RE : BI APO Question Reg Data feeding from cube to Planning area.

Hi BW Experts,
iam working in an Implementation project for SCM in BW prcisely working with APO Bw..
For that I have taken historical data as a flat file and loaded it in to the external BW Infocube and its fine...
Second step I have created generate export datasource on topr of BW infocube and replicated in to Bw and used this export datasource as datasource for APO BW Infocube which is inbulit BW System from External Bw..
also I have created tranformations and data is loaded in the BW cube in APO system.Also Included Version charecterstics..
When I try to fed the APO Cube data to planning area Iam gettinga the following  warning itsnot an error:
1.Key figure copy: InfoCube - planning area (DP) 01.01.2010 to 31.12.2010-- Successful
*2.No data exists for the selection made (see long text*
  Diagnosis:Data could not be loaded from the Cube for the selection you made. Check whether the Cube actually contains data that is relevant for your selection.
For the second point I have time charecterstics filled in the infocube which Iam feding to a Planning area like 0CALMONTH,0CALWEEK,FiscVarnt,0CALMONTH
3.Characteristic assignment: No data copied --- Message
Can you please help me with your thoughts so that i wll try to corner the issue I will be highly obliged

Hi,
As I understood, you have loaded data from external BW cube to APO BW cube and now loading planning area from APO BW cube.
I hope your settings in /SAPAPO/TSCUBE transaction code would be correct and you have selected the correct planning version with correct cube.
Check if Data in APO BW cube is available for reporting or not and data is avilable for given selction (if any but I guess you are not giving any).
Thanks,
S

Similar Messages

  • How is data loaded from Infocube to Planning area - need technical info

    I would like to find out how data is loaded from cube to planning area ,
    I know that CUBE has tables, but how does that get loaded to planning area , where is the mapping from which I can compare
    data in CUBE and the same data that reaches planning area.
    Say for example I have below values in the infocube
    Prod1 --> Loc1 -
    > available provisioning qty
    AAA        AB90             100
    Then where do i check in the planning area tables ( are there any tables mapped) after running the TSINPUT program, i know it can be checked in the planning book , but i want to check in planning area tables if they exi

    Hi ,
    The data is loaded from infocube to planning area using update rules. The issue you have mentioned seems to be two requests are having data for the same CVCs in the cube.
    Example: For the same CVC, two requests avilable in the infocube. When you copy the data using TSCUBE transaction, whatever data avilable in the cube for the CVC gets copied into Planning Area.
    CVC1 - cube - Old Request - 100
    CVC1 - cube - Actual Request - 200
    CVC1 - Planning Area = 300 ( The value is supposed to be 200, but since the old request also contains data in the cube for the cvc, it gets copied as 300)
    Issue : There might two request contains data for the same code
    Solution : 1. Check the data in the cube using transaction LISTCUBE  2.  Delete old request and check the data agian. 3. If it matches with your requirement, run the TSCUBE again.
    Please let me know if you need additional information.
    Thanks,
    Jeysraj

  • Load from cube to planning area

    Hi,
    We are facing a problem in loading data from Cube to planning area, we need to distinguish between the Zero and the blank values in planning area when loading data from cube to planning area.
    Scenario is like this.
    For a CVC u2013A on day D I am having key figure value as blank and on D1 is Zero and on D2 is 2, I want the same to appear as my planning area data If I load this data to cube my day D value will appear as Zero  (but it was blank) and on D1 Zero and on D2 as 2 in cube.
    I am using Std T-code /SAPAPAO/TSCUBE to load data from cube to planning area, in std T-code we are having option of ignore Zero, if I use this it will also stops the actual zero value(which I need) on day D+1 to come in to planning area which I donu2019t want.
    I want my planning area data to be as blank on day D and Zero on D1 and 2 on D2 after loading data from cube to planning area..
    Can any one put some light and help me out from this issue.
    With regards,
    Sreerama

    Hi Seerama,
    I am not sure to understand completely the issue: do you have an issue in the cube or in the planning area?
    In order to differentiate a blank for a zero in the planning area, you need to set the flag "zero allowed" in the planning area settings. (in the tab keyfigure, click details, then for each key figure you can select or not the flag "zero allowed")
    When you load the data, you should indeed not flag "ignore zero value"
    If the issue you have is in your cube (between the file and the cube) then it is another matter...
    Kind Regards,
    Julien

