Purchase requisition flow

hiiiiiiiiii
i m new in company as a Abapr.
i want to know proper flow of purchase requisition and step by step procedure for making them.
its urgent
thanks.

tcode me51n
give material
give plant
give quanity
give purchase group
give purchase org
give requester
if u want u can asign the source of supply auto. or maually by marking the check box of source determination
to create pr u need to have
vendor master data ,material master data

Similar Messages

  • Purchase Requisition Against Sales Order Required Flow

    Dear All,
    I want to create Purchase Requisition against the Sales order user Defined committed quantity (i.e in Mtr) and on the basis of Purchase requisition i want to create Purchase Order.
    Here the Purchase order is standalone or we can take the reference of  one or more than one Purchase Requisition no.,
    Please help me out to map the perfect flow of this scenario to map purchase requisition.
    Note: we can also able to  generate standalone Purchase Order.
    Regards,
    Sumeet Vaity

    Hi Sumeet Vaity
    Use SAP B1 8.81 . Purchase  Requisition available in SAP B1 8.81. You not need to make Purchase  Requisition AddOn  update your product and use it . if u want to developed add on for lower version so u can install 8.81 and can take idea about it.
    Thanks
    Khan Imran

  • Work flow for Purchase requisition

    HI EXPERTS,
       I am new for MM workflow, my client asked me to overall purchase requisition approval through work flow,i did configuration like
        BUS 2105 -OBJ TYPE
        WS20000077-RECIVER TYPE
        RELEASESTEPCREATED-EVENT TYPE
        AND ASSIGN AGENT ALSO.....
       its working fine,and i get messages but my problem is  i didnt release pr from inbox,
       again i used me 54n for release .is there any chance to release pr from in box,,,
       and also how to change time in time stamp column,i am getting wrong time please help me...
       Thanks in advance
    Thanks,
    siva

    You need to verify that there is a teminating event. A terminating event works so that if you perform the action outside of the workflow inbox, the linked work item is "logically deleted" from the user inbox.

  • Purchase Requisition Is Being Getting Created In APO But not being publishe

    On doing, SNP Location Heuristics on  one of our item, purchase requisition is being getting created in APO (We are able to see the same in RRP3) but the same is not being getting published in ECC. On doing CCR of the said location - product combination, it is showing Error u201C182u201D. We have checked the following parameters :-
    Item is an APO Item i.e. X0.
    It is having a proper Purchasing Group.
    As This be a purchase item. So, it is having a valid single Purchase Info Record.
    Item Has Not Been Blocked At Any Level.
    Vendor From Whom This Item is being getting procured is also open (Not Blocked).
    Please suggest what else to be checked  and what else can be the reason for non-flowing of purchase requisition from APO to ECC.
    Thanks & Best Regards,
    Sanjeev Chugh

    Hi Sanjeev,
    Please check change pointers if any and send them to ECC. Check the order in the planning book whether it has picked the same source for which there is a Purchase info record. If these all are fine then You send them to ECC from the CCR then check the log in ECC through CFG1 tcode.
    Regards,
    Kishore k Reddy

  • Sales order item text to purchase requisition

    Hello Team,
    we have scenario in which we create the sales order and while creating the sales order we put the production memo text at the item level under text tab in it.
    We have define copying rules for the production memo text under PR customizing text types to get it copied from the sales order. But when we are creating the PR for the sales order then the production memo text is not flowing into the purchase requisition.
    I checked some OSS notes and found recently released note 448814 which says that text does not gets copied to PR when PR is created manually from the sales order ( question no 24 and 25 in the note ) due to technical reasons and it gets copied only when the PR gets created directly from the sales order.
    Could you please help me to know if this is standard problem or some other settings exists and if anyone have other solution to it. ?
    Thanks and Regards,
    Deepak Gupta

    Hi Jurgen,
    Thanks for the reply. I was expecting to know if others have came across similar kind of issue and after following up with SAP, if they have provided some other solution.
    Thanks
    Deepak

  • Error While Creating Workflow for Purchase Requisition Rejection

    HI Experts,
    Purchase Requisition No is not Displaying in the Business Workplace Inbox after my Work  flow got triggered.
    In Work flow i am Using the Task  97600004  which i copied from the Standard Task  65400032. This Task i called in the Activity Step having Work Item Display Tab. In this Tab while i am checking at Work Item Text  for Identification  of Work item in work flow inbox level it is Giving Error "Container element '_WI_OBJECT_ID' does not exist and also Insert Expression is in Disable Mode.
    In Business Workplace Inbox i am getting message as "Purchase requisition  00000 rejected".
    Please Suggest where i am Committing Error.
    Thanks in Advance
    Srikanth Kumar

