Question on Allocations in Oracle Projects

Hello All ,
Please let me know how to transfer amount on one task to another within the same project using Project allocations.
If there are Multiple Projects present in the system how do we map that cost from a project goes into another task on the same Project . How do we establish a one to one relationship between the source and targets in this case?
Regards
DR.
Edited by: 933993 on Nov 2, 2012 5:14 AM

Hi
You should set up an Allocation Rule for each pair of project and tasks you want to transfer costs between.
Navigate to Project Costing > Allocations > Allocation Rules.
A) On the setup form enter a name to the allocation rule, Select Basis Method as Target % and spread Evenly.
Enter the expenditure organization, exepnditure type class and expenditure type for the EI resulting in the allocation run. Save.
B) Now open the Sources form - Under the Project Sources section select the amount type (raw or total burdened cost), then enter the first line of the source - there you list the projectt and task being the source. Save.
C) Open the Targets form. On the first line enter the project number (same as above), and the task number which you want to be the receiving task. On the % column enter 100%. Save.
D) At last go to the Offset form. There you may choose the offset method and the offset transaction attributes. Save.
Dina

Similar Messages

  • Oracle Projects 11.5.10.2 : Generate Invoice at the lowest task level...

    Oracle Projects: 11.5.10.2.
    We are trying to figure out if we can generate an Invoice at the lowest task level. When I looked at the invoice format there was no option to group by at lowest Invoice level However I looked at one of the documents of project partners vendor and created an Invoice format option of lowest task. However I can not fund the project at lowest taks. When I go to the agreement I only see top tasks in the list of values?
    Does any one know how to achieve /generate billing at lowest task level?
    When I looked at the project type setup there is a billing option called funding level: This only gives two options top task and project level or both but not at lowest task.
    any clue/help would be greatly appreciated.
    The reason we are trying to do this is we want to pass a tax code at the lowest task level.
    --Krishna                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           

    Hi
    There is no way to fund the lowest tasks.
    You cannot generate invoice with invoice lines per lowest level tasks, using standard functionality.
    Assuming your billing is based on WORK, you could customize the Invoice Format to summarize RDL's by lowest task level.
    However, if you need hard limit control by lowest task level you will need to capture the allocation of fund to tasks. That could be done on a revenue budget you maintain by lowest level tasks. In addition, develop billing extension called during GDI that will perform the fund check for each task.
    Dina

  • Meaning of Auto Accounting feature in Oracle Projects

    Dear All,
    Can someone explain me about the Autoaccounting feature in Oracle Projects. How to configure it based on the business requirment.
    Please share if you have any documents on explaining this feature. Please forward me to - [email protected]
    Thanks,
    Arvind

    Pl see if MOS Doc 552086.1 (AutoAccounting Frequently Asked Questions (FAQ's)) answers your questions
    HTH
    Srini

  • Compliance report - Oracle Projects??

    Hi All,
    Does anybody has any idea about Compliance Report.
    If so , can you please guide me how to run it in Oracle Projects.
    Thanks and please reply,
    Anand.

    Hi
    There is no way to fund the lowest tasks.
    You cannot generate invoice with invoice lines per lowest level tasks, using standard functionality.
    Assuming your billing is based on WORK, you could customize the Invoice Format to summarize RDL's by lowest task level.
    However, if you need hard limit control by lowest task level you will need to capture the allocation of fund to tasks. That could be done on a revenue budget you maintain by lowest level tasks. In addition, develop billing extension called during GDI that will perform the fund check for each task.
    Dina

  • Oracle Projects AIM documents template - BR100, TE, BP Etc

    Hi All,
    Can someone help me in getting the AIMs doc for oracle project costing / billing / managment R12?
    It would be gr8 to have any of the business process doc / functional specs ( BR100) / Test cases / Migration Doc / Gap analysis doc etc.
    Just templates of these will also sufficient if docs are not availalble.
    Please send it to [email protected] or guide me with URLs if possible.
    Thanks in Advance. :-)
    Regards

