Hi Sagarika,
The answer to this and you other questions about work schedules would be answered if you took the SAP HR306 course. Work schedules, holiday calendars and quotas are all covered in that course. It is necessary if you are to properly set up work schedules for your organization.
Here the "earliest day and month" refer to the earliest the holiday can occur. For Thanksgiving, for example, the earliest it can be celebrated is the first Thursday in November after November 22nd. Another example is Martin Luther King Day which is the first Monday in January after January 15th.
This differs from holidays which are a fixed date each year - July 4th, December 25th, January 1st, etc. These can be "guaranteed" so they can be celebrated on the work day before if they fall on a Saturday or on the work day after if they fall on a Sunday.
Again, all this guidance is available to you in HR306.
Paul
Similar Messages
-
Public Holiday calendar not to be taken into account for Sick Leave
Dear All,
I need help.
Public Holiday calendar not to be taken into account for Sick Leave.
Eg -When I employee applies for sick leave, the public holiday in between the dates shouldnt be considered. How can I configure this requirement.
Please help.
Regards,
PoornimaFor that group, you need 2 counting rules:
- one for Holiday Class 0 (not a public holiday) and Day Work Schedule Class 0 (not a working day)
- one for Holiday Class 0 (not a public holiday) and Day Work Schedule Class 1 to 9 (a working day)
If you want, you can add an other one or two for Holiday Class 1 to 9 (public holiday)
extract from our T556C
2 1 10 Q 10 Sick leave deduct from quotas (incl personal/spec) XXXXX X X XXXXXXXXXX XXXXXXXXX X X XX XX 100.00 100.00 1 1 10
2 1 10 Q 11 Sick leave deduct from quotas (incl personal/spec) XXXXX X X XXXXXXXXXX X X X XX XX 0.00 0.00 1 1 10
2 1 30 Q 10 Special leave with pay (with quotas deduction) XXXXX X X XXXXXXXXXX XXXXXXXXX X X XX XX 100.00 100.00 1 1 30
2 1 30 Q 11 Special leave with pay (with quotas deduction) XXXXX X X XXXXXXXXXX X X X XX XX 0.00 0.00 1 1 30 -
Error while accessing public holiday calendar
Friends,
Well when creating a work schedule for the year 2008 (practice mode - at home) i am getting the below message..
I checked all the configurations and no where i mention about 2009. Any tips and suggestions.
Error while accessing public holiday calendar
The function module HOLIDAY_CHECK_AND_GET)INFO has generated an errorfriends the problem still exists..
i created a new calender, new dws, pws, bws.. but again the same error comes in play.
Friends,
Well when creating a work schedule for the year 2008 (practice mode - at home) i am getting the below message..
I checked all the configurations and no where i mention about 2009. Any tips and suggestions.
Error while accessing public holiday calendar on 20090101
The function module HOLIDAY_CHECK_AND_GET)INFO has generated an error -
Error while accessing public holiday calendar on 20120101
Dear All,
When I'm posting PL(Personnel Leave) against 31.12.2011 it is working fine but If I'm posting a Sick Leave against 31.12.2011 or CB the error is coming like "Error while accessing public holiday calendar on 20120101".
Please suggest what to do.Dear All,
When I'm posting PL(Personnel Leave) against 31.12.2011
it is working fine but If I'm posting a Sick Leave against 31.12.2011 or
CB the error is coming like "Error while accessing public holiday calendar on 20120101".
Please suggest what to do.
the error clearly saying that you dont have holiday calendar for 01.01.2012,, so please change it using PT02 to avoid the error.
then you check what exactly system is doing.
you have to create a wsr with one month extra validity than the exact periods required to avoid the future errors as you are getting now.
system always takes one month extra validity it is standard functionality.
regards,
mohammed -
Error while accessing public holiday calendar on 20100101
Dear Gurus.
When i was created Work Schedule TC-PT01
Error Showing
"Error while accessing public holiday calendar on 20100101"
Message no. P2518
Diagnosis
The function module HOLIDAY_CHECK_AND_GET_INFO has generated an error.
Please Advised
Regards
MHPOHi
As Surisetti told that, that public holiday might not created in that year. So check the same in SCAL and again re-generate the work schedule.
Thanks & Regards
Bharathi -
Assign Personnel subarea to Public holiday calendar
Hi experts!