    HI.
    I Have Checked the work flow as suggested Dheepak
    In Start Event of Work flow i declared BUS2105 as BOR Object . The Task which i copied contains BUS2009 as default.
    As Raj Suggested In Task i have Created a New Element BUS2105 at Container Tab and set binding in task and set the Binding between Work flow and Task. Now it is working fine and i am getting the PR No in the Message of SBWP inbox.
    But i Having one more doubt regarding this issue only Why BUS2009 BOR object Type is not working which is the Task as default even though its binding is set between work flow and task?
    Thanks Dheepak and Raj for Your Valuable Suggestions. My gmail id is srikanth537. Can u add me In your Friends list.
    Thanks
    Srikanth Kumar
    09937876902
    Edited by: Srikanth Kumar Talasu on Dec 23, 2008 11:59 AM

  • Creation of Purchase Requisition from a BID

    Hi,
    I am trying to create a purchase requisition from a bid instead of a purchase order. Does anyone have any idea on this?
    Thanks
    Sunny

    Hello,
    are you trying to create a local SC or a backend PR ?
    If you are in classic mode (so PR and not SC), you could try to derive the PO flow to create a PR instead.
    But this is not really clean.
    The best way is to add a new button "Create PR" in quote screen (or rename the create PO if you don't use it), linked to your own fcode processing and finally call the META_REQUISITION_CREATE in SRM (instead of META_PO_CREATE).
    The last point would be to create a link BID_INV>BID>PR to be displayed in document flow. You have to check if it is possible, because sometimes the system is designed for limited possible flows and does not take into account the flow you want to add.
    In standard, you can create directly a backend PO only if the bid was created from a SC in the sourcing cockpit. Otherwise use local or extended PO (replicated in R/3).
    If this is the case, FM BBP_PD_SC_TRANS_MULTI_BE_PO will transfer the initial SC items to next document, which is a backend PO. You would need to operate some changes here to create PR.
    Rgds
    Christophe

  • Integration between Purchase Requisition  & external web services

    Hi
    We have a requirement to Integrate  Purchase Requisition Process in MM & external web services(Portal).So we wanted to know what are the third party tools that SAP supports inorder to integrate both the systems.The requirement is like a business user from  Logistics team enters a PR on  a portal and the data flows to SAP through a connector and creates  a PO automtically if it has got sufficient data.
    Regards
    Prasad

    Hi,
    If you have the any transaction codes that are required to do the process in the backend MM, use the same tcodes and create the SAP Transaction iViews in the Portal.
    You can have three GUI (for look and feel) in the Portal iViews, SAP GUI for Windows that is the default one, SAP GUI for HTML has the Web look and feel, which requires you to configure the ITS and SAP GUI for Java. Depending on your requirement you can use any of the three.
    Hope this will help you.
    Sheetal
    Reward if helpful.

  • Purchase requisition creation (STO) from Sales order

    Hi Gurus,
    Read the following scenario:
    Sales order is created with delivery plant A. No stock on plant A.
    Purchase requisition is created from plant B to plant A (intra-company flow or stock transfer order).
    Problem is that the purchase requisition needs a price. It is not logical because intra-company flow (stock transfer in same company flow) is like a stock transfer without purchasing. So in my mind, I don't have to maintain price.
    Also if I use ME27 to create manually STO between both plants, price is not asked.
    Other question is: is it possible to create directly a purchase order when sales order creation (and not purchase requisition, newt convert into PO)?
    Many thanks.
    Stéphane

    Hi Stéphane Vituret, Did you manage to find a solution for this. I have a similar problem as well.
    Please find the scenario below.
    Cusotmer places order of Mat-XX to Company A. The Company A creates PO to Company B. Company B delivers to Company A and then invoices Company A. Company A receives the goods into own stocks. Now the Company A delivers to the customer from its own stocks and then invoices Customer.
    I decide to go ahead with the Individual Purchase order solution and since the Company A is buying from Comapny B, I decided to integrate the Cross Company STO flow in the procurement part. Hence the flow in SAP is like;
    Cusotmer placese order to Company A
    Comapny A creates a Individual Purchase order type Sales order. So the Item category is TAB.
    This sales order generates a PR. PR is conveted into a CC_STO as thenvendor is Plant B in this case . Now this STO appears in the delivery due list of plant B.
    Now I genreate the delivery to move stocks from plant B(of co.cd B) to Plant A(of co.cd A).
    Here is the problem. I am not able to do PGI as the system checks for "sales order" stock at plant B and throws error
    "Sales order stock 36637 000010 does not exist". This should not be the case as the stocks should get attached to the sales order only when recieved into Plant A. Hence system should not check for "sales order stock" at plantB while trying to deliver from Plant B to Plant A.
    Lets take a normal IPO scenario.
    CusotmerA places order of Mat-A to Company A. This sales order generates a PR. The Company A converts the PR into a std.PO to external vendor. The PO from the sales order will have a account assignment "M- Ind. cust. w/o KD-CO". The stocks will be received into Plant with spl indicator "E" while GR (MIGO). Now the system ensures that this stock can only be delivered against the particular sales order. Thus the stock procured for the customerA is delivered to customerA and not consumed by anybody else. In this case there is only one delivery involved, in SAP, which is 601 mvmt type from the Plant A.
    However if the vendor becomes another Plant (Plant B) belonging to another company code then there are two deliveries involved in the SAP system one with mvmt type 643, from Plant B to Pant A, and the second with 601 from Plant A to the customer. Hence the system should check if the stocks are attached with a spl indicator only during the second delivery of 601 mvmt type. I am facing a problem because the system does it for the first delivery itself. If you know the answer please do let me know. I really appreciate it. Thanks a lot in advance.

