Reg:  Reversal of PM order confirmation

Hi All,
    Kindly let me know how to do the reversal of confirmation which we did in IW41??

Dear Sir
Please user IW45 Transaction coded for cancellation of Confirmation of PM order.
Regards

Similar Messages

  • Mass reversal of work order confirmations

    Hi all,
    Can we do a mass reversal of work order confirmations which we do through IW41 transaction,instead of reversing the confirmations one by one, if so please explain how.
    Thanks & Regards,
    Jegashree

    Dear,
    There is no mass confirmation cancellation Txn available in standard SAP.
    Use
    BAPI_ALM_CONF_CANCEL     Cancel confirmation for maintenance/service order
    Hope it will help you.
    Regards,
    R.Brahmankar

  • Reversal of Production Order Confirmation through IDOCS

    Hello all,
                  The time for each operation in a  production order is logged in KabaBEnzing tool called Autotime. This is sent to SAP through IDOCS and the order confirmation is created. There is a scenario where the supervisor could have entered the wrong time against an operation. Is it possible to reverse the confirmation through IDOCs. If yes, please let me know what should be the approach? Also, I heard that SAP does not accept negative time to do the reversal. How true is this?
    All helpful answers will be rewarded.
    Thanks,
    Kalyan

    Hello,
    I saw your message and we are doing the same thing.  Did you find any answers to your questions.   We are using Kaba for our shop system and now we would like to sent negative numbers back to sap because of supervisor adjustments.  I have not found any way to set Sap to allow it.  What conclusions have you came up with the situation.
    Thanks again,
    Jeff

  • Ristrict Cancelling Process Order Confirmation (CORS) after FI MM period cl

    Showing current date as posting date after Cancelling Process Order Confirm:
    Issue with FICO and PP :-, after settlement (ko88) and all period end closing, system still allowed doing Cancelling Process Order Confirmation (CORS) and Showing current data as posting data
    For example:
    My order created on 30th September 2010 and order confirmed on the same day ie my posted date (30th September 2010)
    I have done order reversal on 3rd October 2010 and posting date should be 3rd October 2010 but system showing current data as posting data. Can you please guide me why this unusual behavior happening

    Hi Arun
    Is this  congif change will help me
              1)In BS22 first search for TECO.
               2)Double Click on TECO.
               3)New entry.
               4)Now search FI posting.
               5)Select status as Prohibited
    My Requirement : Ristrict Cancelling Process Order Confirmation (CORS) after FI, MM period closed, and Materail Ledger done
    I want to ristrict the (CORS) reversal of Process Order Confirmation after FI MM ML closed
    right now as per standard its giving warning masage as " Posting with carent date YES or NO, if you say YES then system doing CORS on system carent date, i want to restrict it
    Is above steps you refered will help me
    please confirm
    Regards
    MKbinnal

  • Process order confirmation reversal

    HI friends,
    I am cancelling a process order confirmation using T-code CORS. The confirmation cancellation is happening, but the goods movements are not reversed. Help in resolving will be much appreciated.
    Thanks in advance.
    Warm regards
    Vivek

    Hi All,
    Sorry for the delay in response and thanks for your suggestions.
    The backflushing is activated. I checked in COGI transaction for the concerned order. I got several entries with different error text. The error text is as follows
    "You have no authorization for this transaction with movement type 102"
    "You have no authorization for this transaction in plant XXXX"
    "Deficit of SL Unrestricted-use 6,957 TO : 1030604 XXXX PL01"
    Please let me know how to resolve these errors.
    Warm Regards
    Vivek

  • Reg:Bapi for mass creation of production order/confirmation

    Dear Experts,
    I wanted to know with the following BAPI is it possible to create Multiple production orders for different semifinshed Materials along with material availability check and other functions similar to CO01 transaction.
    I knew there are standard transactions for mass confirmation for production orders. But i need a confirmation on this BAPI . As i am planning to go-ahed with ,mass creation of production order creation / Order confirmation in single custom transaction.Need back flush activity even supported.
    BAPI_PRODORD_CREATE to create the orders.
    BAPI_PRODORD_RELEASE to release the orders.
    BAPI_PRODORDCONF_GET_TT_PROP to get the default data for the confirmation.
    BAPI_PRODORDCONF_CREATE_TT to ost the confirmation of production order.
    Along with this BAPI do i need to commit any other BAPI to carry out back flush for components.
    Need your suggestions to take it further.
    Regards,
    Daya.