Now I'm meeting issue about Assigning Personnel subarea to Public holiday calendar.
I have Personnel subarea is SAP. But in screen of Assign Personnel subarea to public holiday calendar, I don't see Personnel subarea is SAP. Why?
Help me!
Regards, Huy.Dear you!
I processed the issue. Actually I only need access Enterprise Structure in IMG. Check again in part Assignment --> Human Resources Management --> Assignment of Personnel Area to Company Code.
Thank you very much about Your Helping.
Regards Huy. -
Problem in maintaining Public Holiday Calendar
Dear All,
I have to maintain Public Holiday Calendar for 2009. For that I have maintained the holiday dates in Change Public Holidays. Please guide me as to how do I assign these holidays which I have maintained to Public Holiday Calendars being used in different PSA's?
Thanks and Regards,
Kanupriyahi,
for appearing in the holiday calendar of 2009, the Validity year of ur holiday calendar should contain the year 2009. say,
Valid Fr.year 2008
To year 2010
For the day to be a OFF day u have to re-generate the existing work schedule as i mentioned earlier. Only then the new holidays assigned to ur holiday calendar will be taken by the Work Schedule.
U must give the same Holiday class to ur new holidays (Same that u used to create ur earlier holidays to avoid confusions......)
Regards
kiran -
How to tranport the public holiday calendar?
Hi,
Now I have chage a public holiday calendar, but I find I can't tranport this change to another system.
In the initial screen of the public holiday calendar, the "Calendar -> Transport" button is gray. I don't know why? if have another place to be set?
thanks~Hi,
After creation public holidays and holiday calendar and factory calendar, a small "Truck" icon in tcode SCAL , then select publc holidays click on the truck button, again select holiday calendar click on truck button, select the factory calendar click on truck button, when you are clicking the transport it will ask the workbench request not customizing request, create the workbench request TP.
After creation of TP, I think you know all the procedure(release the TP)
Hope this helps.
Warm Regards,
Devi -
Public Holiday Calendar on ESS
Hi
Is there any configuration to show the public holidays on ESS. The Calender overview somehow does not show the public holiday calendar.
Or it has to be shown using a new (customized) iview?
Regards
YashHi Yash,
We used the method TEAM_CALE_ENRICHMENT of badi PT_ABS_REQ for adding weekends and holidays to the teamcalendar. And we made an enhancement in routine COLORIZE_EECALE (include LPT_ARQ_REQUEST_UIAF11) to add holidays and weekends to the employee calendar.
Kind Regards,
Igor -
Creation of Public Holiday Calendar !!
Dear Experts/Gurus,
I know to create a holiday calendar but my query is what is the advantage in creating a Public Holiday with Fixed date and Floating Public holiday.
I want to know what is the advantage & disadvantes using 1) Fixed date and 2) Floating Public holiday. Please let me know asap.
Rgds,
VikrantHi,
Holidays which fall on a fixed day of any year will be defined as Fixed public Holidays (Ex:- Independence Day, Republic day, Christmas etc) whereas holidays for which no fixed day is allocated is defined as a Floating Holiday (Ex:- Ramzan, Dusheera, Diwali etc)
Such a provision is made because we can define a holiday calender for a number of years. As a fixed holiday is always present we can assign it for the entire period (as long as the holiday calender is valid)
The floating hilidays need to be defined for a particular year
Hope this helps
Regards
Raghu -
IPhone-MobileMe Public Holidays Calendar Sync
I have a new iPhone 3G and a Mobile Me account. All of my MM calendars sync fine except for the Public Holidays (I cannot view the holidays on the iPhone). Any solutions?
Syncing subscribed calendars will be supported with firmware update 3.0 to be released this summer.
I did the following with my subscribed holidays calendar. Using iCal on my Mac, I exported the subscribed Holidays calendar. I followed this by importing the calendar export as a new non-subscribed calendar in iCal. -
Maintennace of public Holiday Calendar and Work Schedules
Dear All,
Can the access to maintain Holiday Calendar and Generation Of Workschedule be Given to Users in Production Server.If No why?
