Purchasing Doc. No with reference of Material Document no?

Hello Experts,
                       can you please help with the T-Code where I can find the Purchasing Document no with reference to the Material DOcument no?
Thanks in advance.
Regards,
Yawar Khan

Hi Polly,
             Thanks a Lot for your help, I was able to get the solution with your suggestion.
Points awarded..............
and thanks to all the other people Kilas, sangeeta, and jayakanth.
Regards,
Yawar Khan
Edited by: 1234_abcd on May 27, 2011 11:30 AM

Similar Messages

  • Goods Issue with reference to Material document

    Hello,
    I would like to create Goods Issue with reference to material document (Transfer Posting document) , but the following message appears :
    "Selected material document does not correspond with action to be executed".
    Is it possible to create Goods Issue with reference to Transfer Posting (mov.type 311 - from stor.loc. to stor.loc.)  ?
    Thanks

    Thanks,
    probably I'll have to find another way to solve this business requirement of copying the transfer document data in GI.
    We have an auto created transfer postings via interface from another system and the main idea was to use already entered fields in transfer posting document such as material , quantity , text , goods recepient , etc. and not to enter them twice when GI should be created. In our case (it's a case for certain materials) it's always 1:1 relationship, so the idea was to facilitate the job of creating the GI, because GI should contain the same data as in transfer posting document.

  • Invoice verification with reference to material document

    Dear Experts;
    i want to make invoice verification (MIRO) with reference to good receipt document not the all quantity in the purchase order. is this possible ???

    Hi,
    Option - 1
    If you have done 3 separate GR's for the above qtys then if you do MIRO with reference to PO then 3 line items will appear with the respective qtys. You select the one you want & delete the rest.
    Option - 2
    Check whether you have entered any values in the delivery note field while doing GR. If yes then do MIRO with reference to Delivery note rather than PO so that qty in the GR material doc will flow to MIRO automatically.
    Thanks & Regards,

  • Posting MIRO with reference to MIGO document number

    Hi,
    Is there any way of posting a vendor invoice in MIRO, taking MIGO document number as the reference instead of PO or Delivery Note reference?
    Muru

    Hi,
    In MIGO you mention the delivery note in the header part.
    There is a drop down in MIRO transaction where we enter PO number, please check and you will find the "Delivery Note" option in the drop down list.
    you can do the MIRO with reference to this Delivery Note number from this option.
    (Just make sure, that you have selected the "GR based IR" indicator in the PO line item.)
    Doiong MIRO with reference to material document number of MIGO is not possible in standatd SAP.
    Regards,
    Gaurav

  • Creation of Purchase requisition with reference to Contract documents

    Dear All
    I am not able to create the Purchase requisition with reference to Contract documents, in outline agreement field if I enter the contract document number which is already existing it is not copying the details, again I have to enter all the details like Plant, Material, document type, Qty etc.  Even after selecting the PR document type as RV for outline agreement also it is not coping. Kindly let me know that can we not able to give reference of Contract number in this outline agreement field to create Purchase requisition.
    regards
    Dhanu

    1.Logistics--Materials Management--Purchasing ---Purchase Requisition --Follow-on functions --- Assign and Process
    2.ME57
    3.Select the Assigned Purchase Requisitions checkbox if you also want to see requisitions already assigned, and choose Execute.
    4.On the Assign and Process Purchase Requisitions screen, select the requisition lines for your material.
    5.Choose Assign Manually if the info record already exists.
    6.On the pop-up Assign Source of Supply Manually dialog box, make the following entries:
    Agreement     46XXXXX            Agmt item     10          
    7.Choose Assign Source of Supply.
    For assign the source of supply, you can also choose Assign Automatically (only if not already assigned by MRP due to existing source list). If more than one source exists, select the contract in the Source Overview for Purchase Requisition 100XXXXX window and confirm with Enter.
    When assigning a source, make sure to select the contract.
    8.Choose Save.
    9.Select the line item, and then choose Assignments Overview (SHIFT+F5).
    10.On the Assign and Process Requisitions: Overview of Assignments screen, select the line below Vendor (you can only select one at a time), then choose Process Assignment.
    11.On the Process Assignment: Create PO window, check and make sure the Order Type (NB), Purchasing Group and Purch. Organization fields then choose Continue (Enter) to confirm.
    12.On the Create Purchase Order screen, select the requisition in the Document Overview section and choose Adopt in the left part of the Document Overview screen.
    13.Choose Save.

