Purchase Req and PO questions in 11i

Hi,
I have few questions on Purchasing module, can any one plase provide your inputs, any help is highly apporeciated. i am using 11i
1. When we Auto create PO from a Req, The “Ship To” field does not automatically populate from the REQ. How can we Auto populate Shipt to of a REQ line shipt to PO? Is it Possible?
2. Oracle allows Requestors to submit a REQ for a supplier that is on Hold. Can We make tohave it not allow the REQ to be submitted and provide an error message?.
3. Oracle allows REQ’s to be submitted when missing required information such as “Ship To” and “Supplier Site” as these are not mandatory fields. How can we make these feilds mandatory under REQ screen?can we achieve through Form personalization?.
4. Inorder to Place a supplier on Payment Hold requires checking boxes on the main supplier setup and then on each site setup. Is there any way to we can do one step actions in the main supplier setup affect all existing and subsequent sites.
Thanks
Edited by: 890852 on Mar 6, 2012 7:18 AM

Thanks Sandeep for your inputs. I want to clarify further, please let me know if you could. I appreciate your help.
1. The shipto on the PO shipment defaults from the Requisition. However, the shipto on the PO header remains blank. The buyer has to fill it in manually.
This is correct, can we display what ever displayed under "shipto on the PO shipment" to "shipto on the PO header" , is it achieved only through Form personalization.
4. The payment hold box on supplier screen is used to default the same box when CREATING a new supplier site. Unless you write a customization, I don't know of any way to set the box on all sites when it is checked on the supplier screen.
If we check the "Hold all Payments" under Supplier form, it is not automatically defaulting under sites, but is it required to go manually each site and check the "Hold all Payments"?, I think once we check the "Hold all Payments" under Supplier form it would logically apply for all of its sites as well right, though we dont check under sites?
Thanks

Similar Messages

  • Trigger CIF during custom field change on Purchase Req. and PO

    Hi,
    We added a custom date field in Purchase Req. and Purchase Order transactions (ME52N/ME22N) in ECC. When this custom field gets changed along with any other standard field, outbound CIF process happens. However, when we change this custom field only, then outbound CIF doesn't happen. I believe we need change pointers and may be custom code to trigger outbound CIF. I would appreciate any suggestions on how to achieve this functionality.
    Thanks.
    Naveen

    Hello Naveen,
    Use user exit EXIT_SAPLMEAP_001 here, the structure CIFPUORCUS must be enhanced with custom fields so that the document date can be included (IT_OUTPUT_CUS).transferred to CT_MM_DOC. You need to fill EBAN and EKPO for change transfer. Also you can have the background job for RIMODINI to transfer the changes.
    Best Regards,
    R.Brahmankar

  • How to avoid purchase req and stock transport order to take part in MRP.

    Please suggest how to avoid purchase req and stock transport order to take part in MRP.

    hi,
    check the settings for the MRP type...there you need to show which doc will be taken into considerations...
    SPRO >> MM >> CBP...
    Under CBP check for the MRP settings where it is placed(check under master data settings)...and check for the indicator for PR's and STO's release orders under tab "Additional external req. in the reorder point planning"..
    Regards
    Priyanka.P

  • Purchase Req and Goods Receipt (ESS) question

    Hi,
    My client has ECC 6 and EP 7 in the landscape. I am implementing Employee Self Service portal. It looks like standard Purchasing Requisition and Goods Receipts iviews (ESS package) are pointing to SRM. We are not implementing SRM here. Is there any way I can use these iviews pointing to ECC (probably ME51n, MIGO?)?
    Do I have to have SRM in order to use these standard iviews? Is there any standard iviews available for ECC purchase requisition?
    If you implement Purchase Requisition using ECC instead of SRM, what is the licensing impact? Client has purchased the license for Employee Procurement Self Service.
    Another question is, Is there any standard iview for Travel & Expense approval? I don’t find it in MSS.
    Thanks,
    Umesh Garg

