Regarding rescheduling of purchase requisitions

Hi All,
For raw materials I have maintained safety lead time in the material master and I conduct MRP run. System create the purchase requisitions after MRP run. When I check the requirements in MD04 for the raw material, system show me rescheduled date.
But it doesnot mean that system has rescheduled purchase req.
Is there any transaction, so that I can reschedule the purchase req. ?
Regards,
Mahesh

I think the system gave this exception message becasue of some reason it was not able to do on its own. So, I guess you have to do it manually.
Are you sure it is not fimed?
http://help.sap.com/erp2005_ehp_04/helpdata/EN/f4/7d2c9744af11d182b40000e829fbfe/frameset.htm
An important group of the exception messages mentioned above are the rescheduling proposals. In the net requirements calculation, the system checks whether warehouse stock or firmed receipts are available in sufficient quantity to cover requirements. If a material shortage exists, the system usually creates a new procurement proposal. The rescheduling check is used to change the dates of already existing firmed receipts not planned on the same day as the requirement to suit the requirement date. For this purpose, the system displays the appropriate exception messages with rescheduling proposals for these firmed receipts to be processed by the MRP controller.
Regards,
Csaba
Please also check OSS notes 25388, 550302 about rescheduling.
Edited by: Csaba Szommer on Oct 16, 2009 9:34 PM

Similar Messages

  • Regarding rescheduling of purchase req.

    Hi All,
    For raw materials I have maintained safety lead time in the material master and I conduct MRP run. System create the purchase requisitions after MRP run. When I check the requirements in MD04 for the raw material, system show me rescheduled date.
    But it doesnot mean that system has rescheduled purchase req.
    Is there any transaction, so that I can reschedule the purchase req. ?
    Regards,
    Mahesh

    Hi,
    Do you notice a star indicator next to the PR, if yes it means a firming of the PR has taken place. This firming can be due to manual modification or due to the PR falling in planning fence and an automatic firming.
    MRP does not make changes to firmed proposals. So just close this PR & re-run MRP & system will generate an unfirmed PR. The MRP run will schedule the proposal on the need date.
    Hope it clarifies.
    Regards,
    Vivek

  • Regarding report for purchase requisition

    Hi gurus,
          I am preparing a report for purchase requisitions using SQVI. I am almost done with it but I was stuck at one thing. Our client criteria is to see it by name like they wanted users to view only purchase requisitions they created. They dont want all users to see purchase requisition created by other users. I dont know how to do that. Can anyone help me out with that.
         let me know if I am not clear about anything.
    Thanks in advance.
    Ravi Teja Boppana

    Hi,
          I added the field ERNAM from table EBAN. But the problem I am facing with it is any user can enter any user name in that field. Either I need that feild to be filled automatically with the username who logged in so that I can hide that field if that can be changed or filled automatically and cannot be change by user. Is there any option I can do like that. If I create a report in SQVI no one else except me can see that report, so I need this report in that manner.
          Let me know if i am not clear,
    Thanks in advance,
    Ravi Teja Boppana

  • Regarding changes in Purchase Requisition

    Hi,
    when i make purchase requisition in me51n for a material and then go to me54n to release that purchase requisition, but after release of purchase requisition when i again go to same pr by using me52n and change the material and plant and save the system allows to save.
    if i have already released the pr with particular material and plant then why is the systeem allowing to change the same pr no again with different material and plant.
    the changed material is shown as released in me54n.
    please guide me how to solve this problem
    Regards

    Hi,
    In release procedure for PR under rellease indicators the changebility indicator might have set as 2 or 3 or 4. Hence the system is allowing to change the PR after release. The changeability indicator function to allow changes of PR after completion of release PR. There are 4 indicators pertaining to PR. According to the requirement can set. If you set 1 indicator system won't allow to change the PR. I hope this will resolve your issue. Thanking you.

  • Creation indicator purchase requisition in md02

    Hello SAP Gurus,
         This is regarding creation indicator purchase requisition in md02.In this creation indicator purchase requisition if we keep setting as 2 than it will create purchase requisition if the dates of PR are in the opening period and will create planned order  if dates of PR falls out of opening period.And it takes the opening period from schedule margin key.
         My question is , as system calculate the opening date by subtracting the number of days which we have given in opening period in schedule margin key from the order start date.suppose if order start date is 10.03.2008 and we have given the opening period of 5 days,than the opening date will be 05.03.2008 if there are no holidays between it.So how it comes that PR date will fall in opening period?I am confused that when system will create planned order and when system will create PR if we keep creation indicator purchase requisition as 2.
          Plz help me with this query.If you could explain with one example than it would be great.
                         Thanking all in advance.And obviously for suitable answer i will definately give good points.

