Quality for Dormant material

Hi All,
i have requirement for quality check for dormant material i.e. if a material is not procured (no GR ) for the last 6 months but at the time of last GR date, 6 month back, this material was at skip stage(as per Dynamic modification rule).
and after 6 month also the stage will be same.but i want if material is coming after 6 month the inspection stage should switch to 1st stage(initial stage).
Hope I am clear. Can anyone help me in this issue.
Thanks!!
Vinay Upadhyay

HI
Your correct, u have to assign next stage as initial or as u wish whichever stage you can assign
then system will reset after 6months to next stage
if you have doubt better to test this function, you give the maximum skip duration as 1 day or 2  and test it.
i hope your clear now
thanks
sami
Edited by: sami sami on Nov 3, 2008 3:41 PM

Similar Messages

  • 1080p pour export quality for 25p material from Canon HF100 PAL

    Hi
    I have now tested iMovie 11 with a Canon HF100 PAL version. Shooting in progressive.
    The AIC import has good quality.
    New 1080p export gives same pour quality as before when using QuickTime 7 for h.264 export.
    AIC export provides good quality.
    So still nu easy way for export from iMovie. Is this common or is it a camera compatibility issue?
    Thanks
    Olof

    I just posted this for another user with the same problem.
    I have a Sony VG10 camcorder that shoots 30p and records it as 1080i60. iMovie sees this as interlaced video and deinterlaces it IF I use most FX.
    So I did a bit of googling and found there is a simple solution. I bought Steve Mullens newest version (09 and 11) of his "Ins and Outs of iMovie." With it I got a free copy of his iMakeFullHD utility. So after importing AVCHD I run the utility on the folder of clips and in a few seconds all the clips are now marked as progressive. Which is actually what they are! iMovie now treats them as 1080p30 -- exactly as it should.
    When reading about the utility I remember skipping the stuff on PAL HD camcorders. So I just reread it and it's no big deal eitherl.
    If you shoot 1080i50, the video is marked as 1080p25. This is exactly the reverse of what my camera does. So while I need to use iMakeFullHD, PAL users do not.
    If you shoot 1080p25, the video is marked as 1080i50. This is exactly like my camera. So you have to use iMakeFullHD to remark it is as progressive -- which is what it is.
    Now Ive no idea why Sony or Canon did what they did, but they did. After buying a $2000 camcorder, buying the book was by far the simpler solution.
    I know he has a section on 1080p50 and 1080p60 from the tms700. Didn't apply to me so i skimmed it. Also, having had imovie 09 i was surprised to read that 11 now supports real 1080p24. There's also a section on removing 2-3 pulldown from 1080i60 to get 1080p24. Again i just skimmed this in case sony were to release a firmware update so I could shoot 24fps.
    One more thing I learned. Because my video really is progressive, I can use all FX. They'll always look perfect.
    But, if you shoot 1080i50 -- which imovie sees as 1080p25 -- the good news is that imovie will never deinterlace the clips causing a loss of resolution. But, the clips realy are interlace. this means that sometimes you may see combing during the FX. There are very clear pix of what this looks like in the ebook. But, the solution is so simple -- only shoot 1080p25!
    Most of us want to shoot progresssive anyway!
    The nice thing is i followed the instrictions on burning 1080 avchd video to DVDs and they play in HD on my BD player. And, i didn't have to buy a BD burner.

