Re assignment of material from inspection plan group

Dear Experts,
I have an issue, we got a material which has multiple groups assigned to it.
How to remove the materials assignment from the inspection plan group?
Since the group contains more than 1000 line items, it is very laborious to search every line item and delete manually.
Is there any 1 shot way to remove the assignment?
Please help me out in this, because of multiple assignment, the lot gets into the status of CRTD.
Thanks in advance,
Anitha Pauline.

hi,
Use CWBQM.
Regards

Similar Messages

  • Assignning materials to a Inspection Plan by BAPI? QM

    Dear sappers,
    I a help with QP02. I need 2 Functions modules or BAPI's: 1st for assigning material-plant to an Inpection Plan and 2nd for cancelling the assignment of material-plant to the Inpection Plan automatically.
    I have checked all BAPI's in SE37, but more effort is needed.
    I know this is a real thread, so thanks for your help.
    Does anybody have any brilliant idea?
    Thanks a lot.

    Hi Gerard,
    I am looking for an automated way of assigning materials/plants to inspection plans and also for cancelling such assigments. I assume it is not far from the requirement you describe.
    Have you found a way to solve it ?
    Best regards,
    Thomas

  • CWBQM to remove MIC from Inspection plan

    We have requirement to remove few MIC from multiple inspection plan. SO I wanted to use CWBQM trx for that purpose.
    We maintain inspection plan with unique id of group and gp counter.
    Group 111 Counter 1
    Gp 111 Countr 2
    .Group 111 Counter 110 and many more.
    Q-1: From abouve list I don't want to update all inspection plan. I want to update for only few counter of each group. So how to enter these group and group counter combination in initial screen to do mass change.
    Q-2: We wanted to remove MIC1, MIC2, MIC5 from all inspection plan. Where to enter these MICs in intial screen so system pull only those MIC list of insp plan? these are complete copy model MIC.
    Q-3: As said earlier we wanted to remove MIC from inspection plan. Now after excuting CWBQM we are getting list of MIC. So do mass change I'm selecting MIC column and applicable row and clicking on Extra --> mass change. Then system is not giving me MIC in pop-up list. It gives me all other data including qnt and qualitative field of MIC, but we wanted to remove complete MIC from plan. how to do that?
    Please help.
    Edited by: Tom_Eric on Apr 15, 2011 5:39 AM

    I'm following these steps:
    CWBQM work area - Q_OPR_000000000010
    Entering inspection plan data in selection screen - Ctrl + F7
    Got MIC list
    Select Master Inspection chara. column
    Select row to delete particular MIC
    Menu > Extra > Mass change --> Here I got two pop-up screen
    One with name Mass change inspection char -- but this screen is empty - no field on this screen
    There is one more screen which says "select fields" - List of fields like, lower limit, upper limit, catalog type, selected set, info feild, inspection method, plan, insp qualification, long term indicator, item......but there is no field which says MIC
    If I select any field from second pop-up then it pull that field to mass change screen, but that I don't want to do. My purpose to remove MIC, not its field.
    Please let me know where I am wrong?

  • Mass assignment of materials to Inspection Plan

    All,
    Is there any standard transaction or BAPI/BADI to assign multiple materials viz 1000 plus to an Inspection plan.
    Thanks
    Anup

    You have two option to upload mass materials to inspection plan.
    Option1: Go to QP02 --> Material assignment screen. Here you can assign 14 materials at a time and do page down to assign next 14 materials. This is time consuming activity.
    Option2: With help of techinical person develop LSMW/ BADI which call QP02 to update material assignment in inspection plan.
    Please find few relavent descussion below, I hope it will help you take decisioon.
    [mass assigning of inspection plans]
    [Mass Assign Material to Inspection Plan]
    [Re: Mass material assignment  in Inspection Plan.]

