Regarding Re-sechduling of planned order date

Dear SAP Guru
                            For a  finished material The stock is being zero, although it has  fixed ;lot sizes of 500, and safety stock of 2000.I have run MRP today.The stock of finished material is being 0. It has in In-house production time as "1" day.After runnung MRP the system is displaying the planned start date as 16/08/2011, in the past. Could any among us why this abnormal behaviour.
Thx
Bhupendra Singh

Hi,
check the settings in OPU5
And also you can check the settings in MRP paramters OPPQ.
And also check in MRP Group Paramters OPPR.
Thanks,
JK

Similar Messages

  • How to trace planned order data after it has been converted into production

    Hi, There,
    The planned order has been converted into production order.
    However, I need to trace if this planned order is generated by MRP
    run or created manually. I can't get any planned order info from
    table PLAF. Any input?
    Regards,
    Nancy

    Hi,
    Once fully converted, the Planned Order data will not be available in the Table : PLAF.
    If it is available, then You can have the details with the Time Stamp and User data from PLAF.
    But, the refrence will be available in the Production Order.
    You want to make a Track of the Planned Order details and the Quanity, then you need to have/create Z tables so that the data will be availabe.
    This is how most of the Organizations keep a track of the Planned order data.
    Hope this helps..
    Regards,
    Siva

  • Confirmed date in sales order influenced by planned order dates

    Hi,
    My requirement is that the after the MRP is carried out and planned order is generated, the changes in the dates of the planned order, when carried out, shall accordingly influence the confirmed date of the sales order line item when the availability check is carried out in the sales order.
    Say, the sales order has confirmed a line item for 25.05.2009. Once the MRP is carried out and planned order is generated and owing to unavailablility of a component, the planned order date (finish date) is manually re-scheduled to say 28.05.2009. My requirement is that the sales order confirmed date shall accordingly be re-scheduled when the availability check is carried out.
    Additional Info : Strategy Group - 20,
                           Make-to Order scenario is employed,
                           Standard Item category TAN,
                           Requirement Class - 040.
    Is this possible in standard SAP? If not, please suggest any custom developments that may be required. Looking forward for helpful replies.
    Do revert back if more info required.
    Regards,
    Anil Kumar

    Hi Anil,
    As Suggested in Above reply to your question.
    If Materail component was not available and due to that you had to reshedule the planned order date manually, that definately will affect the material availability date, but i think if material availability will be run once again in Sales Order it will determine the new material availability date, and i dont think there is any need to carry out any enhancement.
    Guru's Please correct me if I am wrong.
    regards,
    Paresh

  • Issue about planned order date of ROH.

    Hi Experts,
    In MD04 , system is displaying planned order date of ROH after the planned order date of FERT i.e., for FERT---- planned order date is 21/01/2009 But for ROH -
    planned order date is 23/01/2009.
    can anyone tell me y its happening here.
    regards,
    sap pp
    Edited by: sap  pp on Jan 22, 2009 11:42 AM

    Dear,
    Go to the BOM of FERT and check the in component details and check Lead-time offset. Make it blank
    In OPU3 and OPU5 Adjust dates in lead time scheduling should = 1 Adjust basic dates to order start date.
    Then run the MRP in MD02 with planning mode 3 deleted and recreated and check your result.
    Regards,
    R.Brahmankar

  • Planned order dates

    Hi Guru's,
                  please explain how the planned order dates are calculated.
    in MTS scenario if a delivery exists and another planned order is raised the system is not calculating dates as per dates given in the Material master.it is cheduling the order depending on the previous delivery date.
    Please explain me How it is calculating the dates in planned order
    Thanks
    Satya

    Hi,
    The scheduling is based on your MRP parameters. If you select the basic dates scheduling while running MRP, the system will consider the material master in house production time. It will not consider the routing standard values.
    If you select the lead time scheduling, the system will explode the routing and it will calculate the operation time based on the standard values which we have maintained in the routing.
    Always there will be some difference between these two type of scheduling. Lead time scheduling will be more accurate than the basic date scheduling.
    Regards,
    V. Suresh

  • Process Orders and Planned Orders data

    Hi,
    I am working on extracting process order and Planned Orders data into BW. I could not find any standard DataSources available for my req, so I want to develop generic extractor. the main key figures are Actual Labor and Machine Hours, Target Labor and Machine hours.
    Please help me if there are any standard datasource available or ECC tables to pull the data or any standard function modules available.
    Thanks,
    Reddy

    Hi Sanath,
    Thanks for your reply. I want to pull Actual Machine hours, Target Machine hours, Actual Labor hours and Target Labor hours.
    these fields are not there in PLAF table.
    I am looking for a table or datasource which can give those details.
    Thanks,
    Reddy

  • SNP Planned Order Date

    Hi Experts,
    May I ask for your help. I have a gr processing time of 1 and In-house production of 1 day as well. But whenever I run heuristic, it results in 4 days from start date to availability date. Say April 16 start date and availability date is April 20. Are there other factors on how this is computed?really hoping for a reply from you.
    Thanks! Sincerely, Ria

