Re: Internal Order & Project system

Dear All,
Please can one give brief explanation of internal Order and Project system.
1) What is the major difference Internal Order and Project system.
why some companies use Internal Order
why some coompanies use Project system.
Thanks in advace
Venkat.

Dear Venkat,
Internal Order is Sub-module of controlling whereas Project System is entire module in SAP.
Internal Order will provide information related to cost posted to the order, budget, commitments etc. And in Project system module you can create various projects to analyze company's profitability.
Substitution between Internal Order and Project system is highly depends upon the size of the Project. Many companies may be using internal order instead of Project in order to trap the cost.
Project system will provide every minute information pertaining to the project. Whereas internal order will not be able dole out.
Companies in Real Estate can not substitute Internal Order with that of Project system. Project System module is both heart and brain for Real Estate industry. And companies in other Industries having small value and size of project can use internal order instead of Project system.
To conclude, Internal Order is narrow concept where Project System is an Ocean
Regards,
Chintan Joshi.

Similar Messages

  • Internal Order & Project systems

    Hi All,
    Why we using PS to manage a project if we can manage a project with the help of internal orders also,please explain all the differences in detail.
    Thanks
    Muzamil

    Hi Muzamil,
    I am not giving you any direct answers for this query, you can follow the link below for the differences as it elaborates in details.
    <u>http://help.sap.com/saphelp_47x200/helpdata/en/a9/ab7376414111d182b10000e829fbfe/frameset.htm
    http://help.sap.com/saphelp_47x200/helpdata/en/04/926eae46f311d189470000e829fbbd/frameset.htm</u>
    Regards
    Rehman Khan

  • Production order-Project system

    Hi
    How can planned order can be converted into production order in project system
    Regards
    Suresh

    Hi
    With manual selection the system lists all the valid task lists that exist for the material at the time of copying and that should be selected according to the selection ID. You can select the required routing from this list.
    Working Without a Routing
    When you work without a routing the system automatically generates an operation. It proceeds as follows:
       If default values have been maintained for the automatic generation of an operation the system uses these values to generate an operation automatically in the order.
       If no default values are specified in Customizing the system generates an operation with the control key 0001 and the operation number 0010.
    <b>If a routing must be selected but no routing can be selected then the system reacts with a termination message and you must carry out order creation again.</b>
    Further information please refer the link
    http://help.sap.com/saphelp_47x200/helpdata/en/b1/c04182439a11d189410000e829fbbd/frameset.htm
    Regards
    Ramakrishna

  • Plan data on Statistical Internal Order

    Dear gurus,
    Presently we have real internal orders for the projects but now we are diverting from real Internal Order to Statistical Internal Order. Before we use to plan data on the real internal order. My concern is by changing the IO to statistical, would it impact on the Plan data? How can we approach the Planning data in the statistical Internal Order?
    Also while creating Statistical Internal Order, the system does not allows to select Plan-Integrated Order field. What is the signficance and by not selecting this field, this does impact the plan data on the statistical IO
    Thank you in advance
    Regards

    Diverting to Statistical order,system will not allow you make settlement. if you need only for information purpose, then u can adopt the statiscal order.
    System will not allow to select statistical indicator & Indicator for Integrated Planning. you will only select one option. u can only select with real indicator
    by selecting the "Indicator for Integrated Planning"activity inputs planned are updated
    directly on the sending cost center if 'Integrated planning with Cost Center Accounting' is activated in the version. You can then also settle plan-integrated orders/projects to cost centers.which only possible with Real order
    I hope this will be helpful

  • Purchase order to Asset non imposed the Internal Order.

    I'm entering a purchase order of an asset tied to an internal order of investment. The order has a budget X. If I enter a purchase order with value greater than the amount budgeted in the internal order, the system allows me to create the request and not imposed the internal order. In the report S_ALR_87013019, the order has no value released.
    How can the system do not allow the purchase of assets with values greater than estimated and how to make that encumbers the purchase order and appear in the report S_ALR_87013019?
    This only happens in the purchases of assets!
    Thanks in advanced!
    GLMacedo