    Dear SAP Daya
    If the issue has been solved, please close this thread.
    You have already mentioned that the issue has been resolved, thefore, you should not ask for help on another thread before closing this one, as it looks like you are trying to force people to answer your threads.
    Users are always trying to answer as many threads as possible on good will we don't need this kind of "incentive".
    Please read carefully the The SCN Rules of Engagement, especially point 8:
    Be responsive. If an SCN member has answered your question, please mark the answer as "helpful” or “correct”. Mark the discussion as “answered,” so that other members can find the answers more easily
    Also, I checked your old threads and I could observe that there is only one closed. Please review your old threads and close those already solved.
    BR
    Caetano

  • PM order confirmation cancellation -reg

    Hi ,
    Using IW45 transaction code , we can do PM order confirmation cancellation by giving one by one order . Is there any other T code where we can give multiple orders as input and do confirmation cancellation for multiple orders at a time ? or LSMW is the only way ?
    regards,
    Madhu kiran

    Hi,
    Go to T.Code IW47, execute with inputs as the order nos/ confirmation nos  whose confirmation you want to cancel and execute. You will get a list display. Then select the confirmations you want to cancel (multi selection) and click on cancel button available at top. System will give a warning msg. Just ignore and cancel all the documents.
    Else you may also go for an LSMW program.
    Regards,
    S.Basu

  • Reg: "Production order confirmation details" table name..

    Hi,
    what is the table name for the production order confirmation details..
    Regards,
    Pavan.

    Hi
    It is the
    <b>AFRU</b> table
    <b>Reward points for useful Answers</b>
    Regards
    Anji

  • Cancel or reverse the process ordrer confirmation posted in a closed period

    Hi SAP experts,
                              It would be very nice of you if you could solve this issue for me.
                              The issue is -
                               There is a process order created and released for a material on 01.07.2010.Partial confirmation for the order was done on 15.07.2010 but the posting date was entered as 14.06.2010.So the stock for the material got posted on 14.06.2010 which was supposed to be posted on 14.07.2010. Now, if we try to cancel the order confirmation in the current month through CORS , system is giving errors because the posting period is closed .
                               Is there any way to reverse the postings without opening the posting period?
                               How we can open the field for the posting date in the transaction CORS where we can assign new posting date for the cancellation of the order confirmation. Is it possible to enter this new posting date as 01.07.2010 now because the posting period for July is currently open?
    Best regards,
    RAB

    The reason for reversal is that - the goods receipt on the date 14.06.2010 should tally with the goods receipt for the process order created for the month of June 2010 on that particular date as per the daily production report developed for client. In this case, only one process order is created for a material for each month and that is confirmed daily as per the daily production and then confirmed and settled finallly at the end of the month.
    Now the requirement is that the excess goods receipt posted in June 2010 for the process order created for July 2010 should be reversed so that the goods receipts for the June's process order on that particular date for that material match properly.
              Actually , to compensate for this wrong posting done  by the user on 14.06.2010, another confirmation for the same order of July 2010 was done for that material with same qty. with correct posting date(14.07.2010) so that the goods receipts for July 2010 for the material for that process order are proper.
             I am sure you must have clearly understood the issue. Is it possible to cancel the the order confirmation done with posting date 14.06.2010 by giving new posting date as 01.07.2010? Whether this will display proper stock for the material in June as well as July? Kindly confirm.
    Best regards,
    RAB
    Best regards,