  • How to progammatically get Inspection Characteristics from Inspection Plan

    How do I programmatically get Inspection Characteristics from an inspection plan? I am currently getting inspection characteristics from inspection lots via a QM-IDI RFC call (QIRF_SEND_REQUIREMENTS_GET_DAT2), but if the Inspection Characteristic is not in an inspection lot, I don't get it via the RFC call. What BAPI/RFC/IDOCS mechanism can I use from an external subsystem (VB.NET app) to get inspection characteristics (Spec Limits, Target, Operation, Activity) associated with a material in an inspection plan?
    Thanks,
    Ed

    The problem is the SAP system that my external subsystem (VB.NET application using QM-IDI) is interfacing with does not have inspection lots (and the customer is not willing to add inspection lots), so the QM-IDI RFC that I'm using (QIRF_SEND_REQUIREMENTS_GET_DAT2) does not return the inspection characteristics (spec limits, etc) that I require. My customer creates a reference (QP11) with inspection characteristics, then attaches the reference to a Material (QP01). When I try to get the inspection characteristics for the material via QIRF_SEND_REQUIREMENTS_GET_DAT2, I don't get the inspection characteristics because there is no inspection lot associated with the material and inspection characteristics.
    The design is for my external subsystem to do the Material Inspection Characteristic valuation, and then send the valuation results back to SAP. Is there a way to get Material Inspection Characteristics and then send the results back given the SAP setup I described above?
    Thanks,
    Ed

  • CoA results from batch, specs from inspection plan

    Hi there,
    I've a problem with my certificate of analysis (coa). I want to do the following. I perform inspections on my semi finished. With the certificate profile i can print these results on the coa for a finished product. I select the results origin from production chain. But i now want to print the specifications that are present in the inspection plan for the semi finished. But SAP only allows inspection spec origin 03 here.
    Is there a possible way to print results for semi finished products on the report of a finished product. For the result it doesn't matter if it comes from QM or batch classification. But the specifications are only stored in the inspection plans.
    Thanks.

    I want to print the result and spec from MIC 50005 which is in my inspection plan for a raw material.
    In my profile i've the follwing
    MIC 50005
    Result origin 03 inspection/ batch from production chain
    Insp spec origin 01 ins. spec from QM.
    At the materials button. In the first tabel Data origin fro characs from insp i mention the material number from the raw material including the inspection type.
    Still nothing is printed while there was an inspection lot for the batch of the raw material...

  • Create PR from Inspection Plan

    Dear Gurus,
    I have a inpection plan for Inspection type 01 with several operation.
    10 Visual Inspection
    20 Microstructure Inspection
    30 Hardness Inspection
    Operation 10 and 30 can do by Internal QC Dept. but Op.20 cannot do by Internal QC Dept.
    So we must send our sample to third party (vendor) to do Microstructure Inspection.
    I already create inspection lot automatically when GR from PO
    How to create PR automatically when we GR.
    Regards,
    Akbar
    Edited by: Arsyad Akbar on Mar 6, 2012 4:13 AM

    You can not create a purchase req from an inspection plan or inspection lot.
    You can do subcontracting order from the production side. 
    If you are simply sending out samples to an outside lab, most places do not drive the process of creating a purchase order on an inspection lot by inspection lot basis.
    I don't think you'll be able to do what I think you want to do.
    The only way I think you might be able to capture this might be to create a Quality notiification against the inspectoin lot.  From the notification you can maybe raise the purchase order.  But I have never tried that so I can't give you much guidance on that.
    But I don't see that as being an automated process driven by the inspection plan.
    FF

  • Remove mass MIC from inspection plan?

    How can we remove mass MICs from multiple inspection plan?
    These are complete copy model MICs.
    Can we use CWBQM? How?
    Edited by: Tom_Eric on Apr 15, 2011 5:38 AM

    I think this is same question with your another thread.
    You can remove mass MIC at transaction CWBQM.
    Regards
    Luke

  • QM_MATERIAL DELETION FROM INSPECTION PLAN

    QM Experts,
    Is there any transaction code by which we can delete the selected materials from the task list of type Q?
    For example in a task list group XYX with group counter 1, there are 1000 materials assigned. Now I want to delete say 400 out of it.
    Whether QSR6 will serve the purpose? How? what precautions need to be taken while executing QSR6?
    Anand Rao

    Hi Anand,
    Do you want to delete it w/o keeping a track of it in any table you can use this transaction.It will delete it from the table level itself.
    If you are Okay to keep a track of it in table ( Del. Id - X), you can go for a LSMW program to do so.
    Please clarify how do you want to do it ?
    Thanks,
    RAVI.