Thanks,
Punam JhaHi Poonam
The access to maintain holiday calendar and generation of wrk schedules could be given to either personnel adminsitrator or time administrator with appropriate authorizations...normally one or 2 power used would be given access like you have mentioned.
cheers
sangeetha -
Public Holiday text not displaying in PT03 (Special Days)
Hi Experts,
For my client, I have to configure a public holiday and restrict it to only few WSRs. This public holiday is not part of any public holiday calendar. I have configured this holiday as a special day by defining the day type selection rule & special day.
When I checked the work schedule in PT03, it is not displaying the holiday class and the text of the public holiday. It is only displaying the day type for this day.
Please help.
Many Thanks for your help in advance.
Warm Rgds,
Arun.MqPane = new JScrollPane(qTextArea);
qPane.add(qTextArea);
performedOpsPane = new JScrollPane(performedOpsTextArea);
performedOpsPane.add(performedOpsTextArea);
logPane = new JScrollPane();
logPane.add(logTextArea); When you create a scrolled component, you either pass the component to the JScrollPane constructor or add it afterward, not both. If you're going to add it afterward, you use the setViewportView() method, not add(). -
Notes to be implemenented after Factory and holiday calendar are extended.
Hi All,
Since most of SAP Factory and Holiday Calendar used had Validity date that ends on 12/31/2010 we have extended them till 2020.
This was done manually using SAP note 1529469 and 501670.
We have also implemented SAP Note 1532398 to avoid jobs going to dump that are running to deleted old spool request in SAP.
We would like to know if there are any other note to be implemented in our SAP production system as a part of year end activity related to Factory and holiday Calendar.
We could find the below note under 1532398
1534735 - Job terminates with error message BT 518
1532398 - Spool requests are no longer deleted as of beginning of year
574628 - Change calendar dates in production system
538344 - Transporting calendar dates
501670 - Public Holiday Calendar Creation/Change
1529649 - Factory Calendar expires 2010
ThanksHi
I suppose the notes 1529649 - Factory Calendar expires 2010 and 501670 - Public Holiday Calendar Creation/Change are sufficient for the extensions.
I don't any extra tasks are involved during the year end activity as far as factory / holiday calendar is concerned. -
Hi all,
I need your suggestion to solve this issue related to public holiday calendars. Jul 4th(paid) is a public holiday and that has been assigned as a fixed day/date when created. In the calendar where it is used, the validity dates have been given as 2004-2005 and it was not used for the year 2006. Instead some other name was used (unpaid). Now, I need to assign the July 4th (paid) public holiday to the same calendar.
When I go in to assign holiday, it does not show the July 4th (paid) holiday to be reassigned. The overall validity of the calendar is till 2007.
July 4th - 2004 - 2005
- I need to assign this to 2007 again
Please advise.
Reward points will be given.
ChrisI've been arguing this issue with SAP for a long time. We have the same problem only ours is more complex because we have over 20 sites and in any given year a site may or may not take a particular holiday. As a result, we ended up creating a separate holiday for each site (i.e. 20 4th of Julys).
Prior to 4.6c it was possible to assign the same holiday more than once. In 4.6c SAP changed transaction SCAL so that it is no longer possible. The problem is with the transaction itself. You can modify table THCOD directly using SE16 and everything (time,payroll, etc) will work fine but then transaction SCAL will abend. What we want to do should be possible since the end year is a key field.
Marvin
Maybe you are looking for
-
You must register your tables using JDDI before you request them
Hey Guys.... I'm trying to query a custom table created on a SQL Server 2005 database, the same RDBMS for the SAP Web AS. I'm using a different database from the sytem's standard. I created a Datasource for it. I can get the connection, but when I ex
-
I need help, How do I take my credit card information off and put none payment And how do that by my iphone. With out using a computer. Because when I use my credit card and I know I have money on it It says decline so I wanna take that off so I can
-
Line Items in Sales Order not Replicated
Hi 1. We created an order in CRM with 10 line items ( all are same service items) and this order is replicated to R/3. 2. We added to the same order 5 more same line items and saved but thid items are not replicted. Please suugest me how to trance it
-
How to open PageMaker files in InDesign?
It seems that this possibillity is taken away although it is told in the helpfile that it is possible. You can´t chose PM file type in Open files.
-
Problem with OOPS ALv-field editable
hi experts, I am displaying one report using OOPS ALV. Now i am inserting a line in the output, so some mandatory fields are automatically filled up in the new line, and i am trying to fill new values for the remaining empty fields, So init