QA32 with status CRTD CHCR

dear all
In  one Material system status CRTD CHCR shown in origin 04 (Shipping inspection) trans code QA32 while it is reqired REL CALC SPRQ for result recording.
what may be the reason?
regards
roshan

Hi,
Please go & check you have not made the inspection plan for the required material. Go and make it in QP01. After that you will get the required statuses.
Then when ou do result recording you will get the result RREC & then you will get the result SPRQ(stock posting required.
Please go & check.
If helpful award points.

Similar Messages

  • Quality Management - Insp lot with status CRTD CHDR SPRQ

    I am not able to do usage decision for Insp lot with status CRTD CHDR SPRQ but I can do usage decision for status REL CALC SPRQ.
    Can anybody know why ?

    Hi
    pl check the lot is assigned for inspectioon plan ore not.
    got QA02 check in inspecion specification TAB.
    If there is noe inspection plan (group)
    you need to create a inspection plan, and then come to QA02
    then you need clickon TAsk list/spec button in insp.specification tab.
    Pl check and try
    -ashok

  • Inspection lot status CRTD CHCR SPRQ

    Dear Expert
    I created inspection plan for a material and generated inspection lot after GR from PO. But it's status is coming as CRTD CHCR SPRQ, release status is not coming, pls suggest where i want to look for this?.

    Hello,
    I am having a similar issue with inspection lots. The information provided has been very helpful, but I have not been able to resolve my issue. Forgive me if my terminology is not clear as SAP is very new to me. Here goes:
    When my inspectors try to enter an inspection lot with transaction QE01, they receive the error "The function you selected cannot be carried out."  When you click the detailed info button, a transaction analysis box appears with the following info:
    Influence of System Status on Transactions
    Stat       Description         Influence
    CRTD    Created             Disallowed 
    If you click on status display instead detailed info, there is a system status tab  with CRTD, PREQ, CHCR & SPRQ. All four options are checked, but to the right of the first two there is a grayed out piece of paper with an arrow. It appears the system is checking for these features, but they aren't properly set up.
    As of now, we have no inspection plans, so material is simply checked to drawings and specifications and and an accept/reject usage decision is entered by receiving inspectors. My immediate concern is to get the material released that is stuck in inspection. If I click on the inspection task list, there is no task list created for the material.
    Our receiving inspection supervisor was the only one trained in QM and he left the company this week. Is anyone familiar with this error?I'm desperate for a solution.
    Regards,
    N. King

  • Posting goods from quality to unrestricted status CRTD CHCR......

    Hi Guru's,.
    I have one issue.
    In QA32 my lot is in CRTD CHCR SPRQ. I have not made quality plan for that.in MM01,quality view i activated inspection type 01.
    now in mmbe stock is showing in quality.
    i want to do transfer posting from quality to unristricted stock.i dont want to use quality plan assign to that lot.
    I tried MB1B movemet type 321. i am getting error Change the inspection stock of article 1111030200267 in QM only.
    Is any way to do that,transfer posting.
    Regards,
    siddharth

    Hi,
    As your lot has been at CRTD status you need to released by assigning inspection plan.
    In QA02 --change inspection lot or in QA32 select lot line item & click on inspection lot so that you can be able to enter in change lot.
    In which you can assign your inspection plan ,you will find icon  inspec tasl list ,click on same icon.so that you will get message inspection plan assigned , .If system wont allowe you then same screen usage ( You have to select same usage by which you created inspection plan.)
    Save the transaction & refresh the QA32 screen
    Regards
    SANIL

  • Print Production Order with status CRTD

    Hi gurus,
    Our system is configured to print production order when the order is released, but when the order is in status CRTD,Created, (not Released) we try print the order an error message appears "Object ORD xxxxxx has system status CRTD (Created).  According to this status, transaction 'Print order (original)' is not allowed".
    Is it possible print orders before release action?
    Thank you, I have points for the best answers.

    Through transaction  BS22 you can configure the system to Print the Order even at CRTD status.

