Regarding the Delivery schedule item in Production order

Hi Gurus,
Kindly can you let me know what are the settings to be done for getting the delivery schedule line number in the production order along with the sales order and item number for a MTO scenario.
Regards
Anand

If you're working with stg. grp 20, it should do what you're looking for.
If you're not sure, do this in your sandbox -> assign the stg. grp in material master, create a SO for this material, run MRP, convert the planned order to production order & verify the results.
To know more about this stg. grp you can go thru SAP help or just do a search in this forum or maybe wait for someone to paste the links for you.

Similar Messages

  • Print out the delivery schedule item wise

    Hi friends..
    can any one pl tell me how to take the printout of the delivery schedules item wise.
    i have checked the ME80RN but it doesnt work for me.
    client want to print delivery schedule not SCHEDULING AGGREMENT.
    Your help will be highly appreciated..with points..
    Regards,
    Anil

    Hi,
    Hope you can create an access sequence with material as a field and create a condition record based on this...
    Bcoz mess determination takes place at header level.
    Reg,
    Deepak

  • System problem in the delivery schedules of a purchase order ?

    hello to all,
    I am creating a purchase order and displaying it (in smart form). what i am noticing is the system does not keep that entry of the delivery schedule(with itself) that has the same audit quantity and delivered quantity. why is this so and how to display that entry ?
    suppose following r thr delivery schedules entries(against a material), while creating a purchase order..
    PO Quantity of Material is  4
    Delivery Schedules are:
    Deliv Date  SL Qty    Stat Del Date  GR Qty   Open Qty
    01.03.2006    1        01.03.2006      1          
    03.03.2006    2        03.03.2006      1           1
    04.03.2006    1        04.03.2006                  1
    where,i believe, 'SL Qty' = Audit Quantity and 'GR Qty' is the Delievered Qty.
    Now when i display these delivery schedules(thru a smart form) the first entry in the deliveryschedules does not get displayed.
    Deliv Date  SL Qty   GR Qty  
    03.03.2006    2        1  
    04.03.2006    1        0  
    why does system deletes the entry whose audit qty is equal to the deliv qty ??
    hope u all got it... Thanks for yur time..

    Hello,
    Refreshin this thread ... can sumone anwser to my query ?

  • Route is not considering in delivery scheduling for Third party order proce

    Hi All
    Advance thanks for your inputs
    We need to consider the route in the delivery scheduling for third party order processing..
    Example
    i have standard order (document type OR)  when i have item cat TAN its considering the route for ariving the material availability date, if it has TAS(third party) then its not considering the route......
    But we want to consider the route in deliver scheduling in case of third party order...
    kindlly pls advice..
    regards
    raja

    Hi Viven.,
                        Routes they come under normal order as we deliver the goods,but here in TAS,third party sale we are not delivering the goods,Just there is logical moment i.e MIGO,So i dont think we do routes for TAS
    Thanks & Regards
    Narayana

  • The delivery schedule lines don't get created automatically on MRP run.

    Hi All,
    The delivery schedule lines don't get created automatically on MRP run for subcontracting material.  I have maintained source list as follow eg.
    Valid from | Valid to | Vendor | Porg | PPI | Agreement | Item | Fix | MRP | MRP area
    02.11.2009 | 31.12.2999| XYZ | XY01|     |AA0000XYZE |10 | X |2 | ABC
    Could you please help me about this issue
    Thanks in advance.

    Hi Amit,
    Please ensure the value of Special procurement key in the MRP2 view for the material. It should be maintained as 30 - subcontracting.
    Thanks and Regards,

  • Error in scheduling parameters for production orders

    Hi Guys,
    Greeting for the day u2026u2026u2026.
    I am trying to create production orders creation for own order  type ex MM01, but I am getting error message as u201C scheduling parameters are not defined for the order type u201C even though I have maintained following parameters as below,
    Production scheduler      -
    xxxxx,
    Detailed scheduling -
    check box of scheduling ticked,
    Rough cut scheduling    --- scheduling id u201301, scheduling and generate capa requi,, boxes     ticked,
    Adjust scheduling  -- requi to operation  date,
    Scheduling control for detailed scheduling ---backwards and check box of auto scheduling ticked
    Operation segment ---setup,
    All operation in order will be reduce
    Do not reduce,
    Could any one light on this issue,
    Thanks in advance,
    Mohan