    My friend, see my answer to witch point.
    1. Your Asset APC account should be Category 90 (Statistical) Cost element
    The Internal Order is Statistical (I see in KO03). Should I verify in another place?
    2. your Internal Order must be of category "Investment" and not "Overhead"
    OK
    3. Assign this Internal order in your Asset Master in the field "Investment Order"and not "Internal Order"....
    OK
    if Investment Order is not visible in Asset Master, change your screen layout of the asset and plug it in (IMG > AA > Master Data > Screen layouts)
    4. Do settings in T code ACSET - Allow EAUFN for Trn Type = *, Acct Assign Type = APC Postings, and check the Acct Assgn check box
    I don´t know how can I do this. How Can I Do?
    Allow commitment management in your contr area OKKP and in your Internal order type (KOT2_OPA)
    My type Order (investment) in KOT2_OPA is OK (commitment management was allowed). But in OKKP it is not! It is a critical setting. Should I flag this field?
    6. Feield Status Group of Asset must allow CO/PP Order in OBC4
    OK
    Thank you very much!

  • Concurrent manager encountered an error while running sql*plus for your concurrent request create internal order

    Hi
    We have a big problem, We can't create internal orders, when I run the CREATE INTERNAL ORDER, it finish with ERROR:
    Concurrent Manager encountered an error while running SQL*Plus for your concurrent request 134980682.
    Review your concurrent request log and/or report output file for more detailed information.
    this is the log:
    +---------------------------------------------------------------------------+
    Purchasing: Version : 12.0.0
    Copyright (c) 1979, 1999, Oracle Corporation. All rights reserved.
    POCISO module: Create Internal Orders
    +---------------------------------------------------------------------------+
    Current system time is 26-JUL-2013 09:21:09
    +---------------------------------------------------------------------------+
    +-----------------------------
    | Starting concurrent program execution...
    +-----------------------------
    +---------------------------------------------------------------------------+
    Start of log messages from FND_FILE
    +---------------------------------------------------------------------------+
    Begin create internal sales order
    Updating Req Headers
    14 Reqs selected for processing
    Top of Fetch Loop
    Source Operating Unit: 82
    Selecting Currency Code
    Currency Code : MXP
    Selecting Order Type
    Order Type ID:1001
    Selecting Price List from Order Type
    Deliver To Location Id: 196
    Inserting Header : 3908784
    Getting the customer id
    Getting the customer id: 15334
    Unhandled Exception : ORA-01403: no data found
    +---------------------------------------------------------------------------+
    End of log messages from FND_FILE
    +---------------------------------------------------------------------------+
    Concurrent Manager encountered an error while running SQL*Plus for your concurrent request 134980682.
    Review your concurrent request log and/or report output file for more detailed information.
    +---------------------------------------------------------------------------+
    Executing request completion options...
    Output file size:
    78
    Output is not being printed because:
    The print option has been disabled for this report.
    Finished executing request completion options.
    +---------------------------------------------------------------------------+
    Concurrent request completed
    Current system time is 26-JUL-2013 09:21:14
    +---------------------------------------------------------------------------+
    Some suggestion for resolve it??
    Thanks & Regards.

    In the document 294932.1 Section 4 there are no pre-installation patches or update for OS RedHat LinuxAS4.
    When I type echo $LD_ASSUME_KERNEL it doesn't display any value so do I need to set the LD_Assume_Kernal value manually.
    If yes, please let me know the path and command to set the kernel value.
    Thanks
    Amith

  • Error message display for PO creation with reference to internal orders

    Sir,
    While creating PO with Tcode ME21N (item category I) with reference to ' Internal Order with Funds provided (Tcode KO12), system displaying error message  when Budget is exceeded.
    But when Funds provision is not mentioned (Funds value is initial in KO12) , error message is not being given by the system during Po creation with ME21N.
    Where should I configure in img(Tcode SPRO) , so that system will throw error mesage while creating PO without Budget Provision (Funds not mentioned ) in Internal Orders.
    Regards,
    Srinivasa Murthy

    Hi Anupam,
    The error message display as follows. (when the PO Price exceeds the Planned Funds kept for internal order)
    This error comes during PO creation Process and PO can not be saved. This error message display is correct.
    Item 001 Order 600643 budget exceeded
    Message no. BP604
    Diagnosis
    In document item 001 Order 600643, budget  for fiscal year 2009 was exceeded by 99,960,000.00 INR.
    But  my question is 'when funds have not at all been mentioned for the internal order' then system has to throw the same error as mentioned above. But it is not happening. System is allowing the PO to save which is not correct.
    Regards,
    Srinivasa Murthy

  • PO & Internal order report

    Dear all,
    I have a requirement related to account asiigned(F) PO.I want internal order wise po status or vice-versa.If there is any standard T-code besides ME2N is there,pls help me.
    Regards,
    DD

    U can also refer ME2K
    And In SAP Menu > Accounting  > Controlling  > Internal Orders  > Information System
    under this path U will get all the postings, actual/plan analysis, etc...