  • Quality Deactivation for Specific Material

    Dear Gurus
    Is there any procedure to deactivate quality for specific material other than Material Master (MM02)
    Thanks & Regards
    Shoib

    Dear
    Go to QA08 and Select the deactivate the Inspection For particular Material and Before that Select Which Inspection Type u want to deactivate
    with regards
    pushpalas

  • Create Quality Management view for a Material in background mode

    I want to know if there is a way to create a Quality Management View (Quality Management tab) on Material Master (material already extended to plant ) in background mode.
    The requirement is to add inspection setup data for a material extended to a particular plant in background. I tried using 'BAPI_MATINSPCTRL_SAVEREPLICA' to add the data and it works perfect as required. Now the problem is this BAPI is creating the inspection setup data only for the material which has QM tab in MM02 for e.g. I manually created the inspection setup for a Material from MM01 and then deleted it , now the BAPI works fine for this material because when I created an inspection setup from MM01 it created the QM tab and after i deleted the entry the tab was still there with no entry in inspection setup.
    I want to create inspection setup for a material which does not have QM tab.
    I have to create everything is background mode. BDC is one option which I am list interested in.
    Thank you for helping in advance.

    Thank you for looking into my issue. I have to do the inspection setup in background without using any front end transaction.

  • Without Quality inforecord for vendor-material  - GR with spection?

    Dear Friends,
    Without Quality inforecord for vendor-material combination  - GR with inspection lots were created, kindly explain me the possible reasons for that. and do also mention that whether the quliaty inforecord is mandatory or not?
    Regards,
    Archana

    In material master - QM view, check the "QM proc. active " indicator and the control key.
    If this indicator is active and any control key except '0000" is assigned in material master, it will ask for Q. info record.
    Vishal
    Edited by: VISHAL JONNALWAR on Dec 13, 2010 7:58 AM

  • Quality Inspection not cominf for a material code

    Hi!
                  For a  particular material code,already there a quality view in material master.but it is not coming  for inspection in QA32.what i have to proceed further for bringing the material for quality inspection?
    -M.Suba

    Hi Suba,
    Try this.
    1.     Go to MM02
    2.     Put material code and press enter
    3.     Go to QM view
    4.     Click on Insp.setup. (It looks like solid rectangular tab)
    5.     Assign inspection type 01 if the material comes from vendor, else 04 for final inspection.
    6.     Ensure that you tick on u201CActiveu201D checkbox.
    7.     Save
    Do fresh GR. System will generate lot this time.
    Regards,
    Anand Rao

  • Re: Quality Certificate requirement At MIGO for raw material

    Dear all,
    I have a requirement where I want the system ask for Quality certificate while doing the goods receipt. The system should not allow me to process the transaction-MIGO if certificate is not recieved.
    Please advice
    Regards,
    Vivek Sharma

    Hi Vivek,
    You need to perform following settings.
    Configuration
    Follow the path
    Run trx QCC0->QM in Logistics->QM in Procurement-->Define Control Keys.
    Here create your own control key
    Where you can set the rest data as per your requirement but for to check the check box for "Cert Required" is must be activated to meet the requirement relevant to this thread.
    Save
    Say you have configured your Control Key ZZ01
    Now just below this one small configuration is mandatory is Run trx QCC0->QM in Logistics->QM in Procurement-->Define Keys for Certificate Processing
    Maintain Description
    Execute it and go to "Define Certificate Types"
    Here either for your relevant certification type or  for new type (if you wish to create new), maintain the data as below
    "Certificate Required for Each Purchase Order Item" ==== Active
    "Certif. per GR Item" ==== Active
    "Certif. check required" ==== Active
    "Control W/O Certif." Set any error message, I would suggest to select "Without lot error message, with lot error message"
    "Enhanced cert. processing" ==== Don't Activate
    "No certif. confirmation at GR" ==== Don't Activate
    The rest settings are not important to maintain so leave them blank.
    At Master Level
    In QM view of MM for the material maintain "QM Control Key" that just created "ZZ01"
    and the certificate type that is just created or amended. under the procurement data.
    Maintain Q-Info record for Material - Vendor - Plant combination (QI01)
    Now as per your requirement system will ask for the confirmation for certificate receipt as Yes/No. under the Purchase Order data in MIGO at item level data.
    If you select "NO" to it it will not allow to post the GR.
    I hope this is what you were looking for.
    Regards,
    Shyamal

  • Quality check for Pipeline Material

    Hi MM Guru's
    Is it possible to do quality check for Pipeline Material?
    If yes what is the process.
    Thank you
    Venu

    you can create a manual inspection lot, analyze a sample and record the results.
    but you cannot have a quality stock and do not do a transfer posting from quality to unrestricted or quality to blocked.
    There a many chemicals that are transported via pipeline and managed as pipleline materials, either supplied by a supplier in the neighborhood or even cross country. And it is needed that you want do quality checks on certain materials before you use them.
    Search the QM forum, you may find some discussions.

