Re: BAPI_ROUTING_UPLOAD

Dear PP Experts
We are working with Product costing and Production planning modules and we get peculiar behaviour as mentioned below
We used the program BAPI_ROUTING_UPLOAD to put the routing in place.
After execution of the standard cost estimate we found that no process cost exists and we could see only the cost of materials.
Later when we delete the routing and create manually the routing data and then execute the standard cost estimate we get the desired results.
Can anyone let me know what could have gone wrong in the upload program and do we need to check any parameters.
Thanks and Regards
Subbu
+91 9910372277

Dear
Thanks for your helpful answer and the issue is resolved
Regards
Subbu