  • With reference to which document Delivery is created in Sub contract

    Hi Friends
    With Reference to  which document delivery document is created in subcontract process .
    through which T code I can see this reference  document .
    Suppose , there are 10 quantity in delivery document , where can I see this 10 numbers  are from in delivery document .
    In delivery ,in subcontract process , from which document , delivery quantities are  copied from . And what should I do in order to avoid over delivery in subcontract process .
    Pala

    Hi,
    Delivery is created with reference to Purchase order for subcontracting, to view  the delivery check  in purchase order history it displays the delivery double click on the delivery.Check in VL02N.
    Delivery quantity are copied from Purchase order,
    To avoid over delivery in subcontract process in material master purchasing view there field called purchase value key which controls this.
    Regards
    Ravi Shankar.

  • Create Sales Order With Reference to Billing Document Using BAPI_SALESORDER

    Hi,
    How can i create a sales order With Reference to Billing Document Using BAPI_SALESORDER_CREATEFROMDAT2?
    Thanks in advance,
    Alejandro.

    I have to create sales order with reference to existing billing document. I have tried to following bapis.
    1. BAPI_SALESORDER_CREATEed
    I have successfully created document with following details.
    -->ORDER_HEADER_IN:
    DOC_TYPE =                  ZRK
    SALES_ORG =              3000
    DISTR_CHAN   =            00
    DIVISION =                    00
    ORD_REASON =            100
    SD_DOC_CAT   =          L
    CURRENCY       =         EUR
    REF_DOC          =         100000028
    REF_DOC_CA    =         M
    -->ORDER_ITEMS_IN:
    ITM_NUMBER    =           000010
    MATERIAL          =          701791
    TARGET_QTY     =          0000000001000
    CURRENCY        =          EUR
    REF_DOC           =          100000028
    REF_DOC_CA     =          M
    -->ORDER_PARTNERS:
    PARTN_ROLE      =          SP
    PARTN_NUMB      =         W12001
    COUNTRY             =         NL
    by providing this input i am able to create the document but it is not picking up the net value. so i have passed some extra paramters in  ORDER_ITEMS_IN
    COND_TYPE          =        PNET
    COND_VALUE        =        14,56
    COND_D_UNT        =         PC.
    folowing error is occured: Condition PNET is missing in pricing procedure A V Z0000.
    is it something related to configuration problem?
    2.BAPI_SALESORDER_CREATEFROMDAT1 or BAPI_SALESORDER_CREATEFROMDAT2
    I have used same test data that is used for BAPI_SALESORDER_CREATEFROMDATA (where in i coudl succefully create doc). but here i encounterd following error.
    Unpermitted combination of business object BUS2032 and sales doc. category L.

  • Materail recevice with referance to material document with mvt type 303

    Hi Guru:
    In MB1B we are creating mateiral document with movement type 303 from one plant to other plant.
    Now same material we need to receive in other plant with movement type 305 in same T code Mb1B.
    Now as per user requirement if there is number of item are coming in material document which is generate with movement type 303, why we need to give all material, qty, batch again in MB1B movement type 305,
    while we are receving same material in plant.
    In MB1B there is link to create material document with referance to material document but we can use this facility for creating new material document for movement type 303 of same mateiral, qty and batch.
    Please suggest is there any way to use this 303 movement type material document with movement type 305.
    Thanks.
    Virendra
    09887603301

    Hi
    In my opinion in MB1B you can not have Material Doc. as a ref. Doc. for M.Type: 305...
    But for MIGO transaction you can have Material doc. as a ref. doc. for M.Type: 305
    Goto ---> OLME ---> Settings for Enjoy Transaction ---> Settings for Goods Movements -
    > Settings for Transactions and Referance Documents ---> There...for MIGO_TR...Transfer Posting ---> Referance Documents ---> For your M.Type: 305 assign Material Document as a Referance Documnt...
    Reward if useful
    Regards
    S.Baskaran

  • Purchase order creation with reference to Contract

    Dear All
                    Purchase order creation with reference to quantity contract the contract quantity is not copied in to po. any configuration copying rules required. please guide
    Regards
    Anand.

