Reciever tracing factor in COPA assessment cycle

Hi All,
I have account-based COPA and am trying to create COPA cost center assessment cycle in Tcode KEU2. While filling the reciever tracing factors, i can see the following values
RCMEGI     Total Quantity
RCWKFI     Fixed Costs
RCWKGI     Total Costs
However i need to define another key figure based on headcount
Can anyone help me with how to create additional Amount/Qty Field for the assessment cycle. Where would be above be defined?
Thanks & Regards
Pooja Saxena

Hi Christian
Are you suggesting that the costs from cost center be allocated upon, say, some IOs based on SKF and then settling the IOs to COPA?
This would be very cumbersome to create as many IOs as the possible combinations of Customer/ product / Other receiver chars
Or are you suggesting some thing else which I could not catch?
Also, new qty field can be created in KEA6... Values updated for this thru KE21N will work for acct based COPA?
Regards
Ajay M

Similar Messages

  • How to analyse the Receiver Tracing Factor in COPA Assessment cycle -KEU5

    Hi
    While executing the COPA Assessment cycle,we will get receiver tracing factor.My client wants to know how we got that.How can i analyse that Receiver tracing factor?Kindly advice me...
    How can I recalculate the tracing factor for assesstment?
    For example, Actual Assessment Cycle RS_A01 under Segment ITCMFG2AD uses Variable Portions Rule for Receiver tracing Factor with Value Field of 62 Sales.
    The intent of this assessment was to be allocated based upon sales dollar values however when I review the test calculation, it appears the tracing factor is in billions of dollars when our monthly sales are in the million of dollars range.
    Supriya

    Hi,
    If Receier Tracing Factor Rule is Variable Portion, then please also check the Receiver Weighting factor (the last tab in the assessment cycle, it normally is 100 for the receivers.
    Secondly also check if there is different currency setting in CO Area & the Operating Concern which translates into different figures.
    Hope this works.
    Regards
    Saket

  • How to find the receiver tracing factor in COPA assessment

    HI,
    how to  find out the receiver tracing factor in COPA assessment.Kindly help me the logic to anylise.
    Thanks
    Supriya

    Hi,
    If Receier Tracing Factor Rule is Variable Portion, then please also check the Receiver Weighting factor (the last tab in the assessment cycle, it normally is 100 for the receivers.
    Secondly also check if there is different currency setting in CO Area & the Operating Concern which translates into different figures.
    Hope this works.
    Regards
    Saket

  • COPA Assessement - reciever tracing factors getting multiplied

    HI All,
    COPA assessment cycle has been defined to send the costs from cost centers to COPA profitability segments.  Posted revenue has been used as tracing factors. My question is regarding calculation of tracing factors.
    The revenue for receivers is 22.22 and 444, however when the cycle is executed, the receiver tracing factors as shown in test run screen is 44 and 888. System is internally doubling the receiver tracing factors while executing the cycle in KEU5. Although the receiver values are correct in absolute terms, Users cannot understand why the receiver tracing factors are multiplied
    Why do the tracing factors get multiplied?
    Thanks & Regards
    Pooja Saxena

    HI Ajay
    Thanks for responding, My error is coming when i am trying to execute the assessment cycle, In some segments, the tracing factor got multiplied by 10!
    So not always doubles
    When you execute the cycles where reciver tracing factor is displayed in the output, is it always equal to the value that is in the system or some multiple of the same
    Thanks & Regards
    Pooja SAxena

  • COPA Assessment cycle run KEU5

    What all  can be as a Reciever in COPA Assessment cycle.Why is COPA Assessment cycle run KEU5.

    Hi,
    What all can be as a Reciever in COPA Assessment cycle.
    ..this is [documented|http://help.sap.com/saphelp_erp60_sp/helpdata/en/7a/4c48c64a0111d1894c0000e829fbbd/frameset.htm] in help.sap.com. As per [rules of engagement |/thread/931177 [original link is broken];pls. search before posting
    Why is COPA Assessment cycle run KEU5.
    ...no idea what you mean. Pls. explain.
    Regards
    Karl

  • COPA Assessment Cycles and FI Period closing.

