Purchase Requisition Release Strategy not triggeringusing Userexit M06B0001

Hi,
My client wants to trigger PR Approval based on the Department,based on User it will go to respective Line Manger.
For that I am using Userexit  M06B0001, But when I am using this Characterictis it is not triggering Release Strategy.
If I am using other Characteristics like Plant it is triggering.
Can Anyone Help me on this.
Best Regards,
Raju

Hi Raju,
Did you checked for this Characteristic if it's attributes are correctly maintained. Also Reference to Table field is correctly mapped. I hope you must have done this correctly, but check it once again to confirm.
Prashant Rathore.

Similar Messages

  • Purchase Requisition Release Strategy not to run when change to PGrp

    We have buyers that are required to change the purchasing group on the purchase requisition before a PO is created.  We would like to allow them to do this without triggering the release strategy.  Any ideas??  Thanks.

    release strategy will change only in the case if you cahnge value or oquntity other wise it will not retrggering.
    If you change the Purcvhase group system will not tregger the release
    let me know if oyu have any other problems

  • Purchase requisition release strategy tab missing

    Hi all
    I configured purchase requisition release strategy and ME51N is working issuing no error but it is not displaying Release Strategy Tab , please help me where i am wrong.

    hi,
    check few reasons:
    1. There might be more than 1 release strategy using the same class, due to which it is not possible for sap system to determine the unique rel. strategy..this normally happens when you copy the exsisting class and assign it to own new one...
    2. check the release strategy OMGSCK, is there any problem with your release strategy...
    3. Check whether you have maintained all the classified field in the document or not..
    4. check whether the release is assigned to any workflow...if so, then check the inbox pls...
    regards
    Priyanka.P

  • Tranposrt - Purchase Requisition Release Strategy with Classification

    Gurus!
    Tell me if I want to Transport the Purchase Requisition release strategy with classification. The Data in each charisteristics in each PR Strategy that I have set in Dev is not getting transported to Quality.
    Do I have to enter the data in characteristics again in Quality and the same procedure I have to apply for Production.
    If yes, in this scenario, Can I make Production modifiable.
    Regards
    Sajid

    Hello,
    Create a special ID in PRD with access to change characteristics. This ID should be released for specific purposes and with approval (project manager/SAP support manager). You can also turn on auditing so that all activites performed are logged which can be used to satify auditors.
    Cheers !

  • Overall Purchase requisition Release strategy : Changed after Rejected

    Hi All,
        I have activated overall purchase requisition Release strategy (20000077) . And its working fine when PR is released at each level and saved.
      Problem I have is when PR is rejected .
    When PR is rejected , workitem is created for initiator with ME52 transaction. When initiator changes the contents of PR and saves , the release strategy should resume back from where it stopped. Thats means when Approver A rejects the PR, after initiator make changes , the workflow should trigger back with a workitem for release to approver A.
    But its not happening as expected. When Approver A rejected the PR and initiator changes the PR , Nothing is triggered, as there is no event raised at this point. 
    ME52 changes for PR is not trigerring any event which can trigger the WF.
    Is there any way we can trigger Workflow in this scenerio.
    Please suggest.

    Hi Subhashini,
    This all depend on release strategy. release should reset completely on tha change.
    For the increase of quantities or values you can maintain tolerance limits in the Customizing. When you increase the amount or value via the tolerance limit the system will reset the release.
    When you reduce quantities or values the system only resets the release if another release strategy is determined for the lower quantity or the lower value.
    If no other release strategy is determined by the reduction of the
    amount or value, the system will keep already existing releases.
    changeability in Release indicator also play a major role. You should set it to either 3 or 4. Now if you change any field, which is also used in any charecteristics in release, it will lead to reset of release startegy.
    Sanjeev

  • Purchase Requisition Release Strategy wont trigger

    All:
    I have set up what i thought was a simple purchase requisition release strategy. Parameters are as follows:
    1.) Doc Type = NB set up as CEBAN-BSART
    2.) Acct Assn Category = k set up as CEBAN-KNTTP
    3.) Purch Org = 300 set up as CEBAN-EKORG
    4.) Overall Value = 0-1000, 1000-10000, 10000-50000, >50000 set up as CEBAN-GFWRT
    Release group is set for overall release, i've checked the release strategy with OMGQCK and everything was good to go, checked CL30N and everything was triggering, checked table T16FS and there weren't any fishy entries. Oh also, i've tried deleting and recreating the entire release strategy at least 3 times.
    Whenever i create a purchase requisition, i get no release tab. Not sure what else i'm missing here.
    Any help is appreciated!

