Reconcillation of subcontracting challan

hi every body
my problem is about reconcillation of subcontracting challan.
let 10 kg material named A is to be manufatured by 16 kg of material B. NOW i created a sub contracting po ,541 tranfer posting, j1if01subcontracting challan, then i do good receipt fpr 10 kg A material and assign the subcontacting chhalan to the good receipt.now quality department reject 5 kg A MATERIAL FROM 10 KG A material and send 5 kg A material to the vendor with movement type 122. with this also 8 kg of material B is also returned with movement type 544 with stock provided to vendor o .
now when we chack with MBLB 8 kg of material B is with subcontractor.now when we reconcile quantity with J1IFQ .
it shows and give the warning massage that  8 KGof B MATERAIL is short.it does not allowed to save
however 8 kg of material B is with subcontractor tehn it should be reconcilled with rest of 8 kg of B material. why it does not save. is this problem of patches. please give solution this is urgent requirement.points will be rewarded.

I want to give it an attempt
while reciving the mat A total 16KG of B is issued, so stock of B is reduced by 16 KG.
Now you did 350 & 122 for rejection and dispatch of mat. A with 5 KG that means for Mat B 8 KG made, so we get 8 KG of B back ( which is in vendor place)
but while doing reconcilation the stock of B is required which is shot by 8 KG. let teh cycle to complet means recive the repaired the material A then do reconcilation. system will not so this error.
simutate in test once to check it now as it seems you r in hurry.
Regards

Similar Messages

  • Re -Reconcillation of subcontracting challan against "102" mov type mat doc

    Dear All,
    While we are doing the reconcilliation of the Material document (mov type-"102" ) against the subcontracting challan (ALREADY fully reconcilled against 101 material document, but not compeleted), then system is NOT allowing us to do the reconcillation, requirement is to reduce the qty assignment  in already reconcilled challan, as we have reversed the material document
    1.) When we have assigned the 102 movement type to movement type group to 0001( Issue movement type group)
    then system is giving an error message : 8I567-Challan not valid, Material doc. is valid for another scenario during J1IFQ.
    2.) and when we are assigning the 102 movement type to movement type group 0002( Receipt movement type group) , then system gives error message : 8I574 -Material XXX is not assigned fully, short by YYY KG
    Please suggest the right way of doing it.
    Thanks & Regards
    Nitin Chhabra

    Hi
    If a challan is reconciled it should not be opened again. That is illegal. You need to do subsequent adjustment if you want to alter your consumption in subcontract. If you do 102 and reverse your consumed material,You need to include 544 movement type in your movement type grouping then You need to create a new 45a challan.
    Regards
    Antony

  • Regarding Reconcillation of Subcontract Challan

    Dear Guru's........,
    The  PO has been created for with 7 child items...
    Against the po  6 items has been despatched and one item has not been despacthced through challan...
    but while recieving the same 7 items has come automatciaaly the 543 movement has happend
    but I am not able to do the reconcilation for the same
    while reconcilling the same , i am getting the error
    Material not assigned fully , short by quantity
    and now i am not able to do the cancellation of matl doc also due to stock is already consumed
    Please help in this regard
    how to proceed further to reconcile the challan
    Thanks in  advance
    Rgds
    Surya

    if you have mantained 7 child itemin PO and S/C for only 6 items and done 541 movement for all 7 items then while doing migo
    system will do 543 for all the 7 child item till here there is no problem then you need to capture the S/C at the header level for all the 6 child items.
    Now while doing the Reco in J1IFQ you need to mantain the qty you have actually consumed for making the FG.
    Just give there the qty you have mantained in the migo document in each chile line item.
    Hope it helps
    Reward if usefull
    Regards
    Sujoy

  • Subcontract challan reconcillation problem

    Dear All,
    We are getting the following message while reconciling Subcontract challans  " Material XXXX is not assigned fully , short by X nos ".  Is it because  if we post a single GR referencing two Purchase orders for same vendor with two different challans , will it be a problem during reconcillation ? since while sending components to vendor we create single challan wrt to 541 mat document.
    Thanks in advance
    Benny

