Regarding Service Order(IW34) creation using BAPI_ALM_ORDER_MAINTAIN

Hi Gurus,
While Creating Service order through BAPI:BAPI_ALM_ORDER_MAINTAIN, Operations tab is only updating for One activity eventhough I Passed 4 activities. also the components tab with the same problem.
Could any plz suggest....
Thanks in Advance..
Regards,
Venkat.

Venkat,
  Check whether you have maintained the proper methods for the key in IT_METHODS table parameter.You should be able to find the relevant values to be passed on the long text of the parameter within the BAPI.
Regards
Narasimhan

Similar Messages

  • Regarding Service orders

    Hi all,
    my client is providing services like ,meter repairs,meter tests,meter upgrades in the electricity sector.how can i configure the service orders in SAP sales and distribution.can u pls explain me the process step by step.
    Thanks & Regards
    Ramesh chandra

    Hi Ramesh,
    its the standard transaction codes that are used like VA41, VA01, VF01
    but the document types are generally customised according to the business requirement i.e. blue print. like va01 would be za01.
    and i cant provide you any documentation unless the busines process is specifically known.
    Go through creating service contracts in glen.c.williams or sap help, that would give you an idea of how service contracts are dealt with.
    reward if helpful
    Regards
    Sai

  • Help needed regarding service order numbers

    Hi,
    Could anyone please help me solve this, i will award good points.
    1.     The program should support a method for the user to input multiple Service Order Numbers simultaneously
    2.     The output should include the following:
    a.     All Service Order Line Item numbers and corresponding material
    b.     Corresponding Service Confirmations
    c.     Service Confirmation Line Items that have doc flow from their corresponding SO line items (and their corresponding material)
    d.     Any additional work item on the Service Order that may not have a corresponding Material on the Service Order
    3.     The output should list all Service Orders and Service Confirmations in separate columns with all related line items/material on the same row in the output
    4.     Any line item on the Service Order or Service Confirmation that does not have a document flow to the respective other document should not have any other value on the same row
    Regards,
    Niloufer

    Hi,
    What is the version of the weblogic server and service pack you are using ?
    Regards
    Anilkumar kari

  • Service order type creation

    Hi,
    I want to create a service order type. We dont have any requirement to create any service notification for it.
    Could any one please tell me is it necessary to create a service notification before a service order.
    Thanks and Regards

    Hi
    No there is no nedd to create service notification before order creation but in real time this logic will not apply before you have to craete the notification.
    But if u want to just check this concept then u can eaisly create a order without creating notification
    Thank & Regards

  • Service order and its use...

    Hello Experts,
    Can anybody explain me what is service order and sevice quotation and billing is done for it.In what scenario it is in use ??
    Please send me some links and documents on that  topic and transaction codes also...
    Will be very greatfull if get some early reply..
    Thanks and Regards

    Check [this|http://help.sap.com/erp2005_ehp_03/helpdata/EN/50/74d5f1a72111d3a6c40060087a7a74/frameset.htm]

  • Regarding Service Order Problem

    Hi Experts,
    I am new to ABAP. When my MM consultant creating Service Order System is showing the message "Last Page Reached". He told me that debug the Standard program. Finally I found where the message is coming, the details are
    Include : LMEGUICJK and Method is FCODE_FINISHED. But I am not getting how to modify the code. Can you please give me the suggestion to resolve this issue? any solution?
    Thanks and Regards,
    Muralikrishna P.
    Edited by: muralipsharma on Dec 3, 2010 4:44 PM
    Moderator Message: Do some R&D on the topic first.
    Edited by: kishan P on Dec 3, 2010 6:28 PM

    Hi,
    Check Linking between  PO document type"NB" to PR document type  and  Item Category  "D" is allowed or not  in following path.
    SPRO- > MM-> Purchase Order- > Document type
    In this select the Document type "NB" and check Linkage to Purcahse Requisition.
    Check if not & enter  Item Category  "D"   and save.
    Now try your transaction.
    Hope the above will helpful & then reward.
    Regards,
    Biju K
    Message was edited by:
            Bijay Kumar Barik
    Message was edited by:
            Bijay Kumar Barik

  • Regarding purchase order pricing conditions using exits or badi

    Hi friends can anybody help me and  let me know the solution.
    Please explain how the change in the pricing condition amount value should update the cost in PO.
    and which EXITS or BADI use for .
    if anybody have the solution send me reply AS SOON AS
    Thanks,
    srinivas

    OK
    But the problem is pricing conditions like transport cost. Because when I do a new purchase order the system use last transport cost and i don´t want it.
    What I want (if possible) with infoupdate is:
    - Update ( PBXX & PB00)
    - Don´t update (other conditions like transport).
    Thanks....

