Hi Experts
Can anyone help mw with the following issue.
We have just starting testing MRP and are looking to covert the purchase req's that have been generated into purchase orders.
I've taken one material by a single vendor as my test subject.
We are using ME57 to assign and process the requisitions.
This then gives me a list of all the purchase reqs and quantities.
I select Assignments -> Process Assignments.
I'm then in "Create PO" (ME21N) with a list of all my Purchase Reqs in the document view.
I then select the req's one by one and drag then into the basket, this then adds an item line to the PO.  Pretty standard stuff!
As all the materials are the same I end up with 30 individual items lines for the same material.
Each line for 1 Pallet - Total PO size is for 30 Pallets.
What we would like is for the item line to increase by one pallet.
This would give us a Purchase Order with ONE item line for the material with a qty of 30 Pallets.
I hope the above makes sense and someone can help
Thanks in adavance
Chris
Edited by: CHRISLAING on Apr 8, 2011 2:18 PM

I'm then in "Create PO" (ME21N) with a list of all my Purchase Reqs in the document view.
I then select the req's one by one and drag then into the basket, this then adds an item line to the PO. Pretty standard stuff!
At this moment you have to change a little bit your approach.
you drag and drop only the first requisition into known basket at the top of the PO.
then you open the item details view and go to the scheduling tab
you will see there another basket.
drag and drop the other 29 requisition into this basket.

Similar Messages

  • Purchase Requisition to Purchase Order conversion through workflow

    Hello Experts,
    My requirement is to create purchase requisition to purchase order automatically through workflow. How to proceed with these conversion, since am new to workflow please help me with the  valuable inputs.
    Thanks,
    Naveen

    How does the senior person approve? using workflow or using transaction ME54N?
    if it's the standrad transaction then again, use a user exit or the released event.
    even if the approval is done in the workflow I would not recomend using creating the purchase order as part of the workflow since this is not a workflow issue, but if there is no other option create a new method in BUS2105 (use delegation) and call the BAPI in it.

  • Purchase requisition to Purchase order conversion

    MRP generated the stock transport purchase requisition. (between two company codes)
    When i converting the PR to PO, system creating Stock transport purchase order, item category as "U" instead of Standard Purchase order, doc type: NB.
    We are using STO between two company codes, PO Doc type should be "NB",Delivery type" NLCC and Checking rule: B - SD Delivery.
    Please give suggestion, where i'm missing the configuration.
    Thanks
    SUNIL

    Hi Sunil,
    Looks like you did everything correctly, except -
    Special procurement key which you assigned in the MRP2 view of material master in the receiving plant:
    Check the configuration of the Special procurement key if it has U:
    Materials Management> Consumption based planning>Master Data-->Define Special Procurement Types
    The two digit key which is assigned in your material master can be looked in the above configuration what is maintained in it:
    If you see: Special procurement  U    Stock transfer.....that is the culprit.
    Fix it or you might have used a wrong key in the material master (check and change it)...
    Regards

  • Purchase order report -help needed.

    Hi guys,
    Can anyone help me create a report for the purchase orders (similar to ME2N) ,my company needs all the info related to a PO like payment history.we need to pull all <b>closed POs</b> during a certain time period.Is ther a way todo this .
    I'd appreciate your help.'
    Thanks
    Cheris T

    Hello,
    You will need to run both ME80N and FBL1N. ME80FN can display PO history and from FBL1N you can get payment history.
    Hope this helps !
    Cheers !

  • Open Purchase Order Conversion Script (Data Loader)

    Hi All,
    Hope you all are doing well.
    I need a Quick help from anyone of you peole. Does anyone having Data Loader script for Open Purchase Order.
    I need it badly. My client is using 12.1.3 version.
    Please help.
    Regards,
    Aditya

    Hi All,
    Hope you all are doing well.
    I need a Quick help from anyone of you peole. Does anyone having Data Loader script for Open Purchase Order.
    I need it badly. My client is using 12.1.3 version.
    Please help.
    Regards,
    Aditya

  • Open Purchase Orders Conversion Document

    Hi All,
    Does any one has Conversion Document for Open POs. if so could you please share.
    Thanks in Advance
    Tenali Prasad
    [email protected]

    See http://oracleappss.blogspot.com/2008/07/purchase-order-interface.html for sample code.

