Raw Material Inspection before Goods Receipt

Hi Gurus,
              My Client wants to carry out Raw material Inspection before doing GRN.How it can be mapped in SAP.Please tell me the steps .
Thanks in advance,
Soumyendu

Dear,
Kindly activate QM view in material master and activate inspection type 02( Goods issue inspection) for the materials you required
Go to tcode mm02 >selcet the purchasing view and mark the quality inspecton check box.
You can inspect & clear the stock before issuing to either costcenter or production etc.
Regards,
R.Brahmankar

Similar Messages

  • Inspection before Goods receipt?

    Hi,
    Is there a good way of handling inspections before GR? We need to do some controls on the truck before we take the goods into the GR area. If the temperature is to high in the truck we will send the truck back right away.
    I have looked at the u201CSource inspectionu201D functionality but I'm not sure if that's a good long term solution. We don't have inbound deliveries today but I think that is something that will be implemented in the future.
    //Kristoffer

    Hi,
    May be you can try with two step GR i.e 103 and 105 movement
    When truck reaches your premises you do the MIGO with 103 movement.
    This will post goods in to GR Block stock.This is not a part of your inventory.
    You can test the material if u find OK then only stores does the GR with 105 movement to take into your factory stock or inventory.
    refer the link
    http://help.sap.com/saphelp_rc10/helpdata/en/a5/6334ef43a211d189410000e829fbbd/frameset.htm
    Regards,
    Nitin

  • SAP QM - Raw material inspection

    Hi,
    I am following these steps for raw material inspection.
    MM01 - Maintaining QM- view & assigned inspection setup
    QDV1 - Creation of sampling procedure
    QS21 - Creation of MIC's.
    QP01 - Creation of Inspection plan
    QA01 - Creation of Inspection lot.
    QA32 - Picking inspection lot, Results recording, Usage decision
    Please correct me if i missed any thing.
    Thanks & Regards
    Srinivas.L

    Hi,
    Inspection lot will generate automatically as per your master setting at the time of goods receipt.
    First go through the process. If you get any error then post the same.

  • Model Inspection & Model Good receipt

    Hi Gurus,
    Can someone explain to me what is the meaning of Model Inspection & Model Good receipt in simple terms ? In the inspection Type assignments and in Inspection lot creation do we necessarily have to assign it?
    Regards,
    Dhanuka

    Dear Dhanuka
    Model inspection is nothing but the approval process for material, vendor combination. Using the status profile in inforecord you can approve a material, vendor through a lab testing, pilot lot, bulk lot, etc.
    Model GR refers to the GR done for the same.
    Regards
    gajesh

  • MPN Material Field in Goods Receipt for Purchase Order

    Hi,
    I have created PO for MPN material "MFG-A" for IM material " 123". ( ECC 6.0)
    Already the material "123" is maintained with other MPN material "MFG-B"
    The have checked the " MPN Change" check box in the respective Mfg Part profile( IMG: OMPN) 
    While I am doing goods receipt, the MPN material field is in display mode.
    But in other system the field is in change mode.
    Default the system will show "MFG-A" as the MPN material is maintained in PO.
    But I need to  change the MPN materail at the time of GR.
    I would like to change the MPN material from "MFG-A" to "MFG-B" while doing GR time.
    kindly guide me what are the settings required to change MPN Material Field in Goods Receipt.
    Thanks in Advance,
    Kumar.

    Hi,
    I have maintained all the settings.
    But the issue was, I have not put the field "MPN material" (GOITEM-EMATN) as input field in field selection group in Inventory management.( it was in display mode )
    Once I have changed to input option, I can able to change the MPN material while GR.
    Regards,
    Kumar

  • System is allowing to do invoice verification before goods receipt.

