Hello Gurus,
Please guide me in following scenario :
FERT - X ---> HALB (subcontracting) - Y ---> ROH - Z
Requirement : X - 1000 , Y - 1000 & Z - 1000
In this case, when I will take the MRP for X ,then MRP will generate PR for Y & Z.
But in my case, client purchase the Z & sell it to vendor & then vendor will sell the Y to my client.  He wants the requirement of Y & Z both after MRP run of X .
FERT - X ---> HALB (Purchase) - Y ---> ROH - Z
What can I do to map this in SAP?
Thanks & Regards,
Sagar

Hi Sagar,
It can also be maped in following way. Please take your MM and FI Consultant with you.
It could be map in following way:
Create BoM for Z (FG) and add Y (SFG) & X (RM). Keep the procurement type for both as F. Use special procurement key as 30 for Y (SFG). Mark NOT RELEVANT TO COSTING indicator for X in BoM. Maintain MRP type = ND for X (RM).
Now when you run MRP system will only create Dependant requirement for X (RM) and it will check stock of Y (SFG) as well. If stock of Y (SFG) is not available, Subcontracting PR will be generated for Y (SFG).
MRP will not be accurate for X (RM) since it has got dependancy on Y (SFG) which is going to be subcontracted from some Vendor. You can look for Re-order point planning or you can adopt the way suggested by Satish or you can make a new Infostructure in MM which will be updated for consumption movements for X (RM) which later can be used to make its PR directly to Vendor.
Regards,
Shoyeb

Similar Messages

  • MD03- Run MRP for all the material

    Hi Expers,
    How to run the MRP for all the material in the Plant.In Transaction MD03 we can have the option for entering the only one material at one time.If we have 10000 material then do we have to run the MRP for 10000 time?
    Kindly guide me....
    Regards,
    Devi.

    MDBT transaction is used to for background MRP Run
    Click the below link for more details on how to proceed further.
    http://www.sap-img.com/pp019.htm
    Scheduling Background Jobs for MRP
    Transaction code : MDBT
    click Create Variant button (specified a variant name and click continue).
    Then fill in the following fields :- 
    Scope of Planning         : Optional (refer to Note if you want to specify a plant grouping)
    Plant                             : Your company Plant
    Processing Key             : NETCH
    Create PUrchase Req.  : 1
    Schedule lines               : 1
    Create MRP lists          : 1
    Planning mode              : 1
    Scheduling                    : 1
    Planning date                 : default date
    Click the Back button and you will be prompt Save Values.
    Type in a Description and click the Save button.
    After creating the variant, park your cursor at the variant and click the Schedule job button.
    Fill in the Date and Time value.
    Click Schedule periodically and you are prompt to choose the period.
    Click the Create button and you are done.
    To check, you can click the Show Scheduling button.
    Note :
    Define Scope of Planning for Total Planning in 'OM0E'.
    1. Choose New entries.
    2. Enter a key and a description for the scope of planning that you would like to define. Save your entries.
    3. Select the scope of planning and choose Sequence of plants/MRP areas.
    4. Choose new entries and enter the plants or the MRP areas in the sequence in which they are to be planned. 
        The counter determines the sequence.
    5. Save your entries.
    Hope this helps.
    Regards
    Dipak

  • Conversion of Planned Order to Purchase Requisition thro MD04 for Quota Arr

    While converting Planned Order to Purchase Requisition  thro' MD04 for a Quota Arrangement  material, on the screen in the Reference section Purchase org automatically does not default  while for a non Quota Arrangement material it defaults. Need P.Org to automatically default.
    Any suggestions
    Thanks

    Does anybody has no answer?
    I have done some researches and i have found that i have to work on the transaction MD14. I have also tested the next enhancement project
    LMDR2001
    LMDZU001
    but they are not called during the execution of the transaction even if those enhancements are activated.
    Lello

  • Ability to Change Overall limit in Purchase Requisition after PO creation.

    Hi,
    I have created a Service Purchase Requisition and released it.Then, I created a Service Purchase Order with reference to the above created Purchase Requisition and released and saved.
    Now, when I go to the Purchase Requisition after creating a Purchase Order, I want to change the values for the Overall Limit and the Expected Value but they are greyed out.
    But what I have noticed is that if I create a Standard Purchase Requisition and release it and then create a standard Purchase Order with reference to the standard PR and release it and save it, I am able to edit the values even after the PO has been created.
    Any help is appreciated.
    Thanks and Regards,
    Puneet Jhari.

