Quotations from Project Simulation Version

Hi experts,
We are creating project quotations using DP81. We create multiple quotations for the same inquiry using Project Simulation Version.
We would like to know from which version the quotation document has been created, is it possible?
Or can you suggest any workaround?
Thanks

Hi,
Both options, as in DP81 we are able to select simulations versions.
But onces the quotations has been created we can't know the source. we know the project as is informed in the account assignment but not the simulation version we have used.
Has anybody faced this issue before?

Similar Messages

  • Sales pricing from Project Simulation Version

    hi.
    Has anybody created sales pricing for the project using transaction DP 82? It does not create the sales pricing for the simulation version, even though I have provided the version key.
    The status of the simulation version of the project is CRTD. I am using the network cost planning in the simulation version of the project. Am I missing something here? I am hoping to get an answer from this community. Thanks for your help in advance.
    Regards
    Mey

    Hi
    The following are the prerequisites for the sucessful fuctioning of sales pricing for simulation versions of the project.
    1. A dynamic item processor profile (DIP profile) must have been maintained in the customer inquiry.and must be Customized for Project System.
    2.The same DIP profile must have been entered on the Sales B tab page of the item detail view in the SD order.
    3. A customer inquiry with at least one item that has to be maintained and assigned to a billing element must exist. The system determines the SD data for sales pricing from this inquiry item.
    4.You have planned costs (in concordance with cost elements) for your project version.
    If these prerequisites are met, i think it will work
    Reward if helpful
    Regards
    Murali

  • Project Simulation Version

    Hi,
    Is there any Function Module or BAPI to extract all details of PRoject Definitions and WBS element and Network Activities for Project simulation Version/Version key.
    Thanks
    Ramesh

    Hi,
    Both options, as in DP81 we are able to select simulations versions.
    But onces the quotations has been created we can't know the source. we know the project as is informed in the account assignment but not the simulation version we have used.
    Has anybody faced this issue before?

  • Proforma Invoice or Quotation from Project

    Hi Experts,
    My client requirement is like this:
    1. Receives request for procurement of goods/service from different user departments.
    2. Will send estimation to the user departments and will proceed further.
    I want to map like this through PS (SD module is not there):
    1. Receive requests
    2. Will create a simulation/plan project version
    3. Will generate the proforma invoice / quotation from the planned costs of this version.
    please let me know exact way to achieve the same.
    Satish

    Hi Satish,
    I am not quiet sure of what exactly is the requirement. It appears that the user department will send the PR to the estimator and  and  then the estimator will estimate the cost and send back to the User. Is your question related to the process of estimation and the way it has to be communicated back to the user?
    Can you please repharse your question for better understanding...Sinces the question is not very clear.
    If you want to Go for Sales Pricing thru projects.and create quotations..then SD module is required.
    Warm regards,
    Srinivas Potluri
    Edited by: Potluri Srinivas on Jul 23, 2011 3:35 PM

  • Comparison between Opreative Project & Simulated version

    Dear Colleague,
    I have one query regarding simulation version, may I know how I will compare operatioe project with any simulation version by using SAP standard reports like CN41N. I already maintained version check box ticked in DB profile. As I know that we can easily compare Project version with operative project but do not know how to compare operative project with simulated version. Please just advice...
    Regards,
    Ashok Sangal

    Hi Ashok,
    Simulation versions are compared with operative versions in the same manner in which project versions are compared with operative project. The simulation versions for the project appears in the "Project version" selection. Select the required Simulation version to include it in the results.
    regards
    Sejo

  • How to create Sales Quotation from project through DP81

    Dear Guru's,
          How to create Sales Quotation(VA22) from project through DP81, what all the customization settings are required for this functionality; please explain me all the step those are required for this process.
    Regards,
    Sai

    Hi,
    You can use DP81 and DP82 to create Quotations .
    If you want to use DP81 then you need to link Sales Inquiry with Project by entering the WBS Element in Account Assignment Tab of Inquiry and also enter the DIP Profile in Sales B View.
    Else you can carry sales pricing without the creation of Inquiry.Enter the DIP Profile ,Dist Channel,Division in control data tab of project and also enter Sold to party in Partner tab.
    See SAP help for customisation of DIP Profile .
    Muzamil

  • Simulation version to Operative project

    Hi experts,
    I am unable to create an operative project structure from a simulation version using project builder.
    My req:
    I have sim version:  T-90001/ SIM001
    I wish to create operative project T-90001
    I can use CJV4 for transfer of project. But is it possible in CJ20N?
    Warm regards
    ramSiva

