Regarding Costing in External processing operation in production Order

Hi Everybody,
We are trying to do sub contracting through external processing operation in production order. In brief, we are creating a production order which contains just one operation and when the prod.order gets released, it creates a purchase req through external processing operation. Pur.Req is being converted to Pur.Order with all the Raw's which we are going to send to Sub Contractor..
The costing issues we are facing are
1. First we receive GR against Pur.Order, once its done, the Raw's which we sent to Sub.Contractor will be backflushed.. but we dont receive the Finihsed part until we confirm the production order.... there is a Gap between this two processes.. so how can we make sure that there wont be any differences in terms of FI..
2. Second issue is, some times even if we ordered 10 pcs, subcontractor can only send 5pcs and 5 pcs afterwards.. but every month end FI dept tries to close the books, so how can we deal with this issue if i receive 5 pcs in this month and remaining 5 in the next month...
If any body dealth with this kind of situation.. your hints will be really valuable,
Adavnce thanks
srikanth

Dear Srikanth,
Please note the following:
1. First we receive GR against Pur.Order, once its done, the Raw's which we sent to Sub.Contractor will be backflushed.. but we dont receive the Finihsed part until we confirm the production order.... there is a Gap between this two processes.. so how can we make sure that there wont be any differences in terms of FI..
  - a) Issue your raw materials through T.Code. - MB1B, Mvt. Type - 541. This will transfer materials from your stock to vendor stock (provided you have initiated vendor material provision and activated 541 mvt. type for PP)
    b) After you receive the material back from vendor, run the T.Code MB01, which will cause Mvt. Types 543 and 101. Now the material has come back to your Production order, but not in Storage location stock.
   c) Then carry on normal CO11N and MB31 for your production order.
Hope this will solve your problem.
Revert back if you still have any question.
Regards,
Angshuman Kar

Similar Messages

  • Externally processed operation and planned order

    Hello experts,
    When an operation is defined as externally processed, once the production order (from a planned order generated via MRP) is created, the purchase requisition for that operation is automatically generated. My question is if it is possible to generate the purchase requisition before generating the production order, I mean, with the planned order.
    Although this external operation is defined in the routing, the planned order does not show it and it means that the purchase requisition is not generated.
    In our scenario we want to convert the production orders as late as possible to have automatic changes in BOM, but if we do not convert the planned orders to production orders, we won’t have this purchase requisitions.
    Is there any way to solve this?
    Regards

    Hi Laura
    No, it's not possible to generate the purchase requisition for an externally processed operation before the creation of the production order. The planned order routing is only exploded for scheduling and capacity requirements calculation and an operation is not actually created.
    As an alternative, you can create a separated material number and assign the special procurement 30 for subcontracting to this material. If you add this component to the BOM of the parent material, MRP will directly generate a purchase requisition for subcontracting.
    BR
    Caetano

  • Tracking of wip material in externally processed operation

    Hi All,
    As part of production process, most of the operations would be processed internally in the manufacturing plant and some of the operations would be
    performed by vendor at his own premises (outside the manufacturing plant). Material will be called as WIP (work in process) material if it completes some of the operations (two operations completed out of four operations) in production process without forming its final product shape
    WIP (work in process) material will be sent out to vendor against externally processed operation in production order. We’ve a business requirement to track the WIP (Work in Process, No inventory yet in system) material status details such as when was the WIP material shipped out to service provider by purchasing department or returned back to production floor from stores after receiving from vendor for externally processed operation in production
    order
    The scenario is explained below and the process in SAP would be as follows.
    1. Production order would be created for
    respective header material (semi-finished/finished) with required quantity with five operations to be processed, for example: OP10 (turning), OP20 (drilling), OP30 (milling), OP40 (shaping), OP50 (powder coating). OP10, OP20, OP40, OP50. would be processed internally in the shop floor of the manufacturing plant
    2.After finishing the internal processing at OP10 and OP20,  Operation no 30 (OP30-milling) for the respective header
    material would be processed externally by sending the partially processed part(WIP) to vendor outside the manufacturing plant. In SAP, the partially processed part doesn't have any material code and will not be updated in the inventory and will be treated as WIP (work in process) and automatic purchase requisition for external processing through production order is generated as follows
    For OP30 Milling (Externally processed operation), from PP module perspective, we would be maintaining a control key which supports external
    processing in the Operation 30 (OP30, external processed operation - An externally processed operation is not carried out within own organization, but is assigned to a vendor, who then does the work) with relevant information such as material group, purchase group, description of operation, cost element to track costs in the production order.
    When the respective production order is saved, system creates a purchase requisition for external processed operation 30. We can see
    the number of the purchase requisition on the external processing tab of operation details screen of OP30 in SAP Production order.
    Purchasing department generates a purchase order against the automatic purchase requisition generated in production order, which informs the
    vendor which service is required.
    With reference to the purchase order – service oriented, the WIP material (no material code exists in SAP) is sent out to vendor. After the material has been processed, the vendor delivers the material back to manufacturing plant. When a goods receipt against purchase order is posted at manufacturing plant, the system displays the received quantity on the external processing tab of operation details screen of the operation - OP30 in production order and also displays in order information system reports. It also possible to track the cost incurred for external operation. However, Goods receipt against production order does not cause an increase in the quantity and value of the warehouse stock of header material of production order.
    The above mentioned process is not a subcontracting process - where in we send raw materials and receive semi-finished/finished materials from vendor
    3. The respective partially processed part (WIP) received from vendor is sent to shop floor to complete the rest of the process
    in OP40 (shaping) and OP50 (powder coating).
    4. After OP50, the respective header material (semi-finished/finished) of the production order will be received (goods
    receipt against production order) as inventory in respective storage location.
    With reference to the above process, we can track the status of receipt of WIP material from vendor after processing at his premises;
    however, we can’t track when WIP material ( after completing processing at OP20) was sent out to vendor for external processing by purchasing department and when WIP material was returned back to production shop floor for further processing at OP40 after receiving from vendor by stores.
       Please provide your feedback for the possibility to track the details of WIP material (no material code exists in SAP system) sent out to
    vendor and received back at shop floor from stores for external processed operation of production order
    Thanks for help in advance.
    Regards,
    Rajesh