    Please see old threads which answer your questions -- http://forums.oracle.com/forums/search.jspa?threadID=&q=Download+AND+AIM&objID=c3&dateRange=all&userID=&numResults=15&rankBy=10001
    Thanks,
    Hussein

  • API to update resource Planning list in Oracle Projects

    I have found the following API to update the RPL in Oracle Projects.
    PA_PLAN_RES_LIST_PUB
    My question is this API updates the RPL only at the Definition level, is there any way that once we update using this API , the changes to be reflected to RPL assigned to the Project Templates.
    We cannot check the check box for Centrally Controlled at the RPL setup due to some business reasons.
    Pleasae let me know if anyone has any idea about this issue.
    Thansk
    Sunil

    You can have customization/trigger on the planning resource list table, whenever it is updated, it checks for the templates which it is being used and it updates it accordingly.
    You may have to careful that the trigger is not mutating though !
    Thanks,
    Sathish
    www.projectsaccounting.com

  • Plz help????????????tell me about the oracle project as i am new to oracle

    plz tell me how i can get oracle project i.e sample project or demo projects
    so that i can have an idea...............
    plz help....................
    thanks

    This is your 4th or 5th post in which you are using subject like this and I guss you might have been told to write in a decent manner. Havnt you learned anything about being bit decent ?
    Why you think that these hell lot of question marks are going to make it more important than other posts. If you want to ask something, just be polite and give some good subject to the post.
    BTW why you are looking for ready made demo projects ? Want for some assignment ? If you are new, think, make a project and learn. There is no tablet that can help you in learning Oracle.
    Sidhu
    http://amardeepsidhu.blogspot.com

  • How to Integrate Oracle Projects(EBS-R12) with Primavera P6

    Dear All,
    As i have a requirement that i need to *"Integrate Oracle Projects(EBS-R12) with Primavera P6 for Oracle Projects Accounting ( Costing & Billing ) using Application Integration Architecture(AIA-PIP)"*.
    So kindly suggest me to do the same.
    Thanks in advance for your valuable suggestion.
    Regards,
    Saravanaa

    Vishal, I would recommend that you post this question on the CRM On Demand Integration Development forum.

  • Oracle Project Analytics - Project Manager Security Implementation

    Has anyone implemented a security scenario for Project Managers, such that they can only see the information associated to their projects when using EBS as the source? If so,
    - How did you identify the relationship between project managers and their projects? Did you use an initialization block and pull this information in from EBS?
    - Where did you define the security/filtering configuration so that they were limited on what they could see?
    - Did you create a custom responsibility for 'Project Managers' and have them access a set of Project Manager dashboard/reports that followed the Project Manager security model?
    Thanks in advance.
    k
    Please note that I have posted this same question/thread in the BI Apps forum. I didn't want to duplicate effort, but I know different users may only come to this forum. The link to the original thread is below:
    BI Apps Forum Thread
    Oracle Project Analytics - Project Manager Security Implementation

    Coolmesh84,
    Thanks for the great info and reply. This makes complete sense to me, but I just want to make sure I am clear on a couple points:
    +1. Use an initialization box to filter the user's emp id+
    You mean use an init block to pull the users employee id and store it in a session variable correct? The session variable will then be used later as part of the filter criteria.
    *2. and add a filter to the required dimension table in business layer to filter based on the project_manager_id column for the project manager group.+*
    To implement the step above, would you follow theses steps:
    1. Go to Manage->Security
    2. Under Groups, select the group planned to be utilized for this filter (in this case I double clicked the Project Manager group).
    3. I then Click permissions button for this group
    4. Go to the Filters tab of the window that pops up
    5. Add a filter, go to BMM tab and select the Project dimension and then define a filter for Proj Mgr Id = nqsession.employeeid
    +3. Ideally you should be able to use the OOTB project manager group for this security.+
    This is a good point, but a few more questions here - There are a number of Project related groups (see below) in the out of box Oracle BI Apps RPD and all of them essentially roll up to the super group 'Operating Unit Org-based Security'. Is there a best practice or preferred approach for utilizing these groups as they related to Oracle EBS v12? Is there any good documentation out there to see what the intended use and setup is for these groups? Do all of these groups relate back to an EBS Responsibility? I have read through the OBIA Security Configuration document and basically all it says is to enable the operating unit org initilization block and thats all .. not really all that helpful.
    Thanks again - k
    Project Executives
    - Project Billing Super User
    - Project Costing Super User
    - Project Super User
    - Projects Implementation Super User
    Project Managers
    - Projects Implementation Super User
    - Project Administrator
    - Project Manager
    - Staffing Manager
    - Operations Manager
    - Project Super User
    - Resource Manager
    Project Team Member
    Edited by: user_K on Nov 22, 2010 5:10 PM

