Purchase order for project

Hello together,
We have a one senerio. At my client end no. of project is going on. We do not have sales order for the project parts. Presently we are creating purchase order with acct.assignment P ( WBS Element ) but our mamangement asking me to have the stock of the material purchased against WBS element. But it is not possible the combination of WBS element with storage location.
How can i create PO where no WBS element but i could get the stock of the material
Is there any work around?
Thanks in advance.
Shailesh

Hi
If you are procuring the material with P as account assignment , after the GR is odne the Material will be consumed & accounted for the Project & the material will not be displayed as Project stock in Stock overview
If you procuring a stock material & doing the GR then the Material will be in unrestricted use stock.
Then You can carry a transfer posting with Movement type 412 special stock indicator as Q, This will post the material from unrestricted use to Project Stock.
Thanks & Regards
Kishore

Similar Messages

  • How to create a purchase order for a purchase requisition

    Dear Experts,
       Explain the steps for creating purchase order for a purchase requisition.
    and where can i find this purchase requisition field in PO creation.

    Hi Ravi,
    Check out these documents:
    http://www.olemiss.edu/projects/sap/MM_Create_PO_with_Ref_to_a_PR.pdf
    http://www.sap.com/africa/services/education/pdf/Work_Instruction.pdf
    Regards,
    Chandra Sekhar

  • Purchase order for external service

    Dear experts,
    I tried creating a purchase order for a service, with account assignment unknown U, with item category D, but after entering the item details in the item overview, it keep saying " ACCOUNT ASSIGNMENT UNKNOWN NOT ALLOWED WITHOUT GOOD RECEIPT", i would like to know why this message is coming up, and how to rectify it, thanks for your anticipated contribution

    Hi,
    You can not use Account assignment unknown U in the creation of service order as system need a cost object with a G/L account during saving of service order which help system to post to required G/L account automatically on further transaction MIGO & MIRO posting.
    You can create contract(ME31) with   Account assignment unknown U & item category D as you do not know from which account or cost object specific  the contract going to be used,so as the contract can be used for all department/cost center./project related in future.And then you can create a release order/call off/service order(ME21N)  with Account assignment unknown K(in case of cost center) & item category D wrt contract  with entering all likes cost object u2013 cost center  , G/L account related with other input data.
    Check any user exit which not allow to create with  Account assignment unknown U & item category D.
    NOTE: if you create service order  with  Account assignment unknown U & item category D,then during SES, you need to enter cost object ( K or P or C  etc) with a G/L account.
    Regards,
    Biju K

  • Need to Track Purchasing Cost for Project without attaching to PO ?

    Hello Guys,
    Can any one Help me on this Question,
    Iam raising a genric Purchase Order for materials without attaching the Project/Task,But I use Materials for many Projects ? How do I track Cost for Materials utilized for a Projects ?
    Regards,
    Satish

    Hi
    If you are purchasing goods for inventory you can get your requirement.
    Receive the goods into the inventory.
    Later on, you can issue items from inventory to any project, and that transaction will be collected into Oracle Projects as expenditure items on the receiving project.
    you may want to review Oracle Projects Implementation Guide, and look for the section - Implementing Oracle Inventory for Projects Integration.
    Dina

  • Report to view pending Purchase Order for Release

    Hi,
    Is there any sap standard report through which we can view pending Purchase Order for Release.
    Regards,

    Hi,
    you can use transaction ME28, this can give information of pending purchase order for release on release level.
    but this transaction is used for releasing the collective release for purchase order. this is not an report.
    if you want transaction for reporting purpose only, you need to create a report or query on EKKO table. based on release indicator.
    vikas,

  • Production order overlapping with purchase orders for outside process

    I set up the overlap option in a router so we can send 50 pieces (total order quantity is 200) of material ahead to an outside heat treat operation.  When we try to create the purchase order for the 50 to be sent out for heat treat two problems occur.
    1. The quatity in the purchase order is for the entire order of 200, not 50.
    2. We get a message "Date /23/2010 period D is not valid.
    We currently do not use the functionality of splits and overlaps so if anyone can help or guide me to a good resource I would appreciate it.
    Regards.
    Gail
    Edited by: Gail Weeks on Nov 12, 2010 4:19 PM
    If anyone could help with this question I'd appreciate it. Thanks.