    I created 4 characteristic with the above mentioned criteria (doc type, purch org, net value, & account assignment category). I assigned all 4 of these characteristics to a class.
    Matrix is as follows:
    0-1000, doc type NB, purch org 3000, acct  assignment 'k' needs approval from release code 01
    1000-10000 doc type NB, purch org 3000, acct  assignment 'k' needs approval from release code 01 & 02
    10000-50000 doc type NB, purch org 3000, acct  assignment 'k' needs approval from release code 01, 02, & 03
    >50000 doc type NB, purch org 3000, acct  assignment 'k' needs approval from release code 01, 02, 03, & 04

  • Badi for Purchase Requisition Release Strategy

    Can any help me to know about the BADI for Purchase Requisition Release Strategy .Is their any BADI to  control the PO Price for a PR release strategy
    Thanks for your help

    This badi is for schedule agreement ?
    BAdI: Release Creation for Scheduling Agreements with Release Documentation
    Use
    You can use this Business Add-In (BAdI) to influence release creation.
    This BAdI is used in the application component Scheduling Agreements (MM-PUR-OA-SCH).
    This BAdI includes the following methods:
    Change Data Before Release Creation (BEFORE_CREATION)
    Change Data After Release Creation (AFTER_CREATION)
    This BAdI is called during manual and automatic release creation.

  • Purchase requisition release strategy

    I want each purchase requisition should be created with valid release strategy. The problem presently is that if somebody puts wrong parametes (such as purchasing group, currency) the purchase requisition will not be applicable to release and the purchase order can be easily created. So in such cases there is no need to release purchase requisition which is not correct for business point.
    Pls advise.

    Hi Balaji
    Ur need is appreciated but inorder for that to work we have to make sure that all the possible combinations exist in ur characteristics list which may not be possible all times.
    So better way would be to check whether the characteristics combinations of ur class and the corresponding data of ur requisitions matches and trigger error msg if differs.
    Ex: Plant and doc type be the characteristics used in ur class.
    Check whether the PR has only the plants and doc types that is specified in ur release strategy and if no trigger error msg.
    Try this using BAPI also. Get help from ur ABAPer.
    Thx
    Raja

  • Release Purchase Requisition - "Release strategy"

    Hi there,
    I am trying to release a purchase requisition. I looked in the table "EBAN" and i can see the entry or in other words, the requisition i created. In the Release indicator, Release status and Release strategy fields, these are empty. How do i add information to these fields which appear to have missing data?
    Speedy repsponse would be very much appreciated.
    Thanks
    Motolani Fatuga

    Hi Motolani
    spro>Materials Management>Purchasing>Purchase Requisition>Release Procedure>Procedure with Classification>Set Up Procedure with Classification-->Release strategy
    Select release strategy> Go to details>classification
    here check what are the charactaristic and what are the values maintained for it
    Check this for all release strategy
    Mostly PR release strategy is based on Document type and PR Value
    Check whether UR PR fits in release strategy criteria
    Suppose Total value of requisition is maintained as 1000-2000
    If UR PR value is less than 1000 Then PR will not subject to release
    Vishal...

  • Purchase Requisition Release strategy for MRP based Requisition

    Hello Gurus
    We want to set up the urchase Requisition Release strategy for MRP based Requisition ..Any can one Please share your experience about the impact down the road?
    Thanks
    Nick

    Hi,
    If you want include the MRP related PR in Release strategy.
    You need to include the field CEBANESTKZ-Creation Indicator (Purchase Requisition/Schedule Lines) in one of the characteristics which you create and include the characteristics value as per the field values like AReal time, BMRP, CConverted Planned order etc.. and include the charactristic in the Release Strategy will release group & release codes.
    So when ever the PR is created through MRP run then this creation indicator will update in the PR as per that release Strategy will trigger in the PR.
    there is one more option you need to create the separate document type as MRP PR then create document type as characteristics and include the values of all these document types and include in Release strategy.
    But it will  not pop up for direct PR from MRP run only trigger when planned order is converted to PR manually there you need to select this MRP document type then release strategy will trigger.
    I think first one is best suited.
    rgds
    Chidanand

  • Purchae requisition Release strategy not Invoked

    Hi,
    I  have Purchase requisition Release startegy.
    Criteria is
    1. Account assignment category -K
    2. Material Group suppose -001
    3. Plant - 4001
    4. Valuation Price - 1000 USD.
    Then Release staregy got Invoked. Presently it is working fine.
    I have Created another Release strategy for with same criteria but I have added another criteria with user name- ernam.
    Same thing I have created characterstic and assigned to Class.
    CL24N and CL20N also Maintained.
    But this New Release stragey Not Invoked and Old one only invoked at the time of requsition created.
    Please guide me is there any configuration to Invoke this new Strategy?
    Regards,
    Sridhar.

    Hi Indranil,
    Thanks for your response.
    I thought user name will differentiate the new release strategy with old one.
    I am using same parameters in both strategies.
    Plants, Material groups, Cost center same with old one.  New release strategy very few members are going to use.
    Business is few users will create Pur Req. Users are not having release codes. Tracking number also used in another release strategy.
    Regards,
    Sridhar.