    Hi,
    System calculates the opening date  by subtracting the number days given as opening period at SMK from order start date.
    For creation ind =2 ,
    MRP run date decides the PR / Planned order creation even if u set procurement F.
    If MRP run date falls bettwen the opening date & order start date , it will create PR only,
    If run MRP run date falls outside the opening preriod ie earlier than the order opening date, system will create planned order and it has to converted to PR
    For  examble,  Order start date is  28.03.2008 and 2 day is defined as opening period SMK for ROH.
    If u run MRP on today it will create planned order.  
    Hope u understand , ifso reward and close.
    Regards
    Pradeep

  • Purchase requisition histry

    Dear Experts.
    As we know for Purchse orders we can get histry of the PO in PO histry tab i.e in EKBE table.
    in line with the same can anybody reply me that in which table PR histry is maintained.
    Regards,
    SDN BRW

    Hi,
    Purchase requisition is the preceding document of the start of procurement cycle.
    When P.R is converted into P.O we can get the details in status tab under item detail of PR.Here we can get the qty for which P.O is created and and the P.O. number .
    Please check the status tab in P.R Also you can refer table MEREQ3316
    BR,
    Tushar Patankar

  • Regarding automatic conversion to purchase requisition for dependent requir

    Hi
    How to get the dependendent requiment  to get converted in purchase requisition on doing MRP run for the finished good.
    Regards,
    vivek

    Hi Vivek,
    In customizing Tcode: OPPQ. maintain the data for your plant.
    Regards
    TRin

  • Regarding-Purchase requisition

    Dear All,
    While creating the purchase requisition user is changing the delivery address. So I need to block the changing options to user. Once we enter the plant name delivery address will extract from the data. Kindly suggest me how can I block the changing option to user.
    Noe:- I donot want to write a screen variant, I am thinking to do  in other way.
    Best answer will be rewarded.
    Reg/ Shankar G.

    Hi Shankar,
    I think It may not possible in defining screen layout at document level.
    I suggest you to use Version Management for Purchase Requisitions so that if any body change the relevant field (in your case Delivery address) He/She should enter the change reason then only system will allow him/her to change the delivery address.
    In this way you can control / Track users for changing the delivery address.
    Hope this will help you to resolve.
    Revert back if you have any doubts.
    Reg,
    Ashok
    Assign points if useful.

  • Purchase requisitions are not created for Component by MRP

    Hi,
    I have created planned orders for assy. When I run the MRP the purchase requisitions are not created by  MRP for the components. If I check the planned order the components tab is showing all the raw materials list as per the BOM. The master data tab shows the BOM,Routing,Production version etc. But when I run the MRP the components planned orders/purchase requisitions are not created.  There is no stocks available for the components in the plant, still the purchase requisition are not created by MRP.
    I have tried in both transactions MD01 and MD02.
    I could notice one thing. Supoose if I enter 31.12.2009 is the order finish date, the system creates exception mesage 10- Rescheduling in with proposed date 01.12.2009.  Why the system is propsoing rescheduling in with date 01.12.2009 which past date.
    Please sugest.
    thanks and regards
    Murugesan

    Hi,
    I am using MRP type PD  for assy and components. There is no planned orders for assy.
    If I run MD02 the planned orders created for assy and purchase requisition are created for raw materials. But if I run MRP in MD01 neither  the planned orders nor the purchase requisitions created.
    I tried the Control keys NETCH,NEUPL but still the planned order and purchase requisitions are not created if I run using MD01.
    Please suggest.
    thanks and regards
    Murugesan

