Purchase order X of Maintenance order Y still without final billing indicat

In maintenance process, while closing the Maintenance order after MIRO and Payment, system is giving warning message as :
"Purchase order item 4520000023 00010 of order 4000020 still without final billing indic.
Message no. IW215
Diagnosis
An invoice receipt is still expected for order 4000020".
We tried with PM consultant but setting is not there for Billing indicator.
Any solution ?
Regards
Rewards if resolved...

Hi,
Goto respective purchage Order, Select Invoice tab in Item, put tick mark in check box of  Final invoice. Then save the purchange order.
Preoceed further.
Regards

Similar Messages

  • Purchase order item of maintenance order still without final billing indic

    In maintenance process, while closing the Maintenance order after MIRO and Payment, system is giving warning message as :
    "Purchase order item 4520000023 00010 of order 4000020 still without final billing indic.
    Message no. IW215
    Diagnosis
    An invoice receipt is still expected for order 4000020".
    We tried with MM consultant but setting is not there for Billing indicator.
    Any solution ?
    Regards
    Rewards if resolved...

    Hi,
    Goto respective purchage Order, Select Invoice tab in Item, put tick mark in check box of  Final invoice. Then save the purchange order.
    Preoceed further.
    Regards

  • Purchase requisition,Purchase order attach to maintenance order

    Dear all,
    Can any one tell me that, is it possible to attach Reservation or Purchase requisition or Purchase order
    attach to maintenance order? (which is not created from the maintenance order)

    hi
    if you have created the material reservation against the movement type 261 the you have the option to specify the order.
    also there will be option to change the order specified.
    kindly check .also  i think there is no provision to assign reservation for material issued
    regards
    thyagarajan

  • One Purchase Requisition for One Maintenance Order

    Dear Consultants,
    We have implemented mySAP ECC 6.0.   We have more than 20 line items in one Maintenance order for  Item category N. Curently system is generating Purchase requisitions by line itemwise for Item category N(Non-stock items). Our client requires only one purchase requisition for every Maintenance Order. Is it possible to generate one PR for one Maintenance Order? If possible please give us the solution.
    Thanks,
    Dev

    Dear Pete Atkin,
    With your help my issue has been resolved. Thank you very much.
    With Best Regards,
    Dev

  • How to block production order creation when maintenance order is generated.

    Hi All,
    Kindly share how to block production order generation when maintenance order is generated.

    Integration between PP module and PM module
    PP/PM Workcenter Integration
    There are many threads & documents available. Please do some search.

  • Maintain settlement rules for order category 30(Maintenance order).

    Hi Gurus,
    Can we maintain two settlement rules for an order without distribution rule?
    Eample:-  In an order there are three  different costs i.e. material cost,external labour cost and internal labour cost.We want to settle the material cost and external labour cost to Profitability segment and the internal cost to a particular GL account directly.
    Note: No distribution rule is required,because all the cost should settle directly to correspoanding heads i.e. PSG or GL.We don't want to assign  the GL# again and again for different orders in the corresponding order's  settlement rule.
    Require your valuable inputs to proceed.
    Best Regards,
    Ramakanta

    Hi Govardhan,
    If you are working in ECS, the Shopping cart will not create any follow on document in backend R/3.
    I think your Product category is 30, thats why the error says Manual reservation for order category 30 is not allowed.
    Where did you get the maintenance order? Generally maintenance order is created in the backend R/3 (Plant Maintenance) and a P.R will get generated against that order.
    Using PDP (Plan driven procurement) you can transfer that P.R to SRM and can carry out sourcing and can complete the procurement cycle.
    Can you please tell me what is your exact business requirement?
    Hope this will make you more clear.
    Clarifications are welcome.
    Award points for helpful answers.
    Rgds,
    Teja

  • Sales orders that have been invoiced are still in the Billing due list

    Friends :
    We have  sales orders that have been invoiced are still in the Billing due list. When i look at sales orders it has 0.00 price.
    The error message is
    Billing not possible because repair is not yet completed
    The item is not relevant for billing
    The item has been fully invoiced already
    Full pints will be given.
    Van bills

    Hello,
    I believe these are repair orders, and invoices through order related billing. Check the incompletion log in the order, check whether the repair is complete. Go to the order VA02 --> Order ---> Environment --> Status. You may know the over all status of the document. Check for the billing status, if the billing status is not invoiced, then you need to generate invoice or Reject the line item.
    Prase

  • Purchase Requisition created from Maintenance Order can not deleted

    Hi Gurus,
    I've create a Maintenance Order for External Service (Control Key: PM02) and Purchase Requisition already created related to this Maintenance Order.
    But when I want to cancel/delete the Purchase Requisition, there is error message "This item is only deletable via the associated production order". So II can not delete the PR.
    Any solution for this problem ?
    Regards,
    Tri W

