Purchase Requisition, overall release
Hi All,
I am using the overall release for my release groups. The releasing strategy depends on the cost center.
The releasing is workling fine so far, after I created a PR, the release tab appears in the header. BUT if I enter several items in one PR with different cost centers, the release tab does not appear. This also happens, if I enter 2 items with different cost centers in the PR and both of them are assigned to the same release strategy.
Are there any configuration in SAP to prevent this or do I have to use the itemwise release for that?
Thank you!
Use userexit
Enhancement : M06B0005
Component : EXIT_SAPLEBND_004
CR : RDAK903063 SPOREDDY 04/05/07 changes to pick the release
strategy if all the cost centers are same for all
line items. Since the user Exit is activated the
program is forcing the data to go through import and*
field I_CEBAN-KOSTL is not blank the user exit is
filling blank values to E_CEBAN during export.
Similar Messages
-
Purchase Requisition Overall Release problem with several CostCenter
Hello Gurus!!
I need your comments!!!
I define the Purchase requisition as Overall Release, and woks !! but I have a Issue.
I have an entry in the CL24N txn as follow:
AccAssgCat = K
Plant = CC01
CostCenters = 10001
10002
10003
totalAmt = 1USD to 1000US
So when I create my purchase requisition with only 1 Cost Center the release strategy is called and PR can be released.
But When I create the purchase requisition with CC 10001 and 10003, the requisition is not subjet to release!!! (note TotalAmt = 15usd)
I assume that as both are into the release strategy the system will take both CC and ask for release!!
What I can do to fix this situation??Dear Marco Antonio,
I have never faced your issue, but have an idea of what you can do.
Activate Enhancement M06B0005 EXIT_SAPLEBND_004
Then in the program zxm06u31 put the following code line:
e_ceban = i_ceban.
and also a breakpoint so that it stops automatically upon PR verification or saving.
Activate and then create a PR with the problem you are facing. On saving the program will stop in your breakpoint.
Look at structure i_ceban there you will find the values that your release strategy is getting from the document and with which it will try to determine the strategy based on your classification.
I the standar logic is not what you want maybe you can put some logic of your own based on account assignments in structure C_EBKN.
Well, tell me what happens
Best Regards,
Sebastián Ligueros -
Purchase Requisition Overall release amount
Hi,
I am working on PR overall release amount workflow.
How can i find the overall release amount in the tables of PR while entering into the workflow.
Depending on this amount we need to further proceed for approval process.
Regards,
Gopinath Addepalli.Dear Marco Antonio,
I have never faced your issue, but have an idea of what you can do.
Activate Enhancement M06B0005 EXIT_SAPLEBND_004
Then in the program zxm06u31 put the following code line:
e_ceban = i_ceban.
and also a breakpoint so that it stops automatically upon PR verification or saving.
Activate and then create a PR with the problem you are facing. On saving the program will stop in your breakpoint.
Look at structure i_ceban there you will find the values that your release strategy is getting from the document and with which it will try to determine the strategy based on your classification.
I the standar logic is not what you want maybe you can put some logic of your own based on account assignments in structure C_EBKN.
Well, tell me what happens
Best Regards,
Sebastián Ligueros -
User exit/BADI for Purchase requisition through release of Process order
Hi ,
i need to add some text to the Pur Req.
The Pur Req will be created THROUGH the release of PROCESS order. Please let me know any exits are available for the same.