    Dear Friends,
                         I need your help in following scenario, as my system is allowing to do invoice verification before goods receipt.
    To test these scenario.I have created one PO.  For this PO I done goods receipt. I done invoice verification by putting invoice date as past date, posting date system date means current date. I want to stop this as system is allowing invoicing verification to be done before goods receipt.
    Also, I tried after un-ticking GR based IV.
    Please suggest me the solution how to stop this. Please help this is urgent.
    With Best Regards,
    Rajesh

    Hi Rajesh,
    A)
    In goods-receipt-based (GR-based) invoice verification, the invoice relates not to the purchase order, but to individual deliveries. That is to say, the reference document for the invoice is not the PO but the delivery note or the goods receipt document.
    Whether you use this approach depends on your billing arrangement with the vendor. This method can be advantageous, for example, when you know the order will be fulfilled by means of many partial deliveries.
    Prerequisites
    Before you can use GR-based invoice verification, the following prerequisites must be satisfied:
    The indicator for GR-based invoice verification (GR-based IV) must be selected for the relevant item in the purchase order (item detail screen).
    <b>
    A goods receipt must occur before the invoice is entered in the system.</b>
    B) If you are carrying out invoice verification with reference to PO, system will not check for the GR. The entire PO amount can be posted.
    Hope this clarifies.
    Thanks,
    Viswanath

  • MRIO Before Goods receipt

    Hi, I am facing a problem, some of goods we need to pay to vendor before goods delivered to us, I know that we can do the MIRO before goods receipt. But I would like to know any influence if I use this approach? Thanks!

    Hi,
    You should ideally go for Down Payment option because how you will decide the quantities to be paid for..
    Because if you do MIRO before GR by removing GR based IV field then when the GR is done and again the remaining amount is to be paid, user posting invoice must adjust the quantities that will lead to inaccuracy in inventory valuation if forgotten.
    Regards,,
    Chintan Joshi

  • Full paid before goods receipt

    Hi all, I would like to know is it possible to make payment before goods receipt? Since we are issuing a PO to vendor, and the goods are partial delivery to us, but now we need to paid all to vendor first. The remaining goods will delivery to us later. Shoud I do the MIRO for all goods, then goods receipt later, is it a good solution. thanks!

    Hi Dear,
    When we are paying to vendor before receipt of goods it is called as advance payment. In sap it is called as down payment. This is because we have not booked any liability against vendor nor we have received goods still we are paying him in advance. So it is called a down payment.
    Regards

  • Update Material availability after goods receipt

    Hello Experts,
    Configured the system to send an email to MRP when a missing part in a Production order Received.
    Now the problem is, How to remove the Missing parts flag from the Pick list ( or How to update the Material availbilty at Goods receipt? ).
    Thanks for your help in advance.
    Govind.

    Mario,
    Thanks for your response.
    We have the ATP mass processing background job scheduled. But thats is running by period value. I am looking for something which updates after the GR Posted. ( Event based ) and should run only for the part no or Oder received.
    Do you have any suggesstions?
    Thanks
    Govnd.

  • Differentiation of raw material and finished goods from tax / valuation

    Hi,
    There are certain materials which are sometimes produced inhouse (considered as finished goods) and sometimes procured from outside (considered as raw material) i.e the same material can be raw material or finished goods depending on its use. Taxes and valuations are different depending on whether the material is RM (Raw material ) or FG (Finished goods) .  How can we differentiate if we intend to have the same material number. Do not intend to have split valuation.
    Thanks in advance .
    With regards,
    Mrinal

    You cannot differemntiate them. Only way to differentiate such materials is by either  by different codes, or by split valuation.

  • REg raw material inspection.

    Hai experts,
    In raw material inspection, we are getting raw material from vendor.we cant able to check 100%.So invoice will be cleared.
    We cant able to use immediately.
    If I use after two months,IT seems 5% will be rejected in producion line (raw material).
    How to retrun these material with respect to vendor.
    How the payment will react..
    Regards
    bhuvan

    hI
    we cant able to check 100%.So invoice will be cleared.
    We cant able to use immediately.
    As per my suggestion.
    Either You have design payment system( payment term in PO) like payment will not happen immediately at least 2 months.
    or
    Do 100 % inspection during Inspection lot creation & usage decision.Then do 122 mvt from UD screen.Also in Qm view use Control key as "Invoice block"
    I hope this suggestion will add some value.
    Regards'
    Sujit

  • Capture excise invoice before goods receipt

    Do we have any advantages of capturing excise invoice before goods receipt ?