    Hi,
      This error will come if you have not maintained Define scheduling parameters for production orders.
    Check this order type whether linked with respective plant in OPU3.*And give production scheduler * mark ie, all.*
    And in Define production scheduling profile - OPKP, link your order type in the page below.
    In material master work scheduling view, input production sch profile or prod scheduler.
    Regards,
    Dharma

  • Link Delivery Schedule Line and Purchase Order History

    Hello,
    Please, i need to know if there is some link between delivery schedule item and PO history like PO history.
    I need to know the quantity of goods issues per schedule line...
    thanxs a lot
    Jean Baena

    Hai.
    Check CO06 for undelivered item list.
    Regards,
    Mani

  • Production scheduling profile for production order type 10 does not exist – SAP Message No.10085

    When i tried to make confirmation for Production Order through CO15 transaction , i receive the following error message “ Production scheduling profile for production order type 10 does not exist – SAP Message No.10085 “
    In Work Scheduling view, Production Scheduling Profile is maintained as per OPKP only.
    How to check whether production scheduling profile is maintained for relevant order type 10.
    To do this , i went to OPKP & KOT2_OPA transactions but i don’t know how to check. I guide me through with a screen shot.
    Also, pls explain about  “Order Type 10” and how it is linked with material and order execution.
    Looking for a detailed explanation with screen shots , since i am new to SAP.
    Thanks With Regards,
    Dinesh Kumar V.

    Hello Dinesh,
    Please check the order type dependent parameter in OPL8 here you will get the Substitute Scheduler
    Then go to OPCH and check valid production scheduling profile assign here as per OPKP to your production scheduler for your plant.
    Production order have Order category as 10  Process Order  40 in standard SAP you can check this in OPJH.
    Best Regards,
    R.Brahmankar

  • Copy variant characteristics from Sales Order/Item to Production Order

    Dear All,
    I have a requirement wherein I have to copy variant characteristics fromSales Order/Item to Production Order. In this regard I was looking at Enhancement "CLFM0002". Is it possible to copy the variant characteristics automatically from the Sales Order/Item to Production Order?
    Thanks,
    Pravat.

    Pravant,
    If you are implementing Variant Configuration, or using configurable material in that case you will have to maintain
    Characteristics in CT04
    Classes in CL02
    Configuration Profile CU41
    The material that you are mentioning must have class and charcteristics activated or mentioned in material master. undre classification view. In production you maintain Configurable material BOM  we will be using the same material
    Regards
    Sathya

  • How I can find the  Delivery address changes in purchase order

    Hi Friends,
    How I can find the  Delivery address changes in purchase order
    item details.And how i can find who did ths changes.

    Hi,
    Go to ME22N, here select the line item and click on menu "Environment > Item Changes" to track the changes.
    For multiple POs, go to ME2N, here enter Selection Parameter as "ALLES" and execute the report to check all the changes.

  • Production scheduling profile for production order type 10 does not exist

    Kindly suggest me how to resolve this error
    Production scheduling profile for production order type 10 does not exist

    Hi Archana,
    Go to material master-work scheduling view and check what is the production scheduling profile maintained for the same materisl -plant combination.
    then go to OPKP and check if production scheduliong profile is maintained for relevent order type 10 in custmizing. If not maintain one and it should resolve the error.

  • How can I add a new line item for production order?

    HI all,
    How can I add a new line item for production order through BAPI/FM? Thanks in advance.

    Hi Mil,
      Unfortunetly SAP is not in front of me.
    But if possible go to BAPI transaction , check for any production order's bapi for CHANGE purpose. Where you will be able to add your new line.
    Reward if useful!