regardsHi
Check the following Exits and BADI for Pur Requisition
Enhancement
MEVME001 WE default quantity calc. and over/ underdelivery tolerance
MM06E001 User exits for EDI inbound and outbound purchasing documents
MM06E003 Number range and document number
MM06E004 Control import data screens in purchase order
MM06E005 Customer fields in purchasing document
MM06E007 Change document for requisitions upon conversion into PO
MM06E008 Monitoring of contr. target value in case of release orders
MM06E009 Relevant texts for "Texts exist" indicator
MM06E010 Field selection for vendor address
MM06E011 Activate PReq Block
MMAL0001 ALE source list distribution: Outbound processing
MMAL0002 ALE source list distribution: Inbound processing
MMAL0003 ALE purcasing info record distribution: Outbound processing
MMAL0004 ALE purchasing info record distribution: Inbound processing
MMDA0001 Default delivery addresses
MMFAB001 User exit for generation of release order
MRFLB001 Control Items for Contract Release Order
AMPL0001 User subscreen for additional data on AMPL
LMEDR001 Enhancements to print program
LMELA002 Adopt batch no. from shipping notification when posting a GR
LMELA010 Inbound shipping notification: Transfer item data from IDOC
LMEQR001 User exit for source determination
LMEXF001 Conditions in Purchasing Documents Without Invoice Receipt
LWSUS001 Customer-Specific Source Determination in Retail
M06B0001 Role determination for purchase requisition release
M06B0002 Changes to comm. structure for purchase requisition release
M06B0003 Number range and document number
MEQUERY1 Enhancement to Document Overview ME21N/ME51N
MELAB001 Gen. forecast delivery schedules: Transfer schedule implem.
MEFLD004 Determine earliest delivery date f. check w. GR (only PO)
MEETA001 Define schedule line type (backlog, immed. req., preview)
ME590001 Grouping of requsitions for PO split in ME59
M06E0005 Role determination for release of purchasing documents
M06E0004 Changes to communication structure for release purch. doc.
M06B0005 Changes to comm. structure for overall release of requisn.
M06B0004 Number range and document number
Business Add-in
ME_PROCESS_REQ_CUST Enhancements for Processing Enjoy PReqs: Customer
ME_PROCESS_REQ Enhancements for Processing Enjoy PReqs: Internal
ME_PROCESS_PO_CUST Enhancements for Processing Enjoy Purchase Order: Customer
ME_PROCESS_PO Enhancements for Processing Enjoy Purchase Order: Intern.
ME_PROCESS_COMP Processing of Component Default Data at Time of GR: Custome
ME_PO_SC_SRV BAdI: Service Tab Page for Subcontracting
ME_PO_PRICING_CUST Enhancements to Price Determination: Customer
ME_PO_PRICING Enhancements to Price Determination: Internal
ME_INFOREC_SEND Capture/Send Purchase Info Record Changes - Internal Use
ME_HOLD_PO Hold Enjoy Purchase Orders: Activation/Deactivation
ME_GUI_PO_CUST Customer's Own Screens in Enjoy Purchase Order
ME_FIELDSTATUS_STOCK FM Account Assignment Behavior for Stock PR/PO
ME_DP_CLEARING Clearing (Offsetting) of Down Payments and Payment Requests
ME_PURCHDOC_POSTED Purchasing Document Posted
SMOD_MRFLB001 Control Items for Contract Release Order
EXTENSION_US_TAXES Extended Tax Calculation with Additional Data
ARC_MM_EKKO_WRITE BAdI: Enhancement of Scope of Archiving (MM_EKKO)
ARC_MM_EKKO_CHECK BAdI: Enhancement of Archivability Check (MM_EKKO)
MM_EDI_DESADV_IN Supplementation of Delivery Interface from Purchase Order
MM_DELIVERY_ADDR_SAP Determination of Delivery Address
ME_WRF_STD_DNG PO Controlling Reminder: Extension to Standard Reminder
ME_TRIGGER_ATP Triggers New ATP for Changes in EKKO, EKPO, EKPV
ME_TRF_RULE_CUST_OFF BADI for Deactivation of Field T161V-REVFE
ME_TAX_FROM_ADDRESS Tax jurisdiction code taken from address
ME_REQ_POSTED Purchase Requisition Posted
ME_REQ_OI_EXT Commitment Update in the Case of External Requisitions
ME_RELEASE_CREATE BAdI: Release Creation for Sched.Agrmts with Release Docu.