  • INSP LOT WITH CRTD  CHCR STATUS

    I have created inspection lot for sample management (insp type 15).
    Quality plan for that is with usage 9.
    but still lot is created with status CRTD  CHCR .
    what may be the possible reasons?
    Message was edited by:
            sandip raut

    In Quality plan at header, i have maintained
    usage 9,
    status 4,
    lot size 0-9999999999,
    insp point 200,
    assigned the sample drawing procedure
    and i have assigned one quantitative inspection charracteristic for which i have not assigned any sampling procedure.
    is it mandatory to assign the sampling procedure to characteristic?
    also i have checked the dates of the Q.plan and inspection lot.
    all dates are same.
    still lot is CRTD.
    when i am tryimg to assign the quality paln through QA02,and clicking the "Task list/spec" tab,nothing is happening.neither system is assigning the plan nor giving any message like "no plan exist"
    please help.
    its urgent,please reply soon.
    Message was edited by:
            sandip raut
    Message was edited by:
            sandip raut
    Message was edited by:
            sandip raut

  • I can change system status without canceling lot,,"CRTD CHCR SPRQ"

    HI
    A insp lot have (System status) "CRTD CHCR SPRQ" system can not allow for any recording at the lot,, But Question is that i want to change status without cancleing this lot, Have any idea for this lot status.. "CRTD CHCR SPRQ"
    thanks Expert
    regards
    kazz

    Hi kazz, i can't tell if your issue was resolved but if not then you should check the 'valid from' date on the ECM used to setup the inspection plan.  this is assuming that you are using ECMs to create inspection plans and maintain revisions on the material.  the valid from date on the ECM used to create/assign the inspeciton plan to the material must have a date that is equal to or before the valid from date on the ECM used to assign the revision to the material.
    for example,
    ECM 123 has a valid from date of 01.01.2013 and was used to assign revision A to the material
    then the ECM used to create/assign the inspection plan to that same material must have a valid from date of 01.01.2013 or prior...otherwise SAP will not find a valid inspection plan that's valid on the date for the inspection lot and revision of the material in the inspection lot.
    hope this helps!
    nicole land

  • CRTD CHCR SPRQ-how to do result recording for that lot.

    Hi All,
    i am having issue.
    i did  GRN,lot is created with this status-CRTD CHCR SPRQ
    i tried for Result recording but  error is showing.
    Then came to know QP01 is not assigned for that material.
    then i created the QP01,but still i am not able to to Result Recording to that Lot.
    is any way to do that.without cancell the lot can we do.
    Regards,
    siddharth shanker

    Hi,
    Your lot is at created status so you need to relesed lot. May be insection plan /task list has not been assigned to lot.
    In Qa32 go in inspection lot Change ( Or T code -QA02 ) .where in tab Inspection specification tab click on task list/speci where you can assign plan theri ( You can assign plan with usage that you have created plan  )
    Save transaction.
    refresh QA32 then try result.
    Regards
    SANIL
    See QP02 with what usage you have cretaed plan.
    as earlier I told you in QA02 tasl inspec tab  in usage field select same usage by which you have created inspection plan.in QP01.
    Regars
    SANIL
    Edited by: Sanil Vadke on Mar 29, 2010 8:40 AM

  • Error while Releasing the Stock from Quality-CRTD CHCR SPRQ

    Hai Experts
                          While releasing the stock from Quality i got  error like function cannot be caried out,
    The Material Status CRTD CHCR SPRQ.
    Thanks
    Rajakarthik

    Rajakarthik
    It looks like the status you mentioned are of inspection lot.
    CRTD mean created status of inspection lot.
    CHCR means characterstics required. in your case the the material master inspection view says characterstics required however your inspection plan does not have any cahracterstics.
    assign the characterstics to inspection plan & both the status of inspection lot will change. you will be then able to process the inspection lot to move the stock from quality to unrestricted.
    Regards
    Mahesh

  • OCM u2013 Production Order Status CRTD

    Dear guru
    I want to use ocm for a production order according to a change of a bill of material with a change number.
    Can I run COCM for a production order with status CRTD ?
    OCM is only possible for production order with status REL ?
    Thanks in advance

    Hi,
    OCM is used particularly for the scenario where customer can order a configurable product & afterwards trigger changes if he wants a different configuration - even if the production has already been started. This configurable product is defind via varient configuration.
    Hence rules are set up to define which kind of changes are allowed or disallowed for a specific status of the production order.
    Changes to configurable product is allowed as long as the production order is released, but they are disallowed when the production order gets confirmed. As when order is confirmed that menas product is manufactured & hence they are no changes allowed except rework.
    Hope this resolve your querry.
    Regards,
    Avinash.