  • QM-Assign inspection plan to a variant of material (classification view)

    Hello,
    Inspection plans are commonly assigned to materials.
    In my case, I would like to manage, in <b>Classification view</b> (MM01), a new characteristics named "Variant" that could have 2 or more values, depending on which variant I order to my supplier.
    <b>But is it possible to assign an inspection plan at this sub-level ?</b> In QP01 the only possibility I see is assigning a material to the inspection plan. Can I customize something, or does it exist a trip to manager another level of assignment ?
    Thanks a lot for your help !
    Emilie

    Hi Emilie,
    Now I understood your requirement. But I would like to know the exact purpose of this requirement so that I can try to give you correct solution.
    I will consider your example:
    Material : 123
    Classification: Inspection
    Characteristics 1: Variant 1 for Inspection 1
    Characteristics 2: Variant 2 for Inspection 2
    Selection of inspection plan takes place during the creation of inspection lot. So now you have to link this material/classifcation/inspection plan combination at the time of inspection lot creation. I doubt whether this can be done using one user exit.
    The user exits are
    EXIT_SAPLCZCL_001
    EXIT_SAPLCZDI_001
    EXIT_SAPLCZDI_002
    Please let me know whether it helps.
    WR,
    Sanjeev
    Message was edited by: Sanjeev
    Selection of inspection plan takes place during the creation of inspection plan
    changed as
    Selection of inspection plan takes place during the creation of inspection lot
            Sanjeev

  • Inspection plan has been deleted- GR from production

    Hi,
    We are doing a goods receipt inspection from production - origin 04.
    The inspection plan group counter that was assigned to the inspection lot has been deleted.
    is there a way to assign another valid inspection plan group counter to the inspection lot so that we can do GR with 04 origin.
    Thanks in advance,
    Manohar

    Hi
    is there a way to assign another valid inspection plan group counter to the inspection lot so that we can do GR with 04 origin.
    Even if the Inspection plan is deleted...you can create a back dated inspection plan with another group counter.system automatically propose next group counter.
    Now lets say that your lot is already created & you want to assign the new inspection plan..
    then go to QA02
    click on reset sample
    save.
    now again go to QA02--->Inspection specification  >click on Inspection specification>click on sample.
    save.
    check the status as REL for inspection lot.
    Now take UD
    I hope you understood
    Regards
    Sujit

  • Assigning a different inspection plan to an inspection lot

    Hi,
    I have a situation where the incorrect inspection plan is assigned to an inspection lot. Is there any mechanism to assign a different inspection plan to an inspection lot i.e. without having to reverse a goods receipt.
    Regards,

    >
    Shyamal Joshi wrote:
    > Hi Kaushal,
    >
    > There are more than one reason for this error. Check the followings.
    >
    > - The key date for inspection lot should be later than the key date for the inspection plan, later then the date when you assigned the material to the plan.
    > - The usage of lot and inspection plan should be same.
    > - The status of inspection plan must be released.
    >
    > Regards,
    > Shyamal
    Why are you not checking these things I am sure the reason would be there only. If dont wana check it is your wish. Any ways best of luck

  • Difference between Material Specs and Inspection Plan

    Hi ALL,
    Whats the difference between Material Specifications and Inspection plan...?...Why Material Specification is required in QM...?
    Thanks & Regards,
    Ameya K.