    Hello Ria,
    Have you maintained any GR time in ECC?
    I faced a similar issue (in PPDS order though) in which it was computing the availability date
    first based on the GR processing time maintained in APO, when the order goes to ECC it would pick up the GR processing time maintained in ECC, and move the availability date of the order in APO.
    We are working on code to stop this transfer back to APO.
    Note 508993 gives more details about the FM.
    You may try an option to stop the transfer from SAP R/3 since you are working with SNP planned orders:
    https://help.sap.com/saphelp_scm50/helpdata/en/80/e8bc0f629af14db213108bb6fa7515/content.htm?frameset=/en/b3/32c5d32970834dadf53cac0aa2b5b4/frameset.htm&current_toc=/en/9b/954d3baf755b67e10000000a114084/plain.htm&node_id=147
    Hope this helps you!
    Regards,
    Subhash

  • Wrong Planned Order dates - MRP Run

    Dear Experts,
    Please guide to resolve the following problem:
    I have uploaded the PIRs for 3 months. When I take the MRP run, the system is scheduling the planned orders for first 2 months only. For the 3rd month's PIR the planned order are created for the PIR dates only. 
    For example, if the PIR (for 3rd month) is maintained on 25th of the month. The planned orders for FG & SFGs are being created for 25th only. While for 2 months the Planned orders are properly scheduled.
    What could be the reason for such behavior.
    The planning horizon is 90 days.
    Regards,
    Rohit.

    Dear Rohit,
    If you are running MRP with NETPL, then the Lead time scheduling will be carried out only for the planning harizon.
    Try executing MRP you can select NETCH key.
    or
    If you want to run MRP with NETPL key, then please give In-house production time in workscheduling view as per the routing values. For example 1 day is the processing time and give the quantity for for 24 hr production. Then the sceduling will be carried out as per this values.
    And change the planning harizon for detailed scheduling in OPU5 transaction.
    Thanks and regards
    Murugesan

  • Planned order date on requirement date

    Hi ,
    My indepenedt req is maintained for monday .By backward scheduling it gets planned on friday(i.e production endson friday)
    How i can schedule the production to take place in current week . That is for PIR entered on monday , the production should be planned in the current week.
    Are there any settings in lot size   ?
    Regards
    ShankarR

    Hi,
    PIR date is the requirement date.
    When you run MRP with this date, the system checks for Avaialble Stock and receipts and does the Net requirement calcualtion.procurement selection, BOM explosion and scheduling.
    When it comes to scheduling, it looks for the requirement date and schedules it based on the scheduling parameters maintained for the Planned orders.OPU3
    You can set the scheduling type as  it forward or Current date scheduling .
    If you set the Current date scheduling, the system will consider the start date as today and does the scheduling, if after the scheduling the availability date is past the requirement date anexception message is raised.
    Hope this clarifies , please revert if you need any details.
    regards
    Ratan

  • Regarding deletion of firmed planned order

    Hi PP Gurus,
                 I want to delete the firmed planned order of header & component materials. Scenerio is after the mrp runs the planned orders are created and automatically gets firmed. Now sitation is that system contains the firmed planned orders for the past period,  with the firmed requirments for the dependent requirment( Components). Now system has a plenty of unnecesary of requirments that in actual is not present. Problem is planned order for the header materail & components are firmed. So that it cannot be changed during the planning run.
                Client wants to see in MD04 only those requirements which are actually present. Can u tell me how can i delete the firmed order. If i manually delete the firmed order of header material in next MRP run requirment not showed for the header but still the requiment for components is showing, That is the main problem .
    Thanks in advance
    ACP

    Hi,
    It will use only if you use MRP group in material master MRP1 view.
    Goto OPPR by entering strategy group ex. 0010
    In that Check Consumption mode & Define roll forward period.
    Input the no of days in roll forward period to delete the old firmed planned order created before.
    So all the firmed planned order will get delete in the next MRP run.
    Regards,
    Dharma

  • Weekly Lot-sizing yielding incorrect Planned Order dates

    Hi All,
    need a help..
    Lot-sizing key = W2 (weekly)
    "Scheduling" on the config of the lot-sizing key = 3 (Period start := start and period end := delivery date). This data has been maintained for a material that is to be planned/produced on a weekly basis.
    Requirement --- Weekly planning on my material. MRP should return Planned Orders with Start Date = Reqt Date (of the Dependent reqt) & End date = Availability date (of the dep reqt).
    Currently, the system is calculating the "only" hours on the basis of the Routing data (I'm running Lead Time Scheduling) while creating Planned Orders during the MRP run against my expectation of spanning the production/order out over multiple days (per the lot-sizing config)
    Any clue would be of a great help
    cheers

    Thanks Mario,
    Had found that out during the course of my testing. I'm doing a Lead Time Sched, so obviously my reqt can't be met..
    So, we can conclude that though a weekly lot-sizing procedure is/could be compatible with LTS, the Config within the lot-size (field Scheduling = 3) cannot be used to influence the dates on the created Planned Orders...
    Cheers

  • BAPI to change components data of planned orders?

