Regarding project activity scheduling based on the personnel resource

hello all,
I need one help from you guys. Before explaining the problem let me tell you all the scenario. We are implementing Project system Version ECC 6.0. We have a requirement of our client that the activity duration to be changed according to the availablity of the personnel resources attached to it. We don't have HR implementation here. I have already tried with the  help of calculation key setting to 'calculate Duration' to get the activity duration automatically. But customer wants as per the availability of the personnel, activity duration should get adjusted.
Thanks in advance
sudhir kesarkar.

Hi,
I do not think it is possible. SAP's logic is to do capacity planning based on the 'work' and 'activity duration'. Hence the requirement of deciding "activity duration' based on available capanity (read man power) is just the opposite of the fundamental logic.
Further, project, by basic defintion, is an entity with definite start and end dates. Hence if you allow available capacity to decide the duration of activity and consequently the project duration, the project end date becomes indefinite and a totally dependent entity.
I do not think any system will support it.
This, I want to clarify, is based on my limited understanding, and not based on any SAP documentation
Muraleedharan.R

Similar Messages

  • How to create activity workflow based on the Web API 2 services

    Hi,
    We have Web API 2 services and we want create activity workflow based on the Web API 2 services.
    Web API 2 services provide some application operations and based on this operations we would like to create custom activity workflow.
    Question:
    Is that possible?
    Could you please give best practices to create activity workflow based on the Web API 2 services ?
    Thanks for your support.

    HI Max_P,
    Welcome to workflow forum.
    ASP.NET Web API is a framework that makes it easy to build HTTP services that reach a broad range of clients, including browsers and mobile devices. ASP.NET Web API is an ideal platform for building RESTful applications on the .NET Framework.
    I researched relevant topic about creating workflow application using Web API 2, I just found these resources about it.
    Learn About ASP.NET Web API
    Hope it helps.
    Best regards,
    Angie
    We are trying to better understand customer views on social support experience, so your participation in this interview project would be greatly appreciated if you have time. Thanks for helping make community forums a great place.
    Click
    HERE to participate the survey.

  • Activity RTE based on the employee Sal who's Time will be captured in CATS

    Hi All,
    I have a scenario to calulate the Activity Rate  based on the employee Salary who's Time will be captured in CATS.
    Eg: One Employee working 2hrs in Admin dept,4 hrs for Rec dept, & 4 hrs for HR dept generally costing will take place on the fixed price from the controliing side. In Our scenario the activity rate should be calculated on the Employee salary we found one user exit Using an SAP enhancement (CATS0002). need to explore on this  before that  If any one has some good solution or suggestion please suggest.
    Regards,
    Raghu Kumar R

    hi
    you can do the coding in the said user exit , and have the hourly rate calculated by taking data from infotype 8 , 14,15, etc where ever the releavant fixed salary components you are maintaining.
    But the issue would be if you go for retro accounting for any of the employees , the cost uploaded in the existing items would remain uneffected also if there are some adhoc earnings that are given later point in time after the rate calculation for a particular day has already been done and data has been passed to co or ps etc. There would be definately a issue for the change in master data happening at later point in time.
    You may consider using some third party solutions which are available for this purpose.
    Regards
    sameer

  • Process order scheduling based on in-house production time.

    Hello!
    I have following problem. My SAP system is configured in that way that process oedrs are schedulled based on times saved in master recipies. When I input data to in-house production time in master data for materials and make new process order, this time is not
    taken into account.
    Where I have to change configuration to use in-house production time from material master data to make scheduling process orders.
    Regards
    Bogdan

    Dear
    Process Order /Production Order scheduling ( Lead Time Scheduling )  based on the Operation timings in the routing not based on the Material Master In house Production Time in Work Scheduling View .
    If you are loking for Basic Date Scheduling then it will happend based on material master , scheduling margin key  at material master level .
    It depends the selection of Schedueling indicator while excetion of MRP in MD02 .
    In case of Process order specifically , you need  to schedule the Master Recipe and check whether operations are getting scheduled, if it is not then you need to first the problem, which may be because of wrong "Forumla" or paramater assigned in resource or the resource is not maintained for Finite scheduling (capacity header).
    Master reciepe can be schedule in the change transaction C202, and from menu you would find the option to schedule the recipe .
    Also  check the OPU3/OPU5-Define scheduling parametres wether scheuling , adjust scheduling , scheuling type , logs all are in place .
    Check and revert
    Regards
    JH

  • Could I update the schedule date by the add-in software OpenPS?