    Hi All,
    After testing in quality system , i found that if GR 105 mvt type was done w.r.t  two different purchase orders for same vendor referencing two challans , the system issues the error message " " Material XXXX is not assigned fully , short by X nos " while trying tor reconcille in J1IFQ.
    Is this a standard SAP behaviour ?
    So for validation purpose i  cancelled the 105 mat doc and posted two different GR's referencing two challans and i was able to reconcile successfully.
    Any idea if the challan reconcillation will work only for one to one combination and i.e., one PO and its 541 mat doc /challan and one 101/105 mat doc.
    Kindly let me know if you have come across this cases.
    Thanks
    Benny

  • J1IFR report of subcontracting challans by material type

    How to extract the list of  subcontracting challans based on Material type selection.with Transaction J1IFR
    Krishna

    Dear,
    Report J1IFR is country specific report of SAP it is not the Standard Report for every country.
    Whatever is ther is the best given by SAP considering the requirement  of the Reporting regarding Challan reconcillation.
    If u still want that ,Then u have to go for the devolopment.
    regards,
    Sujit

  • Printing of subcontracting  challan

    Hello Experts
    Pl guide me how to print the subcontract challan after reconcillation.
    Thx
    Umesh

    Hi,
    Check in SPRO > Logistics - General > Tax on Goods Movements > India > Business Transactions > Subcontracting > Subcontracting Attributes > Check whether Subcon Output Type - J1IF is maintained here.
    Also check in M706 - For Output Type - J1IF, under "Print" Tab Page, what is the Print param., if it is "7 Plant/storage location" then go to OMJ3 and mainatin the entry with J1IF/Plant/Storage location (keep it blank if all the sto locs of plant are to be considered)/Output Device/Name/Print Immediately/Release after output
    Also check condition record for Output Type J1IF in MN22. If not there then mainatin it.
    Note: - It is better to have Condition Table with "Plant" and a new access sequence needs to be created with this table and assign this to J1IF in M706. So condition record maintenance will be easier.

  • How subcontracting challan is manged in multilevel subcontracting process??

    Hi Gurus,
    ***How subcontracting challan is manged in multilevel subcontracting process??
    **In this scenario  *** when we send material to sub con vendor A1 for  job work,with this we create subcon challn(J1IF01) & send it to vendor, when this vendor  completes his job,he directly send this matrl to subcon vendor to B1 for the finishing work, after this vendor B1 will directly send finished matrl to company***
    Here - how the subcontracting challan is managed?? please guide.

    Hi,
    The challan is also widely known as the 57F4 challan, after the law under which it was defined up until the 2000 budget. This law has now been superceded by a new one, 57AC. The challan consists of a header and line items. The header, in addition to T-code is J1IF01 to create subcontracting challan. organizational data, allows you to enter:
    Preprinted number
    Additional data
    Identification marks
    Nature of processing
    Furthermore, each challan has two numbers, an internal document number and a challan number, which the system assigns to the challan when you save it. From a business perspective, this is the most important number. Each challan also has a status, which shows you what stage in processing it is at.
    The line items are copied across from the transfer posting when you create the challan. You can also enter additional data for each item
    T-code for completing the challan is J1IF13. You use this function to close a challan completely after all the materials have been accounted for. If a challan's return date has elapsed, and thus your right to the CENVAT credit, you use it to reverse the excise credit u2013 or, should your subcontractor return the goods subsequently, to re credit the excise credit
    Reconcillation of challan (J1IFQ): Once a subcontractor has processed your materials and returned them to you, you match the items in the challan against those that have been returned . I hope this will resolve your issue. Thanking you.

  • Excise Invoice Selection Vs assessable value in Subcontracting Challan

    Hi,
    I have maintained the Assessable Value for my subcontracting components and also there is Excise Invoice exists for this components. While creating Subcontracting challan, system is displaying information message that Material  XXXXXX has an assessable value, but I would like to refer the Excise Invoice.
    Hence, when I click the Excise Invoice selection, there is no effect. As per SAP message "The message is for information purpose only. Go ahead with the option selected" system should ignore this message and allow me to select Excise Invoices but it is not happening.
    Is this bug or any other config setting to be done to overcome this issue?.
    Your replies to resolve this issue is highly appreciated.
    Thanks,
    Babu.