  • Delete the perticuler Line Items of PURCHASE ORDERS.

    Hi Friends,
    i want delete the perticuler Line Items of PURCHASE ORDERS.
    EXAMPLE :
    I HAVE ONE PO  : 2000010.
    IT HAVING 10 LINE ITEMS. LIKE 1 , 2 , 3 , 4 ,5 ,6 ,7 ,8 ,9 , 10.
    FOR THIS PO , I WANT DELETE THE 5TH LINE ITEM.
    MEAN FOR PERTICULAR PO I WANT DELETE ITS SPECIFIC LINE ITEM NO.
    ANYBODY EXPLIAN..
    THANKS

    Are you looking to do this from an ABAP program or from the PO Screens?   EKPO does have a field for the Deletion Indicator.  Is there a reason why you would choose to do this from an ABAP program rather than the ME22n?

  • User Exit for the Settle rule of a Production Order

    Hello all
    i got a requirement to change the settlement rule of a production order to multiple receivers.
    suppose i have the following rule
    Categeory | Settlement Reciever | Receiver Short text |   %   | Settlement Type | No | Source Assignment
        MAT             ZMDT89                   ZMDT88              100        FUL                 1            left as blank
    now my requirement is that i have to default the source assignment as 200 (Materials) so as to allow the other reciever entered with the same settlement type as FUL and also the No should be 2
    i.e. my req is like this
    Categeory | Settlement Reciever | Receiver Short text |   %   | Settlement Type | No | Source Assignment
        MAT             ZMDT89                   ZMDT88              100        FUL                 1            200
        G/L             G/L A/C no                G/L shor text       100        FUL                 2            100
    the bold one is i have to ADD
    the T-Code is CO02.
    your help is highly appreciated...
    thanks in advance

    hi,
    check these exits in co02.
    Transaction Code - CO02                     Change Production Order
    Enhancement/ Business Add-in            Description
    Enhancement
    PPCO0010                                Enhancement in make-to-order production - Unit of measure
    PPCO0012                                Production Order: Display/Change Order Header Data
    PPCO0013                                Change priorities of selection crit. for batch determination
    PPCO0015                                Additional check for document links from BOMs
    PPCO0016                                Additional check for document links from master data
    PPCO0017                                Additional check for online processing of document links
    PPCO0018                                Check for changes to production order header
    PPCO0019                                Checks for changes to order operations
    PPCO0021                                Release Control for Automatic Batch Determination
    PPCO0022                                Determination of Production Memo
    PPCO0023                                Checks Changes to Order Components
    STATTEXT                                Modification exit for formatting status text lines
    PPCO0009                                Enhancement in goods movements for prod. process order
    CCOWB001                                Customer exit for modifying menu entries
    COIB0001                                Customer Exit for As-Built Assignment Tool
    COZF0001                                Change purchase req. for externally processed operation
    COZF0002                                Change purchase req. for externally procured component
    PPCO0001                                Application development: PP orders
    PPCO0002                                Check exit for setting delete mark / deletion indicator
    PPCO0003                                Check exit for order changes from sales order
    PPCO0004                                Sort and processing exit: Mass processing orders
    PPCO0005                                Storage location/backflushing when order is created
    PPCO0006                                Enhancement to specify defaults for fields in order header
    PPCO0007                                Exit when saving production order
    PPCO0008                                Enhancement in the adding and changing of components
    reward points if hlpful.

  • Transfer to PA the target costs of a production order

    Hi everyone,
    How can I transfer to PA the target costs of a production order?
    Thanks
    Cátia Pereira

    Hi
    1. Check your settings in KE4U - Strategy 001 must be assigned to PV=01 and Rec Type F
    Tick the "Mat Cstng" indicator and assign COPA Qty Field ABSMG
    2. Assign costing key to Mat Type in KE4J or KEPC
    3. assign Cost Comp Str to VF in KE4R
    4. Assign Value Fields to your variance categories in PA Transfer Structure....
    Tick "Variances to Costing Bsed COPA" in your settlement profile
    Br, Ajay M