    Hi Ravi
    Thanks for your response
    Please look at the link http://help.sap.com/saphelp_erp60/helpdata/en/0b/ba853488601e33e10000009b38f83b/frameset.htm
    There is an illustration which depicts that,
    - Project P1234/version 0001 --> Project 1234 --> Project P1234/Version 0002 --> Project P1234
    As per this illustration, the project number remains same.
    As you said, the transaction CJ20N is not allowing me to transfer the simulation version to operative project.
    But, i am experiencing a dump error while trying to transfer simulation to operative in CVJ4.
    At the conclusion, i mean to say that irrespective of transaction code, this may be allowed.
    Please comment.
    warm regards
    ramSiva

  • I am trying out Final Cut Pro X and trying desperately to import a project from iMovie 11 (version 9.0.9). There is no export to FCPX in iMovie 11 nor is there import from iMovie in FCPX.

    Can someone please help me?
    I am trying out Final Cut Pro X on a 30 day trial. So far so good.
    I am now trying desperately to import a project from iMovie 11 (version 9.0.9) into FCPX.
    I have read multiple posts on this subject and they all recommend File/import/ from iMovie project in FCPX
    However there is NO such option under File/import in FCPX - nor is there an option to export to FCPX in iMovie 11
    Can anyone please enlighten me.

    The current version of FCPX does not work with that version of iMovie. You need version 10.0.3, which allows you to send a project to FCP.

  • How to hide the file name (the bizarre number assigned by the camera) when exporting an image version in aperture from an album. Pl understand I want to keep the file name in the project library version.

    how to hide the file name (the bizarre number assigned by the camera) when exporting an image version in aperture from an album. Pl understand I want to keep the file name in the project library version.

    Within Aperture you have Images, which are constructed on-the-fly from two files (the Master and the Version).  You get an image-format file _only_ when you export an Image.  You select the file name (usually a scheme) when you create an image-format file (that is, when you export).  Look under "Aperture→Presets→File Naming" for built-in Presets.  You can, of course, create your own or customize any provided.
    The Preset is applied to only the file newly created by your "export" command.  It is not applied to the Image in Aperture (unless you rename your Versions or your Masters).

  • Why can the old projects from an earlier version of elements transfer to 11

    I just purchased a premiere elements 10, and i tried to open a project from the older version and i says it can not open
    WHy?

    Depends on how old your old version is, I suppose... In any case, ask in the PRE forum and provide a lot more info...
    Mylenium

  • We need to copy planning..etc from simulation version 002 to version 000,

    Hi experts,
    Our simulation Version is 002 and Active Version is 000
    We need to copy planning..etc  from version 002 to version 000, how to do. Explain me  elaborate
    Regards,
    moon

    Hi Moon,
                   There are two things in Copy Version Management.
    1) Copy the master and transaction data from active to simulation version.
    Transaction - /SAPAPO/VERCOP in this you can not copy from Simulation to Active.
    2) Merge the Planning Versions.
    Transaction - /SAPAPO/VERMER in which you can copy the planning area keyfigures from simulation version to Active Version.
    Regards,
    Saurabh

  • Deleting a Simulation version from APO

    Hi Experts,
    We are planning to delete a Simulation Version from our APO system. Till now, we had jobs to copy Active Version to Simulation version. So, at present, the siluation version has all the data which the active version has- which basically means that there is a lot of data that has to be deleted, before we can delete the simulation version.
    Is there a best practice around 'Deletion of Sim Version'? If not, on the basis of your experience, can you please suggest how to go about it?
    Your inputs are highly appreciated.
    Thanks,
    Kunal

    Hi Kunal,
    Simulation versions are used in many business processes and depending upon your business requirements can be manipulated daily, weekly, monthly, etc.
    You can delete a simulation version manually in /SAPAPO/MVM, with transaction /SAPAPO/VERDELLD or program /SAPAPO/VERSION_DELETE_LC_DB.
    I don't think you have to delete any transactional data. Just don't use it on version 000.
    Best Regards,
    Mike

  • HT6012 While trying to update projects and events from a previous version of iMovie to iMovie '11, someone forced iMovie to quit.  Now when I start iMovie '11 and try to update, a message says no projects or events can be found?  Any suggestions?

    While trying to update projects and events from a previous version of iMovie to iMovie '11, someone forced iMovie to quit.  Now when I start iMovie '11 and try to update, a message says no projects or events can be found?  I know there are previous projects and events, and they definitely have not been updated because they do not show up in my iMovie'11 library, events, or projects.  Any suggestions?