    I create the R/3 PS WBS using the add-in software OpenPS from MS Project at the beginning. But according to  our company working business , I can't update the WBS schedule date by  updating the activity schedule date under the WBS, i can only update the WBS schedule. (so I have done some set-up and set the duration of every activity is zero).  I hope I can update the schedule date by the add-in software OpenPS from MS Project during the R/3 system is online running(NOT the beginning). 
    We know the adjustment of schedule in MS Project is very easy and convinent.  So if I adjust the schedule  in MS Project, and I update the schedule in R/3 PS by the add-in software, then everything will be good.
    But  maybe this operation will have a bad effect on the running R/3 system.
    Please give me some advice and practice experience.

    Hi Sanjay,
    You really MUST try things BEFORE saying that they are wrong.
    The CDHDR table DOES store the creation date AND time because the system treats the creation as a Change.
    If you simply enter ME51N as the transaction code in SE16N for table CDHDR you will see that it is YOU that is wrong.
    Please do try to verify your comments before challenging Seema in this way, who has provided a good and workable solution.
    Steve B

  • Creating Outbound deliveries based on the sales order schedule lines

    Dear all.
    Is it possible to create outbound delivery documents based on the sales order schedule lines?
    Eg:
    Let's say I have sales order line item 10 with below mentioned requested delivery dates in its schedule line level.
    30.07.2009
    10.08.2009
    20.08.2009
    30.08.2009
    Will it possible for me to create different deliveries for those 4 schedule lines individually? I should be able to create 10.08.2009 delivery without clubbing 30.07.2009 delivery with it.
    Appreciate your help!

    I'm not sure because I'm not before SAP but try transaction VL10E that is to create delivery for schedule lines. I'm not sure what are the split criterias.
    Please check OSS note 113411 tha has many OSS note reference in this subject.
    Regards,
    Csaba
    Edited by: Csaba Szommer on Jul 29, 2009 2:38 PM

  • Triggering a scheduled event based on the approval status

    Hi,
    I have created schedules for my project (one task and one milestone) with three phases(draft,approval,approved). The milestone is dependent on the task.Task is created for draft phase and milastone for approval phase
    Now after creating the schedules when I have saved the project, even before i put my project in the draft phase the schedule is getting triggered and can be seen on the workbench in the events channel.
    That means the schedules are getting triggered based on the date irrespective of the task or milestone being completed and also the schedule for a task needs to be triggered each time until the task is completed.
    So now I want accomplish two things -
    1. How can I trigger the schedule only when the user puts it in the draft phase or any required phase ?
    2. How can I send a mail to the collaborator each day until he proceed the project to approved status and only on getting "approved" status the milestone schedule should be triggered.

    Both would require scripting...
    on phase change, add the required events
    build a custom class that gets called nightly via scheduled task and searches through the projects meeting your criteria and sends them an email reminder.
    -Howie Wexler
    www.craftysystems.com

  • I have a task, that is i want to retrive the details from active directory based on name and i want show that details into grid view.

    Hi All,
    I have a task, that is i want to retrive the details from active directory based on name and i want show that details into grid view.
    Can any one help how to start.
    Thanks in advance!

    Hi AnilKarthik,
    You can get user details by name using DirectoryService namespace. Then you can create a DataTable to restore the information and then bind to the SharePoint GridView.
    Here are some deatiled code demos for your reference:
    how to get userdetails from Active Directory based on username using asp.net:
    http://www.aspdotnet-suresh.com/2011/03/how-to-get-userdetails-from-active.html
    How to get User Data from the Active Directory:
    http://www.codeproject.com/Articles/6778/How-to-get-User-Data-from-the-Active-Directory
    Using SPGridView to bound to list data in SharePoint:
    http://nishantrana.me/2009/03/23/using-spgridview-to-bound-to-list-data-in-sharepoint/
    Best Regards
    Zhengyu Guo
    TechNet Community Support