  • Service Entry sheet creation - Using a diffent contract diff from line item

    Hi,
    Here is the scenario...
    I have a services purchase order referring to contract  and its service item with services ( service masters) attached to it.
    And the PO  item is a limit item with some limits maintained on the limits tab, but contract reference is specified at the limits level it is only at the line item level.
    System version : ECC 6.0
    Lets say PO number : 123456789
    Lets say contract number and item is : 2323232323  item 10 ( Account assignment U )
    My supplier is : 111111111
    Now I am creating the Service Entry sheet  and I am trying to add the services  ( services selection button)  I get a pop up to  search for services  by certain selection criteria  and one of them is purch document ( remember it doesn't pre-populate and grey out the purch doc field with that the contract number from the item level) and now I can select any service contract that belongs to any supplier and select the services from it and complete my  SES.
    So lets say the contract from which I chose the service is : 3232323232
    And the supplier on the contract is 2222222222
    Is this a valid scenario or not?
    Has any body ran into this situation  before?
    Hope I was clear in explaining my scenario....  
    Thx,
    Krishna.

    Hi Krishna,
    the External Services Management distinguishes between planned and unplanned services.
    In case you have ONLY limits, no planned services in the PO item, it does not matter if you have entered a contract number into the PO item - in this case this contract will be not a real reference for your services.
    If you have entered limit values only as overalllimit and expected value and you did not enter a contract limit on the contract limit tab, then you will not have a special contract reference on unplanned level neither.
    In this case it is NOT an error when you start the entry sheet creation and you can select services from other contracts or purchase orders against your limit values in the PO into the entry sheet.  The system does NOT check for a different vendor when you select services from other documents than the contract which you have specified in your PO item, because it is NOT a real reference - nor on services level as you have only limits in your PO item, nor on limit level since you have NOT entered a contract limit into your PO item.
    In order to understand this process please study the unplanned scenario and contract reference scenarios.
    Regards,
    Edit

  • Regarding service order

    Dear Guru's
          I have created an order for service with two items.When i am creating billing,automatically 2 bills were rasied for each item seperately.why it happened like that .I want only one bill fo rboth the items.
    Thanks in advance
    cherukuri

    Please use the Splitting analysis why 2 bill is created
    go to VF02 put the billing number -> click environment click split analysis-> enter another document -> then system will tell why these 2 documents arecreated instead of one
    regards
    virandra sharda

  • Issue with service entry sheet creation using synchronous service

    Hi,
      I am using a synchronous service inside that i am calling bapi bapi_entrysheet_create with testrun
    set,so that commit doesnot happen inside the bapi,then outside i am explicitly calling commit work.
    Still database table is not updated,commit is not working.

    Hi Venu,
       But I cannot set test run as initial because if testrun is set to initial bapi_entrysheet_create logic
    is written in such a way that it calls commit work inside the bapi....and so we cannot rollback later
    in the synchronous service.
    Regards,
    Tess

  • Regarding service tax invoice creation in SAP SD

    Hi,
    Currently we are using ECC6 EHP4 where my client require separate service tax invoice generation as like excise invoice generation in J1iin. is it possible in ECC6 ehp4? client has excise registration
    if possible what are the steps involved in it?