  • Mapping of status CRTD,AALK with Technical names

    Hi all,
    We have Client requirment in which we are preparing Customized program which will download Budget data for a particular Project.
    After executing this customized z transaction, we are giving following inputs.
    Proj Def.
    WBS Element
    Version
    Scope
    Scale
    Level
    Status
    It works fine if we are giving Status as I0001,I0005,I063,I0064,I0360 which is Technical name derived for Status ( From PRPS & JEST table ).
    But Client wants to put status CRTD,AALK in that.
    Any idea how status CRTD,AALK,REL mapped in Technical field.
    Any pointes on this issue will be highly appericated. Points will be rewarded for useful answers.
    Regards
    Tushar

    Tushar,
    The correspondance between the status "code" and "text" is in table TJ02T.
    I don´t know if this will be useful to your needs.
    Regards
    Martina

  • How to change the Status CRTD of the Inspection Lot?

    Dear all.
    I want to Complete an Inspection Lot 10000000005 In the T-CODE qvm2.When I select the Inspection Lot 10000000005 and press F8 to Complete the Inspection,the SAP show an error message "Status check error".
    And the detail info show that the error was cause by the Status CRTD of the Inspection Lot.I check the Status of the Inspection Lot 10000000005 and found that it's Status was CRTD CHCR SPRQ.My question was how to change the Status CRTD of the Inspection Lot?
    Regard
    Yoda

    Hi
    CRTD means ...
    In material master QM vew-inspection setup->Inspect with task list tick is there.
    Now to change status,
    Go to Qp01>create a task list for material(If not exists)>remember date of creation of task list must be prior to date to creation of inspec lot
    If task list is created/exists>go to QA02.<inspection specification -->click on Inspec Spec
    and attach task list
    go to sample tab....click on sample.
    Now save it.
    Status will change to REL
    Regards
    Sujit

  • User Status CRTD Error

    While creating Sales Order with reference to Quotation Error occured.
    ""Create sales document" not allowed (User Status CRTD, object VB0005000006000000)"
    Same error is also appear while creating Sales Quotation w.r.t. Sales Inquiry
    How to solve?
    Chintan

    Hi,
    It seems you have to change user status as the User status is created which does not allow this business process.
    Reward points if useful.
    Regards,
    Amit

  • System status CRTD is active

    Hi,
    I am having a problem with a service order. When i am tryin to book time on it using CAT2 i get an error message "System status CRTD is active."
    Can any one please advice what is that i need to do in order to remove this error message.
    Regards,
    Chinmaya

    Hi,
    In general if the Order is in CRTD State then you can not post any thing on that.
    So, make the Order to REL (Released Status) and Try..
    Regards,
    Siva

  • Reg. Open Order with Status

    HI,
    can anyone let me know about Open Order with Status normally that we have to create Generic Extractors to extract that data.
    thanx in advance
    peter b

    Hi peter,
    Normally for Open Order with Status, you need to create a generic data source
    on the database table 'VBBE', this table contains the Open Orders along with
    the open quantities, then coming to the status, it is the business process to
    determine since how long the sale order is Open, and the status of the Order..
    I would suggest you to create a table level data souce on VBBE and try to
    build the logic in the extractor if at all needed..
    Hope it would give U an idea to begin..if you can achive any this with this do not
    forget to assign point..
    for any further questions revert..
    Cheers..
    Pattan.

Maybe you are looking for

  • Error while setting arch/dump locations in RAC

    Hi, In 10201, I'm facing below issue in a RAC env. SQL> alter system set log_archive_dest_1='LOCATION=/ESN/arch01/ESNPRD' scope=both; alter system set log_archive_dest_1='LOCATION=/ESN/arch01/ESNPRD' scope=both ERROR at line 1: ORA-32008: error while

  • Camera is not opening in my 3GS

    Hello, I have a problem with my iPhone 3GS The camera is not opening, I have already restored but it is the same... I don't know what to do... please help

  • How to improve the Performance of my T61?

    Hi, I got Lenovo T61 T7300, which means it has Intel Core 2 Duo 2.00 Ghz, 2 GB of ram, and nVidia Quadro NVS 140M. And I want to improve it's performance, so what are the hardwares that I can use on it.. (eg. can I attach another 2GB ram, or replace

  • Confused about jrun-web.xml

    G'day there I'm hoping someone can clarify the *actual* purpose of the [cf]/WEB-INF/jrun-web.xml file, and how CF uses it. My understanding of it was that it was the JRun-internal-webserver's equivalent of Apache's httpd.conf, or IIS's... err... wher

  • Material Groups

    Hi,     In Material Master, MM01,MM02,MM03, in Sales org 2 tab,  where in SPRO ,  I can see the values for Material Group 1, Material Group 2, Material Group 3, Material Group 4, Material Group 5 Field?