PS to xRPM/cProjects integration - phases

Hi all,
We've successfully uploaded a project from PS to xRPM/cProjects but one thing that does not copy over correctly is the phase in cProjects.  After the upload is complete, I look at the cProject structure and the project header is there with all the WBS and network elements created as tasks, but they all reside under a blank phase definition.  How can I configure so that the phase in cProjects is not created?  Or, what do I need to create in PS to populate that phase definition when transferred to cProjects?
Thanks in advance for you help!

Hi all,
I’m working with cProjects 3.1, <b>not installed</b> in CRM Platform. At this moment I have accounting integration, the system create an internal order to collect the costs.
<b><u>My doubt is:</u></b>
If I want to install the cProjects 3.1 in the CRM platform, I’m going to have the PS integration (costs and revenues are collected on the Project WBS), but I’m going to lose the accounting integration (internal order) or not?
It’s possible the multi-object integration (Project and Internal order)?
Thanks,
Alexandra Pires

Similar Messages

  • XRPM-cProjects Integration

    Hi..
    Has anybody got any docs on how cProjects can be integrated with xRPM..how cProjects project can be tranfered in xRPM?
    Thanks,
    Mateen

    My mail ID is [email protected]

  • Diving deep into "Second Integration Phase" error

    Hii,
    During Product master data load through the IBP 4.0.0.1 web UI, I am getting following error -
    Failed to launch second integration phase
    Looking closely into this error I find the error is termed as "Second integration phase"...Can anyone please tell me what exactly happens in this phase of integration? Is there any thing called "First Integration Phase" as well? If yes, what happens in that phase??
    Regards,
    Suprio

    Hi Alecsandra,
    Thanks for sharing this fact. Your response will truly help me in understanding the processing of templates better
    Regard
    Suprio

  • XRPM and cProjects Integration

    Hi!
    Has anybody got any docs on how cProjects can be integrated with xRPM..how cProjects project can be tranfered in xRPM?
    My email address is [email protected]
    Thanks in advance!
    Alex

    Hi,
    yes, the integration is permanent.
    For Example....
    During transfer of work centers from Project System to xRPM, teams are created in xRPM for each of the work centre being transferred to xRPM. One can do this from SAP PLM PS by running the report RPM_WRKCNTR_UPLOAD,
    which transfers work centers to SAP xRPM and uses them to create team master data. The team name in xRPM is generated using a combination of plant and work center, because the work center ID is only unique within a plant and can be used again in a different plant.
    The resources assigned to the work center are used to create the resources assigned to teams in SAP xRPM. The employee IDs of resources in SAP PLM PS are used to search for business partners in SAP xRPM with identicalemployee IDs.
    If a match is found, the business partner is added to theteam.
    If the SAP PLM PS work center is created using organization units, the employees in the organization unit are derived during the transfer of the work center and used as the basis for creating teams. If new employees are added to the organization after you have run the report, these employees are not included in SAP xRPM system unless you run the program again. For
    this reason, you should run the program regularly (for example, weekly) or schedule it for background.
    Hope it helps you.
    Thanks
    Arbind

  • Cproject Integration with BW ( Querys )

    Hi gurus,
    In Cproject i could get detailed information of a particular project by the status Report, but as i mentioned it´s only for a particular project.
    I´m testing with  BW integration but i´m dealing with some problems.
    When i execute a standard querys eg. 0CPR_C01_Q0006, i get incomplete information because the phase and the task of every proyect are with '000000000000000000000' (empty), but the project name / description / responsible resource appears.
    Can anybody help me with this?
    Thanks for all.
    Regards,
    Diego

    Hi Diego,
                  I am interested in BW integration with cProjects. But as of now i dont have much understanding on how it is working. Can you explain the way it is working. I am not able to find anything related to this. What is the transaction code to view/execute the queries available.
    regards,
    rajesh.