    Hi,
    If the PR has not been approved and no PO has been created yet, you have to delete the external service operation (PM02) in the work order. This should delete the Pruchase Requisitions.
    Regards,
    Joey

  • Maintenance order settled to maintenance order-report

    Hi,
    How i can see the cost,maintenance order is settled to maintenance order.
    is it any standard report available?
    since i am not able to see the cost in settlement order.
    Regards,
    Shrithar

    Hi Shrithar,
    In general the cost are collected on Order and after completion they are settled to a Cost Object (Cost Center, G/L, WBS, Order Etc).
    Now can you be clear on your question.
    Are costs not getting posted onto Order? or Unable to Settle the Order? or Need a report to see the settled costs?
    Based on your exact question, the forum can respond.
    Regards,
    MLN Prasad

  • Budget Process (Linked the maintenance Order into Internal Order) in EAM

    Dear Experts,
    Scenario for Repair & Maintenance with only MM & FICO module live w.e.f. 2007 (PM not live)
    Process Managed thru Internal Order (Order Type: RPMT)
    Budget managed through Investment Management (IM); Budget is directly entered against the IO using transaction IM52
    Scenario for Repair & Maintenance with only MM, FICO & PM module live (PM went live in 2010)
    It was proposed to assign budget against each Maintenance Order.  Since the number of maintenance orders being used is very high, it was decided to link the MO & IO so that budget will be assigned to the IO and when the MO is settled against the IO, the budget in IO can be deducted accordingly. The proposed process to assign budget in Internal Order against each Maintenance Order are given below-:
    1.)     In EAM process one can plan/procure material and External Services only when the Maintenance Order is created & released but practically it has to be planned long before any Maintenance Activity (Maintenance Order to be linked with the estimate so that PO can be created against the estimate).
    2.)     The no. of Maintenance Order generated in EAM Module is very large as Maintenance order is created for almost each and every maintenance activity. It is cumbersome to allocate the budget to each and every maintenance order. There should be a single estimate for maintenance activity (as in MM module) and that should be linked to maintenance order so that the actual cost of Indent/Service Entry Sheet can be deducted automatically from the estimate (Maintenance Order is to be linked with estimate).
    3.)      While doing return Indent the cost of return material is not being added to the maintenance order automatically (Maintenance Order is to be linked with estimate).
    4.)      If Material & External Services not planned in the maintenance order (estimate), the user must be able to do that through Internal Order (estimate), hence the Internal Order must be link to the Maintenance Order. They should able to record the planned & actual cost in the maintenance Order.
    Process followed:
    1.) Created Internal Order in KO01 for Repair & Maintenance Order Type
         Assigned budget to Internal Order thru IM52
    2.) Created PM order and assigned Internal order against Settlement Order in tab  
         u2018Locationu2019 and in Settlement Rule with 100%. In this Section attach the Internal  
         Order with selection type u2018ORDu2019. 
    3.) Released both orders and issue the Material for particular Operation and then   
         determine the Cost for material .After that performed MIGO for consumption of
         materials.
    4.) Settled the PM order in KO88.
         Settlement process was successfully saved.
    Problem faced:
    After posting the goods movement (against each Maintenance Order) and settlement of the maintenance order against IO, we still find the budget assigned to the IO is not consumed/deducted.
    1. Actual cost of maintenance is not reflected in the internal order
        immediately. We have to run cost settlement (t-code KO88) for the
        maintenance order each time the actual cost is incurred in the maintenance order.
    2. Also in the case of return indent, the value of returned material is not directly 
        added to the available budget of internal order.
    3. When the material is issued from store through the reservation generated by 
        maintenance order, system does not check for budget in the internal  
        order/maintenance order while issuing material from the store.
    4.  It must not be allowed to create reservation from the internal order of order type
         RPMT.
    5.  In case of external service in the maintenance order, the unit of
         measure in the requisition is set to u201CD (days)u201D by default. System does not allow  
         changing the unit of measure in the requisition (it should allow to change the unit
         of measure or set the unit of measure u201CJOBu201D).
    6.) When the material is issued from  the store through reservation generated  in
         maintenance order, system does not check for budget in Internal Order  
         (estimate)/Maintenance Order while issuing material from store.
    Thanks & Regards
    Deepak Soni

