Re -Reconcillation of subcontracting challan against "102" mov type mat doc

Dear All,
While we are doing the reconcilliation of the Material document (mov type-"102" ) against the subcontracting challan (ALREADY fully reconcilled against 101 material document, but not compeleted), then system is NOT allowing us to do the reconcillation, requirement is to reduce the qty assignment  in already reconcilled challan, as we have reversed the material document
1.) When we have assigned the 102 movement type to movement type group to 0001( Issue movement type group)
then system is giving an error message : 8I567-Challan not valid, Material doc. is valid for another scenario during J1IFQ.
2.) and when we are assigning the 102 movement type to movement type group 0002( Receipt movement type group) , then system gives error message : 8I574 -Material XXX is not assigned fully, short by YYY KG
Please suggest the right way of doing it.
Thanks & Regards
Nitin Chhabra

Hi
If a challan is reconciled it should not be opened again. That is illegal. You need to do subsequent adjustment if you want to alter your consumption in subcontract. If you do 102 and reverse your consumed material,You need to include 544 movement type in your movement type grouping then You need to create a new 45a challan.
Regards
Antony

Similar Messages

  • Reconcillation of subcontracting challan

    hi every body
    my problem is about reconcillation of subcontracting challan.
    let 10 kg material named A is to be manufatured by 16 kg of material B. NOW i created a sub contracting po ,541 tranfer posting, j1if01subcontracting challan, then i do good receipt fpr 10 kg A material and assign the subcontacting chhalan to the good receipt.now quality department reject 5 kg A MATERIAL FROM 10 KG A material and send 5 kg A material to the vendor with movement type 122. with this also 8 kg of material B is also returned with movement type 544 with stock provided to vendor o .
    now when we chack with MBLB 8 kg of material B is with subcontractor.now when we reconcile quantity with J1IFQ .
    it shows and give the warning massage that  8 KGof B MATERAIL is short.it does not allowed to save
    however 8 kg of material B is with subcontractor tehn it should be reconcilled with rest of 8 kg of B material. why it does not save. is this problem of patches. please give solution this is urgent requirement.points will be rewarded.

    I want to give it an attempt
    while reciving the mat A total 16KG of B is issued, so stock of B is reduced by 16 KG.
    Now you did 350 & 122 for rejection and dispatch of mat. A with 5 KG that means for Mat B 8 KG made, so we get 8 KG of B back ( which is in vendor place)
    but while doing reconcilation the stock of B is required which is shot by 8 KG. let teh cycle to complet means recive the repaired the material A then do reconcilation. system will not so this error.
    simutate in test once to check it now as it seems you r in hurry.
    Regards

  • PO Commitment Reversing after 102 Mov Type

    Dear All,
    Please suggest a wayout for the below issue.
    Issue:
       When we are reversing Goods Receipt with 102 Movement Type, system reversing the total commitment created at the time of PO
    Scanario:
    The illustrated Example will give the complete information about the scenario and issue which i am facing.
    Step1: Assignment of Budget
              Fund Center :      12345
              Commitment Item:   CITEM
              Budget Amount:     50000
    Note:   I've Used the Symbol " | " to differciate the Values as Space is not showing in the posted Message
    Step2:  Material PO Created with Special Procurement Type Q
       For Ex:   Material     |  Qty   |     PO Value |   Commitment Created (Budget Consumed in RS)
                       ABC        |   10    |       10000    |                    10000
    Step3: when i see the FMB_PT01 report after PO Creation.
            Budget  |   Bud-Pay  |    Invoice   |   Bud-INV    |       Open Item    |   Res Budget
            50000   |          0       |          0      |          0         |            10000    |      40000
    Step3:  Goods Received against the above PO is 10 Qty for which Rs.10000 which is showing as follows in FMB_PT01
           Budget  |   Bud-Pay  |   Invoice   |    Bud-INV     |   Open Item |   Res Budget
           50000   |         0        |      10000 |        10000    |            0      |        40000
    Step4:  If i reverse the above GR then system is deleting all the consumed amounts and showing as follows
           Budget  |   Bud-Pay  |   Invoice    |    Bud-INV    |     Open Item  |  Res Budget
           50000   |        0         |        0        |          0          |           0         |      50000
    As far as my knowledge, if i reverse the GR, system should only reset the Values under Invoice & Bud-Inv and reassign the value under Open Item, which is not happening in our scenario.
    I hope, you all understood the scenario & issue which i am trying explain.
    So, please suggest me wht went wrong and how to rectify that..
    Thanks in Advance to All.
    Edited by: RAJA TALLURI on Nov 2, 2010 6:33 PM

    Dear Alex,
    Thank you so much for the information
    I've checked the note given by you, 1282074 this is only relevant for Amount type 0300 or it will rectify the error w.r.t amount type 0500 (Adjusted by Followon Document)
    Actually, wht happening is say for example:
      When i created the PO, in the report it will show amount type as 0100 (Original)
        and when i created GR w.r.t the PO, system should show as follows.
        At the PO 2 lines should be shown,,
             1. with Amount Type 0100 &
             2. line with Amount type 0500 which is not happening
      in the place of amount type 0500 system showing 0200 (Reduction) which is wrong.
    will the above specified note, solve this issue also or is there any other note .
    Thanks.