  • Loading data from Cube to Planning area

    Hi,
             If I am loading data from a cube to a planning area using transaction TSCUBE,
    does the system load data into planning area for the combinations that exist in the cube or does it load for all CVCs?
    For example,
    I have my CVC as Plant, Material, Customer
    If there are 4 CVCs in the POS that were previously generated as
    Plant--Material--Customer
    01--M1--
    C1
    01--M2--
    C3
    01--M2--
    C2
    01--M4--
    C5
    If the cube has data like this:
    Plant--MaterialCustomer----Qty.
    01--M1C1--
    10
    01--M2C3--
    20
    01--M2C2--
    5
    (doesnot have the last combination), then if I use TSCUBE transaction to load data to Planning area from this cube,
    is the data loaded as
    Plant--MaterialCustomer----Qty.
    01--M1C1--
    10
    01--M2C3--
    20
    01--M2C2--
    5
    Only for the 3 combinations that exist in the cube and not load anything for the last one
    OR
    is the data loaded as
    Plant--MaterialCustomer----Qty.
    01--M1C1--
    10
    01--M2C3--
    20
    01--M2C2--
    5
    01--M4C5--
    0
    Load all 4 combinations and send 0 as the cube doesnot have this combination?
    Hope I am clear on this question.
    Thanks.

    Thanks a lot Vinod, Srinivas and Harish. The reason why I am asking you is that we have a scenario where we get this situation.
    We initially get data from R/3 to BW to APO like the below:
    Plant--MaterialCustomer----Qty.
    01--M1C1--
    10
    Later when the customer is changed or bought out by somebody C1 is changed to C2. Some times when the business doesnot know who the customer is initially they just put C1 as dummy and then after sometime replace it by C2. Then the new record coming in is as follows:
    Plant--MaterialCustomer----Qty.
    01--M1C2--
    10
    BW can identify changes in transaction data  but not in Master data. What I mean by this is when Qty. 10 changes from 10 to 20, the system can identify it in deltas.
    If the customer (master data) changes to C2 from C1, the system thinks it's a new record all together then if I use delta loads, it gets me the following:
    Plant--MaterialCustomer----Qty.
    01--M1C1--
    10
    01--M1C2--
    10
    If I am looking at Plant and Material Level, my data is doubled.
    So we are planning to do a full load that works like this:
    1. Initial data like the below:
    Plant--MaterialCustomer----Qty.
    01--M1C1--
    10
    The CVC is created and the planning area has Qty.10
    Then we delete the contents of cube and do a full load into the cube with changed customer
    Plant--MaterialCustomer----Qty.
    01--M1C2--
    10
    This time a new CVC is created. Then we have another 10 loaded into Planning area.
    If the system loads all CVCs, then the it would send
    Plant--MaterialCustomer----Qty.
    01--M1C1--
    0
    01--M1C1--
    10
    If the system loads only combinations in cube,
    then it loads
    Plant--MaterialCustomer----Qty.
    01--M1C2--
    10
    But the system already has another 10 for Customer C1 duplicating the values.
    We are trouble in the second case.
    We had to go fr this solution instead of realignment as our business has no way pf knowing that C1 was replaced by C2.
    Hope I am clear.

  • Loading data from cube to Planning Area - Error

    I have two cubes. one has history data and other ratios.
    the forecast is dis aggregated based on that ratios.
    first the ratio data is getting loaded and gets populated.
    when i try to load the history data, a error says, CVC not maintained.
    there are totally 6 Char used in this Config.
    MPOS is created using the ratio cube and has the same char as in history cube, additionally one more sub family.
    Can some one help me in this.??
    Thanks !!!

    hi
    char in hist cube           
    mkt fam                           
    mkt seg                           
    regn                                
    gobl                                
    cntry 
    Char in the MPOS(from Ratio cube)
    mkt fam                           
    mkt seg                           
    regn                                
    gobl                                
    cntry 
    sub family                           
    the main obj of not including it in hist cube, i forecast @ mktfam level n dis aggre to sub family.
    if i include the sub family also in hist cube, then i can forecast @ sub family itself..
    the whole dis agg. logic does not serve the purpose.
    On the Adjustment of Time series, will try it n revert n back.
    like can you please tell me how it affects the process???? or the logic behind doing this????
    Thanks!!!
    Edited by: Aswath ram on Sep 10, 2008 6:33 PM

  • Copy Data from Non CBF Planning Area to CBF Planning Area in APO DP

    Hi Experts,
    I am working in APO implementation in an automative client, here we have material type Vehi and configurable material.
    I have done my forecasting in Non CBF planning area . Now I want to copy Key figure of final conenses forecast which is in non - CBF planning area to a CBF planning area .
    Can anybody has worked on similar scenario or worked in copying data from a non - CBF planning area to CBF planning area.
    Looking for your valuable inputs
    Thanks and regards
    Kapil

    Hi Kapil!
    We have the same need mentioned by you "Copy Data from Non CBF Planning Area to CBF Planning Areau201C.
    We obtained the source data, but can not do to write the same in CBF area.
    You managed to make the recording of such data in CBF area? How did they do it?
    Thanks and regards.
    Clelidon

  • Error while copying data from infoprovider to planning area

    Hi,
    Error for COM routine using application program (return code 40,075)
    Message no. /SAPAPO/OM102
    Diagnosis
    An application program has called a COM routine. During the process, an error occurred.
    I got the above error while copying data from infoprovider to planning area using t code TSCUBE.
    How to resolve this?