  • Delivery Date in Purchase Requisition

    Hello all,
    This could be a kind of familiar post but i need a clear cut advice on this particular aspect.
    Delivery date in a purchase requisition is calculated based on PDT in material or purchasing info record. Date proposed would exclude the non working days as setup in the factory calendar. This is what my understanding with regards to the subject.
    let's take this case.
    #1. PR was created on 20th June so as per the Planned delivery time, delivery date should have calculated to 8th of august. But it's 30.07.2014
    #2. Planning calendar:
    Note: I do see an exception of 30 and rescheduling date is set to current date in the MD04 screen.
    Procurement proposal was triggered for a customer requirement (created on 19.06.2014) with requirement date : 24.06.2014.
    Please do help out.
    Regards,
    Rahul

    Hi Rahul
    Take a look on the following link, where the scheduling for external procurement is described:
    http://help.sap.com/erp2005_ehp_06/helpdata/en/f4/7d29f344af11d182b40000e829fbfe/content.htm?frameset=/en/f4/7d29e644af1…
    As explained here, the delivery date is firstly calculated to match the requirement date minus the goods receipt processing time. After that, the release date is calculated using the planned delivery time and the purchase processing time (defined on customizing). If you don't allow the start in the past on customizing, system switches to forward scheduling and the following procedure is used to schedule the order:
    http://help.sap.com/erp2005_ehp_06/helpdata/en/f4/7d2a0d44af11d182b40000e829fbfe/content.htm?frameset=/en/f4/7d29f344af1…
    BR
    Caetano

  • Help needed for enhancement in Purchase requisition

    Hi all,
    Our client uses me59n to generate PO's automatically using purchase requisitions.
    Now, the requirement is ...
    If net Purchase value  is 0 in purchase requisition, then
    Free(UMSON) field in Purchase order shoud be "checked".
    lemme explain the steps a bit detail.
    1. lots of purchase requisitions will be created in me51n.
    2. Client will use me59n to generate PO's automatically, using Purchase requisitions.
    3. purchase orders will be created.
    3. Now, i am in search of a badi/user exit , which will
         if netPurchasevalue(gswrt) = 0
            (free)umson = X.
         endif.
    so , i need a enhancement, which links both fields(gswrt) from purReq & (umson) in PO. 
    please lemme know if anybody have experience on similar issues earlier.
    Regards.
    santosh.

    Hi,
    Try implementing the BADI -ME_PROCESS_PO_CUST ...the method "PROCESS_ITEM" can be used to do the check that you want...
    Thanks,
    Renjith

  • Service Number is not getting updated in the Purchase Requisition

    Hi All,
    When i create a Service PR using bapi BAPI_REQUISITION_CREATE FM , service details ( Service number, Qty, Gross price, ) are not getting updated in Service tab of Purchase requisition transaction. I am passing all the services related parameters in the FM.
    Please clarify this.
    Thanks for the help.
    Vinoth

    Hi Vinoth,
    Are you getting any error in the return table?Can you show your coding?
    Regards,
    ravi

  • Purchase Requisition not getting generated in APO

    Hi,
    I am facing an issue in APO. Once I confirm a sales order, I have to run the Product Heuristic in APO to generate the purchase requisition through rrp3. The problem is the purchase requisition is getting generated without the PR number. The line does not show the number and also the purchase req is not reflecting in ECC. Please refer the screenshot. Kindly help me with this.
    Thanks & Regards,
    Raja S

    Hi Guys,
    Sorry for the delayed response. Now got another issue. My CIF model for a Sales Order is not getting activated. I also cleared the queue in APO through /sapapo/cq and then start running the CIF. But it runs for a long period.
    What could be the other possible issues with CIF model activation?
    I am getting a message box like the below when try to activate the CIF. I keep ignoring the message and trying to run the CIF. But still I am unable to resolve. Kindly help
    After resolving this only, I can go for the above mentioned issue. I sincerely thank all your support.
    Regards
    Raja S

  • Purchase Requisition Is Being Getting Created In APO But not being publishe

    On doing, SNP Location Heuristics on  one of our item, purchase requisition is being getting created in APO (We are able to see the same in RRP3) but the same is not being getting published in ECC. On doing CCR of the said location - product combination, it is showing Error u201C182u201D. We have checked the following parameters :-
    Item is an APO Item i.e. X0.
    It is having a proper Purchasing Group.
    As This be a purchase item. So, it is having a valid single Purchase Info Record.
    Item Has Not Been Blocked At Any Level.
    Vendor From Whom This Item is being getting procured is also open (Not Blocked).
    Please suggest what else to be checked  and what else can be the reason for non-flowing of purchase requisition from APO to ECC.
    Thanks & Best Regards,
    Sanjeev Chugh

