Record time through CATS on a process order?
Is it possible to record time through CATS on a process order?
This is a requirement from our customer.
No.
Production and process orders cannot be confirmed via CATS.
Similar Messages
-
PP-PI sheet through goods issue for Process order
Hi,
I want to know how to post goods issue without reference of reservation number against process order through PI sheet.
I defined one call function 'ENTER CONFIRMATION' through which I can enter into confirmation screen but after saving confirmation of process order ,generally I switched on to transaction CO54 through which one should sent this PI_CONS message to the desired destination but in that I'm getting an error ,that it is not allowing me to post goods issue excess quantity.(WITHOUT REFERENCE OF RESERVATION NUMBER)
how to by-pass that reservation number.
Manually when we do MB1A it will allow us to issue more quantity but that is manually but when it is through PI sheet it is not allowing me to issue excess quantity.
Regards,
Amit.Hi,
I want to do GI AND GR through PI sheet ,I already used PI_CONS AND PI_PROD ,but it is not allowing me to enter quantity excess from bom quantity mentioned .it is not allowing me to override reservation quantity while making gr .
I'm doing PI sheet with ALV based.
For to by-pass reservation number I already made zpi_cons and zpi_prod under message category and assigned to instruction category. -
User exit/BADI for Purchase requisition through release of Process order
Hi ,
i need to add some text to the Pur Req.
The Pur Req will be created THROUGH the release of PROCESS order. Please let me know any exits are available for the same.
regardsHi
Check the following Exits and BADI for Pur Requisition
Enhancement
MEVME001 WE default quantity calc. and over/ underdelivery tolerance
MM06E001 User exits for EDI inbound and outbound purchasing documents
MM06E003 Number range and document number
MM06E004 Control import data screens in purchase order
MM06E005 Customer fields in purchasing document
MM06E007 Change document for requisitions upon conversion into PO
MM06E008 Monitoring of contr. target value in case of release orders
MM06E009 Relevant texts for "Texts exist" indicator
MM06E010 Field selection for vendor address
MM06E011 Activate PReq Block
MMAL0001 ALE source list distribution: Outbound processing
MMAL0002 ALE source list distribution: Inbound processing
MMAL0003 ALE purcasing info record distribution: Outbound processing
MMAL0004 ALE purchasing info record distribution: Inbound processing
MMDA0001 Default delivery addresses
MMFAB001 User exit for generation of release order
MRFLB001 Control Items for Contract Release Order
AMPL0001 User subscreen for additional data on AMPL
LMEDR001 Enhancements to print program
LMELA002 Adopt batch no. from shipping notification when posting a GR
LMELA010 Inbound shipping notification: Transfer item data from IDOC
LMEQR001 User exit for source determination
LMEXF001 Conditions in Purchasing Documents Without Invoice Receipt
LWSUS001 Customer-Specific Source Determination in Retail
M06B0001 Role determination for purchase requisition release
M06B0002 Changes to comm. structure for purchase requisition release
M06B0003 Number range and document number
MEQUERY1 Enhancement to Document Overview ME21N/ME51N
MELAB001 Gen. forecast delivery schedules: Transfer schedule implem.
MEFLD004 Determine earliest delivery date f. check w. GR (only PO)
MEETA001 Define schedule line type (backlog, immed. req., preview)
ME590001 Grouping of requsitions for PO split in ME59
M06E0005 Role determination for release of purchasing documents
M06E0004 Changes to communication structure for release purch. doc.
M06B0005 Changes to comm. structure for overall release of requisn.
M06B0004 Number range and document number
Business Add-in
ME_PROCESS_REQ_CUST Enhancements for Processing Enjoy PReqs: Customer
ME_PROCESS_REQ Enhancements for Processing Enjoy PReqs: Internal
ME_PROCESS_PO_CUST Enhancements for Processing Enjoy Purchase Order: Customer
ME_PROCESS_PO Enhancements for Processing Enjoy Purchase Order: Intern.
