HI,
Material Quantity fuctionality is used
When the Compoenents quantity or properties impact the Header materials quantities or the remaining components quantities.
For example,
we make 1000 kgs of 10% Sulpuric acid concentration using 10 kgs of 100% Sulphuric acid and 990 kgs of water.
Here if 100 % Sulphurtic acid might not avialble all the time, we may get 80% 90% or some other percentage.
However we always need 10% sulphuric acidas  a Finished product.
Having diffrent PV's is one option.
However the other options is to use the MQC, where formuals can be defined to change the Header and other compoenents quanties based on a active compoenents attributes. Batch characteritics.
Regards
Ratan

Similar Messages

  • Report for Comparison of Material Qty

    Hi All,
    I need to Develop an Interactive report for Comparison of Material Qty. ordered through Purchase requisition, ordered material through PO and corresponding Material Receipt report.
    Can Someone Give a brief description about this & fields tcode & tables regarding this report.A sample code would be much appreciated.
    Thanks & regards,
    Ravi S

    To get the material number combined with the PO text you will need the help of an ABAP programmer.  The programmer can create a report for you using the function module READ_TEXT in the function group STXD.  The tables to use are:
    STXH - STXD SAPscript text file header
    STXL - STXD SAPscript text file lines
    The selection screen should have at least the following:
    OBJECT - STXH-TDOBJECT
    NAME - STXH-TDNAME
    LANGUAGE - STXH-TDSPRAS
    TEXTID - STXH-TDID
    You find the information for these fields by going to the PO text entry screen and displaying the header information under Goto -> Header.  For materials, the object is MATERIAL, the name is "material number", the language is "EN", and the text ID is BEST.  You can use this program to get long text in lots of places like information records, purchase order texts, etc.
    Hope this helps.

  • Material Qty. of Shop floor material

    Hi,
      I want to make a report with certain dat along wiith this I also want material qty. of production florr  means  material isue agains production order or any order to production but partial return or not retun in which table i can get those qty.
    regards,
      zafar

    Dear Zafar,
    You can get in table AUFM
    Else report COOIS, in list just input as components & give plant & basic dates as from & to ( 1 month )
    You can get required qty & issued qty
    Regards
    Madhu

  • How to block the material qty to 1 while creating sales order (VA01)?

    Hi All,
    Scenario :  We have 20 Materials each with 100 qty in Plant. In the sales order we should have all the 20 materials with qty one. The sales order should throw an error if the material qty is more than 1 and should not allow to create a sales order.
    so is there any transaction code where we can block the entire material qty to 1 from the same plant while creating sales order?
    Note: We should not set in MM01 "Minimum order qty". Assume we have 100 material in plant we can't set for each material one by one "minimum order qty".Instead of that is there any option to set the whole material qty to 1 as minimum while creating sales order?
    Kindly guide me how to proceed.
    Thanks,
    Renjith

    If you have access to idoc before calling the processing Function module, Adding header text segments E1EDKT1 and E1EDKT2 to the idoc will create the header text.
    Regards
    Sridhar

  • Batch determination issue in process order Material quantity calculation

    Dear Gurus,
    We are facing issue in auto batch determination in process order (Material quantity calculation ).
    eg Material X  is active material 200 KIA used in BOM as
    10  X   200  KIA  
    20  Y   10           Filler
    30  Z
    40  X   200  KIA
    50  Y
    60  Z
    We select line item 10 and 40 and do Batch determination system proposes 2 batches for line item 10 as Batch A and B
    and for line 40 again Batch A (with 0.01 KIA) and batch B proposed which is wrong.
    For line Item 10 Batch A and B
    For line Item 40 Batch B and C or as per FIFO logic.
    As Batch A should be consumed in Line item 10 then it proposed Batch B and so on....
    We have already maintain data in COB1.
    Can any body explain what is wrong in determination.
    Regards,
    J.H.Pert

    Hi Pert,
    Follow the below link you have some idea OK.
    Any questions revert me back.
    Batch search strategy
    Regards,
    Madhu.G

  • Block sales order creation based on material qty

    Hi,
      In my scenario i want to block the sales order creation based on material qty , how i can do this?
    Example:
    Material qty below 100 = able to create sales order
    Material qty above 100 = not able to create SO
    Thanks,
    Arun