    Hi Sanjeev,
    Please check change pointers if any and send them to ECC. Check the order in the planning book whether it has picked the same source for which there is a Purchase info record. If these all are fine then You send them to ECC from the CCR then check the log in ECC through CFG1 tcode.
    Regards,
    Kishore k Reddy

  • Release strategy for purchase requisition does not kick in

    Hi Gurus!
    I've been struggling with this issue for some weeks now.
    I have set up the release strategy configuration for purchase requisitions with classifications.
    However, if I create a purchase requisition the release functionality is not taken into account by the system.
    See below some more information regarding my configuration:
    1. I've created a new characteristic "REL_PR_GROUP". Status: released, Multiple values, Number of Chars 3, 7 values (TR1, TR2, TR3....TR7), Table name: CEBAN, Field name: EKGRP, Procedure for value assignment set to not ready for input.
    2. I've created a new class: "REL_PR_ANPC". Class type 032, Status: released, Same classification: do not check, Char: "REL_PR_GROUP"
    3. I have one release group "T1", Rel. object 1, OverReqRel is marked, Class: "REL_PR_ANPC"
    4. I have 5 release codes. Grp: T1, Code: 01....05
    5. I have 2 release indicators:
    "R = Released", Rel. for ordering is marked, Changeabil: 4, Value chgs. 100,0
    "X = Blocked",  Changeabil: 4, Value chgs. 100,0
    6. I have 1 release strategy:
    "T1 with Grp T1"
    - one release group, 01 Manager
    - release prerequisites not applicable because of only one release group
    - release status, nothing marked = blocked, 01 marked = released
    - classification, purchasing group is TR1 or TR2 or TR3 or TR4 or TR5 or TR6 or TR7
    I intentionally kept the configuration as simple as possible so I can try to get it working first.
    Now if I create a purchase requisition for an item with release group T1, I would expect the release strategy to be activated. However, this is not the case. I don't see the "release status" tab in the PR, and if I try to relase via ME54 the system says the PR is not relevant for release.
    Could you please assist in getting this working?

    Hi,
    Have you checked in CL30/CL30N if your release strategy is derived successfully?
    See section 3 of Note 365604. A small section of it:
    You can use transaction CL30 search for an object using the data
    of the purchase requisition/purchase order. Here, it is important
    that the object search determines exactly one strategy. If this
    is not the case, this indicates that there are overlapping
    strategies in the system or that the release strategies in
    Customizing do not correspond with those from transaction CL24.
    See the previous point. If the object search returns more than
    one result, the system subsequently determines an incorrect
    release strategy or no release strategy at all.
    If it is derived successfully, next, check the user exit EXIT_SAPLEBND_001 as per Note 371667:
    The following assignment statement has to exist within activated SAP
    enhancements M06B0002 (include zxm06u13) and M06B0005 (include zxm06u31)
    for purchase requisitions:
         E_CEBAN = I_CEBAN.
    Regards,
    Purnima.

Maybe you are looking for

  • I can't open Adobe Reader X

    I reinstalled Reader, repaired through the control panel and downloaded the update as recommended. and I still can not even open Reader, let alone any files. I can't open files in a browser nor any saved files on my computer. Any suggestions would be

  • Set Session Variables

    Is it possible to set 'OS_USER','TERMINAL' or 'HOST' in 'USERENV' in C#? This assignment is possible to do as in the example code in java. Link: https://community.oracle.com/thread/258126

  • Flash builder vs. Flash Pro vs. Flash develop

    Hello! I've bought Ainol NOVO 7" Elf - Chinese high performans/low cost Android 4.0 tablet and everithing works fine, except for applications I've build using Adobe Air, which is pretty sad becouse it suppose to be for testing apps To be more specifi

  • [iPhone] Really struggling with views and transitions.  Please Help.

    Hello All, First off let me apologize; I've been trying to do this on my own, reading the docs and guides and such, but I just can not get this to work. I feel like once I understand this scenario I'll be able to learn the rest on my own. Basically I

  • Pro*c sample programs

    could anyone direct me to where the sample pro*c programs (e.g., cppdemo1.pc) are? I don't find them in the instant client precompiler packages. Thanks in advance.