  • How to conig ALE : Purchase order conversion to Sales Order :

    Hi all expertise,
    i need to setup ALE between 2 systems.
    The requirement is :
    The Purhcase Order (IDOC format ) from company A SAP system need to convert to Sales order into IDOC in company B SAP system.
    both company use FTP tramsmission. So Purchase order in IDOC from system A will be convert into XML file. so XML file need to translate into IDOC when system B receive it and process .
    Thanks for your helps .

    Hi Rejoice ,
    Please Check this link
    http://www.thespot4sap.com/Articles/SAP_ALE_Configuring.asp
    http://help.sap.com/saphelp_erp2005vp/helpdata/en/78/21768451ce11d189570000e829fbbd/content.htm
    [Maintaining ALE Settings|https://www.sdn.sap.com/irj/sdn/bpx-defense?rid=/business_maps/guid/eg1slxvyat1odhrwoi8vzxn3b3jrcgxhy2uuc2fwlmnvbs9zb2nvdmlldy9ty3bnzxquyxnw%0d%0ap3bhy2thz2vpzd0mdmlldz1zbwnyzw5kzxiyjmlkptm2nzvdnkm3rei0nzq1rue5odexrji3ntmx%0d%0aqzeyqujgjiz4c2wtymfzzt1odhrwoi8vzxn3b3jrcgxhy2uuc2fwlmnvbs9zb2nvdmlldy9ty3bn%0d%0azxrfbwltzs5hc3a/dxjspxnkbl9uzxcvjiz3zwitdxjspwh0dhbzoi8vzxn3b3jrcgxhy2uuc2fw%0d%0almnvbs9zb2nvdmlldy9ty3bnzxrfbwltzs5hc3a/dxjspsymehnslwxpc3q9c2rux2dlbmvyywxf%0d%0acmvuzgvylnhzbhq7c2rux2xpbmtyzxdyaxrpbmcuehnsddtnzw5lcmf0zuhutuxfu0rolnhzbhqm%0d%0ajnbhy2thz2utawq9jizyzxnvdxjjzxr5cgu9c2rux3nvbhv0aw9ux2nvbxbvc2vyx2z1bgxwywdl%0d%0ajizwyxjlbnrssuq9l3dlymnvbnrlbnqvd2vicgfnzxmvynb4lzqwieluzhvzdhjpzxmvrgvmzw5z%0d%0azsamifnly3vyaxr5l1nvbhv0aw9uie1hccatierlzmvuc2umjnrpdgxlpu1haw50ywluaw5niefm%0d%0arsbtzxr0aw5ncyymdmlydhvhbd10cnvl&prtmode=default]
    Best regards,
    raam

  • Not Possible to Process Goods Reciept for an Asset Purchase Order.Pl. Help!

    Dear All,
                                                                              I m not able to do Goods Reciept for a Purchase Order . It is an Asset P.O.As  i  wants to Process Goods Reciept am getting a System Message in task Bar as --> "No Goods Reciept Possible for Purchase Order
    XXXXXXXXXX. Message No. M7036.
    Can ne one please help me what to check in this P.O , The Message generated is not an Error it is a Message in task bar with Green Tick, Hope you got it.
    Please Help ,
    Rgds n thanx in advance.
    sap11