  • Guidance regarding oracle projects implementation

    Hi,
    Can you please explain the steps regarding implementation of oracle projects in an organization. what approach we will take. what all things are taking into consideration.
    any documents please share. plse send it to my mail - [email protected]
    Thanks in advance.

    Hi Experts,
    Same question here - is it possible to have some sample Buisness Process documentation, BR100, Functional specification , AS-TO-be or test cases, Tech Spect etc.. which is used for implementation of Oracle Projects in any Orgnization?
    If possible share the same on [email protected]
    Thanks :-)

  • Oracle Projects Differences from 11i to R12

    Hello All,
    Currently we are upgrading from 11.5.10.2 to R 12.1.3
    We have oracle projects implemented in 11i.
    I am researching to get the differences occurred in oracle projects functional and technical from 11i to R12
    It will be a great help to us if we could get some documents or a link which shows the differences.
    Thanks and Regards,
    Ankit Vishwakarma

    Project new features
    Oracle Project Foundation
    New Concurrent Process
    ADM: Purge Obsolete Projects Data
    Oracle Project Costing
    Federal Budgetary Accounting for Project Expenditures via Subledger Accounting
    Contingency Worker Clearing Projects to allow CWK to charge multiple projects
    Additional Project Information in Oracle Time and Labor (Project Name and Task Name)
    Federal Budgetary Accounting for Project Revenue
    Additional journal entries are available in Subledger Accounting for the required Federal Budgetary entries.
    Date Effective Funds Consumption
    Project Type option that requires cost and event transaction dates to fall within the agreement start and end dates.
    Transactions are only billed against the agreement if the entire transaction amount can be funded (no partial recognition) for both revenue and invoicing.
    Without enabling this option, revenue generation supports partial billing for transactions.
    New Parameters for MGT: Invoice Review
    Project Status
    Project Closed After Date
    Project Range
    New Parameters for MGT: Unbilled Receivables Aging
    Project Status
    Project Closed After Date
    Project Range
    Oracle Project Management New Audit Process for Project Performance Reporting Setup
    AUD: Project Performance Reporting Setup
    New Parameters for Refresh Project Performance Data Process
    Actual or All Amounts (Plan and Actual)
    Workplan Version
    Financial Plan Version
    Workplan EnhancementsAbility to Delete Published Workplan Versions (except the latest published version, baseline version, and workplan versions included in a program hierarchy) Usability Enhancements
    Update Work Breakdown Structure page is now obsolete.
    View, maintain, and update a workplan structure from the Update Tasks page.
    Where no latest published workplan version exists, the current working version displays on the Update Tasks page when navigating to the Workplan Tasks.
    Indent or outdent multiple workplan tasks in a single step.
    Confirmation, information, and warning messages appear on HTML pages during Apply Latest Progress as well as the Submit Progress processes. Messages include status information during processing and the availability of the latest progress information.
    New Public API for Creating, Maintaining, and Deleting Programs New set of public API procedures:
    Designate a project as a program and indicate whether projects linked to the program can belong to multiple programs.
    Create links from a program to one or more projects
    Update links from a program to one or more projects
    Delete links from a program to one or more projects
    Budgeting And Forecasting Enhancements Enhanced Automatic Calculation and Derivation Logic
    For plan lines that do not have a specified a quantity, the amount is no longer copied to the quantity field with the rate value set to 1.
