Rejection of WBS settlement step in SAP PS

Dear Experts,
I have on e new requirement to ignore WBS settlement step from SAP PS flow.
Current scenarion ;-
WBS --> Network --> Activity --> Material Po -->Budgeting --> Release budget -->PO creation --> GRN --> GI --> MIRO -->AS01   --> CJIC --> Settlement CJ88 --> Activity Confirm --> WBS Techo --> WBS Closed.
Require Scenarion :-
WBS --> Network --> Activity --> Material Po -->Budgeting --> Release budget -->PO creation --> AS01 --> GRN --> GI --> MIRO ->Activity Confirm --> WBS Techo --> WBS Closed.
At the time of GRN only item should be cpitalised.
can anybody explain is it possible? if not then why?
Please explain impact on PS module.
Please do needful.
Thanks & Regars,
Arvind Tirlotkar.

Hi,
I think you are talking about direct capital item procurement.
you can make statistical project for that; then the wbs will only be used for budget check and you don't have to settle also.
at the time of pr/po creation you can have wbs element field and asset field in account assignment tab (get with the help of MM consultant); all cost will got o asset and budget will be checked against wbse.
Regards,
Harsh.

Similar Messages

  • Any standard report to show WBS,settlement, asset no and asset cost/value

    Hi All,
    Please advice . Is there any standard report to show WBS,settlement, asset no and asset cost/value ? I tried tcode kosrlist_pr but it does not show asset cost/value.. it shows only WBS,settlement and asset no.
    Thank you.
    Best Regards,
    Nies

    Dear,
    der is no such standard report to show WBS,settlement, asset no and asset cost/value as perv my knowlwdge. so do one thing select one standard report which is more similar to standard report to show WBS,settlement, asset no and asset cost/value but some of like asset no or asset cost or some other values not reflecting in that std report. den u take the Table name and field name of that particular fields which u wann reflect in the report. use the logic of STD TC of SAp which more similar to which u wanna preapre the New TC. tae help of Abaper. tell ur querry and content of ur report . he will definately do it
    if ur get my ans reward with points
    Regards
    Rakesh

  • WBS settlement with AUC

    Hello,
    Can anybody help to do the configuration for wbs settlement with AUC other than below mentioned configuration.
    1. New Asset class creation with line iteme settlement.
    2. Allocaiton structure added settlement with FXA.
    3. New settlement profile created with default object type FXA,document type AA and amount settlement check box activated.
    but based on above mentioned configuration i am not moving forward, kindly suggest any more configuration need for this requirement.
    Thanks for your advance help.
    Regards,
    Lakshmi.

    Hi Lakshmi,
    There are quite a few settings to be maintained. I do not remember exact sequence of steps but here are a few pointers.
    1. Investment profile needs to be created with 'line item settlement'
    2. AUC asset class to be created and assigned to this investment profile
    3. Investment profile to be linked to project profile.
    4. Source structure to be assigned to investment profile
    There may be other steps I am missing but I hope these help.
    Also, if you mention any error that you are facing or at which point you are getting stuck, it would be helpful.
    Regards

  • PM order settlement steps

    Hi,
    I have a basic question regarding PM order settlement. I know that for PP orders, following are the settlement steps for individual processing.
    1) After final confirmation of the order (status CNF) using IW41, do GR (IW8W for refurbishment order, etc). Status will now be DLV.
    2) Technically complete the order (IW32-Order-Functions-Complete-Complete (technically). Order status is now TECO.
    3) Actual overhead calculation - tran KGI2
    4) WIP calculation - tran KKAX
    5) Variance calculation - tran KKS2
    6) Actual settlement - tran KO88.
    Now for PM order, please tell whether steps 4 and 5 are relevant. Do we need to calculate WIP and variance for PM order? What are the exact steps to settle a PM order?
    Any help will be highly appreciated.
    Thanks and regards,
    Abhijit

    Hi
    Please refer the link  [http://help.sap.com/saphelp_47x200/helpdata/en/b1/c04d28439a11d189410000e829fbbd/frameset.htm]
    Regards,
    Rakesh

  • Quantity in Account Based COPA upon WBS Settlement

    Hi All
    I am facing an issue with the quantity flow into Account Based COPA.
    We have activated account based COPA and we use sales orders/billing and also Projects.
    When I am creating sales order (no reference to WBS), delivery against sales order and billing from delivery, I see that
    quantity posted in Delivery document and quantity from billing document are transferred to account based COPA along with GL postings.
    But when I am creating sales orders with account assignment of WBS, then all the delivered quantity and billed quantity
    are posted to WBS elements along with the FI postings. Receiver on my WBS is COPA segment.
    When I settle the WBS that carry both revenues and costs (COGS to be sepcific), I see that amounts are settled correctly with
    right GL accounts into account based COPA, but I do not see that quantities getting transferred.
    I know how we can transfer quantities using costing based COPA during settlement (using PA Transfer structure with Qty setting), but
    not sure how it works in account based COPA for settlements.
    Any thoughts on how to transfer quantities from WBS settlement to account based COPA.
    Your help is much appreciated
    Thanks
    Rama