    Hi,
    Following could be the possible reasons for this message:
    o   The purchase order contains no items in the specified plant. - If you have specified plant in MIGO Screen, remove it and keep it blank, let system determine it from PO.
    o   The item specified does not exist. - If you are entering PO line item in MIGO screen then keep it blank and let it get determined form PO
    o   Currently, the scheduling agreement has no open schedule lines, or the schedule lines have not yet been transferred. - This is applicable in case of GR against Scheduling Agreement
    o   The item category of the purchase order items in the plant does not allow goods receipts. - Check the Item Category in PO, it should be blank.
    o   The purchase order items in the plant have been deleted or are blocked.
    o   For confirmation control for the order item(s) to be carried out, a confirmation (shipping notification) must have been received. This has not yet been entered. - Check under "Confirmations" Tab in PO whether any confirmation control key has been specified or selected wrongly. If yes then either create Inbound delivery in VL31N and then do MIGO or remove the Confirmation Control Key from PO ans Save and then do MIGO.

  • Wrong Exg. rate type picking in Foreign Purchase order - URGENT HELP

    Hi Friends,
    We have an issue with Exchange rate type.
    We want to post the exg. taye type SPOT for our doc. types WL, WA, WE in goods movement.
    We have configured the SPOT rate in OBA7 for the above doc. types. In OB08, we have given the exchange rates for our foreign currency.
    Still, the PO and MIGO, MIRO are picking up the default exchange rate "M" and posting the documents.
    We have even written a substitution rule but unfortunately that is not working here.
    Please help me
    Thanks,
    Konni

    Hi Rohit,
    Thanks for your response.
    When i am creating a STO order from (Foreign currency) from ME21N, the exchange rate fields are not appearing in Header data - Deliver / Invoice.
    Please suggest
    Thanks

  • Wrong Purchase order please help

    Frdns
    i posted PO with wrong vendor,
    so is there any way i can change the vendor on the same PO or i can cancel the PO ?
    Please help
    Thanks

    If you haven't done a goods receipt then you probably should delete the PO. You may want to post this message in the "Materials Management" forum as well.

  • Purchase Order Authority Help

    Dear all,
    One of my clients has such a requirement. They are using external software, say X, for PR approval. Once PR is approved then itu2019s transferred from this software X to SAP to create PO. During auditing they face with negative notion because of manual edibility of u201CNet Priceu201Cfield on PO. From customizing u201CNet Fieldu201D price is made as u201Cdisplayu201D but now they cannot create PO from software X since it calls some functions foreground.
    The question is they want to restrict manual edibility of u201CNet Priceu201D field for some users, except the one software X uses.
    I would like know your opinion about this case.
    Best regards.
    Metin.

    Hi,
    you can restict by authorization as said, or make the pricing condition automatic then nn manual change would be allowed it will always pick from PIR. for these you have to mainatin the info recod in ME11 against your material and vendor and also you have to maintain the condition record in MEK1.
    regards
    anamika

  • Purchase Order Release Help

    Dear friends,
    My question is about PO approval strategy. I add a new field to CEKKO (ERNAM - name of person who created the object) and create a characteristic (Z_ERNAM) that referrers to CEKKO-ERNAM. Then assign this characteristic to PO release class. All other release strategy customizing has been done successfully. But when I create PO that is expected to subject a release strategy doesnu2019t happen so. When I remove this characteristic (Z_ERNAM) all POsu2019 I create are subject to release strategy. How can I achieve POsu2019 are subject to release strategy with characteristic Z_ERNAM.
    Best regards
    Thank you

    Hi,
    Did u maintain any values for that characteristic, if not then please maintain it and then check again.
    If u have configured it correctly then release strategy will trigger automatically.......
    regards,
    Uzair

  • Purchase Order Conversion

    Is there any standard program available to convert PO's directly in SRM. We are implementing extended classic scenario EBP 5.0

    Hi Sunil,
    Looks like you did everything correctly, except -
    Special procurement key which you assigned in the MRP2 view of material master in the receiving plant:
    Check the configuration of the Special procurement key if it has U:
    Materials Management> Consumption based planning>Master Data-->Define Special Procurement Types
    The two digit key which is assigned in your material master can be looked in the above configuration what is maintained in it:
    If you see: Special procurement  U    Stock transfer.....that is the culprit.
    Fix it or you might have used a wrong key in the material master (check and change it)...
    Regards