  • HT201472 can apple disable any activity on my stolen IPAD based on the serial number

    can apple disable any activity on my stolen IPAD based on the serial number

    No.
    What To Do If Your iDevice Is Lost Or Stolen
    If you activated Find My Phone before it was lost or stolen, you can track it only if Wi-Fi is enabled on the device. What you cannot do is track your device using a serial number or other identifying number. You cannot expect Apple or anyone else to find your device for you. You cannot recover your loss unless you insure your device for such loss. It is not covered by your warranty.
    If your iPhone, iPod, iPod Touch, or iPad is lost or stolen what do you do? There are things you should have done in advance - before you lost it or it was stolen - and some things to do after the fact. Here are some suggestions:
    This link, Re: Help! I misplaced / lost my iPhone 5 today morning in delta Chelsea hotel downtown an I am not able to track it. Please help!, has some good advice regarding your options when your iDevice is lost or stolen.
      1. Reporting a lost or stolen Apple product
      2. Find my lost iPod Touch
      3. AT&T. Sprint, and Verizon can block stolen phones/tablets
      4. What-To-Do-When-Iphone-Is-Stolen
      5. What to do if your iOS device is lost or stolen
      6. 6 Ways to Track and Recover Your Lost/Stolen iPhone
      7. Find My iPhone
      8. Report Stolen iPad | Stolen Lost Found Online
    It pays to be proactive by following the advice on using Find My Phone before you lose your device:
      1. Find My iPhone
      2. Setup your iDevice on iCloud
      3. OS X Lion/Mountain Lion- About Find My Mac
      4. How To Set Up Free Find Your iPhone (Even on Unsupported Devices)

  • How to get the personnel plan work schedule

    Hi,
    I write a report ,need get the personnel plan work schedule of the input month.
    for example:
    at input screen : I input : 2007-01  and pernr:10000001;
    I hope get the plan work schedule days (rusult :25 work days)of  the  person 10000001  at  January 2007 .
    Now I find some HR TM functions ,such as :
    HR_PERSONAL_WORK_SCHEDULE
    HR_PERSONAL_WORK_SCHEDULE_PNP
    but I don't know how to test , I had try many times ,but not get what I want . so I want to know if have any other function can make me get what I want .

    Hi Olivia,
    tables: ptpsp.
    parameters:
    pernr type pa0001-pernr,
    begda type pa0001-begda,
    endda type pa0001-endda.
    data:
    i_ptpsp type table of ptpsp.
    <b>CALL FUNCTION 'HR_PERSONAL_WORK_SCHEDULE'</b>
           EXPORTING
               <b> PERNR             = PERNR
                BEGDA             = BEGDA
                ENDDA             = ENDDA</b>
              KUG               =
              REFRESH           = 'X'
              WORKING_HOURS     = 'X'
              SWITCH_ACTIV      =
              MODIFY_ENTRIES    = 'X'
              I0001_I0007_ERROR = '0'
         IMPORTING
              WARNING_OCCURED   =
           TABLES
              I0000             =
              I0001             =
              I0002             =
              I0007             =
              I0049             =
              I2001             =
              I2002             =
              I2003             =
      <b>          PERWS             = I_PTPSP</b>
         EXCEPTIONS
              ERROR_OCCURED     = 1
              ABORT_OCCURED     = 2
              OTHERS            = 3
      IF SY-SUBRC <> 0.
    MESSAGE ID SY-MSGID TYPE SY-MSGTY NUMBER SY-MSGNO
            WITH SY-MSGV1 SY-MSGV2 SY-MSGV3 SY-MSGV4.
      ENDIF.
    table <b>I_PTPSP</b> is having all the data u needed..

  • Editing the Schedule PDP, at the Page Details Web Part, inserted wrong Project Web App URL. Cannot access Project Schedule Pages.

    I need a help. The environment, SharePoint and Project Server 2013 and SQL Server 2012, running on Windows Server 2008. Editing Details Web Part in a Schedule PDP Page, saved invalid Project Web App URL. After that, can display the Project Information and Project
    Details Pages from the projects accessed, and can display the Project site, too. But, when I access the Project Schedule Page, receive an error page, because of the invalid URL. The message is obvious: "There
    is no Web named xxxxxxx". I´ve tried to find out how to correct this, but no success, because cannot open the Project Schedule page anymore.
    I would like to know if there is some way to fix it without re-installing the system. Thanks for all. If somebody need more information, have log information and page display available. 