    Rate now has a lower precedence than quantity and amount in automatic calculations.  The rate will be re-derived when the quantity, rate and amount are entered at the same time for a plan line.
    When the burden multiplier is overridden by updates to the raw cost or burden cost, subsequent calculations of the burden cost will use the override burden multiplier.  The same is true when the markup percent is updated by changes to plan line components:  the override markup percentage will be used in revenue calculations.
    Enhanced Handling of Override Rates on Budget / Forecast Lines
    Override rates for a planning transaction on Edit Budget and Edit Forecast pages.
    o   Raw Cost Rateo   Budened Cost Rateo   Bill Rate
    Override rates are applied to all existing and new periodic lines for the planning transaction.
    Average rates fields on these pages are now disabled for entry and are used for display only.
    Simplified Addition of Planning Elements and Resources
    New but unbudgeted tasks and resources can be added to a budget or forecast version.
    Add either all new tasks and planning resources or new tasks only to the current plan version.
    Self Service Expenditure Inquiry
    Ability to drill into expenditure details from the Financials tab.
    Reporting Pack for Generation and Distribution of XML Publisher Reports
    A reporting pack is a set of report templates and recipients by project role.
    The Generate Reporting Pack concurrent program emails the reports generated from the report templates based on pre-defined intervals.
    The report template establishes each report’s layout and content.
    New reports templates are configured using XML Publisher tools.
    New or modified reports can be added to an existing reporting pack or be used to create an entirely new report set.
    Predefined data definition files that contain XML tags for performance measures and project data are provided.
    Predefined Reports:
    Project Change Document Report
    Project Committed Cost Report
    Project Cost Detail Report
    Project Cost Labor Report
    Project Cost Summary Report
    Project Earned Value Report
    Project Financial Summary Report
    Project Forecast Summary Report
    Project Revenue At Risk Report
    Budget Integration with Federal Budget Execution and/or 3rd Party Budget
    The budget integration workflow supports integration with the Federal Budget Execution module..
    The workflow can be customized to interface budget lines to external budgeting applications.
    Microsoft Project 2007 Certification
    Integration with Microsoft Project 2007 is supported.
    Project Performance Reporting: Additional MeasuresYTD, QTD and At Completion calculated measures are available on the following pages:
    Performance Overview Period-to-Date
    Summary/Analysis
    Task Summary/Analysis Resource Summary/Analysis
    Project Performance Reporting: Inter-Project Revenue / Billing AmountsInter project revenue / billing amounts are available on the following pages:
    Project List View Workplan Cost
    Exception Reporting Performance Overview
    Task Summary/Analysis Resource Summary/Analysis
    Period-to-Date Summary/Analysis
    Supplier Cost DashboardSubcontractor Payment ControlsSupport for Pay when Paid Scenarios
    A new “Pay when Paid” payment term for subcontracts automatically places holds on all subcontractor invoices under that subcontract until the corresponding customer payment is received.
    Subcontract Payment Controls workbench allows project manager to manage the holds, with visibility into both the customer invoices and the related subcontractor invoices.
    Workflow notifications about the receipt of the customer payment allow the project manager to automatically or manually release the subcontract invoice.
    Associations between the customer invoices and the subcontractor invoices may be automatically maintained based on the billing of project expenditures for cost-plus contracts, or may be manually maintained for fixed price contracts.
    Payment Controls for Subcontract Deliverables