  • PRD Account hit at the GR reversal (102 movement type)

    Dear Experts'
    At the time of Goods reversal through 102 movement type, system automatically hit PRD account and it
    set off with freight clearing a/c.
    Why PRD a/c will hit at the time of reversal?
    Thnaks
    Suman Mukherjee
    MM Consultant

    Hi,
    In two different scenario, we have faced the same problem.
    1. Reverse GR document in same period with back date
    2. Reverse GR document in previous period .

  • 2LIS_02_ITM not considering 102 movement type

    Hi Friends
    We are facing a issue with the extraction of data from 2LIS_02_ITM. The system is not considering the 102 movement type ie the receipt returned quantity.
    Cheers
    Shivkumar

    Hi Friends
    We are facing a issue with the extraction of data from 2LIS_02_ITM. The system is not considering the 102 movement type ie the receipt returned quantity.
    Has any one faced a similar problem? If yes, please let us know what correction actions were taken.
    Any help will be highly appreciated
    Cheers
    Shivkumar

  • Mb51 trx (movement type 101) - Doc info- FI Doçuments  takes ages

    Hello
    We are experienceing performance problem when accessing FI document (FB03) from MM document.
    in praxis this means when choosing an todays document in mb51 trx (movement type 101) ->Doc info->FI Doçuments
    it takes ages to get FI document
    Does anyone has idea how to make system faster in this regards
    Thank you in advance

    hi
    check out this SAP Notes
    555893  MB51: Preventing runtime error DBIF_RSQL_INVALID_RSQL 15.05.2008
    848474  MB_GET_MM_MATBEL: Performance problem 21.08.2007
    857311  MB_GET_MM_MATBEL: Performance problem / error
    921164  MB51: Improving the runtime using database hints
    1608810  MB51: Enhancements for multiple account assignment MAA2

  • RG1 Updation for 102 mov type

    Dear  all,
    RG1 relevance was set for movement type 101 gr against  order.However 102 was not made relevant for Rg1 ,some documents were reversed using movement type 102 after that 102 was made relevant for RG1. Now when i am going to update RG1 for 102 material documents in J1I5 none of the material documents are getting selected ,Kindly suggest some way to update RG1.

    hi,
    Conceptually and as per rules u cannot reverse the entries of RG1.u can scrap but cannt reversed.
    that is why 102 is not updating RG1.
    in short it is better that u take goods to RG1 when u want to sell them.
    regards,
    sujit borse

  • BADI for Goods Issue against 541 movement type

    We want to check the stock of a subcontracting vendor for some materials, suppose a subcontracting vendor is having a material of 10 qtys. the system should throw an error message saying that the subcontracting vendor is already having the stock of 10 qtys., & no more goods issue not possible to this vendor,  this should happen whenever we issue the goods to subcontractor through 541 movement type if that subcontracting vendor is having a stock of say 10 qtys. Please give me the Solution this.

    HI,
    explore with ABAPer
    MB_DOCUMENT_BADI                      BAdIs when Creating a Material Document
    MB_DOCUMENT_UPDATE                BADI when updating material document: MSEG and MKPF
    MB_MIGO_BADI                              BAdI in MIGO for External Detail Subscreens
    MB_MIGO_ITEM_BADI                     BAdI in MIGO for Changing Item Data

  • Repair / Subcontracting with non standard mov types.

    Dear friends,
    I have copied mov type 541 to 941 , 542 to 942 and 543 to 943.
    When I post trhu MB1B .. with mov.type 941 , and receive it via MIGO with mov type 101 the system is determining the mov type 543 and not the 943 as we do need.
    Does anyone knows if I got to change this behavior ?
    This scenario is to use the same functionality of Subcontracting to repair materials. Other Ideas ?
    best regards,
    Ale

    Hi,
    Please go to the transaction code- ' OPKA ' and in the 'Parts Provided' column of the table replace 543 with 943 movement type for the movement type 101.Save your data and try again the process.
    Please note that, the standard Sub-contracting procedure (541-101(543)) will be impacted with this change.
    Regards,
    Narayana.