ME_DEFINE_CALCTYPE Control of Pricing Type: Additional Fields
ME_CHANGE_OUTTAB Enrich ALV Output Table in Purchasing
ME_CHANGE_CHARACTER Customer-Specific Characteristics for Product Allocation
ME_CCP_DEL_DURATION Calc. of Delivery Duration in CCP Process (Not in Standard)
ME_CCP_BESWK_AUTH_CH BAdI for authorization checks for procuring plant
ME_CCP_ACTIVE_CHECK BAdI to check whether CCP process is active
ME_BSART_DET Change document type for automatically generated POs
ME_BAPI_PR_CREATE_02
ME_BAPI_PR_CREATE_01
ME_BAPI_PO_CREATE_02
ME_BAPI_PO_CREATE_01
ME_BADI_DISPLAY_DOC BAdI for Internal Control of Transaction to be Invoked
ME_ACTV_CANCEL_PO BAdI for Activating the Cancel Function at Header Level
MEGUI_LAYOUT BAdI for Enjoy Purchasing GUI
ME_CHECK_ALL_ITEMS Run Through Items Again in the Event of Changes in EKKO
ME_COMMTMNT_REQ_RE_C Check of Commitment Relevance of Purchase Requisitions
ME_COMMTMNT_REQ_RELE Check of Commitment Relevance of Purchase Requisitions
ME_COMMTMNT_PO_REL_C Check for Commitment-Relevance of Purchase Orders
ME_COMMTMNT_PO_RELEV Check for Commitment-Relevance of Purchase Orders
ME_COMMITMENT_STO_CH BadI for checking if commitments for STOs are active
ME_COMMITMENT_RETURN Commitment for return item
ME_CIP_REF_CHAR Enables Reference Characteristics in Purchasing
ME_CIP_ALLOW_CHANGE Configuration in Purchasing: Changeability Control
ME_CIN_MM06EFKO Copy PO data for use by Country version India
ME_CIN_LEINRF2V BADI for LEINRF03 excise_invoice_details
ME_CIN_LEINRF2R BADI for CIN India - Delivery charges
ME_CHECK_SOURCES Additional Checks in Source Determination/Checking
ME_CHECK_OA Check BAdI for Contracts
Reward points if useful
Regards
Anji -
Purchase requisition create/release
Hi
I am creating purchase requisition. And i want to release this requisition.
But in my created purchase requisition there is no tab such as release strategy
And i want to keep my purchase requisition as blocked initially and later i want to release it. Can u please tell me what are the configuration or release procedure i've to do to make this happen.
I know purchase requisition can be released be me54n. But my created purchase requisition is not release relevant.
I hope u understood.
with regards
mandeepHi Mandeep,
For release strategy cstomising u need to go spro
Matl mgmt>Purchasing>Purchase requisition>Release procedure with classification
there u maintain, characteristics, class, create release strategy and maintain, release group, release code and indicator etc. Once u do all this then u will get the tab in PR
hope this helps
regards
Anand.c -
Creating purchase Requisition and release Overview
Hello,
We have some User which have the authorization to create a purchase Requisition and also to release it by themselves.
We have to Monitor this cases and I' looking for a possibility to check this on a easy way.
I found the Report "Changedocu_read". There I can check several changes in the PR and see who released it. But there I can not see which User created the PR.
The table EBAN has the informations about the User who created the PR and if it had to be released and some more informations. But the informations who released the PR is missing.
I tryed a table-join of the tables EBAN and CDHDR. But it was not possible, because the PR Number (Filed "BANFN" in the EBAN) has not the same format as the number in the Filed "object value" in the table CDHDR.
Perhaps someone has an idea ?
Or there is an Standard Transaction which I did not found to have an overview of the PR and the releases
It would be enough to see following informations with one Join or Transaction:
-PR Number
-Creation Date
- Transaction code
-Change Date
-Release Status
-Released date
-Released by User
I have the same Topic also by purchase orders and the release of them.
Thank you in advance
Regards
DirkThanks both for the quick reply.
@AKPT
The Transaction is nice and helpful to Display some informations. But similar results I also receive when I use the Programm : "changedoc_read". I also had the idea to join the informations of the 2 sources in Excel. For me this Workaround would be ok.
But unfortunately I' m looking for an simply way (for the Enduser). To get this informations mentioned above in one overview directly in SAP.
They have to use this check regularly, to Monitor if there were some wrong Releases.
If there is not such a way then we have to join it in Excel.
But if you have some other suggestions I'm happy to hear them.
Regards
Dirk -
Purchase Requistion : Overall Release Problem
Hi everybody,
Have a peculiar problem where Item Level release seems to be working fine. And the first time we want to use release at header level and its not working.
The OverReqRel (overall requisition release) is 'checked' [at release group level].
There is just one class, one characteristic within that class (document type).
