Regarding Shifts in a work center
Hi experts,
I am facing an issue regarding the shift in workcenter.
I have done all the prerequisite settings in spro like
1. defing a grouping key,
2 defining work break schedule key,
3.definining shift definition,
4.defining shift sequence
now is there something called shift pattern key which does the shift changing on the desired basis like monthly or daily or weekly.
i have created one for my requirement.but whenever I am aasigning my grouping key to the workcenter only one shift reflect in the system.
So can you please help me.
Regards,
Vivek
Hi Vivek,
This seems to be a different question all together,you have to create new thread for each question to get proper/prompt reply
First of all before cerating an inspection plan,you have to first decide what type of inspection you want to do
You can find the std inspection types in the QM view of the material master under Insp.setup
Then maintain the respective inspection type
like Inspection after GR from production
After that create inspection plan for the material in QP01 tcode
Before that you should have inspection characteristics created(MIC's)
It is created in QS21 tcode,here you will have to mention whether its qualitative or quantitative & input data accordingly
In QP01 you have to maintain the usage accordingly like 5,6 etc
Rest is like normal routing
In case of inproces inspection you dont need to create a seperate inspection plan,you can maintain the same in the production routing with MIC's
Hope this hepls
Rgds,
SVP
Similar Messages
-
Our plant works in 3 shifts. for every shift there are total six persons working on it. 2 in each shift.
we need to assign the name of person working on the particular machine. Where can be the assignment of the actual person working on the workcenter be made.
thanks and warm regards.
Edited by: pankaj lade on May 8, 2008 12:32 PMHi,
One information required..
Why you wanted to have the operator names to be attached to your work centers?
You can have the Operator Names at the time of Confirmation of the Operation (This is what you wanted for Tracking purpose?)
1. Have the Operator Name or No. in Personal Number Filed in CO11N (you need to actvate the HR Transactions)
2. Activate a Stadard Value key with Operator and during confirmation the relevnt operator can enter their name or No. there
3. in CO11N text field as the operator to enter their name..
Hope this helps..
Regards,
Siva
Edited by: Siva Kumar M on May 8, 2008 4:22 PM -
Shift definitions for work center capacity planning
Is there a way to create a 9-80 work schedule over a 2 week period. Client doesn't want to maintain date every two weeks.
Hi Dean,
Could you please eloborate your requirement?
Regards,
Prasobh -
hello
is it possible to hav shift report workcentewise? if yes how config is done?In T.code : SHR0 (zero) Shift Report overview.
Enter Report Type and Usage as workcentre, please do the this customazation then you find workcentres in F4.
http://help.sap.com/erp2005_ehp_03/helpdata/en/45/c9ba093c512e96e10000000a155369/frameset.htm
Please read the information from above link this should help.
Jim -
Shift sequence query in PP work center
Dear All,
I am having one problem while maintaining shift sequence in work center. I have maintain all config settings in OP4A shift 1 shift 2 shift 3 but when I create work center and select shift sequence, it is only taking shift 1 and not all 3 shift for all 7 days.
Can anyone tell me the solution?
Thanks in advance.
Regards,
MaxDear Santosh,
Thanks for the valuable inputs.
I have created following sequence in OP4A.
1, Create a Group eg. CB
2.Create a shift definitions like SHIFT1,SHIFT2,SHIFT2, START/END DATE, START/FINISH TIME OF SHIFTS, NO BREAKS ARE THERE and assign it to group.
3. Define individual shifts SEQUENCE DAYWISE wrt to groupo.
4..Assign grouping in capacity header of work center.
5.Now go to add interval option and create a new version of capcity which contains desired shift sequence from the shift group assigned.
7. assign proper valid froma and valid to dates.
8. In capacity header screena ssign the newly created capcity vesrion as active vesrion.
BUT STILL i WILL ABLE TO MAINTAIN ONLY FIRST SHIFT SEQUENCE FOR ALL 7 DAYS.
SYSTEM IS NOT SHOWING 2ND AND 3RD SHIFT.
PLEASE HELP ME OUT.
THANKS
MAX -
Shift patterns for work centers
Hi,
I have question regarding shift patterns for work centers. We are actually utilizing the work centres in a aftermarket setup (service jobs). What we would like to do is to add shift patters to the work centers which look similar to this:
Mo-Su 07:00-19:00, Mo-Su 19:00-07:00 4days on/4 days off/4 days on/4days off. As you see we would like it to be a rolling schedule so the first 4 working days the day shift, then 4 days off, then the next working days the night shift and so on.
Is there a way of simplyfying this setup? The length of the cycle can only be set to a maximum of 7 days meaning I can not create a rolling schedule in a simple way. I do know that I can manually add intervals with say a seven day cycle and defining the working hours and additional create shift for holding predefined working hours and breaks.
I have looked at shift sequences but that doesn't seem to be helpful in this scenario? The sequence seems only to be used as a sequence on a daily basis.