  • Asset under Construction through Internal order- Functional deficit?

    Hi Experts,
    I have created an internal order and all the expenses incurred for the asst under construction are being booked at this internal order.
    While settling the internal order the system always picks up the month end date as the settlement date and hence the balance of internal Order is getting transferred to AUC on month end date (say31.07.2007).
    So,
    The date of transfer of balance from internal order to AUC is month end date that is 31.07.2007.
    But in Actuality the AUC got complited before month end (say 15..07.2007) and the Asset was put to use on 15.07.2007.
    Now the system is not allowing to settle the AUC to Main Asset as on 15.07.2007 as the AUC was not existence on that date. <b>Error:</b> Posting not possible (Value date earlier than capitalization date).
    I am able to transfer the balance in AUC to Main Assets as on 31.07.2007 but in this case my client is loosing the depreciation element on this asset from 15.07.2007 to 30.07.2007. Is this the functional deficit in SAP? Is there any way through which depreciation can be availed from 15.07.2007?
    Thanks & Regards,
    Bijay kumar Deo

    You can settle the AUC value in one period and posting can be made in another period. in the same you can give the different asset value date in KO88 screen. The only limitation is this possible only if the fiscal year is same.
    Give the asset value date as 15.07.2007 in KO88
    Hope this will work
    Radha

  • Clearig buffer from internal order number

    Hello Experts
    When I create internal orders, the system is generating number with a gap of 20.  The last number used is ***81.  I want to clear the buffer (transaction SNRO- Object - AUFTRAG?).  I would like to get next number generated should be ***61. I can delete ***81 order if necessary.
    Please advise the process so as to get number **61 for next internal order.
    Thanks in advance
    Vijay

    Hi,
       Further to the answer given by Ravi regarding note 333356 to fix your problem please note that the object 'AUFTRAG' can be used for "Order number, production, process, maintenance order,network number". For details, please check note 62077
    62077  Info: Internal number assignment is not continuous
    regards
    Waman

  • Profit Center Reports / drill down to assigned internal orders

    Hello guys,
    our company does project business. Our project landscape has been implemented in SAP using a profit-center-structure for reporting purpose and internal orders for every project.
    The internal orders (projects) are assigned to a profit center belonging to the conducting profit-center-group (responsible department).
    Question 1:
    Further development of Profit CenterReport S_ALR_87013340 allowing for a drill down from the profit centers to the actual projects that have been assigned to that profit centers.
    Currently (standard report) each profit center can only be watched in a cumulated way. Since many projects can be assigned to one profit center a drill down to the actual project is required.
    Question 2:
    Currently the desired report Profit Center Report S_ALR_87013340 shows the balance. It is desired to see only the cost incurred on the projects, not the settlement. The report should only show pre-selected cost elements. How can we exclude certain cost elements?
    Could you please give us some hints how to handle our issues?
    Regards

    Hi,
    Question 2:
    Currently the desired report Profit Center Report S_ALR_87013340 shows the balance. It is desired to see only the cost incurred on the projects, not the settlement. The report should only show pre-selected cost elements. How can we exclude certain cost elements?
    A1: you can created cost elements(account group) with selected cost elements and use same group in report.
    Or
    A2:enter only selected cost elements in report P&L account group in multiple selection.
    Thanks,
    Rau

  • Internal Order Cannot Be Closed

    Upon attempting to close an internal order the system returns "There is still a purchase requisition commitment for ORD M4171B5D58." However, when I search for purchase requisitions tied to this order, the system says there are none. The purchase requisition has most likely been archived off.
    How can I go about closing this internal order?
    Thanks - points will be rewarded.