ME_PROCESS_COMP Processing of Component Default Data at Time of GR: Custome
ME_PO_SC_SRV BAdI: Service Tab Page for Subcontracting
ME_PO_PRICING_CUST Enhancements to Price Determination: Customer
ME_PO_PRICING Enhancements to Price Determination: Internal
ME_INFOREC_SEND Capture/Send Purchase Info Record Changes - Internal Use
ME_HOLD_PO Hold Enjoy Purchase Orders: Activation/Deactivation
ME_GUI_PO_CUST Customer's Own Screens in Enjoy Purchase Order
ME_FIELDSTATUS_STOCK FM Account Assignment Behavior for Stock PR/PO
ME_DP_CLEARING Clearing (Offsetting) of Down Payments and Payment Requests
ME_PURCHDOC_POSTED Purchasing Document Posted
SMOD_MRFLB001 Control Items for Contract Release Order
EXTENSION_US_TAXES Extended Tax Calculation with Additional Data
ARC_MM_EKKO_WRITE BAdI: Enhancement of Scope of Archiving (MM_EKKO)
ARC_MM_EKKO_CHECK BAdI: Enhancement of Archivability Check (MM_EKKO)
MM_EDI_DESADV_IN Supplementation of Delivery Interface from Purchase Order
MM_DELIVERY_ADDR_SAP Determination of Delivery Address
ME_WRF_STD_DNG PO Controlling Reminder: Extension to Standard Reminder
ME_TRIGGER_ATP Triggers New ATP for Changes in EKKO, EKPO, EKPV
ME_TRF_RULE_CUST_OFF BADI for Deactivation of Field T161V-REVFE
ME_TAX_FROM_ADDRESS Tax jurisdiction code taken from address
ME_REQ_POSTED Purchase Requisition Posted
ME_REQ_OI_EXT Commitment Update in the Case of External Requisitions
ME_RELEASE_CREATE BAdI: Release Creation for Sched.Agrmts with Release Docu.
ME_DEFINE_CALCTYPE Control of Pricing Type: Additional Fields
ME_CHANGE_OUTTAB Enrich ALV Output Table in Purchasing
ME_CHANGE_CHARACTER Customer-Specific Characteristics for Product Allocation
ME_CCP_DEL_DURATION Calc. of Delivery Duration in CCP Process (Not in Standard)
ME_CCP_BESWK_AUTH_CH BAdI for authorization checks for procuring plant
ME_CCP_ACTIVE_CHECK BAdI to check whether CCP process is active
ME_BSART_DET Change document type for automatically generated POs
ME_BAPI_PR_CREATE_02
ME_BAPI_PR_CREATE_01
ME_BAPI_PO_CREATE_02
ME_BAPI_PO_CREATE_01
ME_BADI_DISPLAY_DOC BAdI for Internal Control of Transaction to be Invoked
ME_ACTV_CANCEL_PO BAdI for Activating the Cancel Function at Header Level
MEGUI_LAYOUT BAdI for Enjoy Purchasing GUI
ME_CHECK_ALL_ITEMS Run Through Items Again in the Event of Changes in EKKO
ME_COMMTMNT_REQ_RE_C Check of Commitment Relevance of Purchase Requisitions
ME_COMMTMNT_REQ_RELE Check of Commitment Relevance of Purchase Requisitions
ME_COMMTMNT_PO_REL_C Check for Commitment-Relevance of Purchase Orders
ME_COMMTMNT_PO_RELEV Check for Commitment-Relevance of Purchase Orders
ME_COMMITMENT_STO_CH BadI for checking if commitments for STOs are active
ME_COMMITMENT_RETURN Commitment for return item
ME_CIP_REF_CHAR Enables Reference Characteristics in Purchasing
ME_CIP_ALLOW_CHANGE Configuration in Purchasing: Changeability Control
ME_CIN_MM06EFKO Copy PO data for use by Country version India
ME_CIN_LEINRF2V BADI for LEINRF03 excise_invoice_details
ME_CIN_LEINRF2R BADI for CIN India - Delivery charges
ME_CHECK_SOURCES Additional Checks in Source Determination/Checking
ME_CHECK_OA Check BAdI for Contracts
Reward points if useful
Regards
Anji -
Time elements in process order
Hi,
Where does the system takes time elements from in a process order. After scheduling the time elements are entered in the process order. But where does the system gets the time elements from. Does the master receipi has a role to play in it?
Thanks and Regards,Hi Jyoti,
It depends upon that whether you are opting for lead time or basic time scheduling.........
It can take the value from the master recipe or the material master based upon the config done ..........
Do let me know if you have any further query regarding this.........
Please reward points help if helpful.......