    Gail:
    the next operation would be an external operation in your order ? That is, has some external Operation Control Key?
    Then the PurReq for this operation is created at creation or release of the production order by the total operation quantity. Ovelapping allows you to reduce some total time in order, but I don think that can be applied for the purpose you describe. Let us know more details about your requirement.
    Regards

  • Creating a Purchase Order for the Asset

    Hi,
    Please see the following steps:
    1.Create a purchase order for the asset.
    2. Post a goods receipt from this PO.
    3. Quantity of asset will be transfered from goods receipt.
    But I find quantity of asset(AS02) was not be transfered and still was equal to 0.
    Could you help me?
    Thanks and Regards,
    Colin.

    see the field status varient for the gl account see the qty field is optional field or not
    and check in the asset group also qty field is the optional field
    Assign point if useful
    Regards
    A.k

  • Purchase order for services

    When creating a purchase order for services, I am entering services lines in the SERVICES TAB, I would like to structure the services in the service specification into a hierarchy of outline levels. How I can do this? How can I activate the Service Specification outline ?
    Thanks

    Hello,
    You can use an outline only in t the 'Full Screen: service'. In the Services full screen, you can choose 'Outline On/Off' to show and hide the service overview. You ser the width of the service overview as desired and when entering the transaction, system displays the settings selected before leaving the transaction.
    If you select an outline level, the data area of the services displays the relevant service lines. You can choose 'Services' to display at outline level whether service line exist at outline level.
    Regards,

  • SMBLN filed blank in case of service Purchase order for MSEG

    Hi expert
    SMBLN (Number of Material Document) filed blank in case of service Purchase order for MSEG.
    if i check for normal  po i get my number for which i have doing reverse.
    Case example
    when i check in mseg for Mvt 106  Material Docu No , in the field SMBLN i get for the  Material Docu No of 105 for normal PO.
    when i check in mseg for Mvt 102  Material Docu No , in the field SMBLN i dont get for the  Material Docu No of 105 for Servicel PO
    Regard
    Nabil
    Edited by: sayednabil on Apr 11, 2011 11:50 AM

    Hello andrewjkasten, 
    It's good to hear from you again, although I truly wish it were to share a more pleasant experience than when we previously conversed. It is always great to keep an eye on sales however you can so you don't miss them! I'm sorry to hear a technical issue may have caused your order to not reach our systems and missing out on a great sale price! 
    Using the information you registered with the forum, I've sadly been unable to locate your computer order. With that said, I would like to look further into this and am sending you a private message to gather the necessary information. I look forward to your correspondence! 
    Respectfully, 
    Tasha|Social Media Specialist | Best Buy® Corporate
     Private Message

  • Delivery completed indicator in purchase order for service item

    How can I make the delivery completed indicator (EKPO-ELIKZ) in a purchase order for a service item ready for direct changes.
    Per default this field is hidden on purpose for service items (according to SAP note 735404). Please inform me of customizing entry where that can be changed!
    Thanks,
    Johnny

    delivery completed indicator only gives information for MRP ( That not consider balance qty as onorder stock), it has no control on GR, so I am not sure what you will achieve to mark it in service PO?

