Regarding scheduling dates & time

Hi,
1)i have created a production order for a finish material "A" mentioning finish dates 21/05/08.
2)order qty is 100 kg's time taken is 1 hour( i.e. 24:00 to 23:00).
NOW,
3) when i create the production order for the same material "A" again, for the qty 200 kg's & finish date is 21/05/08.
4) finish time is taking from 24:00 instead of 23:00.
Actually it should start from 23:00 right????
i think i missed out some settings.
i need all of your suggestions for the above problem.
thanks/regards
vish

Hi ,
            Scheduling depends on the option you select on MD02 screen , if you have selected Determine basic dates then it will search In house production time mentioned in material master . If you select 2 nd option i.e lead time scheduling and capacity planning then system will refer routing ( cap requirements will also be created ).
R/3 does not consider capacity while scheduling the order so check either in house production time or from routing check scheduling results for 100 or 200 quantity .
Reward if useful .
Neal .

Similar Messages

  • Basic and scheduling  dates & time calculation in process order creation

    Hi guru's,
    i have one requirement, i need to calculate and display the basic and scheduled dates & times based on the given input i.e material , plant , process order type , quantity , UOM and scheduling type ( for corresponding scheduling type user will provide either start date or finish date ) using RFC. can  u plz provide any function module for this purpose or logic for calculating the same  , as i am working on version 4.7ee .
    Awaiting for a quick response.
    Regards,
    Madan

    Dear Rohan,
    1.Check the length of break timings defined in the resource that is assigned in the phase.
    2.Check in OPUZ whether for the process order type and plant combination whether scheduling is to include the break time also
    (whether the check box for scheduling with breaks) is included.
    Check and revert back.
    Regards
    Mangalraj.S

  • Identify Jobs that are not running on their Scheduled date time

    I have 29 scheduled jobs that run at different intervals of time. Some run once a day. few others run on hourly basis while others run on Sundays.
    I was working on a query that would let me know if a particular job did not run on its scheduled date and time.
    SELECT * from all_scheduler_jobs WHERE state <>'DISABLED'; will give me a list of all jobs that I have to monitor and that are not in the disabled state. But how can I verify that the jobs are running at their scheduled date time?
    Any help please? I need to create a view of all such jobs and then plan to send an alert so that appropriate action can be taken and it is assured that all important jobs run as per schedule.
    Thanks.

    Hi,
    I can see 2 approaches.
    - for jobs that have run but ran very late you should query dba_scheduler_job_run_details and filter by the difference between req_start_date and actual_start_date
    - for jobs that should have run but shouldn't, query for DBA_SCHEDULER_JOBS jobs that are SCHEDULED where next_run_date is in the past
    Hope this helps,
    Ravi.

  • Scheduling date & time in order

    Hi All,
              From where system picks Scheduling start & finish date & time in order.
    regards
    sunil

    HI
    based upon the routing or task lsit opearation hours the system caliculates the time.
    and your work centre workning times
    when the order is called based on scheduling the start time comes to the start date and time the routing hours are added.
    with this the end date and time comes in order.
    -ashok

  • BAPI PROCESS ORDER Creation u2013 can the SCHEDULE Date/Time be specified?

    I am currently using BAPI_PROCORD_CREATE to create a Process Order from an inbound IDOC.  This works well, when I pass the following fields:
    BAPI Parameter ORDERDATA
    ORDER_NUMBER      Process Order number (EXTERNAL)
    MATERIAL      Material to be produced
    PLANT              Plant
    ORDER_TYPE      Order Type
    BASIC_START_DATE Start Date
    BASIC_START_TIME Start Time
    BASIC_END_DATE   Basic End Date
    BASIC_END_TIME   Basic End Time
    QUANTITY         Process Order Quantity
    QUANTITY_UOM     Quantity Unit of Measure
    However, I have a requirement to also specify the SCHEDULED Start Date (GSTRS) and End Dates (GLTRS), but the BAPI parameters do not the SCHEDULE Dates to be specified.
    I have also used the functions CLOI_CHANGES_UPL_31 and CLOI_CHANGES_UPL_45 to create Process Orders successfully, but neither of these allow for the SCHEDULE dates to be passed in.  
    Does anyone know how I might be able to achieve such a result?
    I am trying to avoid the use of CALL TRANSACTION on COR1, so would be grateful if anyone has any thoughts.   
    In the mean time, Iu2019ll ask the business if it would be possible to apply any rules by whereby if we specified a BASIC_START_DATE, whether it would be able to derive the correct schedule date accordingly.
    PPu2019s not one of my better modules, so apologies if whatu2019s been asked above is a stupid question!
    Alistair