  • XPD and cProjects integration

    Hi All,
    We are implementing xPD 2.0 and cProjects 4.0.
    The scenario of integrating the two is that, in the concept stage, a project in cProject will be created from xPD.
    The master guide of xPD 2.0 states that "<i>You can connect additional back-end systems, such as SAP cProjects, to the SAP xPD landscape using SAP Exchange Infrastructure</i>". But this requirement is not mentioned any where else in the other documents.
    Will somebody be able to highlight on this requirement?
    Any inputs will be highly appreciated.
    Regards
    Amitabh

    Hi
    Try the install guides or xPD and cProjects
    http:// service.sap.com/instguides
    xPD >> SAP xApps
    install guide page 73
    Config guide page 9
    cProjects >> mySAP business suite apps > mySAP PLM
    again check both guides.
    cheers Jo

  • WF - cProjects (Approval Phase)

    Hi all !!!
    I'd like to know what is the number from WF about Approval Phase in cProjects ? The customizing is done and all WF are active. But, when I start the approval, the Standard WF should start and send a email to the responsible (Decision Marker).
    If you can help me, I will appreciate so much !!!
    With best regards,
    Milena

    You can have a look at the configuration guide where is described a Workflow example WS28700001 that sends an email, if a task will be released. (STatus)
    Here exchange it with the Business Object BUS2173 instead of BUS 2175 (TASK) for the phase and reacte on status event Phase.ForApproval

  • CProjects integration with R/3 HR issue

    Dear All,
    We are replicating the HR details to cProjects (CRM) system.
    The replication was happening fine and while the employees(resources) getting replicated to the cProjects system, a Business Partner (BP) number will get generated automatically for each and every employee.
    All of a sudden, we have got an issue.
    While the details are getting replicated to the cProjects system, but the BP number is not getting generated, the BP number is blank.
    FYI: We have not done any changes to the cProjects system recently.
    Will really appreciate your clues.
    Thanks,
    Vijay Anand

    Hi,
    We did all these settings. Just now we found out issue behind this.
    In r/3 table PA0000 employees with the status 0-withdrawn are not downloaded to crm. In this table status of the employee should be active, then only it will download employees to crm.
    Now the issue is client asking us to download employees who quit the organization.  Please suggest if we need to add any filter to download employees who already quit the organization to crm.
    Becuse there are some relationships existed for these employees earlier. When we try to download relationships from r/3 all bdocs are comming to crm and sitting in queues. Showing error. If we can download the employees who left the organization our issue with relationships also got solved.
    Regards,
    Madhu.

  • CProject integration with MS Project

    Hi,
    Bascially can we upload MPP file directly to cProjects, if so what are the settings that we need to do.Do you have any documents which provide this information.
    Normally i heard that MPP files gets converted into XML and this file is generally upload and direct upload from MPP file is not supported, is this correct.
    Regards,
    Srikanth ( [email protected])

    Hi Rehman,
    Thanks for your response, i will wait for your documents.
    I have following questions and here is the business scenario.
    customer download cProjects to MSProject.
    now if he uploads same MSProject to cProject , it will result in simulation version
    can we bypass this simulation version and update directly to operational version.
    is it possible to provide your contact number to discuss this requirement.
    Regards,
    srikanth.([email protected]).

  • XRPM, cProjects and Project Systems link in BI

    Hi Guys,
    We are implementing a RPM solution in our BI 7.0 system. We have a requirement where we need to link RPM data with cProjects(Project, Task) and Projects Systems (Status, WBS Elements, so on) data.
    Could some one give me the links/documents related to linking the above objects.
    Thanks in advance
    Srinivas.

