Please guide me to map in SAP for the below Scenarios of Quality Certificates.
There are two types of Certificates for Finished Products
1.     Permanent Certificates
We have certifications from some Institutes for Finished products.
e.g.  TUV: IEC 61215 Ed.2, IEC 61730 & UL1703
These Certificates are sent to customers only on Demand.
I want to create all these certificates in SAP and assign materials to them. Print should come manually.
2.     IV Testing Report (Certificates for each Product).
Each Product is tested by a machine for its efficiency and power. A Current-Voltage relationship Graph is produced by the Machine. We call it IV TESTING REPORT. Each product has its IV Testing Report and it is sent with the product to customers.
Print of this certificate should come automatically with each Billing Invoice in SD.
Regards
Prashant Atri

These requirements can all be handled by the standard SAP COA process.  You simply have to create a couple of different SAP script forms.  One for the stand COA where you report out the values where you actually test the product via your machine, (requirement 2). 
For the frost requirement, you need to reproduce and send copies of outside certifications.  I assume you actually have a paper copy of these and that these are for specific products.  For these, you create separate COA outputs, one for each cert type.  You create a SAPscript form for each.  These forms will be identical with but one exception.  In the form, instead setting it up for reporting characteristics and product info, you create it with one frame that is a bitmap.  (your programmers should be familiar with doing this for putting on company logos on various forms).  Instead of displaying a logo in those frame, you display the bitmap image of the cert you want to use. So the SAPcript is very easy, just a single bitmap along with anything else you decide you want to include on the form.
All your certs can then be sent automatically at time of delivery just like any regular COA.
FF

Similar Messages

  • Quality Certificate for Goods Receipt - FAIR

    Hi Guys,
    I’m after some advice with regards to the QM module.
    We implemented QM last year to support our incoming inspection process flow.
    The following dynamic rules were created via TCODE QDR1
    Z01       Inspection Always
    Z02       3 Inspections Plus Annual
    Z03       One Off Inspection
    In the material master we have actived the inspection type 01.
    Next steps:
    Quality Certificate for Goods Receipt
    We would like to set the certification flag to identify that a first article inspection report (FAIR) is required from goods externally procured.
    Today all vendors are required to provide a FAIR with the 1st off receipt for a new material or items which have not been delivered for more than 12mths.
    Is it possible to set/create much a rule in QM for the 1st del to be flagged certificate required?
    My initial thoughts were
    1. To setup quality information records for each material + vendor with the certificate “FAIR”.
    2. Then create and assign an inspection plan for the first off delivery.
    Problems I can see,
    1.     The certificate is only required for the first delivery regardless if the material requires a  2nd 3rd or 4th del to be inspected
    2.     How to apply the settings and reset them when a FAIR requirement (Annual)
    3.     Creation of this rule would have to accommodate the current QM rules not impact?
    Has anyone implement certifications in this way or could they suggest a way it could be managed.
    Many Thanks
    Paul

    Hi Craig,
    First thanks for the information on DMR this has solved the problem.
    I do have a second question if you could it would be appreciated.
    Can you change the QM control key for a PO.
    In the material master I've activate QM with control key 0000 no certificate required
    After raising a PO a change note is then released under this circumstances the vendors are required to provide a certificate with the PO.
    To mange this I would like to change the control key in the PO - I get the error message.
    Control key Z001 cannot be used here
    Message no. ME554
    Diagnosis
    You wish to change the control key for quality management in procurement. Only the following changes are allowed:
    Set current control key  from material
    Set existing control key of item 0000
    Procedure
    Is it possible to change the key at direct in the PO?
    Thanks
    Paul

  • How to generate Serial(Unique) Number for finished goods?

    Guru's,
    How do i generate Serial(Unique) Numbers for finished goods.Suppose,if we get an order for a finished good A of 10 qty.We want to generate unique number to identify each and every A item separately for quality purpose.Any help is much appreciated.
    thanks Guru's

    Depending on serial control of item, you will need to generate serial numbers at the time of WIP Completion transaction using Serial Entry window (i.e. if serial control is At Receipt) or at the time of job creation (i.e. if you are using serial control as predefined)
    In latter case, you will have to use MES or MSCA screens to perform serialized WIP completion.
    Thanks,
    Hrishi

  • If Excise invoice required for finished goods.