  • Difference between 122 & 102 movement types

    Hi All SAP experts,
    I have done 101 movement type with incorrect rate.
    So i used 122 mov type for cancellation & then again have done 101 mov type with correct rate.
    But accounting entries are going wrong in GI/IR account related with frieght,issurance & octroi.
    The same GI/IR entries are passing in 122 mov type.
    For GR reversal 102 is standerd one. ?????
    If yes what is exact difference between 102 & 122 mov types in accounting view.
    Please help me out.
    Thanks in advance.
    Regards
    Gitesh

    Jürgen L.  ,
    Ok fine but in case of frieght how both 122 & 102 works.(gi/ir account)
    In migo (122) GI/Ir account is not hitted properly.
    It debiting for two times in case of fright a/c.
    Where as material gi/ir a/csa are hitting properly
    Thanks once again

  • Differentiation of scrap types against 555 movement type

    Dear Gurus,
    Presently scrapping is doing against for 555 mov type both for in house scrap, scrap at workers place. how to differentiate this for analysis purpose please share with detailed explanation

    Hi,
    You are using single movement type 555(Withdrawal for scrapping from blocked stock) both for in house scrap, scrap at workers place.
    Now you need to cross check how you handle house scrap and scrap at workers place. possible posting can identified with having different storage location  ie....  one storage location  for house scrap and another storage location  for  scrap at workers place.
    OR
    You can use split valuation to  identify  scrap at house and  scrap at workers place.
    OR
    Can think of entering manual batch to identify  scrap at house and  scrap at workers place
    Regards,
    Biju K

  • Regarding Reconcillation of Subcontract Challan

    Dear Guru's........,
    The  PO has been created for with 7 child items...
    Against the po  6 items has been despatched and one item has not been despacthced through challan...
    but while recieving the same 7 items has come automatciaaly the 543 movement has happend
    but I am not able to do the reconcilation for the same
    while reconcilling the same , i am getting the error
    Material not assigned fully , short by quantity
    and now i am not able to do the cancellation of matl doc also due to stock is already consumed
    Please help in this regard
    how to proceed further to reconcile the challan
    Thanks in  advance
    Rgds
    Surya

    if you have mantained 7 child itemin PO and S/C for only 6 items and done 541 movement for all 7 items then while doing migo
    system will do 543 for all the 7 child item till here there is no problem then you need to capture the S/C at the header level for all the 6 child items.
    Now while doing the Reco in J1IFQ you need to mantain the qty you have actually consumed for making the FG.
    Just give there the qty you have mantained in the migo document in each chile line item.
    Hope it helps
    Reward if usefull
    Regards
    Sujoy

  • Subcontract challan reconcillation problem

    Dear All,
    We are getting the following message while reconciling Subcontract challans  " Material XXXX is not assigned fully , short by X nos ".  Is it because  if we post a single GR referencing two Purchase orders for same vendor with two different challans , will it be a problem during reconcillation ? since while sending components to vendor we create single challan wrt to 541 mat document.
    Thanks in advance
    Benny

    Hi All,
    After testing in quality system , i found that if GR 105 mvt type was done w.r.t  two different purchase orders for same vendor referencing two challans , the system issues the error message " " Material XXXX is not assigned fully , short by X nos " while trying tor reconcille in J1IFQ.
    Is this a standard SAP behaviour ?
    So for validation purpose i  cancelled the 105 mat doc and posted two different GR's referencing two challans and i was able to reconcile successfully.
    Any idea if the challan reconcillation will work only for one to one combination and i.e., one PO and its 541 mat doc /challan and one 101/105 mat doc.
    Kindly let me know if you have come across this cases.
    Thanks
    Benny

  • MIGO Error -while refering the subcontracting challan

    Hi all
    1.)We purchsed material from vendor A & send these material to vendor B directly for Job work ( for this we have seperate PO with subcontractor)
    2.) In Material PO we tick SC vendor & give vendor B.
    3.) Then made GR(with only part 1)
    4.) MMBE report shows stock provide to vendor B.
    5.) After that we made subcontracting challan for vendor B with reference to GR number.
    6.)Then capture and post the Excise invoice no
    7.) Now when I am trying to the GRN of subcontracting PO and refering the subcontracting challan , system is throwing an error " Challan material is different from material document "
    Usualy in the normal scenario, while doing the 541 movement type , we use to refer the subcon PO(by making the PO no field mandatory/optional against the movement type 541 in customization ) , as during MIGO, system checks the PO no against  the material issued and PO against the GRN is being done, if it does't matches, then the above error comes.
    But in the above scenario, there is no way to give the reference of giving the subcon PO during 101 "o" . that is why , this error is coming.
    Please suggest the way out , how to deal this scenario.
    Thanks & Regards
    Nitin Chhabra

    hi nitin
    pls refer following link
    Re: SUBCONTRACT J1IFQ ERROR
    Vipin

  • J1IFR report of subcontracting challans by material type

    How to extract the list of  subcontracting challans based on Material type selection.with Transaction J1IFR
    Krishna

    Dear,
    Report J1IFR is country specific report of SAP it is not the Standard Report for every country.
    Whatever is ther is the best given by SAP considering the requirement  of the Reporting regarding Challan reconcillation.
    If u still want that ,Then u have to go for the devolopment.
    regards,
    Sujit