Purchase order with out PR Reference controlling to control

Dear All
              I wants to control purchase order creation without PR Reference. i want to control this via standard settings is it possible through standard.
Purchase order creation Through PR only. if user enter powithout pr reference it should through the error.any standard setting available for this.
Regards
Kumar.

Dear,
I am giving you step wise details
Step 1.
1. Goto SPRO --> Materials Management --> Purchasing --> Purchase Order --> Define Document Types.
Check the "Field selection Group" of the "Purchase Order Document Type" (optional Step)
2. Enter T-Code OMET.
3."Change View "Functional Authorizations: Purchase Order" : Overview Screen comes up
4. Click on "New Entries"
5. Give 2-digit "Code (01)" and a "Description" for "Functional Authorization".
6. Select the Check Box " Ref. to Purchasre Requisition".
7. Enter the "Field Selection Group from Step 1. in the Field Selction (optional Step)
8. Save and Back
9. Enter T-Code SU3
10. Select "Parameters" TAB
11. In Parameter ID enter EBF
12 In Parameter Value enter the 01
13 Save.
Now when you try to Create a Purchase Order the System will give and Error "You have no authorization to create without reference to another document"
Hope this will Solve the Problem
Regards,
R.Brahmankar

Similar Messages

  • PURCHASE ORDER WITH OUT BAPI_PO_CREATE CAN WE CREATE?

    PURCHASE ORDER WITH OUT calling BAPI_PO_CREATE CAN WE CREATE?
    Don't Post your question with all Caps. Follow the Rules of Engagement
    Edited by: Vijay Babu Dudla on Apr 23, 2009 1:46 AM

    [Create Purchase order with program|can we create purchase order through report programming?]
    Plz be clear about your requirement instead of posting questions like these.
    Don't violate forum rules with Duplicate posts

  • Can we recieve goods for purchase order with out material master data in PO

    I have service PR for doing the services. I will  give the material which is not accounted ( no material in the PO)and raise PO with reference to production order. but once the service is done,that product will become a  material ( master data available) I have to receive the  final product.Can we do the GR for this product. If so ,could you please explain the scenario

    Hi Sankarkumar
    When you are issuing the material for servicing your existing inventory for the material  will be affected how you are plannignto handle that? You are receiving a different material once the serviceing is done then again yoour inventory will be affected for the new material.  If you do not intend to issue material in SAP then why are you worried when you are bringing the new material into SAP after servicing is over?  It is a subcontract scenario in a normal situation. But since you do not want then you can do a Service PO from the reqn and later use receipt without PO for bringing material in. Just speak to your finance guys how to set right the debit/credit amount resulted due to this transaction.
    Regards
    Sam

  • Purchase order with reference to Sales Order

    Dear SAP Gurus,
    I want to create a Purchase Order with reference to sales order.
    I want to take the material in my stocks also. If i create a Purchase order with account assignment, i am able to take the inventory of that material as it is consumed at the time of GR (MIGO).
    hope you understand my requirement.
    Ashish

    Hi
    Go to SPRO->Logistic general->Tax on goods movement->India->Movement types.
    Here you will find the group of movement types check which movement types is mantained for the out side movement groups or inward movement.
    also check the Material Master in MRP view if the collective requirements (02) is mantained.
    Regards
    Sri

  • Purchase Order with Sales Order Reference

    Hi Gurus,
    I have created a Purchase Order with reference to Sales Order.Now when I post Goods Receipt Mvt 101 system throws a message Update Control of Movement Type is incorrect.
    I have checked in customizing Transaction (OMJJ) cannot find settings related to this particular scenario.Can anyone suggest where I can update control for posting Goods Receipt for this purchase order.

    Hi, Check in OMJJ ,select Movement type>101
    Here click Update control / WM movement types on the left side , maintain the entries with the 101,
    Movement type indicator -B - Goods movement for purchase order

  • Create purchase order with reference to Sales order Line item

    Hi All,
    i had a requirement that i need to create the Purchase order with reference to sales order line item...
    In T.code me27 client requied a input field for sales order no and with that order reference he want the data of line item to PO creation line item screen.....
    please sujjust......how to proceed......
    regards,
    Ravi Nemani

    Hi
    Go to SPRO->Logistic general->Tax on goods movement->India->Movement types.
    Here you will find the group of movement types check which movement types is mantained for the out side movement groups or inward movement.
    also check the Material Master in MRP view if the collective requirements (02) is mantained.
    Regards
    Sri

  • Purchase order with reference to internal order

    Dear all
    I am creating a purchase order with reference to a statistical internal order.The total PO value should not exceed the budgeted amount for that statistical internal order.How should i achieve this?
    Thanks in advance.
    Madhavi

    Hello
    First Create Budget Profile.
    Make Specification In Availability Control as Activation Type ''01- Automatic activation during budget allocation''
    Usage 100 and Tick ''Overall'' check box.
    After that Make Setting for your Controlling area in SPRO Path '' Define Tolerance Limit for Availibility control''

  • Help Bapi Purchase order with reference to purchase requisition no

    Hi,
    i used BAPI_PO_CREATE1 for creating purchase order with reference to Purchase requisition number but im getting these error
    please help me to solve this
    1 E BAPI 001 No instance of object type PurchaseOrder has been created. External reference:
    2 E MEPO 001 Purchase order item 00010 still contains faulty schedule lines
    3 E 06 054 Doc. type/item cat. NB/S (requisition) <-> NB/ (purch. order)
    4 E 8W 162 No schedule line exists for schedule line number 0010000030 00010 0000.
    Thanks & Regards,
    Azhar
    Message was edited by:
            Azhar

    Hi Azar,
    I am also getting the same messages, did you get resolve the issue.