    HI...
    Pls chk in scheduling control for detailed scheduling in T code OPUZ. and change the scheduling type forwards to forwards in time and backwards to backwards in time.
    Now when ever you would create the order system would ask the scheduling dates either start or finish in stead of Basic dates.
    Instead of using BAPI you could make a simple LSMW pogram. It would talk 5 min.
    This is a standard SAP functionality to select Basic dates because SAP consider all master data for scheduling like Schedule margin key.
    I think It would help you.
    Regards
    Vivek

  • Help regarding Scheduling date calculation in APO using Condition Technique

    Hi Team,
               The below is the issue I am facing. Could you please help me regarding this?
    For a material MAT1, a stock of 15 is available today i.e. on 15/05/2014 and a Planned Order of 35 is available on 01/08/2014.  I have created a Sales Order of 50 today i.e. 15/05/2014 for this material with a RDD of 20/05/2014. I have maintained the LEAD and the TRAN times as 5 days and 10 days respectively. These are maintained for a particular Route. LOAD, PICK, and UNLD are 0. In the Location master, I haven't defined any Calendar. So, it has to consider all days as working without any holidays.
    For the given RDD of 20/05/2014, system performs the backward scheduling and arrives at a past date of 05/05/2014(20/05/2014-5D-10D) for the MBDAT. Since this date is in the past, the system should set the MBDAT to the current system date i.e. 15/05/2014. Since PICK is 0, the Loading Date also should be 15/05/2014. Since LOAD is 0, the Goods Issue Date also should be 15/05/2014.  Since LEAD and TRAN are 5D and 10D, the Delivery Date should be 15/05/2014+5D+10D=30/05/2014.
    But, in the Sales Order, I am getting a different date. For MBDAT, Loading Date, and Goods Issue date, the dates are 05/07/2014. Transportation Planning Date is 25/06/2014 and Delivery Date is 01.08.2014. During the GATP check, I am getting only a partial confirmation of 15 and the planned order of 35 is not being considered.
    The material is APO relevant and the Scheduling using Condition Technique is being used.
    Kindly help me regarding this and let me know if I am missing anything here.
    Thanks in advance for the help.
    Thanks & Regards,
    Srikanth.

    Hello Srikanth,
    Let us differentiate the problem into two pieces.
    1) Incorrect Scheduling
    2) Future receipts not being considered.
    For the second problem, future reciepts not being considered, which is on 01/08/2014, please check if your system is allowing you to go further and do the confirmation. How long is your Checking Horizon ? Is your checking horizon configured enough to go ahead and pick this reciept element to give the confirmation by creating a second schedule line ?
    For the first problem, LEAD to the best of my knowledge is transportation planning time which means, the MBDAT would be shifted to the extent of the LEAD time to be able to manage the truck though the stock is available today. However, the dates mentioned by you seems to be completely different. Hence, I suggest you to take the ATP check on this line item, go to Delivery proposal screen and click on the graphical representation of the Scheduling results. There you should be able to understand how the calculation is actually happening. Perhaps, there are some calendars that are being used which you'd not be knowing ? May be the condition record has different times maintained in the condition table ? Check the condition table that the system is picking up ? May be you have maintained the route and transportation scheduling in "X" condition table, however system was able to identify a different detailed level table which satisfied the condition and due to which system got the scheduling calculated accordingly ?
    May be it is a good idea to investigate this way. Hope this helps.
    Babu Kilari

  • Changing time-out for scheduled data refresh

    Using a Power Query connection, is it possible to extend the time-out time for scheduled data refreshes? The amount of data to be retrieved is rather limited, but there's thousands of rows (NAV server).
    If not, any suggestions to how to reduce latency?
    Thanks.

    Thorm,
    Is this still an issue?
    Thanks!
    Ed Price, Azure & Power BI Customer Program Manager (Blog,
    Small Basic,
    Wiki Ninjas,
    Wiki)
    Answer an interesting question?
    Create a wiki article about it!