    Hi Gurus,
    I have question related to the COPA Assessment cycles.
    We have closed the FI Period 03 and running the COPA Assessment cycles. while running the same, for few of the assesment cycles are completed and for the rest of the few  cycles it is error out stating the Period is closed.
    Why it is running successfully for few cycles and why it is complaining for Period closing for the others. We are on ECC 6 Version of SAP.
    Error out cycles contains Cost accounts and Asset Account GL Accoutns.

    Hi:
    If your CO allocation has some external postings (like GL or fixed assets) or generating some intercompany documents, then it needs FI to be open also. It happens sometimes if the allocation goes external so it would need fI period to be open also. If FI is close but CO is open, it would only work for CO specific allocations and others would error out.
    Please check the cycle/segment which is in error. If it is suppose to hit FI, then FI (OB52) and CO (OKP1) periods should be in sync.
    Thanks.
    Rahul

  • COPA-Assessment cycle KEU5

    We have run cost center -assessment cycle for a cost center group and all the cost of the profit centers are distributed to respective costcenters.And now we goto COPA-Assessment cycle KEU5 and run the cycle for the cycle with same cost center group as sender.
    System posts a difference amount of positive amount in the credit side of each costcenter of that group.Which reduces the credit value and shows in over/under absorption.
    Please suggest where from the system is finding the difference when all the costcenters are with zero value as cost is distributed thru CCA assessment cycle.What differences will a cycle run in co-pa determine.Please suggest.

    Hi,
    Actually, the Sales overhead and Corporate expenses which are captured in the Cost Center shall be allocated to the COPA. All other expenses captured in other Cost Centers shall be allocated to the Production and shall be absorped into the products manufactured. Hence, the same Cost Center shall not be used as sender in both the cycles. If we use like what you described, it will definitely result in over absorption that is more credits. Hence, please describe why need to add the same Cost Center group in both the CC cycle and Copa CC cycle.
    Trust this helps much!
    Cheers!

  • COPA Assessment Cycles

    Hi Guru,
    I really need some help with setting up COPA assessment cycles in 6.0.  I have used the best practice guides but unfortunately they were to lazy to be thorough.  I am using transaction code KEU7 to create the cycle.  I have attached a few segments to the cycle and added the sender/receiver (cost centers, companycode) details aswell. I checked it before saving the cycle and i got no error messages.  Now when i execute the cycle through tcode KEUB i get errorr/warning messages saying that "no valid sender entries found" and "this segment does not contain any senders".  I am not sure what i am missing and what i may be doing incorrectly.  Can someone please help me understand how to rectify this issue.  I am extremely generous with rewarding points!!!
    Thanks in advance,
    Shaun

    Hi Smith,
    Basically we created copa cycles in KEU1 and execute through KEU5.Find that recivers are product hi-erarachies, In our orgainisation  Corporate oh are be charge to products through copa cycles.
    Coming to your problem,When ever you define new copa cyle you find the error in differet ways.
    1) NO VALID SENDER FOUND  for segment means, Go to the segment there is an button ie consistancy chek box.Click on the check box System returns relavant segment.Observe that segment contains valid senders and revicers are produtc hierarachies or not.
    2) Other wise go to the segment and clik on find button, give the cost center, cost elements.Observe secondary cost elements and rules.
    3) other wise you can directly execute the co-pa cycle and click on segments.Here you can easily find that sender contains valid recivers or not.Basically these kind of error message will appears still now there is no Transaction passed to that products..
    I hope you understood.
    Regards
    Maruthi

  • Posting - COPA Assessment Cycle

    Hi
    when i am trying to run KEU5 for period 12 for the previous fiscal year,the system is posting (with warning)but when i am running for period 1 for this fiscal year,the system is not posting.Can anyone please help me out.
    Whether any fiscal year change over or period end/year end activity has to be carried out for the COPA ASSESSMENT CYCLE.
    Appreciating for the help extended.
    Thnx & Regards
    Pran

    praveen,
    please check have u maintained fiscal year for the new year in fi and co
    sateesh

  • COPA Assessment Cycle

    Hi,
       I prepared one copa assessment cycle(T.code : KEU1) with a receiver type -Variable portions / Revenue with Billing type (F) . When i run the COPA Assessment cycle , i got a message that no sender values found. I created some revenue entries in the period 12 and some Cost center related expenditure.
      I prepared another cycle with receiving type as fixed amounts. When i run the KEU5 , The values are perfectly flowing.
      Any inputs on this. Thanks in advance.
    Thanking You,
    D.K.Lakshmi Narayana