    Support for the tracking and monitoring of subcontract deliverables that place automatic holds on subcontractor invoices in the case of noncompliance.
    Oracle Procurement Contracts allow a subcontract administrator to specify payment impact controls that will take effect when a subcontract deliverable is not met.
    From the Subcontractor Payment Controls workbench, the project manager can view a checklist of the all the current subcontract deliverables, to assist in evaluating the subcontractor status prior to releasing monthly progress payments.
    Oracle Project Resource ManagementResource Search Enhancements
    Resource Search by Email Address
    Resource Search by Person Type
    Streamlined Navigation on Staffing Home
    Cross Validation of Project and Assignment Dates
    Requirement start dates are equal to or greater than the project start date and less than the project end date and that finish dates are equal to or less than the project end date but greater than the project start date.
    Assignments cannot be added beyond the project end date.
    A project team role end date cannot be beyond the project end date. If the roles are created before the project end dates are entered, users will receive an error if they later try to enter an end date that is earlier than the end date for existing roles.
    When project transaction dates are moved corresponding assignment dates are validated against the new project dates. If the new project transaction dates fall outside the dates for existing assignments, users are given an option to shift the assignment dates or cancel the date adjustment.
    Defaulting of Work Patterns’ From and To Dates
    Work pattern from and to dates will default from the requirement start and end dates.
    Improved Exception Handling of Maintain Project Resources Process
    PRC: Maintain Project Resources delivers improved exception handling and notification when it encounters errors while processing employee records.
    New Public APIs for Resource ManagementThe new PJR APIs fall into the following four categories:
    Requirement Public APIs
    Assignment Public APIs
    Candidate Public APIs
    Competence Public APIs
    Organization Authority: Obsolete Forecast Authority
    Removes the forecast authority functionality from the organization authority form
    Removes existing security data relating to forecast authority.
    Replaces the PJR forecast functionality with the new HTML based forecasting functionality. The new forecasting functionality has its own security mechanism and does not honor the old forecast authority model.
    Improves the performance of security calls to organization authority because the existing security data is being removed.
    Oracle Grants AccountingAward Budgeting Enhancements Budget period validations
    Budget periods will not be validated across award budgets when those awards fund a single project.
    Flexibility to establish award budgets based on the actual duration of the award, while not being confined based on the existing budgets already established for the project.
    Automatic summarization of project budgets
    With the new budget period validations, automatically summarize to a project budget viewable in Project Status Inquiry.
    Two profile options have been added to identify the budget entry methods that will be used to summarize the project budgets.
    Budget Line Sorting Option
    Sort budget lines by Resource name, or by effective dates for budgets with date range periods.  Provides the flexibility to view the budget lines by period or by budgeted resource.
    Award Status Inquiry Enhancements View by budget period
    Allows the Find Award Status window to be limited to a single period, range of periods, or inception to date for a particular award.
    Reflects the budget periods entered on the award budget.
    GL and PA Date Parameters on Find Expenditure Items window
    GL and PA date parameters have been added to the Find Expenditure Items window.
    GL Date Parameters on Find Commitments window
    GL Date parameters have been added to the Find Commitments window.
    KKG