    Hi
    For restricting the order if it is less than a specified qty, you can maintain the 'min order qty' in material master.
    But your requirement is the other way round - Restrict order if it is more than specified qty.
    In this case, you need to use the following sales order exit  in progran MV45AFZZ
    u2022     USEREXIT_SAVE_DOCUMENT_PREPARE
    Use this user exit to make certain changes or checks immediately before saving a document. It is the last possibility for changing or checking a document before posting.
    The user exit is carried out at the beginning of the FORM routine BELEG_SICHERN.
    Hope this helps.
    Regards
    Madhu

  • Material Qty short

    Hi Gurus
    I am  facing the problem during the confirmation of TO  with ref to delivery  . Delivery was created & when I am trying to  confirm the TO it is showing that 4 material qty is short   It is giving error message VL198  .
    In  my item category  customization picking tick mark is  “Unchecked “  in t-code – OVLP   & also maintained  as “Y” in   configuration ( SM30 - V_TVLP-VERPR) .
    My material is batch managed & stock is showing in the LX02 report  which is enough  to confirm the TO  .
    Batch is also  not showing any kind of  block & it in unrestricted use stock  . Only things is to be noticed that  in MD04  we have some safety stock  requirement at plant level  .
    Please let me know where I am  doing mistake . Please  also let know whether system checks  safety stock also  while doing confirmation
    Thanks ,
    Regards,
    Aman

    See my blog Unrestricted use stock not equal to available stock
    I tried to explain the fact that is named in the titel.

  • Raw material qty & value

    hi all
    Raw material qty. is zero in mmbe,mc.9 & material master plant stock .But it shows -ve value in  material master & MC.9
    Whyvalue  is -ve?

    Dear,
    Same Problem i am also facing when i am exexuting MC.9, for ZERO Stock its showing val.valuated Stock
    +ve for some material and -ve  for some materials.
    when i raised a OSS msg to SAP they are telling this id due some of the Info structure tables were not updated i.e S031,s032 and s033 (use Se16 give ur material for these table u wil come to know)
    they have give some note to statistical build but my invoice documents are very old i.e 2001 and 2002 Fiscal year.
    my advice just raise a OSS msg to SAP.
    other check ur data again by executing the T.code MC.9 under valaution sub tab instead od standard please select current price.
    Please gothrough these notes if at all useful79083,64636.
    180952 Negative stock values in Inventory Controlling (MOST RELAVENT)
    487674 Negative consumption value after cancellation movements
    358284 No values for negative stocks
    672183 'Value stock with receipt' is incorrect
    416791 Standard analyses: Error with rounding differences
    453420 Incorrect stock values in LIS
    Please help me if you get any soluation
    regards
    venu gopal
    Edited by: venu kk on Jun 2, 2008 9:15 AM

  • FM for material QTY instead of amount

    Hi All,
    Is it possible to take material QTY in FM. My client want to budget sales target on QTY basis in FM.
    I was thinking if we derive commitment from QTY in FMDERIVE it can work but how to trigger budget with QTY and not amount.
    Thanks,
    Vishal

    Hi,
    The budget in FM is working on amount basis. You can define your commitment management to be triggered by quantities (based on UoM setting), but I guess it's not what you are looking for. PSM-FM is not built to control quantities. You have to manage it via CO planning or logistic modules.
    Regards,
    Eli

  • Cs11 not Display Alternate Material Qty

    Dear Experts
    Whenever we r Putting Alternate Material in BOM and Set it Prioty And define the Qty as similar with other one and after that
    whenever we r checking Display in Cs11 Then System will Not Show Us the Alternate Material Qty And Also The Qty of Number 1 Material whose alternate is Define. both material R Blank Qty .
    What would be there.
    Rgds
    Pankaj Agarwal

    Dear Pankaj,
    Whenever you are checking the BOM display using T code CS11for a product which has alternative item group,then after
    executing the report,click on the change layout(control+F8) and select the fields like component quantity and not
    comp.Qty,and also usage probability and alternative item group,because if you have only the field comp.Qty,then in case if you
    have given the usage prob as zero means then it wont get displayed in the report.
    So select the change layout and select for the field Component quantity and check the same.
    Regards
    Mangalraj.S

  • Optimize MRP material package calculation in parallel MRP

    Dear all,
    How to Optimize MRP material package calculation in parallel MRP?
    How and where can i see and change build up package for parallel  MRP  run?
    Thanks
    RAGHU