There is just one group, release code, release indicator and release strategy.
The classification has 'NB' as the document type to be controlled.
The simulation works fine.
The 'Check Release Strategies' shows 'all green' with no errors.
But when we create a PR (txn ME51N) for document type NB, this procedure does not kick in (hence i dont see a new tab at the header level asking for a release).
We have been using item wise release before and are testing the viability of release at header level.
FYI. This is a test system (sandbox) where we have NO configuration for release procedure. This is the first strategy that has been created for testing.
Any help in getting this to work is most welcome.Hi,
For the document type NB, did you flaged as PR header level release.
Regards,
Ramakrishna -
Purchase Requisition(PR) release related
Hi ,
We have in our system PR release strategy - Release strategy without classification.
For releasing PR's at the moment we have roles assigned at different levels.
For example a person having role z_release_lvl_1 will have access to release codes 01 ;
z_release_lvl_2 will have access to release codes 01 and 02.
z_release_lvl_3 will have access to release codes 01 , 02 and 03....and so on till
z_release_lvl_6 will have access to release codes 01 , 02 , 03 , 04 , 05 and 06.
Requirement - We want that anyone who creates a PR should not be able to release his own PR to reduce the risk of fraud.
Release level 6 role would be with senior management. So at the moment they can create PR's and also release then because they have access to all release codes from 01 till 06.
Main concern is for people who have access to z_release_lvl_1 because these people can raise requisitions and also approve them on their own.
Any ideas of how to restrict users who themselves raise PR's can be stopped from releasing also ?
Thanks in advance.
Regards,
VinayakHi Vinayak,
As far as your Scenario is concern,
1) why the person who is creating the PR, is having ME54 Authorization.
2) you can control the same via Roles and Authorization.
3)
You Said
For releasing PR's at the moment we have roles assigned at different levels.
For example a person having role z_release_lvl_1 will have access to release codes 01 ;
z_release_lvl_2 will have access to release codes 01 and 02.
z_release_lvl_3 will have access to release codes 01 , 02 and 03....and so on till
z_release_lvl_6 will have access to release codes 01 , 02 , 03 , 04 , 05 and 06.
why is it that the person with role Z_release_M_2 is having the Authorization for releas e code 02.
if the person with the with the role is Z_RELEASE_M_6 is having the authorization of all the release codes 01-06 then there is no point of having any junior level.
they can create the PR themselve and release it and the procure the material.
apart from this as the business says that the Creator of PR shoild not have the Approval Authorization and the PR approval Authority should not have the releasing Authority.
Hope I have helped you out.
Regards,
Yawra Khan -
User exit/BADI to for Purchase requisition through release of Process order
Hi ,
i need to add some text to the Pur Req. The Pur Req will be created through the release of PROCESS order. Please let me know any exits are available for the same.
regardsHi,
check the below enhancements in transaction SMOD.
CCOWB001 Customer exit for modifying menu entries
COIB0001 Customer Exit for As-Built Assignment Tool
COZF0001 Change purchase req. for externally processed operation
COZF0002 Change purchase req. for externally procured component
PPCO0001 Application development: PP orders
PPCO0002 Check exit for setting delete mark / deletion indicator
PPCO0003 Check exit for order changes from sales order
PPCO0004 Sort and processing exit: Mass processing orders
PPCO0005 Storage location/backflushing when order is created
PPCO0006 Enhancement to specify defaults for fields in order header
PPCO0007 Exit when saving production order
PPCO0008 Enhancement in the adding and changing of components
PPCO0009 Enhancement in goods movements for prod. process order
PPCO0010 Enhancement in make-to-order production - Unit of measure
PPCO0012 Production Order: Display/Change Order Header Data
PPCO0013 Change priorities of selection crit. for batch determination
PPCO0015 Additional check for document links from BOMs
PPCO0016 Additional check for document links from master data
PPCO0017 Additional check for online processing of document links
PPCO0018 Check for changes to production order header
PPCO0019 Checks for changes to order operations
Thanks
Sandeep
Reward if helpful -
Purchase Requisition Item release not in the change log of the item
Hello Experts,
I have developed a report that displays when purchase requistions have been relesased. To do that, I have used the change table to track the time and date.