  • VS, ODT and using "Oracle Project"-template requires Policy Management

    HI,
    I installed the ODT 11.1.0.6.20 and tried to create a new project using the "Oracle Project" but received the following error message: "The project <ProjectName> requires Policy Management. Open this project in Visual Studio.NET Enterprise Developer or Visual Studio.NET Enterprise Architect."
    I have tried this using VS 2008 Professional and Team Edition. The operating systems is Vista x64 Ultimate.
    Oracle documentation doesn't mention any specific VS version so this is perhaps something else. Is there a workaround or fix to get around this?
    TIA,
    Kari

    OK, I'll give it a try. This suggestion makes perfect sense. I have used that template to create a project before, but noticed that it doesn't contain a windows form by default and so I assumed that it was a build for a n-tier application database access class, which is not necessarily what I want, and so I abandoned the effort. I know I can add a window form. I appreciate the response and will post back my results.
    Is there an example project somewhere that I could download and have a look at?
    Thanks again for your reply, even though you didn't reply to me. I think you resolved my problem! :-)
    Bruce
    Edited by: Bruce Davis on Oct 19, 2009 11:07 AM
    Edited by: Bruce Davis on Oct 19, 2009 11:11 AM
    I replied to the wrong post!

  • Unable to do adjustments for PO Receipt Accrual in Oracle Projects

    We are working on Release 11.5.10.
    The Allow Adjustments flag for the transaction sources in Projects for receipt accruals (Oracle Purchasing Receipt Accruals) and For Supplier Invoices (Oracle Payables Invoice Variance) are not updatable. Since we are using the Accrue on Receipt option, so only the Invoice variance amount is tranferred to Oracle Projects from Accounts payables. There are situations when the cost gets booked to a wrong task or wrong Project. In such case the adjustments to receipt accruals and Invoice Variance needs to be done. But the same cannot happen in Oracle projects without enabling the Allow Adjustments flag, which is not updatable in Release 11i. How can we make any adjustments to receipt accruals and Supplier Invoices matched with the PO Receipts in Release 11i?
    Appreciate any Pointers on this.

    Hi
    In PO receiving form, enter a transaction of type Correction or Return to Receiving, with minus the quantity you want to adjust. This will be a negative transaction to the original project and task.
    Then update the PO line distribution to the new project and task. Finally enter another receipt / deliver transaction to the new project and task.
    Run the PRC: Interface Supplier Cost. This process will create new transactions in the old and new projects. The new transactions are linked to the same PO, same line number as the original PO Accrual transaction.
    If the supplier invoice have not yet entered in AP, then entering a supplier invoice, matching to the PO will get the variances charge to the new project.
    Other wise, you might want to reverse the matching, and reenter the match to the new distribution.
    You could also enter a MIX supplier invoice which has the amount as zero. In such invoice enter a negative distribution line to the old project, and a positive distribution line to the new project.
    Dina

  • Any Automation possible in oracle project module through customization

    Hi,
    Anybody aware of any customization in oracle project module.We have some customized requirements from users
    i.e..1)Can we update the status of task once it is completed.2)When we create the dependency and in case change in schedule does system changes the date of dependent task automatically.
    Regards,
    Chintamani

    Hi,
    Anybody aware of any customization in oracle project module.We have some customized requirements from users
    i.e..1)Can we update the status of task once it is completed.2)When we create the dependency and in case change in schedule does system changes the date of dependent task automatically.
    Regards,
    Chintamani

  • Setup issue in oracle projects - classifications link(standard link) is missing in oracle projects page

    Hi Team,
    I have a setupĀ  issue in oracle projects
    I am unable to find the classifications link in oracle projects page.
    Navigation : Go to any projects responsibility-->search for the projects-->click on project -->click on setup Tab : At the bottom of the page, we can see some standard links along with UDA's.
    Here one standard link Classifications is missing.
    Can anybody guide me what setup we need to do get the link.
    Thank you.

    Hi,
    The classifications link is not appearing in your Project's Setup page because, Classifications must have been unchecked in the Project template from which your project has been created. You can find the Project template information by clicking on the Additional Information link in the same Project -setup page. Once you check the classification flag in the concerned Project Template, all future Project creations made out of this template would have the link enabled.
    But for the current project, classification link cannot be enabled.
    Rgds,
    Shan

Maybe you are looking for

  • Compare two Idoc's and send to te recievers as per the Condition.

    Hi, Scenario: Sender are a Idoc's and Receiver is Mail and File. Sum the value of field1 of IDOC1 loop and compare with the field 2 of IDOC2. If the Condition satisfy send the data to file and mail reciever else send to only mail reciever. I tried us

  • How to find the corrupted files using javascript?

    Hi all, I need to run batch of files some of which were corrupted?? instead of using the method "the files which were not opened are corrupted" is there any way to find the corrupted files?? I need to find this using javascript or apple script?? Plea

  • "Download" Business Rules

    I wasn't sure where to post this, but: Let's say I have boolean code sitting in a file on my computer that probably runs in java... :) I want to read the file into my program and use its boolean code to decide whether or not to do things (since there

  • What does the class CL_EXITHANDLER do ? What the significance of this class

    what does the class CL_EXITHANDLER do ? What the significance of this class,

  • Superdrive spits out CDs?

    Hello, I'm new to this, so I'm not sure how this thread/discussion works, so sorry if this is completely wrong. I have a 2007/2008 MBP. When I try to put a CD/DVD into the superdrive, it makes some weird cranking noises (I guess trying to read it), t