    Hi Rajesh,
    Process what ever you have explained is the right process with respective to operation wise subcontracting as per SAP Best practice. As you rihtly said in operation wise subcontracting PR is created with any material code. Once PR is created after PO and GR actual cost of that particular operation will be seen on the order. I believe sub contact operation after GR can be confirmed through confirmation transactions. Since it is subcontract operation specfic to peration seperate inventory is not tracked instead cost is reflecting directly on order
    If you to want to track the inventory of the intermdiate product then you need to have a seperate material code for intermediate product (Eg A) received after second operation and do seperate subcontacting PR for seperate new material (Eg B) by issuing the intermediate material (Eg. A). Upon receivng GR for PO inventory will be updated for the new material (Eg B).This new material can be issued to your final product which has operation 0040 and 0050. Here two different material codes will be required.
    Else follow the suggestion given by expert Caetano.
    Thanks & Regards,
    Ramagiri

  • Need Schedule Lines for the External Processed Operation

    Dear All,
    In My routing, I have totally 10 operations. 2 of which are externally processed Operations.
    When i create Production Order, the system creates Purchase Requisitions for both the Operations.
    My client wants, Schedule lines to be created in the Production Order Operations.
    Please guide me where will be the settings to get this.
    Thanks & Regards
    Bala

    Hi,
    For schedule lines cofigration kindly check the following Path:
    Material management--  Purchasing--
    Schdulling agreement
    Here you need to do the cofigration of the following as per your requirements:
    Number ranges
    Docuemnt types
    Release procedure
    Screen layout ( if required)
    Authorization check for GL Account
    Regards,
    Syed

  • Error in Externally Processed Operation

    Dear Experts,
    I am setting up "externally processed operation".  I have created the purchase info record & the control key is PP02.  When I release the production order, I get the following error.
    Material class differs from material class  from info record
    Message no. 06354
    Diagnosis
    The material class or material group of the info record differs from that of the item.
    Procedure
    Check the material class or material group entered, or the info record number.
    The material group is same in the material & purchase info record.  I have also maintained the same class in the material (Class type 001) & purchase info record (Claas Type: 057).
    Do I need to make any other settings?  Kindly advice.
    Regards
    Tom

    why don't you use PM02 key?
    an operation can only be processed externally if its control key allows or prescribes external processing
    just in case: since an external operation has to be sent to a different company, additional data needs to be maintained on the 'External processing' tab page. You can maintain the data in the routing or in the production order
    you said that "I have also maintained the same class in the material (Class type 001) & purchase info record (Claas Type: 057)" - what is the 057??

  • External process operation

    hi
    how to inspect external process operation which are given for  subcontracting, how to reject the operation which was done by subcontractiong
    regards
    Baswa

    Dear Raj,
    Inspection of external process is done in the same way as of internal one.
    Please check the following:
    1. You must make sure that the operation control key in the production order specifies external processing.
    2. You must activate a goods receipt inspection for the operations to be processed externally by:
          a. Specifying an inspection type (inspection lot origin 01) in the routing (external processing data for the operation)
          b. Activating this inspection type in the material master of the final product
    Regards,
    Alok Tiwari

  • Confirmation of external processing operation

    Dear All,
    I would like to know is it possible to prevent the confirmation of an external processing operation (pp02 control key) until the Purchase Order associated with that operation is received (GR) ?
    I checked the forum for this, but was unable to find any inputs & also in customizing where i find only settings for confirmation of orders & not at operation level.
    Hope my problem is clear, await inputs.
    Regards,
    Vivek

    Yes,
    it can be done but no through std SAP setting...but with user exit.
    Check this exit
    CONFPP03  PP order conf.: Cust. specific check after op. selection
    CONFPP04  PP order conf.: Customer specific input checks       
    CONFPP05  PP order conf.: Customer specific enhancements.