    Hi ,
    I need to change the Accoun assignment category in back end not in fore ground.
    Is there any EXIT or BADI available for the same.
    Thanks,
    Ranjit

  • Purchase requisition with MRP controller

    Hi everybody, I need support because I have to control during purchase requisition to block users with specific MRP controller.
    I mean, user A only have permission to create purchase requisition with MRP controller Z and user B only have permission to create purchase requisition with MRP controller Y.
    Thanks for all the ASAP cooperation.
    Regards.

    Hi Mitra,
    You will find your answer here.
    MRP controller for PR document type
    Do let me know if it helped, as I might have to explore this option for an upcoming requirement.
    Thanks
    Shailesh

  • Delete Purchase Requisition after PO created

    Hi,
        I want to know if is possible to configure the system to delete automatic the purchase requisition after the PO is created with the PRequistion in reference.
    Best regards

    Hi,
      We have a workflow overall setting for the PR and in the PM module each order have a PR associated. So every time our people create a operaton the systeme create a new line in the PR and the global price change and the workflow restart. If the PO is not created is ok to restart the workflow but if the PO is create for those line I want to be out of the next process.
    Best regards

  • Quality info records: different pack configurations for same raw material

    how can i differentiate different pack configuration for same raw material in quality info records, as one might approved and the other not? that is, besides creating different material master for each packaging?
    thanks
    Alisa

    You need to use the MPN profile functionality that is a standard part of SAP.
    In Config under the purchasing define the MPN profile.  There are several options you can turn on/off including info records.
    You assign the MPN profile to your material. It now is considered by SAP to be an internal material number. 
    You then create a HERS material type for each separate manufacturer material number you have.  You only need the purchasing view for these materials.  You can also create purchasing text views, classification and some others if you wish.
    In the SAP approved vendors list (AVL), you then assign each manufacturer vendor(s) with the HERS material created.
    You create a Q-info record for each manufacturer/HERS material combination.
    Now, when you specify the internal material number in a PO, the system will tell you to order the MPN material.  When you do the drop down for the material now, it will show you the approved manufacturers allowed in the AVL for the ordering plant.
    When the 01 inspection lot is created you will have a vendor number as well as a manufacturer's number in the inspection lot.  The DMR can be done by the manufacturer or the vendor depending on how you set up the inspection plan. Q-info record will be used accordingly.
    Take a look at it and research it.  It's not hard to set up.
    FF

  • Purchase Order is generated after MRP for Material with MRP Type ND

    Hi Everyone,
    Material type := HAWA
    My material procurement type = F i.e. External Procurement.
    MRP Type = ND in Production server , and VB in Quality
    Lot Size = EX
    Material Status :- 15 Pre-release both for Quality and production server
    The Material is bulk material and bulk material indicator is set.
    Purchasing View is also maintained for the same.
    Planning Strat = Z5 Company specific
    Special procurement key:- Z7 Company specific
    I am running MD02 with following parameters.
    Create Pur Req =1, PR
    Create MRP List = 1, MRP List
    Delivery Schedule = 3, Schedule Lines
    Planning Mode = 2 Re- Explode BOM & Routing
    Scheduling = 1
    Issue:
    After MRP run, system is  generating PR, Though with MRP type ND purchase requisition should not be generated.
    Observation:- Looks like there is inconsistency of material date in Quality and production server.
    When I tried to run the planning , The Error message was generated"Material status is set to pre- release.
    After changing the material status to 20 (Active ) , when we run the MRP , The error message is generated "Material is not planned automatically "
    We havent been able to locate the root cause so far
    Please guide us
    Thanks in Advance,
    Ayaz
    Edited by: Ayaz Alam Khan on Feb 16, 2011 2:41 PM

    IF the material is ND, system won't Run MRP for the material
    Observation:- Looks like there is inconsistency of material date in Quality and production server.
    There is no link
    When I tried to run the planning , The Error message was generated"Material status is set to pre- release.After changing the material status to 20 (Active ) , when we run the MRP , The error message is generated "Material is not planned automatically "
    system will read the X plant  material status or plant specific material status first and then only system will read MRP type