  • Workflow for MM purchase Requisition steps required

    Dear all,
            I am trying to configure purchase requisition Workflow.
            I am working with Work flow, WS 00000038
            I have assigned agents to TS 20000162
            Now how to proceed further, do i need to maintain some more settings
            or i should try to test system.
            Regards,
            Gaurav sood

    Under the assumption that things have not changed much since 4.70, here's quick introduction:
    The workflow is started only when a relevant release strategy is found, so customizing of release strategies is a very important (first) step here.
    In the Implementation Guide you find the customizing in the following path:
    Materials Management
    -- Purchasing
    -- -- Purchase Requisition
    -- -- -- Release Procedure
    -- -- -- -- Procedure with Classification
    Only the procedures with classification are relevant if you want to use workflow to notify about requisitions waiting for release.
    First you must set up a classification class if that has not already been done. Derive your characteristics from the structure CEBAN. The online help is not too bad, I had never set up classifications before and managed to get it working.
    If you need data that are not available in CEBAN, or you want to modify them for the purpose of determining the release strategy there is an enhancement you can implement, and there are customer fields you can use. The enhancement definition's name is M06B0002.
    As an example of what you can do, I have used it to set the company code in one of the customer fields, and to change the account assignment type. However, whether you need this enhancement or not depends strongly on what data you use to determine your release procedures (a step in customizing you will get to later).
    When that is done you define release groups and release codes. Release codes are defined within each release group. Whether you should use one group or several groups is often a matter of choice.
    I myself prefer using several groups even if I don't have to, so long as it doesn't lead to having to define duplicate release strategies (which you will soon get to). So, if there is some characteristic that clearly separates your release strategies, e.g. the highest amount that does NOT require release etc, you can define one group for each value (group) of this characteristic.
    For instance, if some company codes require release for everything worth more than 100EUR while the default is to require release from 10.000EUR you could create to release groups. None of your release strategies will be duplicates since the value from which release is required will be different and you thus need to have that as a characteristic.
    You then check that the set-up of release indicators is OK, and then you are ready to start defining the strategies. Release stragies are defined within each release group, and use one or more release codes (two or more release indicators).
    It is fairly self-explanatory once you get into the screens. The thing to be observant about is to not define overlapping strategies, as this will prevent the solution from working.
    When you are done, and have tested the solution in DEV it is time to transport it to the QA system. That's when I got a rather unpleasant surprise. The classification data are not transported, so both the characteristics and class, as well as the classification data in each release strategy had to be redefined. And in roughly two hours I have to do it again in production.
    It is possible to transport classification information, it is described in SAP OSS Notes (different solutions for different versions).

  • Reciept element purchase requisition not appearing in  mrp order report

    Dear Gurus
    Receipt element purchase requisition is not appearing when I am trying to see the order report after running the mrp for the finished product .But the reciept element planned order is appearing for the semifinished products which are in the bom of the finished product.And if stock for raw materials are there then also it is showing the reciept element stock.Why is this happening ?
    Regards
    Sandip Sarkar

    Unable to interpret your query.
    Based on my guessing.... a PR is not visible for the Finished material as it must be a make material & if a planned order is showing up it means there is not enough stock to meet the demand. Now the dependent demand flows down from the finished to SFG & RM respectively & hence the supply proposal.
    The above is a straight forward planning cycle flow, so what the issue am not able to figure it out. Either you upload some screenshots & paste the link here or provide a detailed explanation to get a clear understanding.