  • User Exit for getting Purchase Requisition Release Strategy

    Hi Experts,
    When a user creates a PR I need to know the user exit I need to implement so that the First Approver (Processor) text  in the Release Strategy is populated from a custom table. I have seen that the field is MEREL_S_GRID1-STEXT. I also need to know if I can implement a user exit so that it pulls the release strategy for a PR for assets (Acct Category A) since it is pulling for Acct Category K (Cost Centre) and the Release Strategy tab is appearing in this case.
    Kind Regards,
    Darlington

    Hi Meenakshi,
    Thanks for the very useful answer. It has given clues on how to resolve this issue. I have resolved this issue for the Asset item category using the following thread: user exit for requisition release strategy, and also SAP Note 365604.
    However, I have another issue, the release strategy for Stock Items, (item category blank) is not pulling through. I need to use the same method above but would like to know how it determines the funds centre for a specific stock item. I couldn't find where that is implemented in the material master and I need info on how to determine the account assignment for stock items based on the funds centre.
    Regards and Thanks.

  • Workflow for purchase requisition release strategy

    Hi all,
    I need an urgent help on Workflow for Purchase Requisition Release. The requirement is that when a purchase requisition with a given combination (Purchasing Group, Material Group and Account Assignment Category) is created and saved, it should trigger a workflow for approval of release or rejection to one specific business manager. If he dont responds in 2 days, it should be sent to other business manager. If any one of them releases the requisition, it should send a mail to the requestor that the requisition is released. And if it is rejected, then also a mail to be sent to the requester informing that his requisition is rejected...
    Can anyone take some pain and guide me step by step procedure to implement this or to use any existing one.... I know its BUS2009 thats used in this but really dont know how to implement it properly.
    Its urgent...
    Edited by: Hima on Apr 11, 2008 12:45 PM

    Check this link
    http://help.sap.com/saphelp_47x200/helpdata/en/04/92762546f311d189470000e829fbbd/frameset.htm
    Thanks
    Arghadip

  • Problem in Purchase Requisition Release Strategy

    Hi sapgurus,
                           i am defining a release strategy for Purchase Requisition. but whenver in a strategy two release codes are incorporated suppose
    Release group :MM
    Release Codes: M1 and M2.
    but in relese simulation tab showing
       "M2   Release prerequisite missing"
    and M2 code is not working in releasing pr.only M1 is worked.
    Thanks in advance.
    Regards,
    Bipasha

    Actually I want to create two release strategy
    1. when total value in PR will be 1000.00 then one person can release PR.
    2. when value is greater than  1000.00 then two persons will release.
    For this i created a release group K1 with checkbox against  'OvRelPReq'  is ticked.Then i have created M1 and M2 release codes are created.
    Then I have given release indicator one for realesed and another for not released.
    After that , create a relase strategy
    where after M1 ,M2 can able to release the PR.in prerequisite button i ticked the checkbox near M2.
    It will not work.
    Plz give me a suggestion.

  • Problem in purchase requisition release strategy code

    Hi
    We are facing a problem in purchase requisition, a new release strategy was created and change request transported but when PR is displayed in release strategy chart a same user is showed in different release strategy code.
    Note: new strategy was copied from other.
    Thanks in advance.

    hi,
    As you said tht you have copied the release stategy n created the new one...
    If you do so, you would have copied the class also...to which the release group is attached...
    If this is the case, then system doesn't recognise the new one, and inorder to solve it you have to define the new characteristic and class...then assign this class to the release group and make your release strategy again...
    Once you do this check the release strategy at OMGSCK...and then try at PR...
    You do all settings at :
    SPRO >> IMG>> MM >> Purchasing >> PR >> define release strategy >> W/o classification >> here edit characteristics/class and all other link are provided...
    Regards
    Priyanka.P

Maybe you are looking for

  • Yoga 3 pro box opening problem

    Dear All, I just joined the lenovo world by buying a yoga 3 pro. Unfortunately, I am having an unusual problem. I plugged in the device and tried to turn it on. It did not work. There is no picture on the screen, and there is the light getting on and

  • How to populate custom fields in SAP standard Basic type DELFOR01(E1EDK09)

    I've a requirement to include and populate 2 custom fields in SAP standard basic type DELFOR01 and Segment E1EDK09 (it is at hierarchy level 1 ) . The requirement looks very simple but for this, as per my knowledge, I have to create a new  Basic type

  • Safari 6.1  problem with Java

    Have OS  X  10.8.5 Last Nov. Safari wouldn't work at all with Java. Many of us had this problem and had to uninstall it, and go back to 6.0.5 -- which we were told takes a long time..actually took about 10-12 hrs to download. It's been 4 months.  I'd

  • Intermittent crashes while using Bridge CC2014, with OS X Mavericks.

    Hello! Our Worker(s)  are experiencing Intermittent Crashes on Adobe Bridge CC2014, while browsing pictures. We have done /tested all the suggestions what Adobe page tell: http://helpx.adobe.com/bridge/kb/troubleshoot-errors-freezes-bridge-windows.ht

  • Regarding BAPI_SALESORDER_CHANGE

    Hi All, I am trying to add line items in the Sales Order using BAPI. System is updating only 1 line item and for remaining line items system is giving error saying that 'SO is currently being proceed by user id (who ever running that program) but no