However, a lot of the requistions do not have the release as a change. I am not able to recreate it, and I am not able to point at anything special with the ones that does not have a change log.
Have anybody else experienced this? I am a bit stuck
rgds
GARhas there been a change in the release strategy cusotmizing. maybe the PR was not subject to a release as it was created, but new PRs of the same kind are subject because of this change in customizing?
There are not many possibilities:
a) PR was not subject to release strategy
b) release indicator got cleared by own program or table maintenance
c) program bug (never saw one for change history of PRs)
do you use workflow for releasing? if yes then you can check the log of the workflow item and proof the evidence for a program bug. -
Custom field update in Purchase Requisition Final Release
Hi,
We have PR release strategy at Item level.
In PR table EBAN include I have added new field as ZZREL_DT (for final release date), This Field I want to update when final release will get triggred for the PR item.
For updating this custom field I have try with Enhancement 'M06B0002' but system is not updating the value in new field , and as in BADI 'ME_REQ_POSTED', the IM_EBAN is an importing structure ,system is not allowing to change the value if we implement this BADI.
Is there any user exit or BADI, to update this custom field, I want to update the system date when user releasing the PR item with ME54N or ME55 transaction.
Regards,
ZafarHi ,
Try with create new tab in PR item level, add field in custom tab example Final release Tab.
Try to fetch data from EBAN table when final release happened ( based on status ) the date will update in this table. I hope this is helpful.
Use user exit to create custom tab and custom field
enhancement MEREQ001 : check this enhancement.
user exit EXIT_SAPLMEREQ_0*
I hope it is helpful -
Ability to Change Overall limit in Purchase Requisition after PO creation.
Hi,
I have created a Service Purchase Requisition and released it.Then, I created a Service Purchase Order with reference to the above created Purchase Requisition and released and saved.
Now, when I go to the Purchase Requisition after creating a Purchase Order, I want to change the values for the Overall Limit and the Expected Value but they are greyed out.
But what I have noticed is that if I create a Standard Purchase Requisition and release it and then create a standard Purchase Order with reference to the standard PR and release it and save it, I am able to edit the values even after the PO has been created.
Any help is appreciated.
Thanks and Regards,
Puneet Jhari.Hi ,
I need to change the Accoun assignment category in back end not in fore ground.
Is there any EXIT or BADI available for the same.
Thanks,
Ranjit -
Issue in Purchase Requisition Release Strategy
Hi guru,
I've got an issue in the release strategy;
I have a PR with 3 lines. After Relase I've deleted the last line and system doesn't allow me to release it by ME55 transaction; I'm able to do it only by ME54N.
Thank you for your help.
M.Hi Marco,
I had a problem with ME55 and i wrote to SAP OSS.
The first OSS answer was:
Can it be that your requisition has some deleted items?. If yes, then
take into account the following:
Please consider the definition of ME55 "Collective release":
You release ALL requisition ITEMS or COMPLETE requisitions that are
awaiting processing by your release code.
And also the definition of "the field overall release of PReq":
Determines that the items in a purchase requisition are ALL released at
at the same time (rather than individually).
That means:
If there are some items which can't be released (may be they are
deleted), the transaction ME55 can't be used - so you have to release
over the individual release (and that's why you get this
message in ME55).
If you get such a message for a purchase req. in ME55 you can go over
the menu to release this item(so you don't have to call ME54 directly):
Select the item and choose Goto -> Individual release.
There is a difference between overall release and collective release.
Overall release means that a purchase requisition is released on
header level and not on item level. Collective release means that
several purchase requisitions can be released at the same time.
When one line of a requisition subject to overall release is deleted
you are asked to use the "single release" functionality in transaction
ME54.
Once you delete a line item you MUST work with ME54 to release each
item. By deleting a line you effect the whole purchase requisition
hence collective cannot be used. This is standard SAP functionality.
In this case, you have to individually release each requisition item
through transaction ME54.
I hope this is useful to you.
Ciao
Alberto -
Release strategy for purchase requisition does not kick in
Hi Gurus!
I've been struggling with this issue for some weeks now.
I have set up the release strategy configuration for purchase requisitions with classifications.
However, if I create a purchase requisition the release functionality is not taken into account by the system.