    Hi Ameya,
                    The first thing is that material spec is the client level data in QM where as Inspection plan is the plant level.
    <u><b>
    Case 1:</b></u>    Suppose that there is an attribute Viscosity whivh needs to be checked whose UCL & LCL is 10 to 15. But in one plant where some highy precise requirement is there ...... then in that case we want that for that plant for the material viscocity should be 5 to 7 . In that case the requirement of the inspection plans comes in to picture .
    <b><u>Case 2 :</u></b>    The material got one extra attribute needs to be checked for some plant .... in that case we need to maintain inspection plan for that material with both Insp with material spec &   insp with inspection plan need to be checked  so that during the result recording apart from the attributes in the material spec this extra attribute gets populated from inspection plan
    Note : Apart from this as in material spec the data is maintained in the client level the load in the database will be compartively less  as there will not be any duplication of data which will be there in case of plant level data for the same material ..........
    I hope this will add some info apart from what the gurus has suggested above .....
    Please reward points if helpful.....
    Thanks & Regrads
    Kaushik Choudhury

  • Inspection plan Vs Material specification

    What is the difference between this and their limitation ,,when we have to use Inspection plan and when for the Material specification ?..Any detailed explanation   please
    Thanks for the help

    Inspection plan and when for the Material specification
    Inspection plan is plant specific material & plant combination.Means if same material is used in other plant you can not have Inspection plan of other plant used.
    Whereas when you hava material specs then it is not plant specific.Nce created it can be used for any plant.
    This can be used when your specifications are not plant depeendent.
    Explore on sdn you will get more explainations..........
    Inspection plan Vs Material specification
    Material specification and Inspection plan - Task list usage
    Inspection plan and material specification

  • Error while creating the Inspection plan by T.C QP01

    Hello Friends,
    In QP01, When i am trying to create a inspection plan system throwing the error message "The inspection plan identifier exists already. Enter another."
    Message no. QP054
    But in QP02, When i checked  for that material, Plant, Group Number, Group counter, Usage, Status, i didn't find the entry over there.
    Actually my requirement is to create a inspection plan for a material and plant combination with speicfic Usage as 61(customer requirement and status 4) but when i am trying to create that system throwing the error message explained above.
    Thanks and Regards,
    Jitendra Chauhan.
    Edited by: jitendra chauhan on Jun 1, 2010 4:28 PM

    Hello Friends,
    Thanks for your valuable answers.
    I checked in table MAPL, for a particular material, Plant, Group Number and Group Counter, there is no entry.
    Where as in table PLKO, for a particular Group Number and Group Counter, entry is there. Actually this Inspection Plan Group Number and Group Counter is assigned to multiple materials through Material Assignment. If i delete the entry for this in table PLKO, than for all rest of the materials also entry will be deleted.
    Hence how to resolve this?
    Actually for other material number, same plant, same group number and same group counter, entry exist. So can i simply go in the inspection plan of other material,same plant,same group number,same group counter and than inside the material assignment to assign the required  material code, plant and the group counter number?
    Looking ahead for valuable inputs from the genius.
    Thanks and Regards,
    Jitendra
    Edited by: jitendra chauhan on Jun 2, 2010 8:09 AM

Maybe you are looking for

  • Finding Headers

    Hi All, I have an issue where i need to change the header name of the fields. I cannot find the header names such as planned start time, planned end time, planned group. But when i execute the program it appears. Kindly help me find the same in the b

  • HTTPS not appearing in SMICM ??

    Hi All,        I need to activate the HTTPS in SMICM. I have already got the cryptography installed, and created few new parameters in the instance profile for the SSL activation.       after i restared the system to get those parameters into effect.

  • Can I call an interface from java

    Dear All, Can I call an interface from java in ODI ? Best Regards Arc

  • U0421heck existence partner function on status

    Hello. I need that system could to check existence of partner in servicr document at the certain status. What should I do for this? Dmitry

  • N73 software update "The Phone model is not curren...

    I am trying to update my N73 using Nokia software updater version 1.3.20 EN , but after Searching for a connected phone and detecting it the finally trying to Identify it , this error appear "Unable to retrieve phone information , the phone model is