    Hi,
    The reason for asking a seperate invoice for service tax may be because the client wants to utilize the service tax.
    Other wise there is no need to create separate invoice for service tax. Invoice can be created from VF01 with service tax condition type included in the pricing procedure.
    please check these links
    http://wiki.sdn.sap.com/wiki/display/SI/ServiceTaxCreditandUtilization.
    Service tax utilization through J2IUN
    Hope this helps.
    Regards,
    Sharan

  • Sales Order IDOC creation using IDOC_INPUT_ORDERS

    I am trying to create a Sales order IDOC (Inbound) from a flat file using the FM - IDOC_INPUT_ORDERS .
    I am able to create the sales order. But I don't see the idoc getting generated anywhere.
    I see the import parameter - DOCUMENT_NUMBER coming blank. Why is the IDOC not getting generated ?
    Any tips will be useful ?
    Can we create Inbound SAles Order IDOC using 'MASTER_DISTRIBUTE_IDOC'  FM ?
    THanks.

    Hi Shareen Hegde 
    To create Inbound...idoc
    Use the Function Module in you Program : IDOC_INBOUND_WRITE_TO_DB to create the Inbound idoc
    Pass the Control record and Data record in FM.....
    Use Message type : Orders
    IDoc type : Orders01 or 02 or 03 or 04 or 05 ....  which ever suite for your requirement....
    Process Code : ORDE
    When ever your custom program for creating the inbound sales order with  runs .....
    it call the internally FM IDOC_INPUT_ORDERS to create the Sales order...
    or
    If you are getting the inbound idoc from subsystem .....then check you partner profile ,Message type ed and Process code is correct or not....
    I hope this resolves your issuse..
    Ramesh

  • Error while  changing Service order through  BAPI_ALM_ORDER_MAINTAIN.

    Hi Frens,
    I am facing problem while  changing a service order .
    I am changing the  HEADER ( Planner group & Basic Finish date )   through
    BAPI_ALM_ORDER_MAINTAIN.
      lt_methods-refnumber = '000001'.
      lt_methods-OBJECTTYPE = 'HEADER'.
      lt_methods-METHOD = 'CHANGE'.
      lt_methods-OBJECTKEY = l_aufnr.
      append Lt_methods.
      lt_methods-refnumber = '000001'.
      lt_methods-OBJECTTYPE = ' '.
      lt_methods-METHOD = 'SAVE'.
      append lt_methods.
      lt_header-orderid = l_aufnr.
      lt_header-PLANGROUP = 'GE'.    " Hard coding for testing
      lt_header-FINISH_DATE = '20081114'.
      append lt_header.
      lt_headerup-orderid = L_AUFNR.
      lt_headerup-PLANGROUP = 'X'.
      lt_headerup-FINISH_DATE = 'X'.
      append LT_headerup.
      CALL FUNCTION 'BAPI_ALM_ORDER_MAINTAIN'
        TABLES
          IT_METHODS   = LT_methods
          IT_HEADER    = LT_header
          IT_HEADER_UP = LT_headerup
          RETURN           = LT_return.
      CALL FUNCTION 'BAPI_TRANSACTION_COMMIT'
         EXPORTING
           wait = 'X'.
    I am getting error No : IWO_BAPI2  ( 118 )"  *Order 5001887 cannot be saved, since no operation is maintained."*

    Hi Balu,
    You can refer to the note 966289 which talks about this problem if a service order template is used.
    Thanks
    Abishek

  • Service order number range creation

    Hi,
    Could anyone please tell me how can we create service order number range if we have done a new service order type creation, and what should we do: should we create the number range in development and then transport it to the production or we should directly create it in production.
    Thanks and Regards

    Hi,
    Please guide me what should we first do to transport the service order type transport request to prd.
    1.Should we first transport the request for other components of the service order type?
    2.Then should we transport the request for number range or we directly create it in production server?
    Please guide.
    Thanks and Regards
    Edited by: MPVash Vash on Sep 8, 2008 7:53 AM

  • Number range creation for new service order type

    Hi,
    Could anyone please tell me how can we create service order number range if we have done a new service order type creation, and what should we do: should we create the number range in development and then transport it to the production or we should directly create it in production.
    Thanks and Regards

    HI,
    You just define number range in tcode VN01, but remember that number ranges are not transportable.
    Once you define number ranges in development, do the same in quality & production client.
    Then attach number ranges in document type & transport this config to quality & production
    Please see that before transportating, the number ranges must have been created in quality & production thru VN01.
    Hope this helps you
    Regards
    Dhananjay

Maybe you are looking for