    Paul,
    When I click Schedule after PWA Settings > Project Details Page, there comes the error.
    I can download the Schedule Page. But I don't see where to change, because the wrong URL doesn't apper at the page. 
    I'm sending below the page that I can download. The schedule.aspx.
    <%@ Page language="C#" MasterPageFile="~masterurl/default.master" Inherits="Microsoft.SharePoint.WebPartPages.WebPartPage" %>
    <asp:Content ContentPlaceHolderId="PlaceHolderPageTitle" runat="server">
    <SharePoint:ListProperty Property="Title" runat="server"/> - <SharePoint:ListItemProperty Property="BaseName" maxlength="40" runat="server"/>
    </asp:Content>
    <asp:Content ContentPlaceHolderId="PlaceHolderPageTitleInTitleArea" runat="server">
    <WebPartPages:WebPartZone runat="server" title="loc:TitleBar" id="TitleBar" AllowLayoutChange="false" AllowPersonalization="false" />
    </asp:Content>
    <asp:Content ContentPlaceHolderId="PlaceHolderAdditionalPageHead" runat="server">
    <meta name="GENERATOR" content="Microsoft SharePoint" />
    <meta name="ProgId" content="SharePoint.WebPartPage.Document" />
    <meta http-equiv="Content-Type" content="text/html; charset=utf-8" />
    <meta name="CollaborationServer" content="SharePoint Team Web Site" />
    <script type="text/javascript">
    var navBarHelpOverrideKey = "wssmain";
    </script>
    </asp:Content>
    <asp:Content ContentPlaceHolderId="PlaceHolderSearchArea" runat="server" />
    <asp:Content ContentPlaceHolderId="PlaceHolderPageDescription" runat="server">
       <asp:literal id="idPageDescription" runat="server" text="<%$Resources:PWA,PAGE_DESCRIPTION_SCHEDULE%>" />
    </asp:Content>
    <asp:Content ContentPlaceHolderId="PlaceHolderPageImage" runat="server"></asp:Content>
    <asp:Content ContentPlaceHolderId="PlaceHolderLeftNavBar" runat="server"></asp:Content>
    <asp:Content ContentPlaceHolderId="PlaceHolderNavSpacer" runat="server"></asp:Content>
    <asp:Content ContentPlaceHolderId="PlaceHolderMain" runat="server">
    <WebPartPages:WebPartZone runat="server" Title="loc:FullPage" ID="FullPage" FrameType="TitleBarOnly"/>
    </asp:Content>
    <asp:Content ContentPlaceHolderID="PlaceHolderUtilityContent" Runat="server">
    </asp:Content>
    Thanks
    LuisPerez

  • Editing the Schedule PDP, at the Page Details Web Part, inserted wrong Project Web App URL. Now, cannot access Project Schedules.

    I need a help. The environment, SharePoint and Project Server 2013 and SQL Server 2012, running on Windows Server 2008. Editing Details Web Part in a Schedule PDP Page, saved invalid Project Web App URL. After that, can display the Project Information and
    Project Details Pages from the projects accessed, and can display the Project site, too. But, when I access the Project Schedule Page, receive an error page, because of the invalid URL. The message is obvious: "There
    is no Web named xxxxxxx". I´ve tried to find out how to correct this, but no success, because cannot open the Project Schedule page anymore.
    I would like to know if there is some way to fix it without re-installing the system. Thanks for all. If somebody need more information, have log information and page display available. 

    Luis,
    Have you tried this?
    Navigate to the schedule PDP, in the browser address bar, append the string
    ?Contents=1, like thus:
    https://<your PWA Address>/Project%20Detail%20Pages/Schedule.aspx?Contents=1
    This will open the Webpart Maintenance page. Now, select the Details
    webpart, and Delete it. Once done, navigate bacjk to the webpart page, edit page, and re-add the Details Webpart to the page.
    This should fix your issue.
    Cheers,
    Prasanna Adavi, Project MVP
    Blog:
      Podcast:
       Twitter:   
    LinkedIn:
      

  • Is there any way to revert back to the old Active X based Datasheet view?

