Re: create material cost estimate with ck11n without

hi gurus,
i need to do create material cost estimate with ck11n without cost result but before i need to check the BOM with material component 11111, and also instruct me how to correct maintain BOM list to get the standard cost
if anybody do the same scenoria giveme your golden inputs
thanks in advance,
kumar.b

Hi,
As note 351835 explains, calculation needs an inforecord to calculate prices from purchasing. Prices from outline agreements are generally not taken into account. According to note 499699, the system may consider entries in the source but it will ignore entered agreements (before this correction, any source list entries with agreement were ignored).
Prices from agreements could only be considered either via a modification or by using the user exit for material valuation (COPCP005).
This unfortuntely is a restriction resulting as a side-effect from note 499699. As soon as an agreement is entered in the source list, the fixed indicator will not be considered anymore.
You therefore have two options to overcome this.
1) You create a second source list entry without an agreement; then the fix indicator will be reflected; report Z_CREATE_EORD from note  409960 could be used to do this automatically
2) You are using user-exit EXIT_SAPLMEQR_001 in order to 'overrule'   the standard search for source of supply (enhancement LMEQR001)
regards
Waman

Similar Messages

  • Material cost estimate with quantity structure (tcode: CK11N)

    Hey dear friends.
    I donu2019t know in which forum I should put my question above.
    In fact, Iu2019m new to SAP PM module.
    Iu2019m trying to create material cost estimate with quantity structure (tcode: CK11N) for a material u201CXu201D.
    This material is manufactured.
    While running the transaction CK11N, I got an error message.
    After analyzing this error message, Iu2019ve realised that somebody had assigned wrong activity types to cost centers which are linked to this material in tcode: CR03, tab: costing.
    So Iu2019ve changed and assigned the right activity types.
    Then, Iu2019ve tried to run the tcode CK11N again. But the system still brings the wrong activity types and seems to ignore the ones that Iu2019ve assignedu2026
    It seems like the old activity types still linked to the cost centers somewhere else than in tcode CR03u2026
    Any idea about what am I mising ?
    Thank's in advance.
    Bahia.

    Dear Bahia,
    If its rate routing means,i guess you must be working in REM scenario.
    So goto CA22,delete the existing operation and then assign the same work center in a new
    operation,check what activity types is it proposing in the rate routing,if its reflecting correctly means
    save the datas.
    Also goto KKF6N--->click the change mode icon and then calculator button to create a preliminary cost
    estimate and then save the datas.
    One of our forum friend has asked you to check the production order read PP master data once
    again,but understand there is no production order concept in REM scenario,only planned orders.
    Then come back with your queries.
    Regards
    Mangalraj.S
    Edited by: Mangalraj.S on Jun 17, 2009 12:05 PM

  • No calculation of base when creating material cost estimate

    Dear all,
    I am facing the following problem:
    I have created a costing sheet Z001. I have also created base Z001 to this costing sheet and also overhead Z401. Base is cost element 401100 and 415000. When I am creating material cost estimate in CK11N I only get overhead based on base 401100, not on 415000. What can that depend on?
    I am trying to creat the cost estimate for material 6004 in plant 1111. The material 6004 cost element 415000 consists of materials both in plant 1110 and 1111, could this be some problem? The material 6004 cost element 401100 only consists of material in plant 1111, so this is a difference.
    Very glad for any help!
    Best Regards,
    Åsa

    Hi
    1. Does the cost element 415000 appear in CK11N itemization or not? It must appear in the itemization, for the system to calculate overhead on it
    2. Create a cost element group including both these cost elements and specify the cost element group in your BASE
    3. If you are using Origin group also in the BASE, ensure that materials pertaining to both the cost elements have "origin group" assigned in their material masters
    Whether materials exist in both plant or not wont impact the situation
    BR,Ajay M

  • Error while creating material cost estimate

    Hello All
    I am creating material cost estimate of FG whose components are SF & ROH-2. While creating cost estimate system gives an error message which states: :
    *No cost element segment exists for 40103110 on 01.09.2009
    Message no. CK048
    Diagnosis
    The consumption account found by automatic account determination for material STD-PRICE-SF does not exist for the date 01.09.2009 specified.
    Procedure
    Check the cost element segment's validity period
    Check cost element
    Or, if you have authorization, create a cost element which did not exist previously.
    Create primary cost element*
    Please provide your valuable inputs regarding this error message. Looking forward to your inputs & feedback.
    Regards,
    J K Tharwani

    Dear Jitendra,
    Its Seem primary cost element you mentioned is not defined for 09 period.For this go to KA06,gIve that cost element number and the Valid from  date as 01.09.2009 and valid to date as 30.09.2009, press enter it will take u inside the T.C,feed the relevant data and save.
    Now again take the costing run.This time system should not throw the error.
    Check and Revert back.
    Thanks and Regards,
    Jitendra DIlip Chauhan.