  • Short Closure and Permanent Closure of Purchase Orders

    Dear Experts,
    Our clientu2019s requirement is to close and block the processing of Purchase Orders for either partly received or no receipt at all.
    The following objectives for the closure of Purchase Orders :-
    1.     The useru2019s should not be able to process the Service or Material Purchase Orders after short closure of the Purchase Orders.
    2.     The Budget commitments for the undelivered Services or Material should get released after short closure of the Purchase Order.
    If a Purchase Order is raised for 100 nos. of a material/services @ Rs. 100 per unit, the total value of the Purchase Order will be Rs. 10000/- and GR has been prepared for say 10 nos, so the value of the GR will be Rs. 1000/-. The Purchase Order is now short closed for 90 nos. Then the following are the objectives to be achieved :-
    1.     The user should not be able to make a GR/SES for 90 nos.
    2.     Commitment Budget for 90 nos (Rs. 9000/- should get released from the Purchase Order.
    We have tried the following :-
    1.     Ticking the Delivery Completion Indicator.
    2.     Putting the Last GR Date
    3.     Making the Message of Last GR from Warning to Error.
    4.     Locking the line item for further processing
    But still the Delivery Completion Indicator, Last GR date and Unlock options are are editable to the user in ME22N and ME23N, where he can remove the tick and date and process the gr.
    Please suggest a solution to achieve the above objective.
    Thanks in advance.
    AJ

    Hi Adwait,
    Reducing the quantity to 90 nos. in the Purchase Order will help in release of my commitement budget. But the line item will still be open to the user for amendment and further processing. If the user amends the purchase order again, the line item can be processed by the user again.
    I want that alongwith the release of the commitment budget the line item should also be permanantly locked for modification by the end user.
    Please suggest further in continuance to the above.
    Thanks in advance.
    AJ

  • Import tab in a purchase order

    Hi Friends,
    We have one requirement. How to make commodity code, import procedure and country of origin fields as required fileds in import tab of a purchase order?
    Help appreciated and rewarded. It is urgent
    Thanks,
    Bhairav

    Instead of the PO you can already make the commodity code and country of origin  in the material master mandatory.
    The import procedure should default from info record.
    Accurate maintenance of master data avoids problems in transactional data.
    For the PO you can customize incompletness schemes that makes the fields required.
    No an option for parameter is not available

Maybe you are looking for

  • Please Recommend - AIO/MFP Printer

    Hi, i'm looking for a AIO/MFP printer that support "scan to email" and "scan to network folder". the above functionality should not require the printer to be directly attach to a pc via USB/LAN/WiFi. the printer should only need to be be configured a

  • Black screen after log in

    i have win 8.1 on bootcamp , windows was running very fine after restarting to window , the windows logo apperaed then what regulre happen show me page to enter my pass but it was a black screen .. i can't quit from this just by force shutdown and i

  • Doesn't work after upgrade to leopard

    I recently upgraded my iMac G5 to Leopard, and had been running GarageBand 2 since I got the computer. After upgrading, when I try to work on a song, none of the tracks show up. Usually one or maybe two will be visible, and when I create new tracks,

  • Multiple columns in connect by prior

    Hi, I have data something like below SKU: ITEM LOC PARENT_ITEM PARENT_LOC NULL NULL A 001 A 001 NULL NULL A 001 NULL NULL NULL NULL D 002 D 002 NULL NULL D 002 NULL NULL And I need output like this ITEM LOC PARENT_ITEM PARENT_LOC NULL NULL A 001 B 00

  • Needing recompilation.....!!!!

    Hi, I have noticed that some not all forms (*.fmb) needs manual recompilation (f60gen ....) when they are copied to the client's env. Otherwise the simple copy of .fmx to the proper directory ($CUSTOM_APP/11.5.0/forms/US) generate ORACLE error "ORA-0