    Dear ,
    You can take back the WIP  by canceling Production Order Confirmation (CO11N/CO12)  and also reversing the GI -261 in MIGO .
    So you need to check the folloiwng steps :
    1.Ask your MM person to check wether MM period are opened or not in MMPV
    2.Ask your FI persion to check wther FI period is opend or not
    3.Perfom CO13-Cancel Confriamtion of Production order .You can check in COHV/CO16N/CO13
    3.You can reverse the GI through MIGO-262 or MBST
    Check the Order status after reversing confirmation as well as GI  and check the WIP stsatus of the Order -Costing-Select Costing trend or WIP .
    Try and come back
    Regards
    JH

  • Internal Order Budget Exceeded when creating a PO

    Dear all,
    When we create a PO against an Internal Order, the system displays the message "Item 001 - order X budget exceeded". But checking that order we can see budget available.
    Do you guys have idea the reason of it?
    Many thanks,
    Amanda

    Hi Sreenivas,
    As we are planning to send budget exceed message to responsible person in the internal order, however, from the configuration, it is find that the warning message of budget exceed will send to the budget manager only, and the definition of budget manager is by internal order type and not by individual internal order.
    Please advise how can I send the warning message to the person responsible for the internal order instead of send to the budget manager for the internal order type.
    Thanks,
    Nina

  • 关于CRM service process 和 R/3的internal order.

    这是我最近做的一个问题,觉得比较有意思,拿来和大家分享一下啊。
    客户做了一个service order,有两个items.当他保存这个order的时候,R/3那边就会生成一个internal order,(这个是和
    co 相连的,也就是co那边要做cost analyse) 然后,他又根据这个service order做了一个service confirmation,在完全copy service order的明细之后,又追加了一个新的费用或者spare item, 保存之后,他发现有产生了一个新的internal order,the system do not post to the internal order of the originating document.
    我跟开发确认过,这个是因为如果客户追加的明细是一个 'unplanned' item- by this I mean that there is no reference to another item, specifically a complaint item. In this case, the system creates a new internal order. This is standard bahaviour.
    The second internal order is created because the spare part is added
    manually and no reference exists to the predecessor document/item.
    If you clicked on the copy item in the follow-up then this would have a link to the pre-decessor document and
    only 1 internal order would be created.
    If you want to change this, you'll have to use the CRM_UPLOAD_CO BADI
    note 855906 is needed for the BADI to work correctly.
    In the method, you can ill the reference guid if it's empty, thus
    creating only 1 internal order.
    本来还想写中文,实在太慢了,改英语了,希望大家不要介意啊。
    这块是关于service, 大家一起学习啊。
    谢谢。
    昭杰

    Good article! Maybe I will encounter related issue,thanks.

  • Closing an internal order

    Hi All,
    The order has been settled and when we try to close this in KO02 we are getting the following error.
    " Still there is a purchase order commitment"
    can any one help me how purchase order linked to internal order and how to resolve this issue.
    regards
    prasad

    Hi,
    Do further analysis with the below mentioned reports to understand in detail.
    Path: Accounting -> CO> Internal orders-> Information systems -> Reports for Internal orders ->Plan/Actual comparisons -> Additional key figures>
    Accounting -> CO> Internal orders---> Information systems -
    > Reports for Internal orders ---> Line items -->
    Regards,
    Murali

Maybe you are looking for

  • "Big Bridge" does not launch with Mini Bridge

    When I open Photoshop and launch Mini-Bridge, it does not launch "big bridge."  The littel wheel turns around and a note says "waiting for Bridge CS5," but Bridge CS5 never opens.  The little wheel keeps turning around and keeps waiting and waiting. 

  • Why wont my itunes store open

    I sign in, but cant open itunes store. The progress bar at the top says accessing itunes, but only goes about half way and stops. I have uninstalled and reinstalled itunes 10 a couple of times.

  • Explore Logic Studio file created by the pros....

    ^ That's what Apple say on their Logic Studio web site: http://www.apple.com/logicstudio/ Quote: "Learn all the production tricks the pros used to create these hit singles. You can see how every track was crafted, from the original instrument, sample

  • How do I retrieve my lost data that was backed up on iTunes?

    My phone recently had a problem where it needed to be restored every few hours. So I backed up my data on itunes and just before my phone restored, it completely broke and only the itunes logo appeared on my phone. So I sent it to be fixed and when I

  • Is there a free(non-trial version) document reader...

    I have some document files I want to be able to read on my 5800xm. I just can't afford any of the ones for purchase. Is there any free document readers for this phone? Solved! Go to Solution.