  • Error  - Material cost estimate with quantity structure

    Hello Gurus!
    Can anyone please help with the following problem:
    I’m trying to do the material cost estimate with quantity structure, but the system is throwing back the message  " There is no exchange rate for exchange rate type P on 1.01.2008: CHF -> EUR". 
    This happens because I have a subcontratation in my routing in CHF, and in transaction OB08, and I don’t had defined that rate (type P CHF –EUR).
    I need to know if there is any solution to the system assumes other Type of Exchange Rate (the last real exchange rate that I have introduced in my system, not the planned!)
    Points will be assigned to the suitable answer.
    Thanks in advance.
    Mary Jane

    Hi Sridhar
    Thanks for your reply.
    In OKEQ for the version 0, I have the rate type M.
    I don't understand why the system throwing back the message  " There is no exchange rate for exchange rate type P on 1.01.2008: CHF -> EUR".!
    Do you know why?
    Thanks and regards
    Mary Jane

  • Material Cost Estimate with Quantity Structure (How to download)

    Is there a standard report or feature available in SAP to download the material cost estimate with quantity structure?
    Currently we have to print screen and it is very tedious and can't do analysis with those screenshots.
    Please advice.

    Hi,
    There is a standard report you can use - S_P99_41000111 - Analyze/Compare Material Cost Estimates .
    With this report, you can report the standard cost estimates for a range of materials.
    Good Luck!!!  Assign points if this was a useful input to you.
    Thanks and Regards,
    Bhuvaneswari.S

  • Material cost estimate with Quantiy structure

    Hello All,
    Can anyone please help in the following problem. When we do material cost estimate with quantiy structure, system is throwing message as "source of supply cannot be determined".
    Maximum points will be assigned to the suitable answer.
    Thanks in advance.
    Srinivas

    Hi, Srini,
    Please check in material master data whether this material is in-house produced or externally procured, which can be found in MRP view.
    Please also check your costing variant and valuation variant for material cost estination, I think possibly you chose stratey L FROM Purchasing Info Record. If not, ignor it.
    If it's externally procured, SAP logic is that firstly it will check the source list, then determine the quota arrangement and find proper vendor for the selected material. The error message is possibly caused by missing vendor or wrong quota reason. So please follow the SAP logic to check data one by one.
    Please check the following link on vendor determination in online help document.
    http://help.sap.com/saphelp_erp2005vp/helpdata/en/7e/cb938143a311d189ee0000e81ddfac/frameset.htm
    Please specify if you also used mixed costing for material.
    Good luck!

  • Material cost estimate with quantity structure and without quantity structu

    What is the difference between material cost estiame with quantity strucutre and without quantiry structure?

    For the quantity structure pl read the following link
    http://help.sap.com/erp2005_ehp_02/helpdata/en/7e/cb938143a311d189ee0000e81ddfac/frameset.htm
    For without quantity stucture
    http://help.sap.com/erp2005_ehp_02/helpdata/en/7e/cb938143a311d189ee0000e81ddfac/frameset.htm

  • Material cost estimate with quantity struchture : problem

    while running the costing transaction CK11N , the word u201Croutingu201D is not appearing under the explanation facilities.
    rate routing is already available
    what will be the reason and solution.

    Hi,
    There is a standard report you can use - S_P99_41000111 - Analyze/Compare Material Cost Estimates .
    With this report, you can report the standard cost estimates for a range of materials.
    Good Luck!!!  Assign points if this was a useful input to you.
    Thanks and Regards,
    Bhuvaneswari.S

  • Material Cost Estimate with different lot size.

    What happens if the material cost estimate is run twice using different lot sizes each time  (all other parameters unchanged) for the same period?
    Will the cost estimate run later overwrites the results from cost estimate run earlier (though the lot size is different)? What is the role of lot size in a material cost estimate?

    The costing lot size impacts your cost estimate if you have lot size independent costs (i.e. setup cost).  Those fixed costs are spread over the costing lot sizee to give you a cost per unit..  Larger costing lot sizes can also help you minimize rounding issues.
    You can only have one marked cost estimate in a given period.  However, you can create and save a cost estimate as many times as you want as long as you have not marked it for release.  When you save the estimate it will overwrite an existing estimate.  You also have the option of creating multiple estimates under different versions or with different costing variants.

  • CK11N- Material cost estimate with & without agreement

    Hi,
    I have one material say M1 which I procure from two vendors A1 & B1.
    I have maintained info record for A1 with Rs.150 & B1 with Rs 100.
    Also I have an agreement with vendor A1 with price Rs 150.
    Source list is maintained for these two vendors & I have maintained outline agreement no with vendor A1 & also made vendor A1 Fixed Vendor.
    Now I run T code CK11N, where system is picking price for M1 as 100.
    But when I remove agrrement no from source list for vendor A1, system picks Rs 150 in CK11N.
    What is the logic behind this? Note that in any case my vendor A1 is 'Fixed Vendor'.
    Kindly guide me on the same.
    Regards,
    Piyush