Thanks
Kaushik -
User exit/BADI to for Purchase requisition through release of Process order
Hi ,
i need to add some text to the Pur Req. The Pur Req will be created through the release of PROCESS order. Please let me know any exits are available for the same.
regardsHi,
check the below enhancements in transaction SMOD.
CCOWB001 Customer exit for modifying menu entries
COIB0001 Customer Exit for As-Built Assignment Tool
COZF0001 Change purchase req. for externally processed operation
COZF0002 Change purchase req. for externally procured component
PPCO0001 Application development: PP orders
PPCO0002 Check exit for setting delete mark / deletion indicator
PPCO0003 Check exit for order changes from sales order
PPCO0004 Sort and processing exit: Mass processing orders
PPCO0005 Storage location/backflushing when order is created
PPCO0006 Enhancement to specify defaults for fields in order header
PPCO0007 Exit when saving production order
PPCO0008 Enhancement in the adding and changing of components
PPCO0009 Enhancement in goods movements for prod. process order
PPCO0010 Enhancement in make-to-order production - Unit of measure
PPCO0012 Production Order: Display/Change Order Header Data
PPCO0013 Change priorities of selection crit. for batch determination
PPCO0015 Additional check for document links from BOMs
PPCO0016 Additional check for document links from master data
PPCO0017 Additional check for online processing of document links
PPCO0018 Check for changes to production order header
PPCO0019 Checks for changes to order operations
Thanks
Sandeep
Reward if helpful -
Hi all,
I have create a process order manually by giving shedulling type current date and schedulle margin key is set with no floats...Now in schedulled date the operation is completed today,but the finish date is shown as tomorrows date....Can i know where is the setting to get the finished date the next date of operation....(Float periods in SMK is kept zero)
Regards,
Joseph.please go through the link for your answer
Re: How Basic start and end times are determined for a process order?
As perthe notes, The order finish date is set to 24:00.( means next day)
Edited by: Sundaresan . E. V on Sep 15, 2010 2:17 PM -
Delivered Quantity problem in Process Order
Hi,
I m facing a following situation:
Current Situation:
Process order # 10000
Order Qty 100
Del Qty 650
Order finally delivered
Using auto GR functionality
Usage decision has been posted for that batch
Delivery against sales has been made of that batch
Requirement:
Now, we realize 350 Pc's are produced against that process order number, we are in the situation to reverese all the entries but want to record the remaining qty in the process order
Your guidance will highly be appreciated in this regard.Hi,
Your query is not clear. After UD, you have made Outbound delivery also for the batch???
Also there is wrong practice, first of all your order qty is 100 but you have posted GR of 650. As per standard SAP, it is not recommended practice. You should post it as 100 only & if you want to post more qty against same order you should change Process Order qty to 650.
Further you have not specified why you want to reverse all activities? is this batch came back from customer i.e. customer complaint or any other reason? pls clarify.
Regards,
Tejas -
Release option in process order
dear sir
when i am create process orders.
at that time missing parts are in process order.
my request is any missing parts in process order, process order release option.
in my scenariao missing parts are in process order that order not released.
pls explain any missing parts in process order release option customizing setting.Hi,
if you do not want to Release your Process Order if there are missing components then follow as below:
In the Transaction : OPJK, for business Function 2, you can restrict the Order release if missing components exist by selecting the option "3" ( No release if missing parts).
Deselct "NO avail.check"; Box
Hope this helps..
Regards,
Siva -
Process order TECO cannot be done
Dear Gurus
When I am trying to do teco of a particular process order the message is coming like this.
System status CRCR is active (ORD 1000045)
Message no. BS013
Diagnosis
Object ORD 1000045 has system status CRCR (Control recipe created). According to this status, transaction 'Technically complete' is not allowed.
Procedure
You can only carry out the requested function if this is allowed according to the status of the object.
Please tell me how the staus crcr will allow teco
Regards
Sandip SarkarHi,
Please go through this link
TECO Process Order
Regards,
Suhas -
Phase/operation in process order 1000028 does not exist (please check entr
Dear All
Kindly help me out in the following scenario
I am entering confirmation through COR6N, after selecting process order no. system is giving this error when i click on actual data. However there is only one phase and one operation in master recipe. Furthermore earlier I ran MRP, generated capacity requirements, converted planned order into process order, dispatched process order via CM22-leveling and now i am trying to enter phase confirmation.
waiting for your response..
