
    Thanks a lot in advance.
    Best Regards,
    Yacoa
    Edited by: Yacoa Chen on Mar 15, 2011 9:14 AM

    Hi
    If B is still showing value - It means values are not settled
    After AIAB - You need to run AIBU to settle the values.. Did you run AIBU??
    Br, Ajay M

  • Vendor details along with amount settled to an asset in an investment project.

    Hi Guys,
    Here we are following std process i.e. PR/PO with WBS as account assigned, then GR-GI/SES and then settle it to AUC and then in the end to FXA.
    Now the requirement is to capture all the line item details (including vendor with the amount) settled to asset. I have tried a lot and get the WBS, AUC from FXA and the CO doc., FI Doc. & the settlement doc. but not able to link CO doc. of settlement to the GR-GI CO document.
    Can any one help me on this or can suggest any other work around?
    Thanks & regards,
    Soubhagya

    Hello Soubhagya,
    With % settlement it looks difficult because what if you have total actual cost (6 line items) is 60K and you want to distribute it among 5 FXA on line items wise, as you will be maintaining % distribution rule (12%) but your objective to get the report is like distribute 2 line items(actual) cost to FX1, 1 line item cost to FX2 and so on..
    For that,It will be more appropriate to maintain settlement by 'Amount' also.
    Now,for development of this report, it is actually very difficult because we lose the track of line item details (VT 4) when we reach at settlement (WBS->AUC) ,as we have only the total cost only to be adjusted/distributed and it goes the same way till FXA.
    Even if a report is to be developed then I can think of some 'Reference Fields' at GRN- > Settlement (AUC) -> Settlement (FXA). All these documents should be posted w.r.t. this reference field and ABAPer has to collect the line item details with this reference field and show in the o/p against an asset number.
    (Development of these formats/screens for running actual transaction in background is a tedious job ) And obviously that would be applicable for new projects (new GRNs) only.
    For existing one, it looks near to impossible to me.You can have few words with ABAPer to discuss on it.
    Regards
    Saurabh

  • How to track the corresponding CWIP and Asset after settlement in reports

    Dear gurus,
    We are trying to develop a single report which would have commitments, actual costs, Auc amounts and Final Asset postings w.r.t a project or WBS element.
    What is the table where we can find AuC amount and CWIP number for given WBS elements. Similarly where can we find the Final Asset number corresponding to the WBS element.
    Is there any way we can work around the settlement rules.. Is there any table where the settlement rules are saved??
    Pls guide..
    Thank you
    KAP

    Prafulla wrote:
    we are mentaining few envs where all the envs get refreshed from the same baseload.But due to some reasons in a particular QA env after some time of the db refresh due to some test script execution or from the application, some data are getting deleted .Is there any method to trace the time and the content of the change and send an alert automatically without using trigger, I mean is there any audit method so that we can enble and check and also send the alert.And if possible ,Can any one let me know the details how to send mail from Oracle.
    Code instrumentation?
    As for e-mail - come on! This forum is littered with questions and answers about sending e-mail from Oracle. How about using the search button?

  • Agent Commission Payment via Rebate settlement or any other

    Hi Gurus,
    In our scenario: My client business is 90% through Agents (i.e both Domestic and Exports).
    Client wants to settle the commission 1. immediately after the invoice 2. monthly 3. quarterly.
    Could you please throw light immediately to address this issue.
    As per SDN -  I have configured FA as a partner function to the Customer. But the rebate agreement will be settled with customer. But how to settle that directly to the Agent.
    Through VA05 list the sales orders per the FA and settle it manually or
    Credit memo request to the amount (%) per each and every sales order.
    Please respond to this ...
    Thanks in Advance
    Cheers
    Srikanth

    Hi Gurus,
    Could anybody explore further with details.
    Regards
    Srikanth

  • How can I firce procurement Card settlement in SRM 7.0?

    Hello,
    We are moving from SRM 5.0 to SRM 7.0, and I would like to understand if there is a way to force items to be settled to a procurement card in 7.0 (using an external cataog aggregator). Currently, in 5.0, we have a "P" appended to the end of a product category when they come from the catalog if they are forced to be settled to a procurement card. This means we also have to maintain all product categories twice (once with a P and once without) in COMM_HIERARCHY. we have a BADI in place to force the pro card selection if the product category ends with a "P".
    Is there an easier way in SRM 7.0? We want to replice PO's back to ECC but do not want to have to maintain all product categories twice in both environments!
    Thanks in advance for any help!
    -Eric

    Masa,
    Can you please provide more details on this for me? Is the "Customer Field" the supplier, because we would like to be able to have different settlement methods for each supplier in some cases, because it will be possible to procure items from a supplier for MRO items and settle them to a work order and cost center, while still procuring from that same supplier for non maintenance items that will be paid for with a procurement card.
    Thanks - Eric

  • Report on settlement profile/rule for the Process Orders ?