    Hi,
    1. Actual cost of maintenance is not reflected in the internal order
    immediately. We have to run cost settlement (t-code KO88) for the
    maintenance order each time the actual cost is incurred in the maintenance order.
    As per the standard system budgeting is done against the actual cost only. And until you settle your order the actual cost from
    maint order are not getting transfered to IO. Once they are transfered system is checking for the budget.
    2. Also in the case of return indent, the value of returned material is not directly added to the available budget of internal order.
    This is similar to first point, when you return goods there will be negative cost on the order, this has to be settled until that system will not compare the IO budget with maintenance order actual cost.
    3. When the material is issued from store through the reservation generated by maintenance order, system does not check for budget in the internal order/maintenance order while issuing material from the store.
    The budget you have assigned is at IO, how can system will check the budget while issueing goods for maintenance order. We may have to develop or use some user exit over here. Which will trigger checking of budget from the settlement receiver IO for that maintenance order.
    I think you may have to go for development. These are my observations from my experience.
    Regards,
    NNR

  • PR type generated by maintenance orders

    Hi Gurus,
    Where do you defined the type of purchase requisition generated by maintenance order ? Is it possible to have different types of PR depending on the material type of the component in the maintenance order ?
    Cheers
    Olivier

    Hi,
    You can define the PR type at following IMG point:
    - Plant Maintenance and Customer Service
      - Maintenance and Service Processing
       - Maintenance and Service Orders
         - General Data
           - Define Account Assignment Cat. and Document Type for Purchase Requisitions
    The value is usually set to NB but this can be different. Only one value can be defined for PM orders.
    To get varying document types consider exits COZF0001/COZF0002 and adjust the field BSART.
    -Paul

  • Plan Component from Maintenance Order

    Hi,
    When i plan a component from maintenance order I use item category N with key MATE.
    But i woul plan component for purchase requisition on project stock( account assign Q) directly from Maintenance Order. Allow I insert item category N in the field ad near insert the value 2 for project stock.
    When i release the order the system blank the field and i don't create a Purchase requisition with project stock but i purchase requisition with account assignement F
    Because the system put away the field blank?, I must done another customizing, or i must utilize another KEY?
    Thank you

    Hi,
    When you make Item cat as N it means they are non stock .
    For non stock & with F order as account assignment system creates PR.
    if you want this componenet as Project stock them there are following  ways
    1.Make PR with item cat as Q & make PR on WBS or PS System.
      System will post direct entries.
    2.Make normal stock PR then issue against WBS by order
       Settle the maintenance order to WBS element
    3.Get material as normal stock material issue with 221 mvt against WBS or PS system.
       Systme will make enties to WBS.
    Ramesh

  • Tables for Materials in Maintenance Order

    Hi experts,
    I need to implement a program that let me view the materials contained in the maintenance order, but I can not find the tables that contain this information.
    Can anyone help me or tell me how to get this information (Function or other)?
    Thanks in advance
    L.

    Hi,
        Check in RESB- Reservation table..,enter order no 
       Alternatively for Purchase requisition generated from Maintenance Order - u can find EBKN Table ..
    Check if IWBK Report - satisfies your requirement or no
    regrds
    pushpa