    Hi,
    For every excisable material (whether you procure, manufacture or sale) has to be declared as excisable material in table J1ID with appropriate chapter ID, assessable value & CENVAT declaration.
    When you send the excisable material to the sub-contractor the material needs to be returned back to your plant within 180 days. If this is not done, then you will have to pay back the excise duty on the material with base value as assessable value. Hence it is required to maintain the assessable value.
    Hope this clears your query.
    Regards,
    Prashant

  • Error While creating Subcontracting challan in J1IF01

    Hi,
    While creating Subcontracting challan in J1IF01Im getting error " Deficit of 3.2000000000000002E+00 in RG23ABED".
    Any suggestion in this regard is very helpful.
    durga
    [email protected]

    Hi,
    You are referring the material challan, which is not posted for Sub-Contracting PO. Pl. check your Material document number. Also pl. check that plant is same in material document & s/c Challan.
    Excise values are not appearing in the S/C Excise Challan, because you are sending the excisable material to your sub-contractor without paying any excise duty. When you reverse & recredit the S/C Challan, it will show the Excise Amounts.
    Regards,
    Prashant Kolhatkar

  • Mismatch of qty in subcontracting challan reconcilliation

    Hi,
    When we issue the material using subsequent adjustment.During the reconciliation of subcontracting challan,
    1) Challan quantity is not getting updated,
    2) Material sent to item in subsequent adjustment  is getting added in GR quantity, in subcontracting challan
    E.g.
    Subcontract PO qty: 10
    Qty sent to vendor using subsequent adjustment: 5
    After reconciliation of subcontracting challan,challan qty remains same i.e. 10. 
    GR qty in the challan is 5.
    Please help.
    Your quick response will be a great full.

    It has been resolved at the author side.

  • MIGO Error -while refering the subcontracting challan

    Hi all
    1.)We purchsed material from vendor A & send these material to vendor B directly for Job work ( for this we have seperate PO with subcontractor)
    2.) In Material PO we tick SC vendor & give vendor B.
    3.) Then made GR(with only part 1)
    4.) MMBE report shows stock provide to vendor B.
    5.) After that we made subcontracting challan for vendor B with reference to GR number.
    6.)Then capture and post the Excise invoice no
    7.) Now when I am trying to the GRN of subcontracting PO and refering the subcontracting challan , system is throwing an error " Challan material is different from material document "
    Usualy in the normal scenario, while doing the 541 movement type , we use to refer the subcon PO(by making the PO no field mandatory/optional against the movement type 541 in customization ) , as during MIGO, system checks the PO no against  the material issued and PO against the GRN is being done, if it does't matches, then the above error comes.
    But in the above scenario, there is no way to give the reference of giving the subcon PO during 101 "o" . that is why , this error is coming.
    Please suggest the way out , how to deal this scenario.
    Thanks & Regards
    Nitin Chhabra

    hi nitin
    pls refer following link
    Re: SUBCONTRACT J1IFQ ERROR
    Vipin

  • MIGO with reference to Subcontracting challan

    Dear Friends,
    I have a couple of questions which u may be able to solve:-
    1. In a MIGO for a subcontracting PO, i can select the option Refer subcontracting challan in the excise invoice tab. I wanted to know the purpose of this functionality. If i refer the subcontracting challan in the MIGO does it mean I dont have to reconcile the challan after MIGO.
    2. When I refer the subcontracting challan in the GR and enter the challan no and year the system throws an  error which says - Challan material is different from material document. i have checked the material document for the transfer posting made. But the material is the same in all the cases and flows from the PO itself. please help me out with this error.
    Regards
    Gurvinder

    for point 2 do this
    In spro --> taxon goods movemnt > indiac> business transaction --> subcontrcating --> maintain movement type grp
    here miantain
    0001 101 O
    0001 122
    0001 541
    0001 544 O
    0002 542
    0002 543 O
    Edited by: Kedar Kulkarni on Jan 27, 2010 7:53 PM
    Edited by: Kedar Kulkarni on Jan 27, 2010 8:21 PM
    Edited by: Kedar Kulkarni on Jan 27, 2010 8:26 PM