    Is there any report which will display settlement profile for process order or settlement rule for process order.

    Hi,
    Did you try this one: KOSRLIST_OR - Settlement Rules?
    Regards,
    Eli

  • Report for Settled production orders

    Hi All,
    Is there a report I can use to show that these production orders are settled and these production orders need settlement. any clue on this. and when I ran the settlement does it chnages the production order status to reflect that it is settled ?
    Thanks
    MKR

    Hi MKR,
    Please go to COOIS,
    Give the plant and give the status of the order that u want to ge the list.
    then execute.
    System will give you all the production Orders which are having the particular status.
    Hope this will answer your query
    Best Regards
    Surya

  • Production order with negative amount for settlement in to Material for MAP

    Hi All,
    When I am trying to settle some production orders, it is giving me an error "Moving average price for material is negative" and doesnot let me settle them. we have maintained our materials at MAP and settle our production order variances to material to adjust its MAP. In these orders, it is trying to settle negative value, which is greater than the total value of the stock of materials and if settled leaving some of the stock with negative value. does any body has this situation and what would be the solution for this ?
    Thanks
    MKR

    Hi,
    This is Pavan Fronm IBGroup Rajnandgaon.
    To My Knowledge,
    When U Settle the Production Order, the Diffence Between the Target cost and Actual cost(MAP) of Finished Material hits the Material Account of the finished goods.
    Say Suppose,
    Target cost (Production Cost) =   Cost of Raw material + consumable,   =  10
                                                    Activity ( Labour, Power, etc)              =    5
                                                    Overheads.                                        =    2
                                                                                    17
    Actual Cost is ur Finished Material (MAP). = 18
    CASE 1:
    Now the system calculate the difference as 17 - 18 = -1 Rs , it try to reduce from Material Cost,
    Now in case if Material has the stock say 1 unit.
    it will reduce the cost of material by 1 rs in Material Master.
    If the Material has no stock , as we know the system try to reduce the cost from zero stock tends to
    give us a message saying
    MOVING AVERAGE PRICE OF MATERIAL IS NEGATIVE.
    CASE 2:
    If Target - Actual is say +1 RS it increases the material price to 1 Rupee, if stock is Zero , then 1 Rupee
    hits the Price Difference
    CASE 3: *STANDARD PRICE INDICATOR*
    In case of Standard Price indicator Every thing beyone the Material Price , whether respect to negative
    variance  or positive variance hits the price difference.
    So I request u to settle the order if u use MAP for Finished goods befor dispatch of finished good to calculate actual production cost for ur finished material..
    We can Also use MR21 for price change if the stock has dispatched befor settlement, but it is not suggestable to my knowledge hence ur material wont carry actual production cost if that is thae case.
    Please Correct if I m Wrong.
    Regards
    J .K .PAVAN KUMAR
    SAP PP-PI Consultant
    Edited by: PAVANIDLUR on Mar 30, 2009 9:05 PM
    Edited by: PAVANIDLUR on Mar 30, 2009 9:09 PM
    Edited by: PAVANIDLUR on Mar 30, 2009 9:11 PM

Maybe you are looking for

  • Document and form

    Dear All, How to copy one screen layout especially document's layout to another user using query or SP ? is it possible ? I appreciate your answer. TIA Rajh

  • Is it possible to download a split track accompaniment CD onto an iMac and play it back without the voices?

    Does anyone know if it is possible to download an split track accompaniment cd to the iMac and then play it back and tune the voice track out?

  • DW CS3 Insert Record/Update Record: Record Form Wizard Error

    I have just bought Dreamweaver CS3 and I am running into some problems. I also have Dreamweaver MX 2004. When I use the Insert Record: Record Insertion Form Wizard on my Dreamweaver MX 2004 I have no problems using the Insert Record function. However

  • IPod Flashing Screen Of Death?

    I've seen similar topics with this problem, but still no answer. ***? The issue is that my iPod was playing normally, doing everything jsut fine, then all of a sudden it shut off. Figuring that it had just run out of jucie, I plugged it into the wall

  • Oracle Export Error For version 9.2.0.6.0

    I can run an export with owner='my user' however when i set it to run as full =Y i get the following error at the end: . exporting dimensions . exporting post-schema procedural objects and actions EXP-00008: ORACLE error 933 encountered ORA-00933: SQ