    Hi,
    Is your issue resolved, If not please run MPOS consistency checks, Planning area consistency check and livecache consistency check.
    Below are the programs for the same.
    /SAPAPO/TS_lcm_cons_check
    /SAPAPO/TS_PSTRU_TOOL
    /SAPAPO/TS_PSTRU_CONS_CHECK
    Regards
    Kishore

  • Release of History from Info Cube to Planning Area

    Hi Experts,
    I am using program /SAPAPO/RTSINPUT_CUBE to load sales history data from Info Cube to Planning area. Most of the data gets loaded but for few CVCs we get following message: -
    549 combinationens of InfoCube are not contained in the BasisPlobStru
    While checking up these CVCs in transaction /SAPAPO/MC62 and Planning Book I can see that these CVC exist and data is also visible.
    Could anyone please help me out with the reason and what should be done to encounter this.
    Thanks in Advance.
    Thanks and Regards,
    Chandan

    hi Chandan,
    First of sincere apologies for not having read the query completely.
    regarding your query on 549 combinationens of InfoCube are not contained in the BasisPlobStru, as you have stated that the CVCs exist in the MPOS.
    But can you please check if the CVCs maintained in the MPOS are the exact CVCs that are mentioned in the messgae. For example, the message is for location product sales org Country. Can you check if the CVC exists for this combination for which the forecast is being loaded from the source? For example it is possible that data is being loaded for Loc1 Prod1 SalesOrg1 Country1, but the CVC exists for Loc1 Prod1 SalesOrg2 Country1, then such message appears.
    So can you check if the exact CVCs are exisitng in the MPOS as indicated in the messages?
    Rgds, Sandeep
    Sorry again for misreading on your query.

  • I need format for data in excel file load into info cube to planning area.

    Hi gurus,
    I need format for data in excel file load into info cube to planning area.
    can you send me what should i maintain header
    i have knowledge on like
    plant,location,customer,product,history qty,calander
    100,delhi,suresh,nokia,250,2011211
    if it is  right or wrong can u explain  and send me about excel file format.
    babu

    Hi Babu,
    The file format should be same as you want to upload. The sequence of File format should be same communication structure.
    Like,
    Initial columns with Characteristics (ex: plant,location,customer,product)
    date column (check for data format) (ex: calander)
    Last columsn with Key figures (history qty)
    Hope this helps.
    Regards,
    Nawanit

  • I have a question about data aqusition from PCI bus

    Hi.
    I am designing a PCI card.I wonder if I want to do some process in LabVIEW,such as power spectrum analyse, oscilloscope, do I have to transfer the data continuously from my card?
    Thank you.

    Simple answer - no.
    More complex answer - LabVIEW is just like any other programming
    language when it comes to data collection frequency.  The
    frequency (intermittent, continuous, timed, etc.) depends upon the
    analysis you are attempting.  To do power spectra or display
    waveforms, all you need is one set of data at a time.  The data
    does not have to be continuous.  There are classes of problems
    which require continuous data.  If you are trying to address them,
    you will need to have this mode of operation available.  Most NI
    input boards offer both modes - continuous and intermittent, with
    intermittent being the most used, by far.
    Note that with proper buffering, both modes end up being about the
    same.  Whether your buffer resides on the card (preferred, is more
    robust, data transfer timing is not so critical) or in the computer
    main RAM, the LabVIEW side of things will always take a single set of
    data at once.  Admittedly, this data set can be one point at a
    time, but you really don't want the overhead of that in LabVIEW (or any
    other higher level function - should be in your driver).
    This account is no longer active. Contact ShadesOfGray for current posts and information.