  • Transfer of tax indicator to purchase order for service items in shopping cart

    Hi all.
    I have a problem with the tax indicator in the shopping carts and in the backend purchase orders for service items. If I create a shopping cart with service items with different tax indicators, the backend purchase order have a unique item including all the services. So, all the PO items are under one tax indicator while in the shopping cart there is more than one indicator. I mean, the PO is not correctly replicated with the information of the SC.
    Example: shopping cart in SRM with 3 items, tax codes: V1, V2, V1. The standard code transfers the information to the backend, and creates a purchase order with an unique item with the 3 services under tax code V1. So, the second service is not under the correct tax code, and will be wrongly invoiced.
    We have debugged all the code of the process, and we think it is a standard bug. When you replicate a PO in the backend from a SC in SRM, have you experienced this behaviour, or the service items are grouped in different PO items each one with the correct tax indicator?
    Thanks in advance.

    Hi again...
    I forgot to mention that we have found and applied the note 1822107 (Purchase order: wrong tax code for PO with 2 service items), that fits exactly to our problem. But after testing, it doesn't work.
    Regards.

  • Capital  Import Purchase Order  for  1000000000.0000 Euro

    Dear Sir
              I am creating Capital  Import Purchase Order  for  1000000000.0000 Euro.We have already set  price up to four decimals also in case of Imports.   But Field is not allowing  Purchase Order for that amount, its reducing the price. Maximum field length is 13 Charectar.
    How its possible ?
    Regards
    Manoj

    are you from Microsoft trying to buy Yahoo?
    I dont think that 1 Billion Doller purchase order is standard business that really need to be created as a PO in SAP.
    You just have a technical limitation of the field size.
    You will not only have this issue for the PO. you will get it with the GR and IR  and payment as well.

  • Block purchase order for releasing

    Hi expert,
    is it possible for us to block a PO for release if the item in PO already been blocked ?
    Thank you.
    Regards
    Simonksh

    user11197404 wrote:
    We sent the purchase order for the new license to Oracle on last Friday
    yet to receive the new CSI for the new server .
    can we still move forward with deployment activity and later specify the CSI
    or would that stop us suring the install process if we don't have yet the CSI ?
    Are you asking from a technical or legal standpoint?
    If technical, do you see anything in the installation instructions that mention entering license information? What happens if you try to go ahead and install? What could be the worst that could happen?
    >
    Kindly help me .
    If you have any idea any metaline node pls let me know ..
    Thanks an addvance..
    j2vinod

  • Purchase order for the new license

    We sent the purchase order for the new license to Oracle on last Friday
    yet to receive the new CSI for the new server .
    can we still move forward with deployment activity and later specify the CSI
    or would that stop us suring the install process if we don't have yet the CSI ?
    Kindly help me .
    If you have any idea any metaline node pls let me know ..
    Thanks an addvance..
    j2vinod

    user11197404 wrote:
    We sent the purchase order for the new license to Oracle on last Friday
    yet to receive the new CSI for the new server .
    can we still move forward with deployment activity and later specify the CSI
    or would that stop us suring the install process if we don't have yet the CSI ?
    Are you asking from a technical or legal standpoint?
    If technical, do you see anything in the installation instructions that mention entering license information? What happens if you try to go ahead and install? What could be the worst that could happen?
    >
    Kindly help me .
    If you have any idea any metaline node pls let me know ..
    Thanks an addvance..
    j2vinod

  • Purchase order for KIT item

    Hi,
    my requirement is to raise Purchase order for KIT item.For Example--
    For 1 Kit item A, including 1 table and 4 chairs. Define components (table and chair) for item A by using Bills of Material screen. In Order Management, when user orders 100 item A, system will generate automatically 100 tables and 400 chairs and Ship to customer. Item A does not have Onhand, only its components have Onhand.
    will the oracle purchasing support this KIT purchase concept.
    pl give me suggestions.
    Thanks in Advance,
    regards,
    venkat

    Venkat
    I'm thinking that your requisition from OM will be automatically converted to internal requisition for 100 tables and 400 chairs, based on your setup.
    Would you still need to have 'KIT' setup in procurement?
    The other thing I can think of is, you can use Requisition Templates to help in ordering items on a repetitive basis.
    Let us know what you think.