    Dear,
    Please run report program RMMDMONI
    Important point.
    -Materials
    -Runtime
    -Read situation
    Save result
    -MRP list
    In.Last page of MRP Spool. In the end of the spool, you can see
    how the WPs is used.
    Depending on the usage of WP, you need to think of packet size used for
    parallel planning.
    Also refer the OSS Note 568593 for details.
    Also please test BAdI MD_MRP_RUN_PARALLEL to set the package.
    OPP1 -> Business Add-Ins - > 'Package size in parallel planning contains detailed information about this topic.
    Hope clear to you.
    Regards,
    R.Brahmankar

  • Material quantity calculation to be done upto a limit

    Dear PP experts,
    I am using material quantity calculation for acitve ingredients. The quantity of API should be calculated as per the assay recorded in inspection lot. But the additional requirement is that the API quantity should be calculated after batch determination only if the assay recorded is 99 % or below 99 %. If the assay recorded against inspection lot is more than 99 % the API quantity should remain the same.
    Pl. suggest how to proceed.
    Thanks,
    Prashant

    Dear Prashant
    If you can post this question in PP forum, may be you can get lot of suggestions.
    thanks
    G. Lakshmipathi

  • MCBZ report how to get total stock qty calculation?

    Dear Guru,
            if i checking one material in Tcode:MMBE having unrestricted stock is 356 & reserved qty is 56. After this when i am executing report MCBZ-- Current stock reqmt list & get Total stock qty is 120 for same material.
    can any one tell me how it is calculated (i.e. Total Stock).
    My requirement is we want to see a report which shows diffrence bewtwwen satfey stock & total stock. so i am using this report, if any othere suggestion then please reply me.
    Best Regards,
    Dev

    Dear,
           You can see in MD04 t-code here u can find safety stock and inventory stock.
    Regards
    Ravi

  • Material Qty Calclation

    Dear Experts,
    Can we use ingredient specification calculation in batch for by product because by product is producing so its with -ve sign. no batch determination takes place in process order. and that qty takes according to BOM not according to  batch specific characteristics.
    if i want to produce by product on the basis on second raw material's batch specification. how could i do that?
    Regards
    Pravin

    Yes, U can use the Base UOM in MQC.
    Further while processing the Process order, you need to go to MQC screen after assgining the relevant batches,
    do the Clauclation and update the process order.
    Then only the By-product value changes with the Batch chracteristic value.
    regards
    Ratan

  • Fixed material qty rate

    Hi
    I have one requirement where for 1 material supplier wish to supply the material on fixed rate basis. Whehter u placed order for 50 pieces or 1000 pieces the rate will be fixed 500rs.
    How can i handle this problem?
    Thanks in advance

    Hi
    Basic Price Condition Type  is based on the Calculation Type Qty  , so as you change the Qty the Value in the Basic Price Changes.
    What you need to have a Fixed Value Condition Type in Such Cases.
    goto M/06 , Clcik on the Condition Type PB00 if you rae using this as the gross price ,you copy the PB00 & create a condition type ZPB0 use the same & change the Calculation TYpe as B - Fixed Amount
    Use the same in the Pricing Procedure & use it in the PO.
    Thanks & Regards
    Kishore

Maybe you are looking for

  • My iphone 4 won't turn on and when on charge i unplug and plug in it makes noises but it still won't go on.

    i was on settings and i was clicking on a app so i could remove but then it froze well not froze something would pop up and then go when i turned the off button it didnt go off for a while then it went off and my iphone was charging when i clicked th

  • BH-600 Headset - No sound through speaker

    Hi, I have a Nokia BH-600 headset which has no sound through the earpiece after successful pairing with my phone which is a Nokia E61i. It used to work perfectly until I upgraded the software for the phone. I have had Nokia Customer Support try to so

  • Wired keyboard and mouse

    I am interested in buying a wired keyboard and mouse with the Apple cinema display. I am in Korea. I went to the Apple site and it just advertises the wireless versions. I do not like wireless versions because I do not like to mess around with batter

  • SAP Solman Installation

    I need to install SAP Solman 7 + EHP1; AS ABAP +DB on one server and java on other server, based on Windows 2K3 Ent Server 64bit and Oracle 10.2. This is because of the limited hardware resources on a single server. Is it mandatory to have ABAP and J

  • HELP ON javax.crypto

    hi i am currently coding a little small program that include of encrypting and decrypting my project consist of a sql database server and java program where java program will encrypt a password etc "iamapassword" and stores the encrypted : ("Xsde8EDF