  • Multiple Posting change notice created for one material document

    Hi All,
    The scenario is that the user needs to transfer material from unrestricted to quality stock type. while doing so the storage type is different than the actual storage type for the material. Meaning if the material is normally stored in high rack storage type, when it is found that the material is damaged or expired it need to be moved to the quality storage type. For this the user will first create  material document in IM with movement type 322 transferring material from unrestricted stock to qualtiy stock. A PCN will be created in back ground which will in turn be converted manually by the user to a TO. while doing so the user will pick the quant manually from the required storage type and select the destination storage type as the quality or quanranntine area.
    The issue here is that system creates one PCN for each material document line item. The requirement is that the system should create only one PCN with multiple lines for one Material document.
    The setting in the movememnt type clearly says that it will behave as it is behaving.
    Is there any other way or setting by which we can create one PCN with multiple line items for a material document.
    Would look forward to your replies.
    Regards,
    Jeetendra

    Thanks and Sorry for the delayed reply. We have now convinced the users that the system behaviour is standard and we cannot change the same.
    To your question about the need to have one PCN with multiple lines please note that the setup is such that when material document is created for transferring material from unrestricted to quality and vice versa this document is created with multiple materials in one go. Now when the PCN is to be converted to TO then the user ends up in creating number of TO's equal to the number of lines in the Material Document. We wanted to avoid this and hence this was posted in SDN.

  • Urgent issue REPORT FOR ALL MATERIAL BASED ON STOC TYPE

    Hi
    I want report for based on stock type
    i want to check the stock for all mterial with  stock type "quality inspction"
    i want that type of material documents
    is it possible to see the report
    regards sesidhar

    I CREATE material A...with out seleting QM view
    I create one more material B.... with select QM view
    both r ROH material type..
    when i caeate GR for material A. with stoc type 'QYALITY INSPECTION.. for this material system does not creat quality LOT....
    when i create GR for material B with stock type 'QYALITY INSPECTION.... for this material system created lot..
    but are GR done by 101 movement..
    but i want report for materials which are stock type QI...but does not display Material which r lot created...?
    is it possible..
    regards
    sesidhar

  • No inspection lot can be opened for this material and vendor -QA228

    Hi every one !
    Iam  getting  Error while doing Migo -"No inspection lot can be opened for this material and vendor-QA228"
    we analyze the issue asfollow -
    1.checked Quality Lot-Available
    2.Quality info record- Availble
    3. Quality plan is exist.
    But stil throwing  above Error.

    Hi,
    Check the below threads,
    [No inspection lot can be opened for this material and vendor;
    [No inspection lot can be opened for this material and vendor;

  • Line item for header material not updating in COEP table

    Hi all,
    from last few days, I found that   when I do confirmation and GR for process order, system is updating all line ( i.e. components, activity types) but line for header material that is finished goods  or semi finished goods is not updating in COEP table,  I have done GR for order and transferred stock from quality too.
    But still its not updating. What could be the reason for it .
    Thanks
    Vivek Varun

    Hi Krishnendu,
    Thanks for the reply ,  FI document is not getting generated.
    What could be the reason for it, as before it was working fine.
    Thanks
    Vivek Varun