  • Purchase Order with reference to Purchase Requisition

    Hello
    I have this situation:
    One Purchase Requisition with quantity of 10.
    When I issue a Purchase Order with reference to this purchase requisition, for the moment I can use this Purchase Requisition many times. For example: two Purchase Order with the same purchase requisition, same item and same quantity.
    The objective is thay the system only allows to use the Purchase Requisition until the quantity is completed. For example: one purchase order for 10, or two purchase orders with 5 each. But never with a quantity superior to the total quantity in the purchase requisition.
    Somebody can help?
    Thank you,
    Elena

    Hi,
    1) By setting the configuration paths as suggested by the previous posts.
    2) In the first place, when converting a PR in PO Create Screen (ME21N), you should make the Open only and Released only field as Display. This way, the results will only show Open and Released PRs to be converted to PO
    Hope this helps

  • Net price on purchase order with reference to purchase requisition

    Hello!
    When I create a purchase order with reference to purchase requisition, the net price goes automatically to the purchase order.
    But It's possible change the net price on PO, and I must close this possibility.
    Do you know how can I do this?
    Thanks, Camila!

    Hello
    Try to search SCN for EVO
    You will find this: PR price in PO

  • Program for Creating Purchase Order with reference to purchase requisition

    Hi ,
    I need to Create purchase Order with reference to  Purchase requisition,
    in my case i need to automize the Process which is happening in MD04,
    Can you please suggest me ?
    Thanks ,
    Murali

    Hi,
    Plz check this link. It will be helpful to you.
    Purchase order creation with reference to PR
    We can also create the PO Using the BAPI_PO_CREATE1 function module.
    In this function module fill up the all necessary Details.
    With details in Item Table we haveto give the Fields PREQ_NO and PREQ_ITEM for each item .
    then it will creates the PO with PREQ.
    Thanks & Regards,
    Sarita Singh Rathour
    Edited by: Sarita Rathour on Aug 3, 2009 7:01 AM

  • Create Purchase Order with reference to Purchase Requisition using BAPI's

    Hello Experts,
    I need to create a Purchase order with reference to a Purchase Requisition.
    All the above has to be done by using BAPI's.
    For creating PR, I am using BAPI_REQUISITION_CREATE.
    and for PO, I am using BAPI_PO_CREATE.
    I am not able to use the requistion number in the PO. BAPI throws the following exception
    "Requisition 1014396 00010 not selectable"
    "Document contains no items"
    Query's:
    1. Do I need to release the PR for using it in PO?
    2. If so how can I work with the "BAPI_REQUISITION_RELEASE_GEN" to release PR?
    I have tried using the BAPI getting the following error "Release outside filed of responsibility".
    Please help I am in critical Postion...
    Thanks,
    Suma

    Hi Meenakshi,
    When, I try to release error I am getting the following the error " Purchase Requisition can not be released".
    Is this problem because of authorization or data issue?
    Thanks
    Suma

  • Purchase Order with reference to Purchase Order

    Dear SAP Gurus,
    Can it be possible to have a purchase order with reference to purchase order.
    Regards
    Vinod Kakade

    Hi,
    there is an option to give document date in the Purchase order selection in Document overview, what you can do here is that you can get a TVARVC variable created with date range of today - Today - 179 Days, in the attributes of the variant enter the TVARVC variable so that when the user uses this variant, he will get PO's only for that date range, if you  have any confusion on this then please speak to your ABAP Consultant.
    Regards
    Chandra Shekhar

  • ME21N Create Purchase Order with reference to previous Purchase Order

    Hello Expert,
    Previously have been using Purchase Info Records for reference when creating Purchase Orders using ME21N.  We then have deleted the Pricing Condition in the Purchase Info Record using ME12.  Now when we are trying to create a new Purchase Order with the same values (Vendor, Material, Plant and Storage Location), the transaction code ME21N automatically fetches the previous values of the Pricing Condition as if it was cached.  I remember of studying this in the MM academy but I am not sure how to disable it. 
    This error only happens when we are creating the first Purchase Order after the deletion, for the second Purchase Order, error will be prompted to the user saying that the Pricing Condition could not be found. 
    I would like to ask where in configuration can I delete this cache behaviour or is that any work around for this. 
    Thanks in advance.

    Hello Antony,
    I found the "Update Prices" function in the Conditions Tab of the Item Details helps to refresh the data and fetch the new information from the Purchase Info Record.  I would like to ask is there anyway to provoke this function automatically everytime when a user runs the transaction ME21N.
    Thanks in advance again.

  • Subcontracting Purchase order with Sales order Reference

    Hi friends,
    I am facing a problem during GR of Purchase order with Acc. Assignment E and Item Cat L i.e. purchase order is MTO and of Subcontracting.
    During GR, system is purposing movement type 543 E instead of 543 O for BOM components. Please suggest how can I get the correct movement type during GR. I would like to appreciate for your kind response.
    Kraheja.

    Hi
    Go to SPRO->Logistic general->Tax on goods movement->India->Movement types.
    Here you will find the group of movement types check which movement types is mantained for the out side movement groups or inward movement.
    also check the Material Master in MRP view if the collective requirements (02) is mantained.
    Regards
    Sujoy