    HI Horny,
    Can you use the Following Tables:
    S039 - > LETZTABG - Date: last (i.e. most recent) goods issue
    EKPO -> EBELN - Purchasing Document Number.
    You can create View by using these two tables (Material Number is the Common) and uploade the data.
    Hope this will be helpful for your question.
    Thanks
    Rajesh
    Message was edited by:
            rajesh

  • Purchase Req and Goods Receipt

    My client has ECC 6 and EP 7 in the landscape. I am implementing Employee Self Service portal. It looks like standard Purchasing Requisition and Goods Receipts iviews (ESS package) are pointing to SRM. We are not implementing SRM here. Is there any way I can use these iviews pointing to ECC (probably ME51n, MIGO?)?
    Do I have to have SRM in order to use these standard iviews? Is there any standard iviews available for ECC purchase requisition?
    If you implement Purchase Requisition using ECC instead of SRM, what is the licensing impact? Client has purchased the license for Employee Procurement Self Service.
    Another question is, Is there any standard iview for Travel & Expense approval? I don’t find it in MSS.

    ok

  • Price differece between purchase req and PO for free text purchase

    Hi there
    Has anyone found a good solution for the following problem. 
    A free text purchase requisition item is created with a value = x.  The buyer goes out to quote (not using SAP RFQ - manual) and comes back with a price change.  The buyer creates the purchase order referencing the purchase requisition, but they need to change the value to x+10. 
    The client wants to stop the purchase order been created if the value is above a certain percentage.  The standard settings in the system are for material values.  Does anyone know how to extend this to a short text item on a purchase requistion?
    Thanks
    Roz

    Hi,
    This is not possible to achieve in SAP standard functionality.
    You can do one thing, keep Price field for the PO Document type of Text Purchases as display, which will not allow user to change the price for Text POs.
    Use Release Strategy for Purchase Requisitions and keep changeability for the Release indicator as "4" and % Changeability as 10%. And ask user ro change the price in ME52N only instead of changing it in PO. If it will increase more than 10% the PR Value then system will reset the release and this PR needs to be released again.
    If it is not acceptable then you can try it with user exit "MM06E007" - Change document for requisitions upon conversion into PO

  • Purchasing Imac and CS4 question

    I am planning purchasing an imac in the next couple of months. Mostly work with adobe suite and possibly doing some video editing with After effects.
    My question is this; are there any significant benefits with the higher end graphics card and some of the newer features in CS4? I'm debating between a refurb 2.8 and 3.06 but not sure if the added cost is justified.
    Also I have read a number of rumors that the iMacs will receive a speed bump before the holidays, can anyone comment if that is likely or unlikely to happen?
    thanks in advance.

    If you were to buy new you could go for the 2.8 and upgrade the graphics processor for $150. I doubt you will see much difference with the lower power GPU in 2D graphics Apps unless you are planning on running multiple displays. However if you were going to use After Effects or Premier the 8800GT might do better.
    OTOH since you are buying for the future the overall CPU gain is probably worth the extra cash. Think of it this way, one year from now will you be wishing you had the additional 200MHz and better GPU?
    For reference I am running CS3 Design Premium, After Effects CS3, and FCP Studio on 2.16GHz iMacs with 3GB RAM and X1600 Graphics without any noticeable problems.
    George

  • Info Record and Purchase Req

    I created a purchase Req and when and I have following doubts in this.
    1. Once I entered plant itu2019s automatically populating storage location. Material maintained for different storage locations but I am not sure how it's populating specific one.
    2. One I click on source of supply it shows me different info record and I selected one of the info record for assigning the source. How this process is different from mE57.To me both look same.
    3. I created the PO and I entered different price then info record and my info update was checked but still it didn't update info record with new price. Any suggestion why?
    Thanks

    hi,
    1. You would be maintaining the MRP view of the MMR....Never forget the possible assignment for the Plant to the storage location is provided in the SPRO enterprise structure for the MM....
    2. Yes the process is merely same...Also never forget that there may be many inforecords for the vendor material, based on the different organisatinal levels provided and for its combinations...
    3. THe price never gets updated in the info record, but always the PO price history gets updated...you can see the PO price history in transaction ME1P...
    Regards
    Priyanka.P