  • Goods receipt during reversal of production order

    Hello ALL,
    I use production orders confirmation with Aut.goods receipt.
    Example is the following:
    I confirm 3psc of production order for semi-finished product, so system posts 3pcs with 101 movement type.
    Production order status is DLV
    Then 1 pc is consumed for the next production step, it means the physical stock is now 2 pcs.
    In the next step I want to reverse the confirmation of  production order with movement type 102 ( I use CO13 )
    I get message in COGI - Deficit of  unrestricted-use - 1pc and I am not able to reverse goods receipt at all. Production order status is still DLV. Reversal of material document is impossible.
    I know it is reasonable but my question is: is it possible to reverse goods receipt only partially during CO13 - for 2 pcs and get production status PDLV ???
    I know the sulution is to return missing 1 pc, but I would like to avoid this
    thanks for help
    KS

    dear KS,
    as far as i know...
    ...every confirmation entered in the system can be canceled : if you entered three confirmations (just an example) for an operation, you can also cancel three confirmations and all confirmations automatically created by them
    1. you can change confirmations or partially cancel them;
    2. if you also activate user statuses when confirming an operation, these statuses are not automatically canceled when you cancel the confirmation;
    3.if you cancel a confirmation, the functions that were triggered by a trigger point are not revoked (for example, creating a rework operation).
    good luck!

  • Change Work Center during production order confirmation

    Dear All,
    I must to modeling this situation:
    I created an production order. In routing I used an work center A.
    After I confirmed a half of quantity, the work center A was damaged and I must to change it, with the work center B.
    The system allow this change, but when I checked the costing, the situation isn't real. The system counted the costs just for the work center A, and no for work center B.
    My question is: it's possible to change the work center, during production order confirmation and the costs updated with new cost?
    Thank you for your answer!
    Regards,
    Marian

    once a Order is released, the Process order detaisl for that order is frozen.
    however if you want to do it, change the order status to CRTD after reversing the Movements done.
    Do READ MAster data , this will copy the new Work center , redo the previously done Moevements.
    if the change is long term.
    or
    Just manually add the new work center and do the processing. if the change is temporary.

  • Price difference on cancellation of production order confirmation

    Hi,
    We are having a material which is maintained at price control "S". We have created a production order for the material. In due course of business, we did confirmation for say 100 pcs of the material. However, immediatly on confirmation, we realized that we do not need to do the confirmation & hence we did the cancellation of the production order confirmation using CO13.
    On doing the production order confirmation cancellation, we observed that the system has posted some amount to "price difference account"
    We also observed that once in a while this kind of entries do get posted.
    It is requested to please let us know in why system is behaving this way?
    We have checked SAP Note no 216080 "Price difference when reversing GI for S-Priced material" & SAP Note no 215980 'Price difference during GR for the production order". However we are not convinced that these could be the reason for the price difference.
    Thanking you in anticipation
    Regards
    Santosh Kumar Agarwal

    Hi,
    Yes, you are correct in the understanding that the system creates quants in 914 when the production order confirmation is cancelled. But, it does not generate any TR or TO in the background to post the stock back into the original storage type.
    Can we not use the put away strategies so that the system determines where to place the material? My query is that despite all the configurations for automatic TO creation and confirmation for movement type 262, it does not generate a TO (or TR) in the background when a production order confirmation is cancelled using CO13.
    However, if I manually post a material using MB1A for 261 movement type and reverse it using 262, it generates a TO and confirms it as per the setting in configuration.
    The same thing does not work when we run it through PP (CO11N and then CO13).
    Any suggestions on how to approach this and where to check for missing configurations?
    Thanks and Regards,
    Gaurishankar

  • Cancellation of Production Order confirmation (CO13) not generating TR/TO

    Hi,
    We are facing a typical issue in the PP-WM interface. When we create an order and confirm it (partial confirmation), the Goods movement happens (261 mvt type) as desired and the TO is created and confirmed in the background.
    But, when we try to reverse the movement type (cancelling the production order confirmation using CO13) then there are no TRs or TOs generated in the background (for movement type 262).
    When I manually try to post a material document for 262 movement type, it creates a TO in the background (as per the configurations that I maintained) but this does not happen when movement type 262 is called using PP interface.
    The movement type configurations are all done for Automatic TR and TO generations - this works with normal IM process (when we manually post using MB1A transaction) but not with the return Goods movement happening with PP.....here, the material comes back to the interim storage type 914. We then need to create a TO manually and confirm it to take the stock back in to the original storage type and bin.
    We want that when a process order confirmation is cancelled then the materials should be posted back in to the original storage type and bin (from where the material was issued against the order).
    For Info: COGI shows no errors during the 262 movements, also, material document is generated for 262 movement type but no TR/TO generated.
    Is there any configuration that we have missed?
    Thanks and Regards,
    Shankar