  • APO DP - loading from InfoCube to planning area

    I am using APO DP V5.
    I have the following situation:
    1. I am extracting sales history data at the end of each day from a connected ECC system into an InfoCube, using delta logic, so in the Cube I just have the new sales history transactions (despatches) for the day
    2. I am then loading data from the Cube to my DP planning area via transaction /SAPAPO/TSCUBE
    I assume I must have the 'add data' flag set for each key figure in this transaction, to ensure I see the consolidated sales history in the planning area.
    Is this the 'best practice' approach for regular loading of sales history? I assume it's better to have a 'delta' approach for the Cube, for improved performance.
    Thanks, Bob Austin

    Hi,
            Good questions!
    1. What does the 'period' really refer to? Is it referring to the date of a particular key figure? Or the 'date of data being added to Cube'?
    A: Both are same
    The date is generally the date in your cube like the calendar day, month etc. This date is again based on a time stamp in the format DDMMYYYYHHMMSS. The calendar day is part of this field as DDMMYYYY. Also the system recognizes the changes by the same time stamp. So, if a customer changes the qty 05/15 at 3.30 pm, then the time stamp is 15052007153000. The calendar day in your cube or your key figure date is 15052007 and the delta is recognized by the changes in time stamp, between last load at the current system time. So , you are talking about the same time field.
    Check in your system if this is the same case you got. let me know if not.
    2. Suppose original dispatch qty = 100 (two weeks ago), and 'today' the customer returns a qty of 60; how does system handle this - I would want this posted to the original date of two weeks ago.
    A: The data from your ECC system is generally brought to an ODS first. The reason is we overwrite the data there if there is any data that has the same key. If your key for the ODS is Customer and division. Then you overwrite the customer qty for that division whenever the value changes. If you need it by time, lets say per month, include it in the key. The system over writes the value for that month only. For next month, it's a new record.
    In your case, if the qty. is 100 2 weeks back and now it's 60, if the time stamp is not in key, the system overwrites it to 60 and you have only 60 when you load it to your ODS and thereby to your PA as it overwrites. Delete the delta in your ODS and it shows the same 100 again. Then load it to PA. This is not a good option. The alternative is to include time stamp like calweek in your ODS key and load it over to cube. That way you have two records.
    I hope I answered all your questions.  Please feel free to ask more. I would love to answer that way I can also brush things up that were unused.
    Thanks.

  • Issue with Data Extraction from OAGIS 9 User Area Tags ...

    We are working on displaying the data coming from OAGIS9 into Excel sheet. We created a custom Schema for the Excel sheet and are able to display all the data in OAGIS9 except for the ones in UserArea. We are facing issue in extracting data from tags present in UserArea of OAGIS 9 schema and transforming it into our Custom built schema.
    Can you please suggest us some way in which we extract data from userArea?
    Thanks in advance ~

    Here is the example with instructions, we have just done it and working
    1.You need to have the custom schema that is coming with in the <UserArea>/<any>
    For example this custom schema is like this one shown below and you are using this CutomerPartyMaster of OAGIS
    <?xml version="1.0" encoding="utf-8"?>
    <xs:schema xmlns="http://www.userarea.com/mdm/oagisextensions" elementFormDefault="qualified" targetNamespace="http://www.userarea.com/mdm/oagisextensions" xmlns:xs="http://www.w3.org/2001/XMLSchema">
    <xs:element name="Customer" type="CustomerType" />
    <xs:complexType name="CustomerType">
    <xs:sequence>
    <xs:element minOccurs="0" name="Gender" type="xs:string" />
    <xs:element minOccurs="0" name="DOB" type="xs:date" />
    <xs:element minOccurs="0" name="SSN" type="xs:string" />
    <xs:element minOccurs="0" name="PAN" type="xs:string" />
    </xs:sequence>
    </xs:complexType>
    </xs:schema>
    and the Input data snippet will be like this inside CustomerPartyMaster
    <tnsa:UserArea>
         <tnso:Customer>
              <tnso:Gender>string</tnso:Gender>
              <tnso:DOB>1980-10-13</tnso:DOB>
              <tnso:SSN>string</tnso:SSN>
              <tnso:PAN>string</tnso:PAN>
         </tnso:Customer>
    </tnsa:UserArea>
    where xmlns:tnsa="http://www.openapplications.org/oagis/9" and xmlns:tnso="http://www.userarea.com/mdm/oagisextensions"
    Lets assume your Target Schema is like this where only DOB is coming from userarea
    <CreateRequest>
    <record>
    <firstname></firstname>
    <lastname></lastname>
    <dob></dob>
    </record>
    </CreateRequest>
    2.declare the name space of incoming userarea custom schema in your xsl file like this
    xmlns:nsext="http://www.userarea.com/mdm/oagisextensions"
    3.here is xsl code that copies element from CustomerPartyMaster/UserArea
    <xsl:template match="/">
    <imp1:CreateRequest>
    <xsl:for-each select="/inp1:ESBProcessCustomerRequest/body/ns4:ProcessCustomerPartyMaster/ns4:DataArea/ns4:CustomerPartyMaster">
         <imp1:record>
    <xsl:for-each select="ns4:UserArea/nsext:Customer/nsext:DOB">
              <imp1:dob>
              <xsl:value-of select="."/>
              </imp1:dob>
         <imp1:record>
    </xsl:for-each>     
    where imp1 is target schema namespace
         ns4 is OAGIS standard namespace.
    *****************

  • Report data is from Cube or Aggregates ??