See below some more information regarding my configuration:
1. I've created a new characteristic "REL_PR_GROUP". Status: released, Multiple values, Number of Chars 3, 7 values (TR1, TR2, TR3....TR7), Table name: CEBAN, Field name: EKGRP, Procedure for value assignment set to not ready for input.
2. I've created a new class: "REL_PR_ANPC". Class type 032, Status: released, Same classification: do not check, Char: "REL_PR_GROUP"
3. I have one release group "T1", Rel. object 1, OverReqRel is marked, Class: "REL_PR_ANPC"
4. I have 5 release codes. Grp: T1, Code: 01....05
5. I have 2 release indicators:
"R = Released", Rel. for ordering is marked, Changeabil: 4, Value chgs. 100,0
"X = Blocked", Changeabil: 4, Value chgs. 100,0
6. I have 1 release strategy:
"T1 with Grp T1"
- one release group, 01 Manager
- release prerequisites not applicable because of only one release group
- release status, nothing marked = blocked, 01 marked = released
- classification, purchasing group is TR1 or TR2 or TR3 or TR4 or TR5 or TR6 or TR7
I intentionally kept the configuration as simple as possible so I can try to get it working first.
Now if I create a purchase requisition for an item with release group T1, I would expect the release strategy to be activated. However, this is not the case. I don't see the "release status" tab in the PR, and if I try to relase via ME54 the system says the PR is not relevant for release.
Could you please assist in getting this working?Hi,
Have you checked in CL30/CL30N if your release strategy is derived successfully?
See section 3 of Note 365604. A small section of it:
You can use transaction CL30 search for an object using the data
of the purchase requisition/purchase order. Here, it is important
that the object search determines exactly one strategy. If this
is not the case, this indicates that there are overlapping
strategies in the system or that the release strategies in
Customizing do not correspond with those from transaction CL24.
See the previous point. If the object search returns more than
one result, the system subsequently determines an incorrect
release strategy or no release strategy at all.
If it is derived successfully, next, check the user exit EXIT_SAPLEBND_001 as per Note 371667:
The following assignment statement has to exist within activated SAP
enhancements M06B0002 (include zxm06u13) and M06B0005 (include zxm06u31)
for purchase requisitions:
E_CEBAN = I_CEBAN.
Regards,
Purnima. -
Purchase Requisition Attachement Should not be Modified when it is released
Hi Experts,
I've a requirement that, In ME52N, if the Purchase Requisition is Released then, the user should not add or delete or change the Attachments. Pl help me in this how to do.
Regards
Rajiv.Thanks giri.
For the following reasons, the billing documents are not released to accounting.
1. If the user wrongly chosen the billing type for the delivery.
2. After creating condition type, it has to be assigned in COPA. If we forgot to do it, billing doc will not released.
Our requirement is that if the billing document is not able create accounting document, the billing document itself should not be generated.
Hope this will be suffice to understand my issue and suggest a suitable solution.
Points will be rewarded.
Regards,
Kumar.
Maybe you are looking for
-
LDAP supporting multiple DNS domains
I have an environment with multiple DNS domains, and am configuring a Directory server (DS 6.3.1) to centralize various OS configuration maps including user authentication. None of the DNS domains have unique data, so I'd like to do something like st
-
Remove EDIT button from FPM ToolBar
Hi All, I am new to FPM, and I am working on SRM 7.0. In the Monitor Shopping cart WD application, after search event, a list of Shopping Carts are displayed, when we click on one of the SC number, the SC screen opens as a new Pop-up. Here we have an
-
Importing and organizing raw video footage - options
greetings- Looking for a better solution, if available, for importing & organizing raw video. I am using imovie for now. Soon to switch to FC express. After much exploring & learning on my new machine (recent convert), I'm a bit frustrated on how it
-
Need a Way to Clear Keywords from Query HUD
I like using the Query HUD to select a variety of criteria (show me images in this import session with three or more stars keyworded "times square"). But if I select a large project, there might be hundreds of keywords. (In my 2009 project alone, I h
-
Handle Exceptions during the Render Response phase
Hi, How can we handle exceptions that occur during the render response phase, e.g. to redirect the user to an error page? In our application we have an unbounded taskflow with one page (jspx). It's quite a simple page, as it only displays some data f