    Hello Pran,
    With reference to your Error
    1) Please check the value of Sender. I think it is 0.
    2) In second case please add the reported GL in allocation structure KF which you are using.
    Hope this will help you.
    Regards,
    Pawan Kumar

  • COPA Assessment cycle + OKP1

    Hi,
    As part of month end activities, OB52 and OKP1 were closed for last month.
    But still COPA assessment cycle is not completed.
    Pls. let me know if they need to be opened again for executing the assessment cycles.
    Thanks,
    Sridevi

    Hi Sridevi,
    Goto OKP1 T.code and open transaction "Assessment to CO-PA" for particulare period and execute Assessment cycles for COPA and  Goto OKP1 T.code and close transaction "Assessment to CO-PA" for previously open period.
    Hope this helps you.
    Thanks,
    Rau

  • COPA Assessment Cycle Process

    Hi
    Can any one tell me the entire COPA assessement Cycle with its uses and period end activity,sender and receiver logic,etc.
    If u have any document,can u send it to me... praviin_5at yahoo.co.in
    I m in 6.0
    Regards
    Praveen

    Hi,
    COPA assessment cycle is used to bring the overhead values, cost center values to copa through copa assessment cycle. for that you have to create a COPA assessment cycle in KEU1 with senders, receivers value fields. After that you have to execute  KEU5 t code.
    Sateesh

  • COPA Assessment Cycles Issue.

    Dear All,
    I have an issue with assessment cycles through COPA.
    I have created assessment cycles for transferring the cost from cost center to products. So Maintained the sender cost center and cost elements but i maintained the receiver charecteristics which is not executing.
    We have many charecteristics in copa report. But client has given the percentages for products only to distribute the cost from cost center to Products.
    How can i achive this with proper execution of assessment cycles.
    Regards,
    Prakash.

    Dear Prakash,
    Check in Tcode KE24 whether values are posted for the combination of receivers you have mentioned in Assessment cycle. If the values are not posted for the combinations as receivers, system will not post the values through assessment cycle.Restrict the receiver characteristics for e.g. company code, Material Group etc.
    regards,
    Makrand

  • COPA assessment cycles for revenue postings

    Dear SAP gurus,
    is it possible to allocate revenues to COPA via assessment cycles (tcode KEU5)? We have service income related revenues that are not linked to COGS therefore they are posted to Cost Centers but they need to be visible in the cOPA report to have a complete profitability by product. at the moment I am not allowed as revenue are considered statistical postings... any clue how can I solve this?
    Thanks
    Monica

    Hi Monica
    Welcome to SDN!
    I dont agree with the responses provided above.. As far as I know, statistical postings can neither be settled, nor can they be allocated
    Catg 11 cost elements post statistically to Cost Centers.. Hence, you cant allocate...
    For the postings made till now, Manually update COPA using KE21N (If you are using Costing Based COPA)
    Way Forward: Make your service income postings in an Internal Order and you can settle the same to COPA and then allocate using Top Down Dist KE28...
    Try note 605281  and see if it allows to use IO as senders in KEU5.... 
    BR,Ajay M

  • COPA Assessment Cycle - Segment Wise

    Hello Friends,
    Good Day!
    I have created COPA Actual Assessment Cycle by T-Code KEU1. I have created around 5 Segments in that cycle. I want to execute the Assessment Cycle, but Segment Wise. I am trying to execute KEU5 and execute the Cycle. The assessment was properly as desired but for all Segment at once.
    But if I want to execute this Cycle Segment Wise, is there any possible way to do that?
    Many Thanks,
    Pritesh Lodha

    Dear Lodha,
    Please try in the following manner which may suits your requirement:
    Lock indicator available in Assessment cycles segment wise.
    If you have many segments and want to run for few segments, you can use the lock indicator in assessment cycle T Code: KSU2
    After locking the required segments you can run the assessment cycle using KEU5 by specifying the cycle name.
    Cycle will consider the active segments only.
    Regards,
    Pavan Kumar Arvapally