  • UD for a Material in HU-Storage location

    Hi Gurus,
    I have situation where Stock posting tab is not coming while doing the UD for a material
    Process flow is below:
    1. Creation/Release of Process - Inspection lot get created since early lot creation status REL CALC
    2. GR of Process Order is done in MIGO in Hu storage location
    3. Inbound Delivery is created (WM integration)
    4. Inbound Delivery is processed with TR creation/Confirmation
    5. Stock can be seen in Q under HU active storage location & Material document is created in IM . Inspection lot status is same
    6. Result recording is done against Lot Status INSP RREC
    7. While doing UD. Tab for Stock posting is missing. Status UD   ICCO CLAS STUP
    This inspection type has following settings: - tick post to insp stock, Insp with task list , early lot creation , auto UD etc
    Not sure what I am missing some settings since that is HU storage location
    Please guide
    Thanks,
    Ishwar

    Hi Yogini,
    Thanks for that .
    I tested as per suggestion but that is also not working basically no inspection lot is getting created for the GR after completion of WM transaction
    I have tested my senerio for non-HU storage location (doing GR in no-HU storage location ) & that works correctly . After UD i was able to see tab for stock posting & stock get posted successfully
    I think need expert advice who has work on QM-WM integration part ... can we able to post the stock from Quality stock from HU storage location to unrestricted use using only IM transaction ( QA11/12 ) or do i need to perform some additional steps in WM ?
    Thanks,
    Ishwar

  • In process Quality for Production orders

    Hi Guys,
    I am facing issues while doing an in process quality for production order.The usage is In process quality,
    can anyone help me to carry out a flow for this usage type.
    What are the necessary settings to be done and also explain the workflow for this inspection type.
    Thanks,
    Krishna

    Hi,
    For in process quality you have to activate "03" type quality in the QM view for the material.
    After creation of the order you have to generate inspection lot and based on the inspection lot you have to do result recording.
    After that you will do the GR followed by usage decision of the inspation lot.
    Hope this will help.Please elaborate the details for further clarification.
    regards,
    kaushik

  • Purchase order for sample material

    Dear All,
    Do you have any suggestion about purchase for sample material?
    During we develop new vendor, we will get sample material from them and do not pay, but after we use the material to produce, and the quality is OK, we will pay for the sample materials, the process should cover purchase, production, QM, warehouse.
    I will reward you.
    Best regards
    Gang

    Hi,
    I would suggest that you try a consignment PO.
    this will bring the item into stock but the item will not cause any finacial postings (the item is classed as still belonging to the vendor). Then if and when you decide to uise the item in production, consume it from consignement stock and this will  then trigger a debt to the vendor of the value of that item (from the consignment info record) and so you can then accept an invoice from the vendor or simply send them a payment by using consignmenmt settlement functionality.
    Worth considering
    Steve B

Maybe you are looking for

  • Yahoo emails not working in iphone 5

    Hi, I have just changed to Iphone 5 and I noticed that my yahoo emails are not working. I cannot save the yahoo password when I set up my yahoo email accounts in Iphone 5. The error message says "Yahoo Server unvailable". Please try again later. I tr

  • I have unknown charges on my account. How can I tell what I am being charged for?

    I would like to know how to tell what I am being charged for. I have two .99 charges on my bank account and I am unsure as to what they are for. One in particular is from today and I have not purchased anything. I did do some app updates. Am I being

  • How to pass multiple values to a single parameter in BW report URL

    Hi Experts, I am new to EP and learning .... i am stuck at one point where we need to pass multiple parameters to a BW report URL, this is the URL that we launch from BSP.... Suppose i have to pass different multiple values to a single parameter, how

  • Apple's Single-Document Interface in Windows

    I've been a Windows user all my life, but I use a Mac at work.  I've come to appreciate one and only thing about OSX, and that is the SDI (single document interface).  I can easily drag vector objects from my Illustrator window into a Photoshop windo

  • Help needed with forms

    Hi, I need help with 2 things: 1. I want to create a form with name,subject and message box on for the user to fill out and then when they click submit it sends the form to my email address. 2. I want to create a form where the user can upload their