  • Purchase requisition not generate for dependent requirement after MRP run

    Hello PP expert,
      In our MTO scenario after MRP run planned order generate for header material but no PR generate for BOM components, (BOM not explode) when we run MRP component level in MD02 PR generate, system showing message "40- No coverage not provided by master plan" in MD04 order tree. this problem coming after when we DIMP applied. I checked some OSS note also.
    Can any one provide right solution.
    thanks in advance.....its urgent as client requirement.
    regards,
    Amit Awasthi.

    Hi Amit
    You must select the green star for the correct answer, in order to close the thread.
    You may also select the yellow start for the helpful answers, in order to award points for those who helped you. See the blog below for more details:
    How to close a discussion and why
    I can see that most of your old threads are still open, therefore, I'd like to ask you to review and close them, by selecting the correct answer.
    BR
    Caetano

  • BADI/User exit for Purchase Requisition from MRP

    I am looking for a BADI or any enhancement when a purchase requisition is created or modified from MRP .ie. MD50 transaction. Can anyone help ?
    THanks in advance.

    Hello Shareen
    Have you had a look at package <b>MD03 </b>(contains transaction MD50). It contains lots of BAdIs. Perhaps the following ones may be useful:
    MD_PLDORD_CHANGE (BAdI for Changing Planned Orders)
    MD_PURREQ_CHANGE (BADI for changing purchase requisitions)
    However, I should mention that I have not found anything when I checked the <i>Where-Used-List</i> for these BAdIs (on ECC 5.0).
    Regards
      Uwe

  • Purchase Requisition Release strategy for MRP based Requisition

    Hello Gurus
    We want to set up the urchase Requisition Release strategy for MRP based Requisition ..Any can one Please share your experience about the impact down the road?
    Thanks
    Nick

    Hi,
    If you want include the MRP related PR in Release strategy.
    You need to include the field CEBANESTKZ-Creation Indicator (Purchase Requisition/Schedule Lines) in one of the characteristics which you create and include the characteristics value as per the field values like AReal time, BMRP, CConverted Planned order etc.. and include the charactristic in the Release Strategy will release group & release codes.
    So when ever the PR is created through MRP run then this creation indicator will update in the PR as per that release Strategy will trigger in the PR.
    there is one more option you need to create the separate document type as MRP PR then create document type as characteristics and include the values of all these document types and include in Release strategy.
    But it will  not pop up for direct PR from MRP run only trigger when planned order is converted to PR manually there you need to select this MRP document type then release strategy will trigger.
    I think first one is best suited.
    rgds
    Chidanand

  • For production - Raw material & WIP after system Live

    Hi All,
    I have taken the cutover data with WIP value for GOLIVE; we have put the value in WIP in GL for trial Balance;
    After System Live, we are facing the two scenarios to map in system.
    u2022     Open production which has no needed more raw materials (all included in WIP) to completion of production order.
    We have uploaded the finish product with movement type -521 and reduce the value from WIP with help of manual entry; but below scenario have confusion how to map.
    u2022     Open production which needs more raw material (apart of WIP) to complete the production,
    Please guide to me how to map in system.
    Thanks
    Rajesh Tiwari

    Hi,
    The best practice followed is you need to close the legacy system production order and you need to create a new production order in SAP. Against the new SAP production order number, you can issue the raw materials.
    Regards,
    V. Suresh

  • Purchase requisitions in MRP run

    Hi ,
    When MRP is run for the total plant , MD01,what should be the control parameter for create pur req ?.
    I checked by altering the control parameters for MRP run(MD01). When MRP is run with option 1 (in create pur. req) it creates pur requistion and when run with option 3, it creates planned order.
    In the plant there are raw material as well as semi  finished products. So when MRP is run for the total plant what control parameter should be used ?
    Regards
    ShankarR