    Hi,
    Currently we are using BDC to change components at planned orders.
    Due to big data volume, we have performance issue now. Just checked
    if there is any BAPI to replace BDC. But can't find proper one. Anyone has
    any expeerience about changing components at planned order?
    Thanks.
    B. Regards,
    Nancy

    Hi,
    It's planned order due to biz requirement.
    B. Regards,
    Nancy

  • Planned order Basic dates

    Dear All,
    The sales order was input by the CSR on today the delivery date entered in the order was next day. Therefore, the planned order should have been todayu2019s date. This would give us enough time to manufacture the product and deliver to the customer as requested.  But the planned get created for next day.
    Planning strategy for material is 40 and MRP type is PD and Lot size EX and all scheduling parameters are 0 day.
    Can you please update me the factors from sales order which affect planned order dates.
    Regards,
    p983331

    Hi
    Basic dates depends on GR processing time, in house production time and opening period
    In the material master two types of in house production times are available:
    Lot-size Independent - (Integer values only) MRP 2 orWork Scheduling view
    Lot-size Dependent - (real numbers - decimal) Work Scheduling view
    also check SD processing time (pick/pack, Load, Transit)
    regards
    Dev

  • Planned Order creation date

    Hi,
    Please let me know where can we find out the date the planned order was created. In which table and which table it is tored. I have tried in table PLAF. Unable to find out this.
    Regards,
    V. Suresh

    hi
    Please try
    PLAF and Field PEDTR
    Order start date is Basis start Date  in the planned order.
    If you go to Det Scheduling tab of planned order in a Planned order there option Basic Dates , there are two dates Start and Finish ... these are the dates required by you......opt for  Help Window it Shows you a Description :           "Order finish date in the planned order
    Date, according to the planned order, that you should expect either the completion or the delivery of the planned order quantity."
    BV

  • Planned Orders and Process Orders Data Extractor

    Hi,
    I am working on extracting process order and Planned Orders data into BW. I could not find any standard DataSources available for my req, so I want to develop generic extractor. the main key figures are Actual Labor and Machine Hours, Target Labor and Machine hours.
    Could you please help me if there are any standard datasource available or ECC tables to pull the data or any standard function modules available?
    Thanks,
    Hanuma

    hi,
    hope the mfg datasources were useful.
    chk the LBWE -> application 4 -> chk the DS 2lis_04_P_arbpl,2LIS_04_Matnr etc...
    All R/3 Tables
    http://www.sap-img.com/sap-download/sap-tables.zip
    Generic Extraction
    https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/84bf4d68-0601-0010-13b5-b062adbb3e33
    http://help.sap.com/saphelp_nw04/helpdata/en/3f/548c9ec754ee4d90188a4f108e0121/content.htm
    LO Extraction:
    /people/sap.user72/blog/2004/12/16/logistic-cockpit-delta-mechanism--episode-one-v3-update-the-145serializer146
    /people/sap.user72/blog/2005/01/19/logistic-cockpit-delta-mechanism--episode-three-the-new-update-methods
    /people/sap.user72/blog/2005/02/14/logistic-cockpit--when-you-need-more--first-option-enhance-it
    /people/sap.user72/blog/2004/12/23/logistic-cockpit-delta-mechanism--episode-two-v3-update-when-some-problems-can-occur
    /people/sap.user72/blog/2005/04/19/logistic-cockpit-a-new-deal-overshadowed-by-the-old-fashioned-lis
    Ramesh

Maybe you are looking for

  • Send email from OWB with authenticated SMTP server (AUTH_LOGIN)

    Hi all, I want to send email from Oracle Warehouse Builder 11.2.0.2 using a SMTP server with basic authentication (AUTH_LOGIN). I've created an ACL for OWBSYS user according to note ID 1229769.1 in support.oracle.com. But, I need to configure again t

  • GL Account opening balance & closing balance

    Hi Experts, We have loaded the infocube 0figl_c10. Our report requirement is as follows: Input variables: Fiscal year: 2010 Company code:xxxx GL Accoutn: X Expected Output 000.2010 - Opening balance, Debit, Credit, Closing balance 001.2010 - Opening

  • How can i use bapi in my report program

    hi am new to this forum , i have doubt in bapi's how can i call bapi into my report program and what is the difference between normal function module and bapi, and bdc plz clear my doubts Moderator message: please search for available information/doc

  • Officejet 7780 slow printing

    I have an Officejet 7780 on a wired network with 3 PC's. Printing is exceptionally slow (minutes to print a page of normal type). Any ideas?

  • How to upload non itunes lectures on ipod classic?

    I am trying to load some philosophy lectures on my ipod. Unfortunately these lectures are not available in tunes. Any help is much appreciated