  • Add the budget profile in the order type Maintenance Order

    Dear Experts,
    Scenario for Repair & Maintenance with only MM & FICO module live w.e.f. 2007 (PM not live)
    Process Managed thru Internal Order (Order Type: RPMT)
    Budget managed through Investment Management (IM); Budget is directly entered against the IO using transaction IM52
    Scenario for Repair & Maintenance with only MM, FICO & PM module live (PM went live in 2010)
    It was proposed to assign budget against each Maintenance Order. Since the number of maintenance orders being used is very high, it was decided to link the MO & IO so that budget will be assigned to the IO and when the MO is settled against the IO, the budget in IO can be deducted accordingly. The proposed process to assign budget in Internal Order against each Maintenance Order are given below-:
    1.) In EAM process one can plan/procure material and External Services only when the Maintenance Order is created & released but practically it has to be planned long before any Maintenance Activity (Maintenance Order to be linked with the estimate so that PO can be created against the estimate).
    2.) The no. of Maintenance Order generated in EAM Module is very large as Maintenance order is created for almost each and every maintenance activity. It is cumbersome to allocate the budget to each and every maintenance order. There should be a single estimate for maintenance activity (as in MM module) and that should be linked to maintenance order so that the actual cost of Indent/Service Entry Sheet can be deducted automatically from the estimate (Maintenance Order is to be linked with estimate).
    3.) While doing return Indent the cost of return material is not being added to the maintenance order automatically (Maintenance Order is to be linked with estimate).
    4.) If Material & External Services not planned in the maintenance order (estimate), the user must be able to do that through Internal Order (estimate), hence the Internal Order must be link to the Maintenance Order. They should able to record the planned & actual cost in the maintenance Order.
    Process followed:
    1.) Created Internal Order in KO01 for Repair & Maintenance Order Type
    Assigned budget to Internal Order thru IM52
    2.) Created PM order and assigned Internal order against Settlement Order in tab
    u2018Locationu2019 and in Settlement Rule with 100%. In this Section attach the Internal
    Order with selection type u2018ORDu2019.
    3.) Released both orders and issue the Material for particular Operation and then
    determine the Cost for material .After that performed MIGO for consumption of
    materials.
    4.) Settled the PM order in KO88.
    Settlement process was successfully saved.
    Problem faced:
    After posting the goods movement (against each Maintenance Order) and settlement of the maintenance order against IO, we still find the budget assigned to the IO is not consumed/deducted.
    1. Actual cost of maintenance is not reflected in the internal order
    immediately. We have to run cost settlement (t-code KO88) for the
    maintenance order each time the actual cost is incurred in the maintenance order.
    2. Also in the case of return indent, the value of returned material is not directly
    added to the available budget of internal order.
    3. When the material is issued from store through the reservation generated by
    maintenance order, system does not check for budget in the internal
    order/maintenance order while issuing material from the store.
    4. It must not be allowed to create reservation from the internal order of order type
    RPMT.
    5. In case of external service in the maintenance order, the unit of
    measure in the requisition is set to u201CD (days)u201D by default. System does not allow
    changing the unit of measure in the requisition (it should allow to change the unit
    of measure or set the unit of measure u201CJOBu201D).
    6.) When the material is issued from the store through reservation generated in
    maintenance order, system does not check for budget in Internal Order
    (estimate)/Maintenance Order while issuing material from store.
    7.) My first problem is every time running the cost settlement(KO88) is maindetory.Without running cost settlement, How we can settle the actual amount of MO with IO (Estimate budget).
    2.) As you know that I have assigned the budget in IO.How system will check the budget while issuing the goods for maintenance order.So will please tell me that which user-exit is used over here.
    Thanks & Regards,

    Hi Deepak1103,
    Well, obviously you will have to settle the costs incurred at the maintenance order. The internal order should be mentioned in the settlement order field in the location tab of the maintenance order. What you can do is to ask your ABAP person to activate this enhancement IWO10004: Maintenance order: Customer check for order completion, use the CAUFVD structure to get the internal order number, then use the BAPI BAPI_INTERNALORDER_GETDETAIL and pass the details to the function module BBPG_BUDGET_CHECK and check the actual cost against the required budget. In case of a conflict raise an error other wise run the function module CK_F_IH_ORDER_SETTLE to settle the costs of the maintenance order to the internal order. Budget would also be consumed and you can verify the same in S_ALR_87013019.
    Regards,
    Muhammad Usman Kahoot

  • Receiving defective component from Maintenance order

    Hi friends,
          My client wants to capture the defective spares issued against maintenance order in the system.The scenario is for a maintenance order spares(components) are issued through movement type 261 and unused spares(components) are returned to the warehouse through reversal movement type 262. but for the replaced spares the user has to return the defective spares and it must be entered in the system Please suggest me possible solutions.
    Thanks in advance.
    Sankar

    Hi,
    When you make Item cat as N it means they are non stock .
    For non stock & with F order as account assignment system creates PR.
    if you want this componenet as Project stock them there are following  ways
    1.Make PR with item cat as Q & make PR on WBS or PS System.
      System will post direct entries.
    2.Make normal stock PR then issue against WBS by order
       Settle the maintenance order to WBS element
    3.Get material as normal stock material issue with 221 mvt against WBS or PS system.
       Systme will make enties to WBS.
    Ramesh

Maybe you are looking for

  • RE: GETTING AN ERROR WHILE LOADING ACL USING XML FILE

    I have generated several XML files (ACL) to load in the share services but when I do I get the following error message: "Errors occured during syncrhonization: [com.hyperion.planning.DuplicateUserException: Another user with the name admin already ex

  • Help plz, i need back up my phone

    Help plz, i have iphone 4 i still have icloud  on my itunes and i need to update it to the new one but i dont want to lose any of my pictues of my kids im not sure if ive backed it up before if i have it would of been a long time ago plz help me than

  • Display goes fuzzy then shuts down

    HI, my macbook pro display just goes fuzzy all of a sudden and I can't do anything. It's hard to explain but it's just like a bunch of lines flickering. Then most of the time it shuts itself down or I have to do it manually. I'll restart it and most

  • How to add Visual Composer to CE 7.1 trial

    Hi, after having installed CE 7.1 (english, Windows OS) and assigning VisualComposerUser role to my admin, i tried to have a look at the visual composer http://hostName:50000/VC Problem is: only an empty page is displayed - grmph! After searching SDN

  • Oracle CHR(n) Function

    I need an Oracle CHR(n) Function to have a BOLD message. Have someone any idea?