If anyone has solution for this or if you have any thought on how to process I would be very thankful if you shared these.
Thanks in advance
Edited by: Karimi on Aug 12, 2008 1:13 PMIn T.code : SHR0 (zero) Shift Report overview.
Enter Report Type and Usage as workcentre, please do the this customazation then you find workcentres in F4.
http://help.sap.com/erp2005_ehp_03/helpdata/en/45/c9ba093c512e96e10000000a155369/frameset.htm
Please read the information from above link this should help.
Jim -
Work center capacity header freezed
Dear Gurus,
we're not able to edit the work center capacity header. not able to edit the start and finish times.
it is happening only for one work center. in other work centers same capacity category is editable.
Please help us in resolving this.
Regards,
GowriHi,
Check your work center categeroy definition for which edit is not possible.
The work center category determines which data can be maintained in a work center.
Each work center category is assigned to the applications (for example, production, plant maintenance or quality management) whose menus allow you to maintain work centers with this category.
Each work center category has a number of screens assigned to it which the system displays when work centers of this category are displayed. The screens contain groups of fields (for example, scheduling data). Depending on the work center category, you can make field selections on these screens (for example, defining required entry fields).
Thanks,
nandha -
Work Center Capacity Shift Interval
Hello,
I'm looking for a function or Tables from which I can get Work Center Capacity Shift & Interval data, Transaction CRC3.
Any help in this regard will be highly appreciated.
Regards,
Hashir Ahmed.hi,
check these tables.
AFIH Transparent table Maintenance order header Application table (master and transaction data)
AFKO Transparent table Order header data PP orders Application table (master and transaction data)
AFRU Transparent table Order Confirmations Application table (master and transaction data)
AFVC Transparent table Operation within an order Application table (master and transaction data)
CABN Transparent table Characteristic Application table (master and transaction data)
CBPR Transparent table CO-ABC: Activity Master Table Application table (master and transaction data)
COEP Transparent table CO Object: Line Items (by Period) Application table (master and transaction data)
CRCA Transparent table Work Center Capacity Allocation Application table (master and transaction data)
CRHD Transparent table Work Center Header Application table (master and transaction data)
CSKS Transparent table Cost Center Master Data Application table (master and transaction data)
CSSL Transparent table Cost Center / Activity Type Application table (master and transaction data) -
Hi PP Expert,
I have requirement for this shift :
Shift 1 : 08.00 to 17.00
Shift 2 : 20.00 to 04.00 next day
How do you define it in SAP ?
Should i create that like this ?
Shift 1 : 00.00 to 04.00
Shift 2 : 08.00 to 17.00
Shift 3 : 20.00 to 24.00
Is it normally maintain like that or is there any way to create in two shift definition?
Regards,
Arman LieDear Arman,
During shift definition generally the previous shift end time will be taken as the next shift start time,but in your case the first shift
starts at 08:00 and ends at 17:00.
The second shift is starting at 20:00(Night 8'o clock) and ending at 04:00 in the morning.How do you treat the time between 17:00
to 20:00?
Check out in this way,In OP4A,create the grouping logic->shift defiition->
S1 first shift 01.08.2011 31.12.9999 08:00:00 17:00:00 9.00
S2 second shift 01.08.2011 31.12.9999 20:00:00 04:00:00 8.00
Then under Shift Sequence,
2S 1 2 shift sequence S1 S1 S1 S1 S1 S1
2S 2 S2 S2 S2 S2 S2 S2
Assign this in the work center capacity header,by definish the shift start as 08:00:00 and end time as 04:00:00 by mentioning the
duration of break,then in the grouping mention the respective shift grouping,in the intervals and shifts mention the start date and
end date and select the shift sequence.
Now in CM01 accordingly you will be able to see the available capacity,assuming you have not defined any break timings either in
the shift sequence or else in the capacity header in the work center.
Check and revert back with your queries.
Regards
Mangalraj.S -
how we configure the shifts in work center. please describe the whole procedure.
thanks in advanceDear,
You need to define a shift in OP4A - define new grouping
click on New entries...let us say 99, give some text
Select 99 and double click on shift definition
click on new entry
shift - 1, text - first shift, start date-010108, end date - 31129999, start=07:00:00, finish-15:00:00
shift - 2, text - second shift, start date-010108, end date - 31129999, start=15:00:00, finish-23:00:00
shift - 3, text -Generalshift, start date-010108, end date - 31129999, start=08:30:00, finish-16:30:00
Double click on shift Sequence
Seq-1shift-1,des-shift-1,day1-1,day2-1,day3-1,day4-1,day5-1,day6-1,day7-1
Seq-1shift-2,des-shift-2,day1-2,day2-2,day3-2,day4-2,day5-2,day6-2,day7-2
Seq-1shift-3,des-shift-3,day1-3,day2-3,day3-3,day4-3,day5-3.(hope only 5 days working for General shift)
save this.
In work center change transaction capacity view
assign this grouping no 99.