  • CDP Purchase Reqs in ECC

    Hi,
    I have a purchase reqs and planned orders with characteristic reqts in APO. How will these be maintained in ECC ?
    All my materials are batch managed and  material types are ROH, FERT and HALB. I'm using CDP to plan based on the batch characteristic requirement.
    Can you guys please tell me this, seems to be a big road block for me.
    thanks

    Hi sapcrs,
    Now I am clear with your question. 
    You maintain class and characteristics.
    Followed by assigning those into the material master
    Assign those into work center if required
    Assign those into the production version
    Then in the routing, double click on the operation number, followed by goto the top menu, Extras ---> Classification
    In this, you maintain the characteristic propagation as required.
    Once maintained, you cif the bom and routing .
    The characteristic propagation maintained will get attached into the PPM
    Please confirm.
    Regards
    R. Senthil Mareeswaran.

  • How to Change attachment URL on a Purchase Req?

    Attachments in the EBP shopping carts are transferred to an ITS server and are linked to a back end R/3 Purchase Requisition. 
    Note that the attachments are physically stored on ITS server and the link (URL) to the attachment and Purchase Req is stored in SAP. 
    As a part of decommissioning, the server which was used for storing attachments is replaced with a new server and all the attachments are moved to new server.  
    Since the link associated to the Purchase Req and attachment is not changed, when user is trying to open the Purchase Req attachment, it is not displaying becuase all the attachments are moved to new server. 
    How to change the link (URL) in the Purchase Req so that it will point out to the new server instead of old server. 
    Due to the following reasons manually changing the URL is not advisable.
    1) 40,000 attachments link need to be changed.
    2) System is not allowing to change the URL manually because of the user differences.  All the attachment links are attached to Purchase Reqs by RFC user (since these are transferred from EBP environment). 
    Please advise what should be the feasible solution to change the URL (link) on the Purchase Req so that business can open the attachment with no issues.
    Thanks in advance

    According to SAP, since purchase order is a legal document they do not support the process of changing document number.  They suggested I do the change with debug and replace at my own risk.  In ME22N go to debug and type MEPO_TOPLINE-BEDAT.  The values for this field show up as 29991231 that should be changed to 20191231 and press F8, then save the purchase order.

  • Purchase Req Release Reset After Addition of New Component in Service Order

    Hello,
    We have a scenario where we create a service order, add some operations, and then some components to the operations. Note that we are set up to use the same purchase req for all components so all components, regardless of operation, are on the same req.
    We then release all lines on the purchase req and continue on to convert to purchase orders. In some cases, the PO's are then received.
    Now, it is discovered that we need to add addtional components to the same service order so we do that. These new components are added to the original purchase req. Upon saving the service order, all of the previously released lines have reverted back to unreleased. Very frustrating since some of the req lines are already converted to purchase orders.
    Note that the changability flag is set to 4 for our release indicator.
    We are at a loss as to how to fix this. Anyt insights are appreciated.
    Regards,
    Greg

    Hello All,
    Thank you for your replies.
    @Sebastien: We are using collective PR's. If we cannot solve, we will entertain individual PR's
    @Maheswaran: It's MM from the PR perspective but since it is only happening when the PR's are tied to the service order, I asked here. We are releasing at the line level of the PR.
    @Linganna: Are you talking about an enhancement to create individual PR's? That is taken care of in configuration, no?
    Thanks again and regards,
    Greg

  • Prevent Hourly Employees from Ordering Non-stocked Materials and Creating Purchase Reqs in Work Order

    Our SAP plant maintenance system is configured to create a purchase req when a non-stocked material is ordered. We would like to prevent hourly employees from creating a purchase req or ordering non-stocked materials. Only supervisors should be able to order non-stocked materials and create a purchase req. Is there a way to do this via config or system enhancement?