    Hi Buddy
    The correct business process is RV Preq created by a user from any department then buyer converts this Preq to a MK contract with some quantity keeping the duration as some months/year. Then as and when material mentioned in the contract is required during the validity period of the contract MRP creates Preq or buyer manually creates NB preqs , same are then converted to PO but these PO are released against MK contract. So qty in PO are different then mentioned in contract because contract is for  a large qty keeping in mind the duration (for example one year).
    Regrds
    Yogesh

  • Invoice verification with reference to billing document in cross company

    Hi Gurus,
    We need to do "Invoice verification with reference to billing document in cross company code scenarios".
    At present I am processing through MIRO by calling the PO.
    What is the alternative for this and how to do it?
    Thnx

    Hi
    It is not possible to do the invoice with reference to billing document.
    You can create the Invoice referncing the PO used for STO or the delivery note (as mentioned in the Material document) or directly on the vendor.
    Thanks & Regards
    Kishore

  • Mandatory fields With reference to Material types

    Dear Gurus,
    I need to make few fields as mandatory with reference to material types while creation of the material master data.
    For example:
    For Semi finished and Finished Schedule margin key is required(mandatory)
    For Raw Materials Schedule margin key is optional.
    Regards,
    Siddharth

    Hi
    find  following step to make field mandatory for material type
    Follow the stpes for making field as optional, required entry
    1 click the tab ,(Which is u want to be Required entry )and get the field name by pressing F1 key and then
    2.Go to T.Code: OMSR and enter that field name and get Selection Group
    once you get selection group and field name
    3 Use t.Code: OMS2 and click your material type and in next screen check Field reference ( you have assigned for material type; example :;For ROH material type the Field reference is ROH
    3. Use T.code:OMS9,, Double Click your Field Reference and select field selection Group , & select round box of Required Entry or optional and save
    check following link you will get clear idea [How to configure the fields required for each Material type ?;
    Regards
    Kailas ugale

  • Credit Memo request with reference to Billing Document number via IDoc

    Hi,
    I want to create credit memo request with reference to billing document number via IDocs.
    I have tried through ORDERS05, but when I process I saw that it is only processing with reference to contract  number or quotation.
    So is any other way of creating credit memo request creation with reference to Billing document number via IDocs?
    Thank you in advance.
    Regards,
    Santhi

    Please Help... it is Urgent...  Thank you

  • Credit/Debit Memo Request with reference to Billing document via IDoc

    Hello Experts,
    It seems SAP doesn't support Credit/Debit Memo Request with reference to Billing document via IDoc. Via IDoc, we can create sales document only with reference to contract or quotation but not with reference to billing/invoice document.
    Wanted to check if anybody came across such requirement and what would be the best way to acheive (Other than custom program using BAPI).
    Additional Information: Its ECC 6.0 Environment with AFS 6.03
    Appreciate your help.
    Thanks,
    Shekhar.

    Please Help... it is Urgent...  Thank you

  • Credit Memo request with reference to billing document

    Dear all,
    I am having a requirement to create credit memo request with reference to Billing document. But the issue is, I have separate pricing procedure for normal sales to billing, and different pricing procedure for CMR to Credit memo.
    When I am creating CMR with reference to Billing document it copies the pricing procedure, Please suggest how to block pricing procedure to get copied. (please note that B: redetermine pricing, is not working in this case)
    Suitable points for valuable answers guerenteed.
    Regards
    Bidhu

    Hi,
    In VTAF maintain the folowing parameters,
    HEADER
    053,103 and 03 in the Data T in this order from top to bottom,maintain 021 in the billing header box and check the copy item number box.
    ITEM
    153,104,004 in the Data T in this order from top to bottom,maintain 303 in the copying requirements box and pricing type E.
    This should resolve your issue.

  • Create with reference where original document is incomplete

    Hi Guys
    We use variant configuration as part of our sales order process. Within the VC we have 'discontinued' validation i.e. a component of the configuration may be discontinued and therefore unavailable. In this case, we would want to lock the configuration, reject the order item and create a new order item for a different component. We do not wish to delete the order item because of the effect this has on BI sales reporting.
    However, if we later wish to create another document (such as a FOC replacement) with reference to this document we receive an error message to the effect that the document being referenced is incomplete and cannot be used as a reference.
    Does anyone know of a way of being able to copy complete items only during create with reference or being able to set the status of an incomplete ('being processed') item to complete.

    "Incomplete" and "being processed" are two different things. If document is "incomplete", there are some fields that are required and must be filled in before the document may be processed any further. As correctly pointed out above, such fields will appear in the incompletion log.
    There is no way to work around the incompletion procedure. If you need to make the field required only in certain situations, you might want to take it out of the incompletion procedure and add a user exit instead.
    If an order is displayed as "being processed", this means that one of the statuses (see Status tab on header and item level) is "partially processed". Normally setting the rejection reason updates the overall item's status (not to be confused with the header's status) to "complete", but I've heard of some cases when for some reason this does not happen. Unfortunately, I don't recall if there was any solution.
    Hope this helps.

Maybe you are looking for