  • Goods Issue To Each Operation Of Production Order?

    As we know, in SAP ,when we create and realse the production order,we could posts good issue to the production order ,using MB1A. And in SAP , the components can be assigned to the operations of the finished product.
    But in our company, the production order will take long time,and during production,different materials will be used in different phase of the production order,that means different components will be used for different operations.
    And for some reason,we don't want our material to be backflushed during production.
    So I want to ask can we post goods issue to each operation of the production order,not to the whole production order? Can SAP support Post Goods Issue To Each Operation Of Production Order?
    What shall we do if we want do this?By ABAP development ? Or there is third party software
    can do this with SAP? 
    Thanks for any reply!
    Edited by: Fei Liu on Mar 14, 2009 4:56 PM

    Hi Fei,
    As explained above, i think the concept of releasing the individual operations instead of releasing the order at header level would work fine for your requirement.
    Steps:
    1. Go to operation page in co02.
    2. Select the first operation, at the bottom of the screen you would find a Green Flag, click on the same.
    3. You will now find that the status of the first operation has changed to REL, while the others are still not.
    4. At header level you will find a status PREL, indicating partial release.
    5. After completion of the first operation, confirm the same & select the second operation & click release, & the process follows in this manner
    6. Please do not click the green flag at the header level as this will release the entire order.
    Pre-requisite:
    1. You have assigned components to the respective operations.
    You might also want to consider the usage of trigger points. This you can assign to each operation, where-in if the status changes to CNF, you trigger the release of the following operation. But before opting for this flow, first do it manually to ensure it meets your need.
    Also if the components assigned to the same operation, needs to be issued at different date, then you can use the lead time offset in BOM. In cs02, go to item details, here you can specify the same. Eg: If your operation stats on 15th March & you want this component to be issue only on 17th March, then specify the offset as 2. But if you want the components to be issued 2 days in advance of 15th march, then specify as 2-.
    Hope the above helps.
    Regards,
    Vivek

  • In process Quality for Production orders

    Hi Guys,
    I am facing issues while doing an in process quality for production order.The usage is In process quality,
    can anyone help me to carry out a flow for this usage type.
    What are the necessary settings to be done and also explain the workflow for this inspection type.
    Thanks,
    Krishna

    Hi,
    For in process quality you have to activate "03" type quality in the QM view for the material.
    After creation of the order you have to generate inspection lot and based on the inspection lot you have to do result recording.
    After that you will do the GR followed by usage decision of the inspation lot.
    Hope this will help.Please elaborate the details for further clarification.
    regards,
    kaushik

  • Specific process code for Production order message type LOIPRO

    Hello,
    Is there any specific process code for Production order message type LOIPRO.
    Request you to reply.
    Thanks
    Prashanth

    Hi Prashanth,
    sorry for last thread ... that not contain full information ...
    For message type LOIPRO you can use process code APLI.
    In IDOC PARTNER definition, the partner is linked with an IDOC TYPE and PROCESS CODE for inbound processing. This process code is in turn linked with a FUNCTION MODULE to process the IDoc such as IDOC_INPUT_INVOIC_MRM (Reff..  http://searchsap.techtarget.com/expert/KnowledgebaseAnswer/0,289625,sid21_cid519558,00.html)
    Regards,
    Amit

  • GR for production order post to cost center and not to the production order

    Hi all,
    when we post the goods receipt for the finished product against the production order (mov. type 101), the order is not credited with the corresponding stock value. Instead of this, the value accounts to a cost center.
    We specified this cost center in OKB9 (Default account assignment), because if not, we get an error when posting the goods receipt cause of lacking accounting object.
    I can't see why the system does not credit the production order?
    Any ideas?
    Thanks for your time
    Daniel

    Hi Daniel,
    This is the first time i am coming across an issue like this.
    neverthless from a logical front,
    1. Remove Cost center as a valid receiver in Settlement Profile.
    2. Your OKB9 setting are pretty much good. No need to worry about it.  Becasue, OKB9 only will work if the system doesn't identify any other cost object. In this case Production Order is an automatic cost object which system should have taken.
    3. Check the Settlement rule when you have created Production Order. It should have been MAT.
    4. I hope you are creating Production Order with Material (using CO01 and not CO07)
    5. Make sure in OPL8, the default rule in controlling tab is PP1.
    Once all these are fine, i do not see any reason why you will get your probelm.
    Please check and revert back to me if the problem still persists.
    Best Regards
    Surya

  • Operation on production order - what is the object (BOR) to manage it ?