    Hi All
    I have doubt, whether excise invoice is required for finished goods or not. As I am trying to create MIGO doc for PO of finished material, and it is saying, no excise invoice possible for finished material RG1.
    Can you advise please.
    Regards
    Mukta

    HI
    Thanks for this. When we are executing Utilization transaction J2IU, it is giving dump after prompting popup with  'Data will be lost PLA NCCD B35', 'No record selected , excise invoice cancelled'.
    Run time error is saying -
    Short text
        Structure-type conflict when calling a FORM
    What happened?
        Error in the ABAP Application Program
        The current ABAP program "J_1IRUTZ" had to be terminated because it has
        come across a statement that unfortunately cannot be executed.
    An exception occurred that is explained in detail below.
    The exception, which is assigned to class 'CX_SY_DYN_CALL_ILLEGAL_TYPE', was
    not caught and
    therefore caused a runtime error.
    The reason for the exception is:
    The call of the FORM "DETERMINE_DEFAULT_VALUES" is incorrect:
    The actual parameter no. 2 is at PERFORM not compatible with the
    structure type requested by FORM "DETERMINE_DEFAULT_VALUES".
    The FORM "DETERMINE_DEFAULT_VALUES" is defined in program "SAPMJ1II".
    This error occurs in Unicode if the fragment view of the types is
    incompatible.
    Can some one suggest if we need to apply any OSS NOTE.
    Regards
    Mukta

  • Error while executing the transaction QC22 (Quality Certificate for Batch)

    Hello Friends,
    While executing the transaction QC22(Quality Certificate for Batch), after giving the Batch Number and Customer Number, when i am executing it , system is throwing the error message as "Not all data was found for characteristic 90139982 in profile D80D8".
    Message no. ZQ010
    Diagnosis
    Not all data was found for characteristic 90139982, referenced as number 0030 in certificate profile D80D8. The missing data could be the short text, specifications, or results.
    System Response
    The missing charactertistic will not be printed on the certificate,
    Procedure
    Review the settings for data orgin of the short text, specifications, and results, and adjust accordingly.
    One more thing i would like to add here as against the same batch in april we had taken the print of COA (Quality Certificate) through the transaction QC22. But now we are trying to do that than system is thrown above mentioned error.
    As i am new in QM, kindly explain we were to maintain the certificate profile.
    Waiting for the experts inputs.
    Thanks and Regards,
    Jitendra Chauhan

    Hi
    Try with QA33 you may have display authorization,  or check in MB51 on the base of material and batch you can find the lot number generated, then go to QA03 and check the result, if you want to validate the characters check with the inspection plan, the characters entered in the inspection plan and the characters in the concerned certificate profile.
    Regards
    Naveen.
    Edited by: vaddapalli naveen on Jul 1, 2010 1:57 PM

  • Validation of batch nos. in migo for finished goods (fert)

    I want to validate batch number entered by user at the time of migo for finished goods (fert) against the batchs in mcha. how can i do this? also is it possible to give f4 help to user for available bach nos. for the particular material ?

    Hi,
    Cannot you use message M7 668 for this purpose?
    Problem is "batch has been already posted in stock"
    Regards,
    Csaba

  • How to get unit cost for finished goods in prod order

    HI all,
    IN a production order of type PP04, there is cost analysis you can get from CO03.  This shows the cost for finished goods and BOM components.  Would anyone know how the cost for finished goods are calculated ?  The issue i have is that the unit cost of the finished goods is not correct.  It is higher than what it should be.  I looked at the moving avg price at material master but the cost used in calculation is different than in material master.   Can anyone shed light how finished goods are calculated and why it is picking up a higher unit cost ?  Where is the higher cost coming from  for finished goods material as shown in CO03 ?  The BOM materials are picking unit cost correctly.  Would this have anything to do with cost settlement ?
    thank you.
    joyce

    Hi,
    Finished goods price will depend on BOM componenet price,  activity price and overhead price. Check whether this prices are picking correctly or not.
    Regards,
    Sreekanth

  • PO for Finished Goods with Tax Code - Inventorise

    Hi All,
    Our Client is procuring Finished Goods from Domestic Vendor & Excise Duty is paid to the Vendor for that i am defining the tax code in PO. Over here For the Finished Good in Tax Code it is not capturing - (Condition Type - JMO2). I have checked it in PO for ROH, HALB tax code is working perfectly with (Condition Type - JMO2). I like to know will it work for finished goods or not. In J1ID i have maintained Excise Rate.
    I had followed the following steps.
    1) Material code- Chapter id maintained in J1ID
    2) Vendor code excisable in J1ID
    3) Maintain condition record in FV11 for the correct validity period
    4) Check the PO creation date whcih should fall between condition record validity period
    Every thing is maintained i have checked it Thoroughly fot this particular material i am not getting it. This one is a finished goods material.
    I am not able to identify what is happening.
    I will give the flow so that you can help me out.
    1. Created Material - Finished with all views except - Classification, Forecasting,
    Work Scheduling & QM
    2. Create Info Record - Tax Code given
    3. J1ID - Chapter ID, Chap ID with Material, *** Val for Mat, Vendor Excise Detail, Excise ind. for Plant, Excise ind. for Plant & Vendor, & Excise Tax Rate.
    4. FV11 - Maintained till - 31.12.9999.
    5. FTXP - Tax Code is Maintained & it's working fine with other PO.
    6. ME21N - PO is done for Domestic vendor with Standard PO With no condition & With only tax code for ED & CST.
    7. In J1ID cenvat determination has been maintained.
    Also the material type should be raw in material chapter id combination instead of RG1 even though the material is finished to take credit of excise it should be maintained as RAW .
    Over Here if i see i am not able to capture (JMO2 A/P Eduty for Inven 0.000%) &
    For Sale tax i have maintained it in FTXP as (A/P C Sales Tax Inv  NVV   12.500%  JIP1) but it is not appering in PO Tax code. I can See the sale tax is geting updated in Tax code for Inventorise if i give it with out ED in tax code. With ED it is not Appering in Taxcode.
    Can you help me resolving the issue.
    Once again thanks for youre help.
    Thanks in Advance,
    sapuser.
    Edited by: sapuser on Dec 26, 2008 10:10 AM