Enter active version = 1
Click on interval and shift push button (left top)
follow the menu path Edit>insert>insert interval
enter valid from and valid from field enter shift sequence and remove the data if there in any other filed and click on ENTER. all the days in week are defaulted with the shift seq you defined.
Hope it is clear, or come back
Please check this link also,
[Shift Sequence|https://forums.sdn.sap.com/click.jspa?searchID=16735253&messageID=3810730]
Regards,
R.Brahmankar -
Hi all,
Im little confused with the capacity header in work center. In the capacity header there is one place to give start time, end time, length of break and number of individual capacity. And in grouping key i can define the shift and shift sequence. So if im maintaining both of these ( standard avilable capacity and grouping key), which will be considered to calaculate avilable capacity?Hi
If you are running three shifts ,please maintain the data as given belwo
start :00:00:00
End:23:59:59
Break :03:00:00 ( 1 Hour per shift so 3 hrs for 3 shifts)
No.of individual capacity :1
System will understand that it is round the clock operation with total three hour brak and you will get 21 hour per capacity
Hope this helps
regards
Prakash -
Hi gurus,
Presently I am working for a Engineering and Construction Project, I am new to Project systems. In this project client have one Fabrication unit and 20 Projects across the India. In project site also they are doing some production activities. How to create a work center in this aspect( There is no planned activities as of my knowledge)
Thanks & Regards,
Sudhahai,
you are saying workcenter needed for Fabrication unit,
As per my experiance in Fabrication unit it mainly consist of all types of welding(manuval, MIG, TIG etc) , and also bending and ctting of rods with (power saw, band saw etc).
find out one suitable Activity unit for welding with time, Power consumption etc -
Regarding Work Center Capacities
Dear Exprts,
How many Capacity Categories Can we maintain in Work center.
Regards,
MANOJDear Manoj,
How many Capacity Categories Can we maintain in Work center.
One can maintain any no of Capacity Categories in the work center, provided that you have actually defined/maintained
that no of Capacity categories in customizing.
So while creating work center you can have capacity categories like machine, person, processing unit, lab etc. as per requirements.
Revert back in case of query,
Thanks,
Sudhakar -
Regarding work center hierarchy
Hi all,
I have 2 work centers liked to a superior work center in a hirarchy.
Is it possible to do capacity planning at the superior work center level.
The scenario is like this - I will get planned order at a superior work center level. I will convert the planned order into 2 production orders with child work centers in respective order.
Now I want that, when I see the capacity overview for the superior work center, it should be full. That means I want to link the capacities of the child work centers to the parent work center.
Please let me know if it is possible ?
Regards,
YogeshHi,
Work center hierarchies are used in capacity planning to cumulate available capacity and capacity requirements. You can cumulate available capacities from subordinate work centers to a superior work center level in order to determine the total available capacity for the superior work center.
In your situation, I think you need to create two planned orders with the two work centers and after this you will be able to see the capacity requirements cumulated at the superior WC.
Regards
Datta -
Regarding work center master creation In PP
Hi Iam Kiran working on routings and work centers creation.I want to know how the formulaes are derived for caluculating capacities,shedulling,Costing.where can I find study material regarding formulae derivation.For the above mentioned.Please respond if your having any material with respect to this content.
Hi Kiran,
Please use the following transaction to create/check the parameters & formulas,
OP17 - Create formula parameter
OP19 - Maintain standard value key. (The parameters created are entered in this standard value key & this std value key is used in the work center (CR03) basic data tab page)
OP21 - Create Formulas
These formulas are assigned in the capacity, scheduling & costing tab page in the workcenter.
This workcenter is assigned to an operation in the routing (CA03).
Regards,
Senthilkumar
Maybe you are looking for
-
How to Add New Parameter in Cluster with LabVIEW Executable Program?
In this VI,it can write the parameter in Cluster to the database (Access 2003).it run well. But When I add another parameter in Cluster,such as EE,I have to modify this Cluster. And at the same time,I have to modiy the database (I should add
-
AM and VO classes in oracle/apps/xxcus/objname/server
Hello, I have created an OA search page using p7523554_R12_GENERIC for Release 12.0.6 I have created my project in oracle.apps.xxcus.objname.webui I created: my VO in oracle.apps.xxcus.objname.server my AM in oracle.apps.xxcus.objname.serveri my PG i
-
GR done as Non Valuated Goods Receipt
Hy Gurus, We have rescently implimented MTO for all our 3 manufactruing plants.Problem is, during the GR of Header Materials we have noticed that GR is done as Non Valuated - there is an automatick tick activated for Goods Receipt, Non Valuated in Go
-
My computer is part of the iMac 1TB Seagate Hard Drive replacement program. What is the best external modem to use in order to back up my files prior to me dropping off my computer.
-
Couldn't open text messages on E63
I could not read my message. While browsed to understand the issue & I was advised to update the firmware from 400.21.13 to 500.21.009. Is there I can update my E63 device software using phone browser? I do understand why I'm not able to open the tex