    In terms of distribution of labor, yes. It gives more control to the excise personnel in your org rather than allow the control to the stores personnel who may or may not have sufficient knowlegde to handle these legal documents.

  • Enter Invoice before Goods Receipt

    Hi
    I have scenario:
    I receipt Invoice and I want to enter invoice to SAP system.
    After goods coming, I will receipt goods by MIGO.
    I want to enter MIGO reference to invoice above.
    Regards,

    Hi
    You can do it , but if you carry out Invoice before Goods receipt then how will have the reference of the GR during it?
    To carryout this , you have to remove the GR_bsd IV indicator in Invoice Tab of  Purchase order.
    You may have this indicator flowing to PO for the vendor from the Purchasing view of vendor mastr data
    You can carry out GRN later but can not have any reference to the it in the Invoice already processed.
    Regards

  • Need a Badi to look the good issue status for prod order before good receipt in MIGO

    Hi ,
    Need a Badi to look the good issue status for compoents for prod order before good receipt in MIGO.
    Example : There are 10 comps need to be issued to production order to make any assy but 6 comps were issued
    and remaining 4 comps are not yet issued.,in this situation if I try to do goods receipt for prod order through MIGO.,system should populate the warning
    message saying still goods issue are pending for prod order.
    Please advise .
    Thanks
    Prasad

    Hi Prasad,
    Before trying with a BAdI, have you tried to control this behaviour thru the Order confirmation parameters (OPK4)?
    Note that you can have a termination in case of having problems in the goods movements..
    Take a look of this and the SAP help:
    Termination of Confirmation if Incorrect Goods Movements
    Controls if the confirmation is terminated in the event of incorrect goods
    movements.
    Use
    This enables you to terminate the confirmation in the event of incorrect
    items, for example, to prevent postprocessing records.
    Dependencies
    The indicator is only evaluated if either no process control key or one
    process control key has been stored that enbles the goods movements to be posted
    in dialog AND for which the "provide error handling for goods movements"
    indicator is active. If there are incorrect goods movements, the system behaves
    as follows:
    A log is issued that gives information on the incorrect goods movements
    If these incorrect goods movements are determined by inventory management,
    then the option of correcting these errors is offered in the error handling
    If the correction is not successful, the confirmation is terminated
    Kind Regards,
    Mariano

  • Value of inventory after Goods Issue, before Goods Receipt for open order

    Dear Experts,
    Raw materials R72 and R82 are required to produce Semifinished Product S10.
    Semifinished product S10 is required to produce Fnished product F20
    On 10th August 2011, I created and release a Process Order for material S10 copying component materials R72 and R82.. Goods issue for component materials R72 and R82 were done for this process order using tcode MIGO (mvt type 261).
    It  takes four to five days to properly blend components R72 and R82 to obtain S10.
    It means Goods Receipt for this process order will be done on 14th or 15th August when this blending has been completed.
    Management suddenly issues a directive that stock take should be carried out in the plant on the 12th August 2011, and my process order is still open and cannot be closed ( or goods receipt cannot be done)  because blending is yet to be completed.
    Please how do I take care of this scenario/situation since Goods Issue has been done already?
    How will the Accountants see or get the correct value of inventory?

    When I run WIP Calculation for my Process Order, what will be the effect ? I mean what accouts are updated by WIP Calculation within a period (not across a perion or  at period end)?
    GI values issued to the Process order will come into WIP GL .( Since your client want to know the stock take should be carried out in the plant on the 12th August 2011- we are doing WIP calculation)
    > After  this WIP Calculation is run,  and say about 2days later, Goods Receipt for this process order is to be posted, what steps am I suppose to carry out?
    After GR Made, Run a WIP calculation again for the order so that The WIP from the GL account will get reduced ,now WIP= (GI value + confirmation ) -(GR Value),
    Check in DEV system before doing in PRD,
    On Month end, do the variance calculation and do the settlement