    Hi Shankar,
    Once you define which type of procesing you need for Raw Materials and Semifinished products you can control the creation indicator per material with MRP GROUP in MRP 1 View (MARC-DISGR).
    You define this parameter per plant and you can assign it to different materials. Tx: OPPZ
    IE
    MRP Group
    0000              Creates Purchase Requisition
    0001              Creates Planned Order
    There are other parameters that you can control with MRP Group
    So for Raw Materials you can use 0000 and for semifinished product 0001. (Let you Key user know what he prefers, its going to depend on the business!!!)
    Kind regards,
    Federico

  • Creation of Purchase Requisition with MRP - MD02

    Hello,
    I have created a sales order using one material with MRP. When I run MRP-transaction MD02 for this material, a purchase requisition is created.
    What we want is to block the creation of the purchase requisition when the sales order has delivery block (code 02). I have been trying to use this enhancements; setting break-points in all function modules, but when running MD02 is does not stop there:
    MEREQ001      Customers' Own Data in Purchase Requisi
    LMDR2001      User exits restr. profiles of opt. pur.ord.-based load bldg
    LMDZU001      User exits in additional planning                         
    M61X0001      User exits PP-MRP materials planning                      
    M61X0002      User Exits PP-MRP Material Requirements Planning Evaluation
    Do you know a way to do this or also change data in the purchase requisition created with MD02?
    Thanks and regards.

    Dear ,
    Are you very particualr to process the Sales Order demand when there is a delivery block ?
    To restrict that  one you can do the following steps :
    1.Goto Sales Order -VA02-Select the line item -Double Click -Select the Schedule line  tab -Set Sechedule line item categoery as CN instead of CP.If it is CP then it will processed through MRP
    2.Change the pricining date and make credit block for sales Order and do not release though VKM3 so it will not be tearted through MRP run  to have PR geneartion
    Hope this is clear
    regards
    JH

  • Stock Transfer Reservation in spite of Purchase Requisition in MRP run

    Dear SAP gurus,
    We are running MRP heuristic on the PP/DS and we have different results comparing our development and productive environments.
    In our productive environment purchase requisitions are generated and in our development environment stock transfer reservations are generated as result of the MRP run.
    Where can I check differences of configuration that would be causing this?
    Thanks and BR
    Mauricio

    Mauricio,
    I guess I was not clear in my suggestion, I apologize.  Differences in T001W between ERP dev and prod will not necessarily generate your problem, differences in sourcing within APO between APO dev and APO prod will generate the differences.  I only mentioned the vendor number because a transportation lane can exist 'source plant > destination plant', but also you can have a transportation lane 'vendor of source plant > destination plant' which would also have an impact on the type of req created.
    Easier to check the sourcing, //PWBSRC1, mentioned earlier.  Your dev system should contain no objects that relate to Stock Transport orders.  You can delete the STO sourcing records within that transaction, which will also delete the material assignment to the Transportation lane.  Hopefully you will then get the default external supply proposal, which is normally a Purchase req.
    Also check for presence of quota arrangements //SCC_TQ1.  Delete any that unnecessarily refer to an STO object.
    Best Regards,
    DB49

Maybe you are looking for

  • How can I use find coordsys(p​attern)2 to locate for template in an image when the image is threshold-​ed?

    I'm trying to locate for a template in an image, and the image is threshold-ed. I tried to threshold both the template and the image to try if it can locate the template, but there was an error, it said that the template has not enough contrast or so

  • Change a Sub-Project to be a "standalone" project

    I have searched but cannot find an easy answer to this. I am working with someone who created a Master Project and sub-projects using Project Server 2010 and then deleted the master project, the sub-projects can now only be accessed in PWA if the sub

  • Deploying Azure Web Site and Custom Domain Name

    I'm new to Azure and not at all familiar with the various methods of publishing to Azure via Git, etc. I belong to the old school of plain old IIS folder structures and uploading HTML files to Inetpub directory for deploying web contents. I have crea

  • My speakers won't work on my new computer with a Soundblaster live! 24

    When I was in college, I bought a Gateway computer that came with with Boston Acoustics speaker model BA735. Recently, I bought a new Dell computer with the Soundblaster Li've! 24 bit and my speakers won't work. I have an old set at my house that wor

  • Battery drain is excessive

    i am getting a big drain on my iphone5 battery and i need to find out what app or something that is causing this i have air plane mode and bluetooth mode off and still i am getting a battery drain too fast and its at a point being to recharge 3x a da