  • Purchase Requisition & Shopping cart status report

    Hi
    Is there any standard BW report by which we can get the Purchasing Requisition , Shopping Cart & its status report.
    Thanks in advance
    Amit

    I have got standard report which is close to my need.
    However I cannot find the below 2  datasources mentioned as per the SAP document
    0BBP_DOC_ITM_1  Document Flow (Item Information) 
    0BBP_DOC_HDR_1  Document Flow (Header Information) 
    Any pointers hoe to find them.
    Regards
    Amit

  • Purchase Requisition from CRM Service Order

    Hello Everybody,
    I am trying to create Purchase requisition from Service Order for Service(Material type DIEN) as well as Material (Material type HAWA). I have maintained all the necessary configuration in CRM as well as ECC, like in CRM,  Logistic integration we maintained settings for Purchase requisition and in ECC we have maintained Document type and schema for the purchase requisition.
    For information purpose, I have created Service Material in ECC as DIEN and item category group as LIES.
    As soon as we save the Service Order in CRM with that item category, it should create Purchase requisition in ECC and the document flow in CRM should get activated.
    Currently we are not able to create Purchase requisition in ECC.
    Kindly let me know if there’s any configuration settings missing in CRM as well as ECC or if note to be applied.
    Best regards,
    Anup Bansal

    Hi Anup,
    I am facing purchase requisition creation problem for service products from crm.
    I have seen your query which was posted on same issue, so i thought i could get some help.
    The problem here is when i am saving the service order i am getting the below message.
    Enter a (default) purchasing group for material group SUB_MC (Notification E CRM_SRV_LOG_EXT_OLTP 002).
    I have actually downloaded mat_dien materials from ecc to crm and for material purchase group is already assigned for one plant, but still not able to recognise.
    Please help me out.
    Thanks in advance.

  • Purchase Requisition conversion into Purchase Order

    Hi,
    We are developing an intercompany process and we have a problem with the purchase requisition conversion.
    When we convert the PURCHASE REQUISITION into PURCHASE ORDER we need to mantain purchase requisition ITEM number/s.
    For example:
    PURCHASE REQUISITION: 10015720 / 50 / 60 ---> PURCHASE ORDER: 210515 / 50 / 60   
    We are trying to do it with some enhancements but we have not found any solution. Is posible to customize this requirement ?
    Thanks in advance.
    Regards,

    Hi Orion
    I suggest you to translate it to english before somebody feels awful. Orion's customer wants mantain a kind of register to trace or manage the traceability for this flow from SO to PO in a cross company scenario.
    If a understand you, you do this flow:
    SO from a customer not cross company-> request from this SO to other company cross company -> PO with ME59 (is the third part customer if I'm right)
    Do you check all flow in VBFA table? I suggest to see the SAP Note 627846 - AFS: Purchase order document flow for
    sales order incorrect, although it's so older, it gave me ideas in the past. I suggest you to avoid 'handle' the fields related with key fields (number of documents, number of items, and so on). Create reports or create customer tables and populate records for this trace. After, you can create lists for your customer to know about this traceability.
    If you are agree other possibilty is enhance SAP tables with customer fields and see them in the documents. There a lot of tools to do it (VOFM subroutines in the copy rules, BADI's and enhancemetns to see customer fields in new tabs in SO, PO and so on).
    I hope this helps you
    Regards
    Eduardo
    Edited by: E_Hinojosa on Sep 26, 2011 6:42 PM
    Edited by: E_Hinojosa on Sep 26, 2011 6:42 PM
    Edited by: E_Hinojosa on Sep 26, 2011 6:43 PM

  • Purchase Requisition No data satisfying selection criteria

    We have created a Maintenance Notification and converted it into Maintenance Order, after approval of maintenance Order it will generate a MM purchase requisition automatically.
    But upon checking on Me53N or any other report for MM PR the PR does not exist. on Me53n it gives the error: No data satisfying selection criteria
    but the PR exist on table EBAN.
    thanks God bless

    If you give proper inputs in ME5K or ME5A, you can get the PR list without any problem.
    Also, while selecting PR in ME53N, have you given proper PR number directly or are you searching through some Search help option??
    Please post your screen shots PM Order document flow, Operation tab, Components tab, ME53N search steps as well as MM PR reporting selection screen with that error message.

Maybe you are looking for

  • Can i use my joystick on the sb live gamepo

    Hello all you experts. I have a simple one, here. (not me, the question!). How do I get my pc to recognize my Wingman Extreme 3D joystick while it resides on the SB Li've gameport? Is this even possible? My pc doesn't have a 5-pin connector, and i ge

  • Black and White RDP session

    Is it possible to view an RDP sessions as black and white?  I'm considering ordering a privacy screen, but I think if the RDP sessions could be black and white that would be sufficient.

  • Accounting doc Open can't reversed

    Hi I have cancelled billing document but accounting document is still appearing as Open Item. How this accounting document can be reversed. This problem is coming for the billing document which was cancelled without logical system. However after conf

  • Find Report Name based on Report ID

    How do I find out the report name based on the report id ('D12C939B-4309-4364-A025-BFDB5203EE0B')?

  • Drake Installed but no Gauges Available in Portal

    We recently installed Drake and we are working on configuring the ability to see workbooks and worksheets in Portal. When I go to the "BI Discoverer" portlet group, I only have options for list of workbooks and worksheets. There is no entry for Gauge