    Hi Neelam:
    Check Project system tables like PROJ etc and create a View for the fields you want.
    Use this View as your datasource to extract data.
    Thanks,
    Jagadish B V

  • CProjects: Include Phase does not copy "Responsible Role"

    We have several hundred projects where we want to add a complete new phase which contains 20-30 tasks. Rather than manually add each of these tasks, I want to use the 'Include' functionality to copy the phase from a template, which works to a degree.
    However, the responsible role is not transferred over.
    When a reference to a checklist is used, you get the choice to import all the roles associated with the checklist or to try and match to the existing project roles, but this functionality is not available when using 'Include'.
    The documentation makes not reference to role resolution using this functionality.
    Does anybody have any ideas how I could achieve this using standard functionality?

    Did any one else come across the same issue and have fixed it ? , I am facing this problem and would need a solution or work around. Please let me know.
    Thanks
    Pugazh
    [email protected]

  • XRPM cProjects how import HR absences

    Hi Gurus,
    My problem is: how to import from SAP HR not only Planned Time data (IT0007 - work schedule), but also the absences (IT2001).
    I generally use both RPM_TIME filter through PFAL transaction and by RPM_TIME01 (launched through se38).
    Then I verify time data in RPM / cProjects through the transaction rpm_empdata, where the bp availability is recorded.
    I read that RPM_TIME also imports to RPM the absences, but actually I'm not able to check them.
    Thank you!

    Hi Ema,
    BAdI 'RPM_PROCESS_DATA' can be used for processing IDoc for availability and absence information. This BAdI is processed when iDocs of message type RPM_TIME are posted. Here one can modify the Availability IDoc as per the Absence IDoc to reflect the correct availability. The Absence records needs to be processed by custom coding as per your requirements. Standard code is not available for absence, as there is no specific table for absences all data is reflected in RPM_BUPA_AVL.                                                                               
    The method to be implemented is 'PROCESS_DATA'. The method has availability and absence infotypes as importing parameters and ET_CUST_TIMEDATA as exporting parameter, which will contain the resulting availability.                                                        
    I hope this helps.
    Best regards,
    Silvia

  • General Info on integration between Project Systems (PS) and cProjects

    Hi,
    I would like some general info on the integration scenarios between PS and cProjects. Links to any documentation/blogs on this would also be very helpful.
    Thanks,
    Lashan

    Hi Srini,
    Thanks very much for the links. However, I've already gone through the standard documentation in SAP and they are a bit too high level/vague for me. I have considerable experience in xRPM, cProjects Suite and have good grasp of project management concepts, tool and techniques. My knowledge of PS is somewhat limited though.
    What I am specifically looking for is what type integration options and scenarios are available. For example, cProjects can have phases and tasks defined. How would these integrate with for example WBS elements and networks in PS? What are the things you would do in cProjects and not PS and vice versa? Hope my question is clearer now.
    Appreciate any further information you may have on the above.
    Thanks,
    Lashan

  • XRPM 2.0 - cProject Object Link

    Hi all,
    I am using xRPM 2.0
    SPRO Path: SAP xApp Resource and Portfolio Management (SAP xRPM) -> Base System Interfaces -> SAP cProjects Integration -> Define Business Object Links for SAP cProjects
    Within this the following object types do not have any values maintained for Internal Key, External Key, Search Fields, Result Fields and Proxy Class.
    Object Types are: 0CPCHECKLIST, 0CPCHECKLISTITM, 0CPPHASE, 0CPPROJECT, 0CPRESOURCE
    0CPROLE and 0CPTASK
    Can someone pl post in the values in these fields.
    Regards,
    Reema Shahbazkar

    found sol

  • CProjects - DMS integration:26 036 You are not authorized for with doc.type

    Hi Experts,
    I need to use cProjects integration with DMS. When I try to create a link to an existing document I find the following error:
    26 036 You are not authorized for with document type DRW
    My user has authorization to the doc type in the DMS system (linked by RFC to cProjects system). I also have defined the object link in the document type.
    Do you know which configuration may be missing?
    Thanks in advance!
    Neil

    Hi Niel,
    How is the RFC connection established between DMS and cProjects system? Do check the authorizations of the RFC user through which the connection is established.
    Regards,
    Vivek Pandey