    Hello,
    I have to call a workflow when an operation on production order is confirmed, or partially confirmed, or deleted.
    What is the business object to use to manage it ??
    Tks,
    Roberto.

    Hello Uma,
    yes, right...
    yesterday, I was not able to see the trace when I deleting a production order becuase the object BUS2005 was not
    active on customizing:
    after I found it
    No business object triggered for production order creation
    end now is showed...
    SO, we have to use BSVW ... and so the consequences is : How to know what is the object BOR to activate !??!?!
    tks

  • Externally Processed Operation

    Hi All,
    I want to perform end-to-end cycle for externally processed material. Please provide link or document having step-by-step guideline.
    I got following error:
    I have performed following steps:
    1) In the routing control key maintained which is externally processed (PP02)
    2) Purchase Info record (ME11) maintained with 'Subcontracting' item category
    3) While creating production order if I select that purchase info record then it prompts me an error "Material class differs from material class  from info record"
    Purchase Info record is created with 057 class default. The same class is not available under material classification.

    Raja Sekhar.S wrote:
    Hi,
    >
    > In external Processing
    >
    > you will not create Production order you have to Create purchase order for the material
    >
    > In this case you will create Purchase order on the material which you would receive but you will be sending different semi finished material. (because you will be sending one material and after the operation it will convert to other form)
    > you should create separate BOM for the material which you will be receiving after external operation
    > You have to  create work center with Control key=PP02
    > with 521 movement type you can send the material to vendor
    >
    >
    > Regards,
    > Raj
    Hi  typing error
    Actually  movement should me 541 instead of 521
    regards,
    Raj

  • Control key for external process operation & internal.

    Hello,
    We have created one control key (ZP01) T code OP67.
    In the customisation (OP67) for "External processing" selection field we select "X" i.e. "Internal processed operation / Extarnal processing possible.
    If this field is blank then it is a "Internal operation"
    If this field is "+" Then it is external operation, in this case system creates the purchase requisition after release the production order.
    We want to know,
    If this field is with "X", then what is the proceedure to create the purchase requisition for external operation.
    Thanks in advance.
    Best regards
    Nilesh

    Hello Brahmankar,
    Thanks for your prompt detail reply.
    As per your suggestion already we have that setting for another controll key (PP02)
    It is std for SAP it is working fine, in this control key the setting is "+" for external proceesing in OP67.
    Now my requirement is instead of "+" I made it "X" i.e. Internal processed operation / External processing possible. In this case system is not generating purchase requisition after production order release.
    I want to know for external processing whether I have to create purchase requisition manualy?
    or any other process we have to follow?
    Thanks & Regards,
    Nilesh..

  • Standard Cost from External Process

    Hi Experts.
    I have a finished goods procured from other plant, need to send for additional process
    I want capture the cost for additional process without Purchase Info.
    I  maintained the price details  in the routing external process tab.price unit & net price.
    But while doing the CK11N it is not picking these cost element.
    Pls explain what would be the additional setting I suppose to do.

    Dear Sriram,
    Check what costing variant are you using in the initial screen of CK11N,now take this costing variant
    and check in OKKN--->(click on)valuation variant--->(Click on )Ext.Processing and check the priority
    defined,only if the value is set as price from operation,then the system picks up the value maintained
    in the routing(operation),also ensure the costing relevancy is set in the control key of that particular
    operation.
    Check and revert back.
    Regards
    Mangalraj.S

Maybe you are looking for

  • How do I find the pixel size of a photo?

    I have taken a photo or found one online. It's now on my ipad. How do I tell the pixel resoution of the photo via the ipad? I have two of the same photos on my device at the moment and want to delete one.  They may both be 2048/2048, but without emai

  • Report for PO history

    Hi, Whether any standard report is availble to display the PO, item, qty, value, GR , value , qty, IR , value , qty ( PO history ) in a single report. Please expedite. Regards, R. Dillibabu.

  • How can I get the tabs back where they belong beneath the address bar , NOT on top ???

    how can I get the tabs back where they belong beneath the address bar , NOT on top ??? they are on top, which puts the address bar at a variable position depending on how many tab rows exist - makes a moving target for navigating to across my dual 24

  • How to refer to the class in the regular function module

    Hi ABAP guru's I wish to get details of GET_REQUID parameter of method IF_RSBK_REQUEST_GENERAL that is available in class CL_RSBK_REQUEST. I am writing a ABAP function module and I wish to use this class in that function module. Can someone help to w

  • Foreign trade data default

    while doing export billing, foreign trade data is not getting defaulted, how do we get the data like means of transport and domestic mode of transport etc., where do we have maintain these data to get defaulted in billing document thanks