  • Displaying Date & Time in Scheduled Worksheet

    I'm using BI Discoverer Plus & BI Viewer.
    In Discoverer I've set up a scheduled workbook to create a workbook once per day.
    It runs fine and creates worksheets as required.
    In Viewer I can open the Workbooks and Worksheets as required.
    I want the worksheet to contain the time & date when the data was brought
    into the report.
    It seems that the date and time is the date and time when I open the report for printing.
    Anyone know how I can get the report to include the time and date when the
    report was run, rather than when it is displayed/printed?
    Thanks
    Suhada

    Russ,
    I think perhaps I'm not explaining what I want very clearly so
    here's another attempt:
    What I want is in one place on the page, to show the date & time
    when the data was extracted.
    If I understand correctly, putting &Date and &Time in the Page Title
    displays the Time and Date that the Report is display on screen rather than when the Data was extracted from the database.
    If I create a Worksheet which has &Date and &Time in it and then
    refresh it and then print it then the date and time shown are about right.
    However if I create a scheduled workbook which say runs once per day,
    wait for a week and then open a report from a few days ago, the data shown
    was extracted a few days ago but the &Date and &Time show the current date and time.
    It seems to me that when you print a report, what's most relevant is the time
    and date when the data was extracted, rather than the time & date that the
    report is printed.
    I've worked in Business Objects before and it's fairly easy in that to set things
    up so that every report has on it both the date & time of when the data was
    extracted AND the date & time when the report was printed.
    So what I want is a way of showing on the report, the date and time at which the data was extracted, i.e. when the query was run.
    Just once, say in the top right hand corner of the page.
    I hope that's clearer.
    Suhada

  • MD04 dates not showing lead time scheduled dates

    Hi experts,
    In my MD04 screen, dates are not showing lead time scheduled dates (showing only basic dates scheduling) even after MRP run with lead time scheduling.
    Please let me know if there is a way that the date column in MD04, shows the finish date from lead time scheduling.
    thanks
    Jay

    Hello
    Production dates are not displayed on MD04.
    You can include additional fields on MD04 using a BAdI and you can use your own logic to add the production dates.
    You will find the relevant BAdI on the following document:
    BAdIs for MRP
    BR
    Caetano

  • Schedule vibration mode for iphone using date/time

    Can we schedule iphone using date/time  (duration in each day) , so that iphone can go into vibration/silent mode as per the schedule!!
    Please share your views , Thanks in advance.

    Thank you , I'm aware of this , but the bet is to make some app to play around for myself, any idea !!

  • Sales order schedule date is a (working) day before Scheduled ship date

    In MRP/MPS planning, the forecast consumption is occuring for all sales orders at a date (sales order schedule date) which is always a working day before the Scheduled Ship Date (SSD). What is the logic?
    Time fences are not used.
    E.g. Sales order is scheduled to ship (SSD) on 30th Nov, in forecast set > Forecast items > Consumptiion > Detail, the sales order schedule date is a day before SSD.

    Hi,
    This is a complex issue; best solution is by using APO/GATP.
    If not, then in ERP only, the second best is:
    1) Work with assembly processing in SO, meaning that a production/planned order is automatically created in the customer order during order creation.
    2) Then, after the order is created it is scheduled, and the delivery date proposal is based on that.
    3) Now you can check in the order that there are no capacity overloads, and all capacity required to produce on the proposed date is available. If yes, you're done. If not, it gets a bit complex, since you actualy need to switch to capacity planning, do capacity leveling and dispatch (PP), and the you get a new feasible schedule proposal based on that.
    APO/GATP could do all that automatically!
    Regards,
    Mario

  • Basic date is not same with schedule dates

    Hi,
    I have a problem in MD04 stock requirement list.
    Planned order basic date and schedule date is not the same.
    The schedule date finish at year 2010 but basic date still end ad 2009
    in MD04, the date display is basic date.
    Why the basic date is not adjusted?
    in configuration i had choosen adjust basic date in scheduling planned order.
    In material master in house production time is not updated because we use lead time scheduling
    Please kindly help
    Best regards,
    Freddy Ha