    Hello Rick,
    Clearly there will be 2 ways if not more. One is the Authorization object route and another is Enhancement route. I'm not going to touch the former one. So let's expect answers from other members for that. For the later one, we need to know the answer for the question below:
    'Can we distinguish the hourly employees from regular employees by the user-Id or some other means? If yes, how ?'
    Once we know this, we need to use some user-exit or enhancement spot of the program SAPLCOIH to capture the event of 'N' in the ItemCategory field of Components tab by such UserIds and trigger an error message.  (Suitable user-exit is not striking my mind, so this might go the implicit enhancement way of Order program SAPLCOIH ).
    KJogeswaraRao

  • Question: how to move purchase req without firming

    Hi SAP folks,
    I've overcome this purchase req that is always showing after MPS run even the actual coverage is not so close to target (i.e. actual coverage=160, target coverage=30), i just want to know if there are possibilities that a purchase req can move in another date without firming it? i've tried removing PIRs but they still show up in the same period. Deleting it also not help as it again generated after closing.
    Thanks and waiting for all your replies

    Hi,
    Not sure what you're trying to achieve as the question is not quite clear, but based on what i understand, a procurement proposal is generated by mrp / mps run when the available stock is not able to meet the demand.
    If the need date shifts to a later date, the mrp / mps run will automatically reschedule the procurement proposal to a later date if the same is not firmed. So from your side ensure that the PR is not firmed, then system will automatically reschedule the proposals.
    A PR will be firmed if you manually edit it or manually create it or if MRP / MPS run firms the PR when it falls within the planning time fence.
    Hope the above clarifies your query.
    Regards,
    Vivek

  • I have purchased music with my old apple id, old computer and old email. My old email and computer are not available anymore and I dont remember my password and securtiy question anymore. How can I authorise my old apple id to authorise the new computer?

    Hi, I have a new computer and new apple id. I've purchased music with my old computer, email and apple id.
    I cant access now the previously purchase music, because it wants to authorize the new computer to play the
    music. I cant remember password and security questions for my old id and the old email doest exist anymore.
    What can I do?

    Hi, Carmen. 
    Thank you for visiting Apple Support Communities. 
    If you need to reset you security questions, do not know the answers and no longer have access to that email account, see the last sentence under Note in step 5.
    You'll be asked to answer 2 of your 3 security questions before you can make any modifications. If you are unable to remember your answers, you can choose to send an email to your rescue email to reset your security questions.
    Note: The option to send an email to reset your security questions and answers will not be available if a rescue email address is not provided. You will need tocontact iTunes Store support in order to do so.
    Rescue email address and how to reset Apple ID security questions
    http://support.apple.com/kb/ht5312
    Cheers,
    Jason H.

  • MRP run and creation of one cumulative purchase req

    Hello,
    mrp run is creating a lot of single purchase reqs with one line (quantity and dates are fine)
    but how to set up MRP so that instead of multiple purchase reqs ONE purchase req with many lines is created.
    Thanks, Sebastian

    this is not forseen in the design.
    Where would be the benefit? have a look into table EBAN.
    There would not be one record less with this concept.
    Further, in bigger organizations, several buyers would then work with the same purchase requisition, which could lead to lock and update problems.

Maybe you are looking for

  • External drive- is firewire 800 drive compatible w/ PBook g4 firewire port

    I need to buy an external hard drive. Will this model connect to my PowerBook G4 which is about 3 years old without any additional upgrading of the firewire ports? (G-Tech G-DRIVE mini 120GB FW800 Portable Hard Drive) Would this drive be more benefic

  • Sync messages archive?

    Hi ,        Is there a work around to archive synchronous message (error and successful)? We may need it for erro analysis later and we dont want to keep too many messages in our system.. Also ... How does async errored messages get archived/deleted?

  • Messenger and skype

    is it possible to use yahoo messenger and skype on the iphone?...

  • Install Disc 3i User Edition 3.3 on iAS 8i

    how to make installation User Edition 3.3 on the iAS (Enterprise Edition) while its have Viewer Edition in it that cannot be remove. or we can just install User Edition on it without removing the Viewer Editon? thanks on advance.

  • When I open Reader why does screen flash and parts of document are not readable?

    When I open a PDF my screen flashes, changes color and then when the document comes up parts of it are blacked out. When I close the document the screen flashes again. I have just downloaded the latest version of Reader.