Regards
NavaidHi,
Please check your operation/phase control key in your recipe (C202), may be it will be PI07 (no confirmation).
If yes, you can enter the phase number manually in COR6N
Thanks,
JK -
Conflict between CAT2 and ESS Record Time
Does anyone know how to set up security to allow someone to record time through ESS while prohibiting that person from recording their own time through transaction CAT2 in ECC? Our Payroll Department uses CAT2 to record/correct time for the entire company, but they are prohibited from recording/correcting their own time through CAT2 due to SOD violations. Prohibiting them from recording their own time in CAT2, however, also prohibits them from recording their time through ESS. We've tried using two login IDs for each Payroll user, but that did not work because each would have to be linked to the user ID so you end up with two IDs that can either record their time through both CAT2 and ESS or neither. We're also aware of context-sensitive based security, but we've been told that would require redoing all of our security roles, so we're trying to avoid it. Does anyone know of another way to achieve what we're trying to achieve?
Why is time recording an SoD and if so why is ESS not an SoD?
Probably because the ruleset does not include the webservice but only the cat2 tcode... in which case you might as well create zcat2 which calls cat2 without skip first screen --> no SoD anymore...
Cheers,
Julius -
Process Order Material availability check error
Dear All,
At the time of i create the process order after that i push Material availability button system give me the following error log.
Please provide me the solution how can i resolved following Error.
"No control data maintained for checking group 01 and checking rule Z1"Dear,
Go to OPJK and maintain the setting for rule Z1 and group 01
Then go to OPJJ here select your plant and order type then Business funct.1 for order creation then in side assign checking rule Z1 and remove the tick mark for NO check then repeat same setting for Business funct.2 same rule and remove no check.
Then material master assign the same group after that create the order and check.
Regards,
R.Brahmankar -
Standard Value doesn't carried to Process Order Confirmation
Dear Experts,
I was trying to run Process Order Confirmation via COR6N but I found out that the Activities shown are NOT consistent with the Activities set in Master Recipe. The following are the figures shown in master recipe, process order and order confirmation.
Master Recipe (via C202)
Base Qty =1
Operation/phase = 0020
1st Standard Value (activity 3 setup) = 1Hr
2nd Standard Value (acitivity 1 machine) = 2Hr
3rd Standard Value (activity 11 labour) = 3Hr
Process Order (via COR2)
Order Qty = 1,000
Operation/phase = 0020
Setup (to be confirmed) = 1Hr
Machine (to be confirmed) = 2,000Hr
Labour (to be confirmed) = 3,000Hr
Order Confirmation
Operation/phase = 0020
Machine time (to be confirmed) = 1Hr
Labour time (to be confirmed) = 2,000Hr
My question are as follows :-
1) Why the Machine time NOT same as in Process Order
2) Why Setup time NOT shown in Order Confirmation
Does anyone have any idea?
regards,
AbrahamHi,
all the master recipe, process order and order confirmation, including the material master are maintained by myself alone.
Is it due to some parameters are not defined properly such as in the formula key?
The formula key are defined as below.
Formula key defined in OP21
Setup = SAP005 = SAP_01 x SAP_11
Machine = SAP006 = SAP_02 x SAP_09 / SAP_08
Labour = SAP007 = SAP_03 x SAP_09 / SAP_08
Paramater defined in OP17
SAP_01 = Setup
SAP_02 = Machine
SAP_03 = Labour
SAP_08 = Base Quantity
SAP_09 = Operation Quantity
SAP_11 = Operation Splits
I'm a bit confused with these formula keys. Could you explain to me how they work?
regards,
Abraham -
Error while updating the sales order through Process Order API
Hi,
Please any one will help plz.
I am updating the promise_date through oe_order_pub.process_order(Process Order API) i am getting the following error.
FND_AS_UNEXPECTED_ERROR N PKG_NAME OE_Order_Cache N PROCEDURE_NAME get_tax_calculation_flag N ERROR_TEXT ORA-01403:no data found
Please any one will help plz
Below is my code.