    Hi,
    i omit the scheduling maergin key in material master,
    the result of MRP is
    BASIC DATES
    Finish 15.10.2009
    Start 14.10.2009
    PRODUCTION DATES
    15.02.2010 14:33:25
    14.10.2009 07:00:00
    scheduling type i planned order is still "backwards"
    so in MD04 it is say that the goods is available at 15.10.2009 same with requirement dates.
    this seem not right.
    it seems that order finish date is not adjusted by lead time scheduling on "today scheduling".
    Is there a way so order finish date is adjusted by lead time scheduling on "today scheduling" ????
    Best regards,
    Freddy Ha
    Edited by: Freddy Halim on Oct 14, 2009 10:01 AM

  • Scheduling Date issue in Assemble to Order Scenario

    Hi Friends,
    I am facing a Weird issue with Production order Scheduled dates created automatically after creation of Sales Order for configurable material.
    Our availability check is set to check  open Purchase orders, for one component the delivery date in the PO is 20.12.2011, currently at the time of creation of SO the availability check shows this component as a missing part and committed date as 20.12.2011.
    Now the issue is that for one type of customers when the SO is saved, the production order gets created with basic start and finish date of 20.12.2011 with a status CRTD PRC MACM SETC.
    But with another customer group it creates the Production order with today's date basic start and finish date, with a status CRTD MSPT PRC  SETC.
    Now since in both the cases the Material is same and also the components are exactly the same, the only difference is the customer, I am unable to make out why it is happening.
    I am basically a MM  Consultant so am unaware if there is any standard setting relating to customer or something relating to that which is causing such  a issue in scheduling date of the Production Order.
    Regards
    Chandra Shekhar

    Hi Vivek,
    Yes, the availability check is working in both the cases, when I create the sales order, I key in the Configurable material code, then do the configuration, after that system does availability check, in both the cases the result of availability check is same with one component marked as a missing part, available date as 20.12.2011.
    One more thing if I try to view the Production order at the time of SO creation before saving it, the Production order shows today's date, but when I save the SO, and do Credit release, the actual Production order gives different scheduling date based on customer. Just wondering what could be affecting based on Customer, is there any other field present in Customer master which could alter the date.
    I also saw today's scheduling note in some of the cases, but its not coming up in all of the orders created with today's date and moreover the same components are getting scheduled for 20.12.2011 also for diff customer.
    I am afraid I can't provide any screenshots for this as am not permitted to publish any screenshots of the client.
    Regards
    Chandra Shekhar

  • Calculation of basic dates and schedule dates

    I update material master from routing with CA97 to material master
    work scheduling data with base quantity 1000
    When MRP running, planned order for 54000 PCS is schedule with work scheduling data.
    when i schedule planned order (change)
    the calculation basic date & schedule date differs for 19 days
    cause basic start shift
    why is this happend?
    is this cause by rounding when transforming minute from routing to days in material master?
    is this because i used shift sequence and scheduling with breaks?
    some strage case again is
    for base qty 1000 processing time is 0.97
    for base qty 10000 processing time is 6.93
    is there any solution for this case?
    please help.
    Best regards,
    Freddy Ha

    i forgot i used overlapping
    sorry

  • Calculation of basic date and schedule date

    I update material master from routing with CA97 to material master
    work scheduling data with base quantity 1000
    When MRP running, planned order for 54000 PCS is schedule with work scheduling data.
    when i schedule planned order (change)
    the calculation basic date & schedule date differs for 19 days
    cause basic start shift
    why is this happend?
    is this cause by rounding when transforming minute from routing to days in material master?
    is this because i used shift sequence and scheduling with breaks?
    some strage case again is
    for base qty 1000 processing time is 0.97
    for base qty 10000 processing time is 6.93
    is there any solution for this case?
    please help.
    Best regards,
    Freddy Ha
    Edited by: Freddy Halim on Jan 28, 2010 7:40 AM

    Hi,
    Yes. The schedule date is generated considering your factory calender also in addition to the routing data. For eg.. Suppose if Saturday and sunday are holidays, the schedule date will be extended to 2 days.
    Pl. check the  unit in your routing for the second query.
    Pl. refer the link
    http://help.sap.com/saphelp_47x200/helpdata/en/b1/c042b7439a11d189410000e829fbbd/frameset.htm
    Madhava

Maybe you are looking for