    Hi,
    As note 351835 explains, calculation needs an inforecord to calculate prices from purchasing. Prices from outline agreements are generally not taken into account. According to note 499699, the system may consider entries in the source but it will ignore entered agreements (before this correction, any source list entries with agreement were ignored).
    Prices from agreements could only be considered either via a modification or by using the user exit for material valuation (COPCP005).
    This unfortuntely is a restriction resulting as a side-effect from note 499699. As soon as an agreement is entered in the source list, the fixed indicator will not be considered anymore.
    You therefore have two options to overcome this.
    1) You create a second source list entry without an agreement; then the fix indicator will be reflected; report Z_CREATE_EORD from note  409960 could be used to do this automatically
    2) You are using user-exit EXIT_SAPLMEQR_001 in order to 'overrule'   the standard search for source of supply (enhancement LMEQR001)
    regards
    Waman

  • Material Cost Estimate with Qty Structure - Activity Cost

    Hi All
    While executing the Cost Roll up (CK11n) Im facing a peculiar problem . I have defined an activity for which the rates are also maintained in KP26 against the Basic UOM(eg for 1000 activity 10Rs is the variable price mentioned)  . When Im taking the min lot size say 1 for the costing run the quantity appearing against this activity is appearing in the lower UOM (taking actual gms but the value for this activity is appearing in rupees only calculating from activity price x this figure). This is making the whole activity cost on very higher side .whereas If I execute with the same factors but with big lotsize say 1000 the value for the activity is coming absolutely ok .
    Pls confirm me how to put a check on the value of activity or uom of activity to evaluate the standard costing with minimum lower size also
    Best Regards
    Manoj

    Im closing this thread

  • Material cost estimate and mateiral cost estimate with quantity structure

    Hi sap guys,
    What is the difference between material cost estimate and material cost estimate with quantity structure

    Hi
    Both are in one way the same.
    Material cost estimate can be calculated as
    1. Material with quantity structure
    2. Material without quantity structure
    You can get more insight into it at the following link
    http://help.sap.com/saphelp_47x200/helpdata/en/7e/cb938143a311d189ee0000e81ddfac/frameset.htm
    Regards,
    Suraj

  • Digits Of Significance/Rounding Issue-Cost Estimate With Quantity Structure

    I have an Excel based BOM which includes Material (Yield) Qty, plus a scrap factor. This adjusted yield is then multiplied by the Unit Price to get the Extended Amount. An example from my file is:
    Material 10-0766 = yield of 1.824 sq ft less 4% scrap 0.07 sq ft = adjusted yield 1.897 sq ft * 1.836 USD/sq ft = Ext. Amt of 3.483 USD.
    In SAP, I created a BOM via CS01 with this material as a line item, 1.824 as the qty, UOM is FT2 (sq ft) and I added a Assembly Scrap of 4% with the Net ID indicator checked. When I create a cost estimate via CK11N (in our SAP AFS 6.0 sandbox), the itemization for this material reads: qty of 1.897, total cost of 3.48 USD.
    The math all works, but the resultant USD amount in SAP is short by .003 USD. I realize that USD currency is configured to only 2 decimal places, and that is fine. But, I thought that the calculations that costing was doing was retaining all the digits of significance past the 2 decimal places being shown, rather than rounding off to 2 decimal places. There are 24 materials in this BOM, and the total delta between my Excel sheet total (17.647 USD) and my SAP estimate (17.63 USD) is 0.017 USD. If I look at each item, the cumulative difference is due to each line rounding off to 2 decimal places.
    The units of measure (via tcode CUNI) are all configured to show display 3 decimal places (field DECAN) and round to 5 decimal places (field ANDEC).
    Does anyone have any information/suggestions around the precision in my SAP cost estimate? Am I stuck with these differences, or is there something I can do differently to prevent them? I know I can increase digits of significance in Activity Price Calculation, but I can't find anything similar in Product Cost Planning. Any help would be greatly appreciated.

    Hi
    To achieve you have to run the costing run twice once normally.
    Secondly you create an alternate BOM 2 by having the same alternate BOM 1 and remove the 2 materials which you dont want.
    Execute the costing run, provide the details required in the Costing data screen, press enter, go to the Qty structure screen give the details of the Alternate BOM 2 in the BOM details and execute the costing run.
    Save the cost estimate, which would be have been costed without the values of two materials as you wanted by using the alternate BOM 2.
    Then use CK24, select the option "other prices" to release the cost estimate for the commercial price only by selecting the indicator of commercial price 3 only.
    Regards,
    Suraj

  • Material cost estimate using recursive BOM

    Hello everybody.
    I want create material cost estimate (CK11N) using a recipe with recursive BOM. When I execute the transaction CK11N the following message is display Costing of cycle 00001 does not converge
    Do you know what is missing?
    Thanks in advance.

    Dear,
    Message no CK740?
    Please do check the link below......
    http://help.sap.com/erp2005_ehp_03/helpdata/EN/f8/a3e333bf3d11d189900000e8214595/content.htm
    and OSS note : 858384
    Regards,