    Hi All,
    Just give a check by entering cenvat determination table. System checks this by default for excise details. Enter i/p and o/p material as same.
    Hope this will resolve you Problem,
    Pherasath

  • Uploading Production Requirements For Finished Goods From External System To Run MRP For Components in SAP.

    Hello Production Planning experts,
    I'm looking to solve the current business problem:
    The company bought a third party software (JD Edwards) to calculate production requirements instead of using SAP's standard Production Planning or a tool like SAP's APO. They run a batch job to query Sales Orders, Deliveries, available stock, stock in transit, etc. from sap and feed/upload it to the third party software so it can calculate the Finished Goods Production Requirements for them. They love the third party software, so replacing it is not an option. Since the third party software is already taking into account Sales Orders, Deliveries, available stock, stock in transit, etc. from SAP, it just outputs a "Finished Goods Production Schedule" by week.
    My questions are:
    1) What's the best way to upload something like that in SAP in the form of Planned Orders or something of that nature?
    After i get that schedule in SAP:
    2) Is there any way to calculate components' requirements for that "Finished Goods Production Schedule" alone? The company would like to IGNORE existing stock AND expected-goods-issues in the future (sales orders, deliveries, etc) for Finished Goods ONLY. The components calculations would work the standard MRP way, taking into account existing stock and AND expected-goods-issues in the future (sales orders, deliveries, etc)
    I started looking into Master Production Schedule (MPS), but I don't know if that's the right approach since I'm not very familiar with it.
    Thanks in Advance! I will gladly reward points for helpful/correct answers.

    Hello Oscar
    I suggest you to upload your production plan in the for of "Planned Independent Requirements" using BAPI BAPI_REQUIREMENTS_CREATE. Later, MRP will create planned orders to cover the PIRs.
    If you don't want to consider the existing stock of the finished product, you should use the planning strategy 11 to create your PIRs. Take a look on the following link for more details about this planning strategy:
    Gross Requirements Planning (11) - Demand Management (PP-MP-DEM) - SAP Library
    Here you will find the following information:
    The make-to-stock strategy gross requirements planning is particularly useful in mass production environments; it is often combined with repetitive manufacturing. This strategy is particularly useful if you need to produce, regardless of whether you have stock or not. For instance, steel or cement producers might want to use this strategy because they cannot shut down production; a blast furnace or a cement factory must continue to produce, even if this means having to produce to stock.
    This strategy is also frequently used if there is a Material Requirements Planning system in a legacy system that needs to be linked to an SAP system which serves as a production execution system. The legacy system calculates a specific production plan, which has to be executed, regardless of the stock situation in the SAP system
    It looks like this planning strategy is exactly what you are looking for.
    BR
    Caetano

  • Discontinuity and Follow-up Materials for Finish Goods

    Dear all,
    We have used for a long time the Discontinuity functionality and Follow-up Materials for Raw and Packaging materials (components in BOMs).
    We would like to use the same functionalities for Finish Goods, but after setting fields in MRP4 View, it seems not to work as it did for components.
    Is it possible to reproduce the same effect in Finish Goods as we had with components, i.e., use some kind of Discontinuity and Follow-up materials for Finish Goods?
    We currently work with R/3 V.4.7.
    Thank you all in advance for any support.
    Best Regards,
    Alberto

    Dear Alberto,
    If my understanding is correct then this discontinued material concept works only for the components and not for the finished
    product during MRP.
    Discontinuation Data Use
    In MRP, the discontinuation functionality is used to transfer dependent requirements of a component to one or several follow-up
    materials, if the requirements are no longer covered by stock. You can also define a follow-up material in the bill of material.
    Check this link to explore more.
    http://help.sap.com/erp2005_ehp_05/helpdata/EN/b1/c044d1439a11d189410000e829fbbd/frameset.htm
    Regards
    Mangalraj.S