Declare
l_archive_file_name VARCHAR2(1000);
l_shipment_exists NUMBER:=0;
l_header_id NUMBER;
l_line_id NUMBER;
p_header_rec Oe_Order_Pub.Header_Rec_Type;
l_line_tbl oe_order_pub.line_tbl_type := oe_order_pub.g_miss_line_tbl;
l_header_rec OE_ORDER_PUB.Header_Rec_Type;
l_header_val_out_rec OE_ORDER_PUB.Header_Val_Rec_Type;
l_header_adj_out_tbl OE_Order_PUB.Header_Adj_Tbl_Type;
l_header_adj_val_out_tbl OE_Order_PUB.Header_Adj_Val_Tbl_Type;
l_header_price_att_out_tbl OE_ORDER_PUB.Header_Price_Att_Tbl_Type;
l_header_adj_att_out_tbl OE_ORDER_PUB.Header_Adj_Att_Tbl_Type;
l_header_adj_assoc_out_tbl OE_ORDER_PUB.Header_Adj_Assoc_Tbl_Type;
l_header_scredit_out_tbl OE_Order_PUB.Header_Scredit_Tbl_Type;
l_header_scredit_val_out_tbl OE_Order_PUB.Header_Scredit_Val_Tbl_Type;
l_line_rec OE_ORDER_PUB.line_rec_type;
l_line_out_tbl OE_ORDER_PUB.Line_Tbl_Type;
l_line_val_out_tbl OE_ORDER_PUB.Line_Val_Tbl_Type;
l_line_adj_out_tbl OE_ORDER_PUB.Line_Adj_Tbl_Type;
l_line_adj_val_out_tbl OE_ORDER_PUB.Line_Adj_Val_Tbl_Type;
l_line_price_att_out_tbl OE_ORDER_PUB.Line_Price_Att_Tbl_Type;
l_line_adj_att_out_tbl OE_ORDER_PUB.Line_Adj_Att_Tbl_Type;
l_line_adj_assoc_out_tbl OE_ORDER_PUB.Line_Adj_Assoc_Tbl_Type;
l_line_scredit_out_tbl OE_Order_PUB.Line_Scredit_Tbl_Type;
l_line_scredit_val_out_tbl OE_Order_PUB.Line_Scredit_Val_Tbl_Type;
l_lot_serial_out_tbl OE_Order_PUB.Lot_Serial_Tbl_Type;
l_lot_serial_val_out_tbl OE_Order_PUB.Lot_Serial_Val_Tbl_Type;
l_action_request_out_tbl OE_Order_PUB.Request_Tbl_Type;
l_msg_count NUMBER;
l_msg_data VARCHAR2(2000);
l_return_status VARCHAR2(1);
l_index NUMBER;
l_rows_processed NUMBER:=0;
l_line_mawb VARCHAR2(240);
l_line_hawb VARCHAR2(240);
l_line_flight_num VARCHAR2(240);
l_org_id NUMBER :=143;--FND_GLOBAL.ORG_ID;
l_resp_id NUMBER:=FND_GLOBAL.RESP_ID;
l_resp_appl_id NUMBER:=FND_GLOBAL.RESP_APPL_ID;
l_user_id number := FND_GLOBAL.USER_ID;
l_promise_date date;
BEGIN
SELECT ol.org_id, oh.header_id, ol.line_id,ol.promise_date
INTO l_org_id, l_header_id, l_line_id,l_promise_date
FROM apps.oe_order_headers_all oh, apps.oe_order_lines_all ol
WHERE ol.header_id=oh.header_id
AND ol.line_id =1319526; --&line_id
-- apps.fnd_global.apps_initialize(&l_USER_ID,&l_resp_id,&l_resp_appl_id);
apps.fnd_global.apps_initialize(67778,51017,660);
p_header_rec := OE_ORDER_PUB.G_MISS_HEADER_REC;
p_header_rec.header_id :=835035;-- l_header_id;
p_header_rec.operation := OE_GLOBALS.G_OPR_UPDATE;
l_line_tbl := oe_order_pub.g_miss_line_tbl;
-------------------------Line Record -------------------------------
l_line_tbl(1) := oe_order_pub.g_miss_line_rec;
l_line_tbl(1).header_id := 835035;
l_line_tbl(1).line_id := 1319526;
l_line_tbl(1).promise_date := sysdate;
l_line_tbl(1).operation := oe_globals.g_opr_update;
BEGIN
apps.oe_order_pub.process_order
(p_api_version_number => 1.0
,p_init_msg_list => fnd_api.g_true
,p_return_values => fnd_api.g_true
,x_return_status => l_return_status
,x_msg_count => l_msg_count
,x_msg_data => l_msg_data
,p_header_rec => p_header_rec
,p_line_tbl => l_line_tbl
-- out variables
,x_header_rec => l_header_rec
,x_header_val_rec => l_header_val_out_rec
,x_header_adj_tbl => l_header_adj_out_tbl
,x_header_adj_val_tbl => l_header_adj_val_out_tbl
,x_header_price_att_tbl => l_header_price_att_out_tbl
,x_header_adj_att_tbl => l_header_adj_att_out_tbl
,x_header_adj_assoc_tbl => l_header_adj_assoc_out_tbl
,x_header_scredit_tbl => l_header_scredit_out_tbl
,x_header_scredit_val_tbl => l_header_scredit_val_out_tbl
,x_line_tbl => l_line_out_tbl
,x_line_val_tbl => l_line_val_out_tbl