    Hello,
    Is there a setting I can check to use the old Active X based Datasheet view from 2010? If not, then is there a way to have the new 2013 Datasheet view display more than 30 items per line? I clicked display all in the view settings and it displays 30
    items and gives me a little arrow at the bottom to get to the next set of 30. My list has close to 800 items and I want to edit them on one page without having to scroll to other pages. Its more user friendly that way

    > use the old Active X based Datasheet view from 2010
    No way I know of.
    But you can edit the view and set the item limit to a large number. One of my lists has 672 items and I can display them all in a single Quick Edit view.
    Mike Smith TechTrainingNotes.blogspot.com
    Books:
    SharePoint 2007 2010 Customization for the Site Owner,
    SharePoint 2010 Security for the Site Owner

  • OTL Approvals routing based on the project and task type

    We are implementing OTL with Projects in our system.
    We have about 200 projects each with a different project manager. The requirement is to route billable tasks to project managers and non billable tasks to HR Supervisor. Employees may enter time for both billable and non-billable tasks in the same timecard.
    I tried using fast formula approval style, but it does not split the timecard data based on the chosen project - task. All the time entries are sent to the same approver.
    I tried using 2 time categories(using 2 user defined valuesets). However it seems ELA will not work when have different project managers for projects in the same time category.
    Please suggest a way to implement approvals for this requirement

    The best approach here would be a custom Workflow.

  • How to schedule report filtered by dynamic date based on the date the Agent runs

    Hello
    I have a question about delivering report using OBIEE agent.
    If i am running an agent today to deliver report A, can I get report A based on Last Monday's date or any dynamic dates?
    For example, say today is Dec 18th 2013 and my agent is running according to how I set the schedule. Now the deliver content will have report A being delivered. Now report A has a date column, normally this column is filtered by current date. But if it's delivered through agents to various users, Report A's data should be the previous Monday, so in this case Dec 9th 2013. When this agent is run again said on Dec 27th 2013, then report A should be filtered by Dec 16th 2013, which is the previous monday of Dec 27th.
    Can something like this be achieved in OBIEE 11G?
    Thanks in advance.

    Yala,
    Not a straight forward way
    1) Let the report run through Agent with Current Date filter
    2) once it ran for the first time you can see IBOT name/last run time(LAST_RUNTIME_TS) in  S_NQ_JOB
    Create a repository variable 'last_run_agent' using below sql to get max(LAST_RUNTIME_TS)
    select max(LAST_RUNTIME_TS) from s_nq_job where name = 'AGENT_NAME';
    Edit the analysis report with current date filter and modify the filter condition accordingly to filter on newly created repository variable
    Thanks,
    Saichand

Maybe you are looking for

  • Inbound LOIPRO01

    I have a problem with an interface between third party and SAP R/3 system. I have to send an IDOC from third party system to SAP R/3 to create a production order. Can somebody help me? I don’t know how I can to test it (we19), what configuration I ha

  • Weblogic LDAP startup problem

    We are runnign BEA weblogic server 8.1 sp2 on windows 2000 machine. It starts up fine but after some days the service is stopped. If I try to restart it, it doesn't start but shows the following exception. <main> <<WLS Kernel>> <> <BEA-000364> <Serve

  • Project and its Cost center

    Hi All, For a particular Project, how to find the corresponding Cost Center? I believe teh relation between Project and Cost Center is through a common object Work Center. Then how to get from Project>Work Center>Cost Center? Regards Pavan

  • 1Z0-147 Quiz

    Hi, I have come across 1Z0-147 Quiz on www.proprofs.com but i am not sure if this quiz is not a braindump. I haven't tried it yet but like to know if this is a braindump or not? I have checked the status of www.proprofs.com on certguard and it says i

  • Oracle 9i - SP2-0735

    I'm trying to install Oracle 9.2.x on Windows XP Professional. The install gets to the point of running the Oracle Data Configuration Assistant and bombs out with a large exection stack trace. While its running I see a whole bunch of command line box