  • Re: Automatic Reorder point Planning for Finished Goods

    Hi All,
    I have some doubts regrading the Automatic Reorder point Planning for Finished Goods.
    For testing purpose I have entered the consumption values for two month.
    Say :
    Nov-08=13
    Dec-08=20
    ROL level=5
    Safety stock =4
    Model =constant
    Now when I execute the forecasting,The system gives me the forcast for the next two month jan & Feb.
    But when I run the MRP I see planned order for 5.So how to fulfill my forecast for jan?
    Please Advice.
    Regards,
    Vivek

    Hi Brahamakar,
    Can you please help me.
    Regards
    Vivek

  • Plantwise Production & Sales report for Finished Goods

    Dear All,
                  Please let me know how to generate Plantwise Production & Sales report for Finished Goods. Is there any t code?
    Regards,
    Anil

    Dear All,
                         Thank you for the solutions. But can i draw the values in one single report. It will be more useful.
    Regards
    Anil

  • Moving average price for finished goods

    Hi All
    I am using moving average price for finished goods.  My question is, Does the price on the material master record adjusts, when we do goods receipt on a production order( If there are variances)?
    here is a scenario:
    Moving avrage price  of finished goods=2$ and total stock =1
    it has two components in the Bom
    Raw1-3$
    Raw2-3$
    Now when I am producing 1 qy of finished goods with 6 $ of Raw materials, moving average price of fert should  be 6+2/2=4 $. But I noticed the moving average price  in the material master record is not changing.
    My question is, Does the MVP changes with production order goods receipt, If so, what setting should I change to acheive that functionality.
    Thanks
    Steve

    Hi Guys
    Thanks for responding
    I am aware that sap does not recommend MAP for finished goods. But we have a weird requirement. And I am doing a demo on this. My thought on MAP is, It changes for every goods receipt. But when I am doing goods receipt on production order, It is not changing the MAP, Even though there is variance on production order. So, My question is, Did I miss any configuration ?

  • Split valuation for Finished Goods - Target cost was not updated

    Hi,
    We are following split valuation for 'Finished goods'.
    Valuation typte 1 is for 'manufacture' and
    Valuation type 2 is for 'External procurement'
    For production orders with this material, we are not getting target costs. It is showing zero.
    We have done release of standard cost estimate before creation of production orders and goods receipt for these orders. But still it is not updating.
    Pls guide me.
    Regards
    MadhuSekhar Gupta

    Hi,
    Thanks for your reply.
    At the time of variance calculation only the credit part of target cost will update and at the time of goods receipt debit part of the target cost will update.
    Our client has done goods receipt but debit part of the target cost was not updated. and the order status is DLV.
    I simulated the scenario in QAS by creating new finished goods materials (Industry-Construction) one is with split valuation and another is without split valuation, then the debit part of target cost was updated at the time of goods receipt and credit part was updated at the time of variance calculation for both the materials. So this problem was not arised because of split valuation.
    Was this problem arising because of the material master data, because for one material it is updating and for another it is not for the same configuration?
    Regards
    MadhuSekhar Gupta
    Edited by: gms gupta on Oct 22, 2011 3:39 PM
    Edited by: gms gupta on Oct 22, 2011 3:41 PM

  • PO for Finished Goods with Tax Code

    Hi All,
       Our Client is procuring Finished Goods from Domestic Vendor & Excise Duty is paid to the Vendor for that i am defining the tax code in PO. Over here For the Finished Good in Tax Code it is not capturing - (Condition Type - JMO1). I have checked it in PO for ROH, HALB tax code is working perfectly with (Condition Type - JMO1). I like to know will it work for finished goods or not. In J1ID i have maintained Excise Rate.
    Help me to resolve tis issue.
    Thanks in Advance,
    sapuser
    Edited by: sap user on Dec 18, 2008 4:04 PM

    Hi All,
    Every thing is maintained i have checked it Thoroughly fot this particular material i am not getting it. This one is a finished goods material.
    I am not able to identify what is happening.
    I will give the flow so that you can help me out.
    Created Material - Finished with all views except - Classification, Forecasting,
    Work Scheduling & QM
    Create Info Record  - Tax Code given
    J1ID - Chapter ID, Chap ID with Material, *** Val for Mat, Vendor Excise Detail, Excise ind. for Plant, Excise ind. for Plant & Vendor, & Excise Tax Rate.
    FV11 - Maintained till - 31.12.9999.
    FTXP - Tax Code is Maintained & it's working fine with other PO.
    ME21N - PO is done for Domestic vendor with Standard PO With no condition & With only tax code for ED & CST.
    Over Here if i see i am not able to capture (JMO1 - A/P Eduty for Setoff 0.000 %).
    Any other thing has to be taken care let me know.