    Hello Friends,
    Can any one please tell.
    The data in the BW Report is comming from a cube where Aggregates are bulid on it. The data is loading into the cube daily and roll up of aggregates are done one month back, since a month roll up was not taking place.
    When i run report now which data i can see in the report only rollup data which is one month old (or) fresh updated data in the cube ??
    Please tell me in detail.
    Thanks in advance..
    Tony
    null

    HI tony,
    If request has not been rolled up, then it would not be available for reportin ...check roll up flag in manage of cube...
    So data is coming from aggregates, if your query can access aggregates( drilldown data is avail in aggregates),..otherwise from cube...
    But there would be data sync b/w cube and aggregates...
    Also you can check RSRT ( display aggregates found) to check if your quer is accessing aggregates or not.
    Let me knw if you hve more doubts
    Gaurav

  • After technical a upgrade no data available from cube for loading

    Hello,
    We are having a technical upgrade. From an ODS to cube, loading is ok. From cube to another cube is not working. The source cube contains data in tables and the export data source is extracting data in test mode. I have already activated the export data source and update rules without result. "No data availabe in the source". I'm out of ideas...please help.
    BR, Auli

    Auli,
    Did you load new data to the first Infocube after the upgrade?
    Did you check if there are any filters or conditions in your update rules? Maybe there's no data for any possible condition or filter you might be using in there.
    Regards,
    Luis

  • Question concerning data removal from external hard drive

    I have been backing up via Time Machine to a 500 Gig external hard drive. I will be adding a 1 TB external hard drive and switch the Time Machine backups to that unit. I want to then use the 500 Gig unit to store photos, music and video, to free up space on the iMac. I have found the tutorials/threads that explain how to move the photos and music. I have two questions.
    First, will moving video from iMovie work basically the same as moving the photos and/or music?
    Secondly, what is the proper way to remove the existing Time Machine data from the 500 gig unit, once I have the 1TB unit up and running and know that Time Machine is backing up to it?

    I can help with number two. There are two things you can do, one quickly, the second more securely.
    Both can be done with Disk Utility in the Apps/Utilities folder. Open DU with the HDD attached to your Mac and highlight the HDD in the left hand pane and choose Erase for the right hand pane. Press the Erase button. It should happen pretty fast, but because it is a big drive it may take a couple of minutes. But this does not really erase the data, and some recovery software could do a good job of getting a lot of you data back.
    Since you want to store media libraries on this drive perhaps a better way to condition the drive is to select a Security Option and write zeros to the drive. After this any bad sectors on the drive will be locked out and not used in the future. Because this is a big drive this could take a few hours.
    Dah•veed

Maybe you are looking for

  • Need API or interface table for manufacturer & mfr part

    We are developing integration that would push data to following base tables. 1.     mtl_item_categories 2.     mtl_manufacturers 3.     mtl_mfg_part_numbers We could find interface table for category but nothing for manufacturers and manufacturer par

  • Mail Package with XML attachment

    Hi Everybody, I am using Mail Package to implement dynamic mail. The email is sent successfully, the problem is that when I try to open my XML attachment and the error 'The page can not be displayed'  appears in my browser. I changed charset from ISO

  • SPA112 - problem with VLAN

    Hello, recently I bought few of SPA112 gateways, and I have two problems: 1. provisioning using xml file; device is not using new vlan setting (other settings such as dialplan, line number, user and passwd are working correctly), what I'm trying to a

  • Not getting advertised internet speed

    It's been about 2 weeks since this problem started happening and I can't fix it no matter what I do. I'm currently on the Blast Plus package which should give me 105 Mbps down and 10 Mbps up, but I'm getting no where near that anymore. I used to hit

  • Sorting a DMEE tree

    I have made a very simple DMEE tree to generate a flat file from program SAPFPAYM. I would like to sort the file by FPAYH-BNKL1 (Bank key) and FPAYH-ZPFAC (PO Box) (which is are not key fields). When the file is generated, the entries are not sorted.