    I also have Jolly's problem. I found the iMovie 9.0.9 folder and tried to launch the older version of iMove. It would not launch. I removed all of the iMovie preferences from the Preferences folder, removed iMove 10 from the applications folder, and restarted my Mac. iMove 9.0.9 still won't launch and I can't access my videos created with the older version of iMovie. Is there a way to uninstall iMovie 10 and reinstall iMovie 9.0.9?
    I am running Yosemitie on a  iMac.
    Paul

  • Can I transfer a project from the trial version of Final Cut Pro X to the Full version

    Can I transfer a project from the trial version of Final Cut Pro X to the Full version which I have now downloaded.

    The trial version is named "Final Cut Pro Trial" and the App Store version is called "Final Cut Pro".
    So, they can both be in the Applications folder at the same time, but only one can be open/launched at a time.
    If, for some reason, your trial is older (like version 10.0.4) that your newly purchased FCPX (should be 10.0.5), and you do not click Update to your events/Projects, they will NOT show in the bought version!
    Open the licensed FCPX and make sure it does update your things, in case it asks for it!

  • How to open project from an earlier version (RH x3) using RoboHelp 6.

    Hello everyone, I need your help. I have recently upgraded
    from RH x3 to RH V6. I have just completed the installation of RH6
    after spending long time with Adobe customer support as it took
    them long time to figure out how to provide me the unlocking key to
    install RH v6.
    BTW I have only installed RoboHelp 6 by itself. I did not
    install their Source Control because we already have Visual Source
    Safe which we have been using in our company.
    Also, since I had Adobe Reader 8 installed on my PC, I did
    not install Acrobat Element 7 either. As I suppose if Acrobat 7 or
    higher is installed RH v6 was not going to install Acrobat Element
    7.
    Well, now after I have installed RH v6, my first step is to
    find out how to open project from an earlier version (RH x3) using
    RoboHelp 6.
    RH x3 is installed on my old PC and I am working on my new PC
    where I have installed RH V6.
    Sorry, for providing you too many details, the purpose is
    only to give you a clear picture.
    Please, give me your feedback if I am doing everything
    correct and how should I open the project from an earlier version.
    Thanks

    Hi Peter,
    Thank you so much for the response. Actually, after I posted
    the question on Forum we had lost internet connection for some time
    and I just went ahead and tried it by myself.
    This is what I did – since we use MS Visual Source
    Safe, my all files were in the working folder of VSS in my c drive.
    I just clicked the Open tab/More Files in RoboHelp Starter and
    located the RoboHelp HTML Project File. It opened without any
    problem. Everything looks alright.
    Is there anything specific I should be checking to make sure
    if it is working fine in this version of RH. Because I did not
    create this project, somebody else did and I have never used this
    tool before this is the first time I will be using.
    I found your site pretty helpful though and it did have some
    information about Source Safe. I still have one question related to
    Visual Source Safe that Is RoboHelp v6 linked to VSS automatically
    and check the files out from it automatically whenever a project is
    opened or we have to manually set the link between the RH6 &
    VSS.
    In RH x3 whenever I would open a project it would prompt a
    message that in order to open this project the following files need
    to be writable, would you like to make them writable, selecting
    that option would checkout all the files from the VSS to make them
    writable. However, in RH V6 I opened an existing project and it
    opened without checking out the project files from VSS. Do you have
    any idea what’s happening?
    Ps: Do you recommend any book on RH 6 for starters or any
    other recommendation?
    Your help is always appreciated

Maybe you are looking for

  • Print preview vs print

    Hi Experts, I have a problem when trying to see the result of mijn sapscript or smartform via print preview. The result of the print preview is very different from the real print (if i print the same form). By sapscript i get the text : display text

  • Event for browse button for fileupload control

    I'm creating an application, where I need to check which file is choosen for the file-upload. Depending on the file upload, 2 other fields will be filled in because the filename is concerning a certain standard. Can I do this with javascript for exam

  • Fm Radio problems

    Hello , My name Is Egzon and I have a blackberry bold 9790 , it is perfect but I have a small problem . My problem is that my BlackBerry Bold 9790 does not have Fm Radio , I Need to know if this is for all Blackberry bold's or is only my problem . I

  • GB legislative patch confusion

    We went live on HR and Payroll in March (11.5.10.2), so of course I then had to look at legislative patches. Having found note 145837.1, I though this was not too bad, but I am now getting confused. Just wondered if anyone else has gone through the f

  • XI3.1 stop start input/output

    windows clustered BOE XI 3.1 environment.. now that services run under the SIA.. how can I stop and start input and output from dos command.  I need this because I have a .bat file that stops these services at 11 pm every night to backup for DR Thank