,x_line_adj_tbl => l_line_adj_out_tbl
,x_line_adj_val_tbl => l_line_adj_val_out_tbl
,x_line_price_att_tbl => l_line_price_att_out_tbl
,x_line_adj_att_tbl => l_line_adj_att_out_tbl
,x_line_adj_assoc_tbl => l_line_adj_assoc_out_tbl
,x_line_scredit_tbl => l_line_scredit_out_tbl
,x_line_scredit_val_tbl => l_line_scredit_val_out_tbl
,x_lot_serial_tbl => l_lot_serial_out_tbl
,x_lot_serial_val_tbl => l_lot_serial_val_out_tbl
,x_action_request_tbl => l_action_request_out_tbl
--dbms_output.put_line('l_msg_data-->' ||l_msg_data ||' l_return_status --> ' ||l_return_status);
END;
commit;
END;
Regards,
SanguHi Sangu,
See if the following notes help you:
Error when calling API from SQL*Developer, eg. ORA-01403 in API OE_ORDER_PUB.PROCESS_ORDER (Doc ID 1054295.1)
Cancellation Of Transfer Orders Is Not Possible - ORA-01403: no data found in Package OE_Order_PVT Procedure Process_Order (Doc ID 391307.1)
Thanks &
Best Regards, -
Automatic Reservation at the time of process order creation
Hi Experts,
As you are aware, when we create a process order and save, system automatically generates the reservation and the reservation will be for movement type 261. My requirement is like this. When system creates reservation, system should consider for which order type the process order is created and create a reservation for other movement type also.
For eg. Iam having order type ZRRW. When system creates reservation at the time of order creation, system should check the order type and reservation should be created for a movement type Z11 instead of 261 in the normal case.
Is there any user exit for the same. Please let me know.
Else how can I post the goods issue with a movement type other than 261. MIGO is not accepting other movement types.
Anticipating your reply
Regards
PrathibHi Ayethebing,
Thanks for the reply. we created the new movement types inorder to use the SAP standard reports and get the different types of goods movements based on the different processes.
We can do the goods issue using the custom movement type through MB1A. But I was trying to use in MIGO and this is where system wont allow this.
In MIGO, system will do the goods issue based on reservation only. The reservation is created at the time of order creation and it uses movement type 261 irrespective of the order type.
I was trying to find out whether any option is there to use custom movement type to create reservation so that system would propose this movement type in MIGO for goods issue against process order.
This is an interesting case but unfortunately dont have any option of user exit or Badi. Only one user exit related to reservation is to change the str loc and back flush indicator.
@Sabine: Thanks for your reply. But the BADI that you provided wont serve the purpose.
Thanks
Prathib
Maybe you are looking for
-
How many install can I do with one license of FCPX?
hi, if i have 3 MAC on my home, and i would use them, can I install and use at the same time?? Thanks Ruggero
-
How do I share more than one file at once in Adobe Creative Cloud?
How do I share more than one file at once in Adobe Creative Cloud?
-
Version 2.0 How Tos?
Hello, I'm looking for the How To examples for Version 2.0. Specifically the How to Upload and Download Files in an Application. I found the How To for version 3.0, but I'm having difficulty finding the How To for the version 2.0. Can anyone direct m
-
InDesign CS5.5. I can Select all unused styles but the option to delete and the trash can icom are grayed out and not selectable. What am I missing??
-