    Hi,
    Yes, you are correct in the understanding that the system creates quants in 914 when the production order confirmation is cancelled. But, it does not generate any TR or TO in the background to post the stock back into the original storage type.
    Can we not use the put away strategies so that the system determines where to place the material? My query is that despite all the configurations for automatic TO creation and confirmation for movement type 262, it does not generate a TO (or TR) in the background when a production order confirmation is cancelled using CO13.
    However, if I manually post a material using MB1A for 261 movement type and reverse it using 262, it generates a TO and confirms it as per the setting in configuration.
    The same thing does not work when we run it through PP (CO11N and then CO13).
    Any suggestions on how to approach this and where to check for missing configurations?
    Thanks and Regards,
    Gaurishankar

  • Need help on Production order confirmation cancel issue

    Hi,
    I need your help regarding Prduction Order issue.
    We have created Production Order and issued raw materials and we done paritial confirmation also. Now the order status is PNCF.
    After that we notice that it was wrong confirmation so we went CO13 we cancel those confirmations.
    But in our zprogram still those order is showing as paritial confirmation order.
    I need in which SAP table confirmation status stored and what will be the production order status after cancel the confirmation.
    and in which table cancel production order confirmation data will be availiable.
    please guide me
    sateesh

    HI,
    There is No Standard Status for Reversing or cancelling the Confirmation.
    Generally, When you confirm the status PCNF or CNF gets active.
    When you reverse it theybecome inactive.
    also let us know, whether You cancelled or reversed the confirmation or revesed the GI postings.
    If you have reversed the GI postings using Reverse Movement type or Materail documents, it is possible to have the PCNF order status unchanged.
    Regards
    Ratan
    Edited by: Ratan on Aug 28, 2009 7:23 PM

  • Production order confirmation issue

    Hello,
    When we are trying to reverse the production order 262 happened , 102 didn't occurred. No COGI update
    Afterwards we didn't confirm the order as well as we cannot reverse the existing order also. Some data inconsistency happened. 
    Can anyone recommend any sort of trouble shooting or any OSS notes ?
    Thanks,
    Nic

    Dear Nick ,
    Please chek the set up in OMJJ-Cluster Maintaince-Movement Typ 102  is allowed  for production order reversal 262 movement type  in Allowed Trancstion /Update Control .
    Analysis and revert back .Hope this will help you even after appling the OSS Notes : 175842.
    Regards
    JH

Maybe you are looking for

  • Performance degradation: unfetched field [PublishingPageContent] caused extra roundtrip

    Hi All,    I am facing some serious application pool crash in one of my customer's Production site SharePoint servers. The Application Error logs in the event Viewer says - Faulting application name: w3wp.exe, version: 7.5.7601.17514, time stamp: 0x4

  • How to restore a backed up iTunes library from discs?

    I had backed up my iTunes library a while ago (more than a couple years) on CDs as Apple "demanded" at the time.  Now I find that I need to restore my library to iTunes on the computer, and lo and behold, restoration doesn't work in the same manner a

  • AIR auto update error, and question about POST parameters

    Hello, I'm getting a Download Failed error in the AIR autoupdating process; There was an error downloading the update. Error# 16822 I recall this working once, the very first time that I tried it. My app.xml file contains this line:     <version>12</

  • Can I set a role using a encrypted password ?

    Sir, I encrypt the role password using dbms_obfuscation package. Can I enable a role using such a password before decrypting it ? Thanks a lot Stephen

  • Smpte time code off in FCP X - LPX xml transfer