  • Issue in Subcontract Challan Creation

    Dear All,
    We just started subcontractor challan process in sap for tracking the material supplied to vendor and finding the stock which will be laying at more than 180 days at vendor end.
    The issue we found is while creating subcontract challan excise group and other details not stored, since we are doing testing and it would be resolve before implementing.
    Regards,
    Malini

    Hi,
    Please do the necessary settings if customization is missing then you need to do it. If your asking how to making the settings please sit with FICO consultant and Client Discuss it and come with your questions
    Hope it is clear
    Shiva
    http://scn.sap.com/thread/1950603

  • Creation of subcontracting challan

    Hi all,
    I have done all the required customization settings,,,
    procedure i followed is:
    1. created two raw materials with material type ROH, - materials R1, R2
        cretated a semifinished material with material type HALB- material S1
    2.created a BOM for semifinished material S1 and assigned materials R1, R2      as components.
    3. Created a PO with item category 'L', material S1, quantity 1, exploded BOM for assigning rawmaterials R1, R2.
    4. Accessed t_code MB1B- movement type 541, with reference to purchase order for providing material to vendor.
    5. Now I run t_code J1IF01 for creating subcontracting challan,,, there i had given material document, year, excise group, service group and executed the t_code,
    and all the required fields in the transaction were filled and saved.
    so finally system giving me this message:
    Document  2007 10 created
    problem is ,,, its not creating a number for subcontracting challan,,,
    i had filled up all the excise data for the material,,,
    someone can me help me out in this issue,urgent.
    regards,
    urendra

    Hi Prasanna,
    I had checked these number ranges viz. J_1IINTNUM, J_1IRG23A1,J_1IRG23A2, J_1I57FC all were maintained correctly,
    System creating the subcontracting challan,, but it is not picking up the number range, I have selected the print immediately option and got the print with no subcontracting challan number...
    as soon as I saved the Subcontracting challan, system gives this message
    Document 2007, 50 created,,, here 2007 is the fiscal year, and 50 is the series group.
    checked all the excise registers, excise group, material chapter id combination,,, everythings is ok,, kindly help me out in this issue.
    regards,
    urendra
    [email protected]

  • In J1IFR-List subcontracting challans, system showing Zero Quantity pending although Qty is pending

    In J1IFR-List subcontracting challans, system showing Zero Quantity pending although Qty is pending at MASOP vendor. After reconciliation of challan, the Qty sent=250 , Qty received= 113. system must show Qty pending = 137. But when we check in J1IF12, Qty sent=250 and Qty received=113. Why J1IFR report is showing incorrect output.
    I am facing this problem after Ehp7 upgrade in SAP ECC 6.0 version.
    Thanks & Regards,
    Neeraj.

    Are you using the same number ranges for different series group. This can cause inconsistency. Also check table J_1IGRXSUB whether right material documents are attached to your Challan.
    Also refer to these notes which is only applicable for EHP6.
    1753000 - Wrong output displayed for status in report selection-
    J1IFR
    and
    1674607 - Duplicate entries while displaying Annexure IV in
    J1IFR
    Regards
    Binoy

Maybe you are looking for

  • SSL - Always Prompted with "Request Authentication"

    Hi, We have developed an Applet which works as an Download Manager and we had it signed as it needs to access the file system of the users. We have two deployment environments one over SSL (Entrust) and other Non-SSL. The signed applet works well ove

  • Freezing of new ABAP-Debugger

    Hi, every time when I try to use the new ABAP-Debugger I can just see the screen and then it freezes. I use SAP Web AS 6.4. SAP_BASIS SP17 and SAP_ABA SP17. Please help! Regards Christian

  • Availability in In

    When will the Zen X-Fi be available in India?

  • 2 Init with different selection

    Hi All, I want to run 2 inits on a single data source with different selections for that , after running the first init do I have to remove the init from the first package and then run the second package? Thanks. Tina

  • Order Type for Item Demo - Suggestion Required

    Hi Gurus, My client has a specific requirement of capturing items issued in Demo terms to their customers. The business process is that they issue an item, say a new photocopier to the customer for 15 days as demo. If the customer is satisfied, he wi