    Hello Rama,
    First of all, I want to give you with note 352610 some general
    information about the update of quantities in CO. For further
    analyses I would recommand you report RKACSHOW where you can
    find the relevant tables you can take a look, f.e. table COKA,
    COSS(A) and COSS(A). Probabely in table COKA the field 'MEINH'
    is not filled.
    Furthermore I want to provide you note 27922 which explains in detail
    the system behaviour for settlements in this case.
    https://service.sap.com/sap/support/notes/352610
    https://service.sap.com/sap/support/notes/27922
    Thanks and best regards,
    Ronghua Fan

  • Error when reversing WBS settlement

    Hi guys,
    When i am reversing the WBS settlement i am getting dump with this program error
    BALANCE_CALC_LOGVO_2.
    I searched some SAP notes and it is saying about document splitting. Did anyone see this before? I couldn't understand a bit. I will appreciate any sort of help.
    thanks, Satya

    Hi
    Check out this note for correction
    [1046656|https://websmp130.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=1046656]
    - Pithan

  • BAPI/FM to create WBS settlement rules.

    Hi,
    I would like to know if there is a FM or BAPI to create WBS settlement rules. I use CJ20N transaction to create manually. Any qucik response will be much appreciated and Obviously rewarded
    Thanks,
    Vivek.T

    U can use the user exit
    COPCP005 and its function exit EXIT_SAPLCKAZ_001. Try this out....
    Or choose any one options from the below list which suits ur requirement:
    Develop Enhancements for Material Costing
    The following SAP enhancements are available for the area Cost Estimate with Quantity Structure:
    o Costing Reports (SAPLXCKA)
    o Costing Production Resources and Tools (COPCP003)
    o Material Valuation with Cross-Company Costing (COPCP001)
    o Costing Bulk Materials (COPCP004)
    o Valuation Price for Materials from User Exit (COPCP005)
    1. Costing Reports: SAPLXCKA
    Here you can create your own reports for displaying cost estimates with quantity structure or activate the example reports in the standard system.
    This enhancement contains the following components:
    · EXIT_SAPLCKAZ_001 Display/print itemization
    This enhancement contains example program code from SAP that you can modify and use for your own enhancement, or activate directly as a report for the itemization.
    · EXIT_SAPLCKAZ_002 Display/print cost components
    This enhancement contains example program code from SAP that you can either modify and use for your own enhancement, or activate as a report for the cost components.
    · EXIT_SAPLCKAZ_003 Display/print cost components and itemization
    This enhancement does not contain example program code.
    In the cost estimate with quantity structure you access the reports with Costs -> Display user exit. The report refers to the first cost component view listed. If you want to see the costs with reference to another cost component view, choose Settings -> Cost display and choose the desired report under Select view.
    You can display your own reports in the information system by adding them to the report list for product costing.
    See also:
    Check report list for material cost estimate
    2. Costing production resources/tools: COPCP003
    This enhancement contains the component EXIT_SAPLCK01_001.
    The costs for production resources and tools are calculated as a flat rate within production overhead.
    This enhancement enables you to plan the costs for production resources in costing with quantity structure in different ways. Here you can specify how the production resources are to be costed.
    In the cost component structure, the production resources can be shown in separate cost components.
    This enhancement contains example program code from SAP that you can modify or use as is.
    3. Material valuation with cross-company costing: COPCP001
    This enhancement contains the component EXIT_SAPLCK21_001.
    Here you can enter the prices for valuation of a material that is transferred between company codes.
    You have the following options for the valuation of materials that are transferred between company codes:
    o You are using the standard system without cross-company costing. In this case the system uses a price in the material master record in accordance with the valuation strategy. The material is treated as if it were externally procured.
    o You activate cross-company costing. In this case the material is recosted in the other company code or transferred according to the transfer control ID.
    If you have not activated cross-company costing, you can use this enhancement to define alternative prices for valuation of a material that is transferred between company codes. That is, this enhancement allows you to specify which price should be used instead of the price from the material master record.
    In include LXCKAF)) you can find an example program code. However, this code example can not be directly copied and used
    4. Costing Bulk Materials: COPCP004
    This enhancement contains the component EXIT_SAPLKKEX_001.
    You can use this enhancement to plan the costs for bulk materials and show in the cost element itemization.
    If the indicator Bulk material is set in the material master, the indicator Relevant to costing in in the BOM does not accept input for the item. The enhancement allows you to determine the costing relevancy. The items with the bulk materials indicator at item level of BOM are also included as relevant to costing.
    This enhancement contains example program code from SAP that you can modify or use as is.
    5. Valuation Price with Valuation Strategy U: COPCP005
    This enhancement contains the component EXIT_SAPLCK21_002.
    You can use this enhancement to specify prices for valuation of materials if you want to use valuation strategy U (valuation with USER EXIT) for material valuation to find a price for the materials.
    This enhancement does not contain any example program code from SAP.
    Activities
    To activate the SAP example reports (the procedure is similar forthe other enhancements):
    1. Create a new project or use an existing one.
    2. Set the indicator SAP enhancements and choose Change.
    3. Enter SAPLXCKA as the SAP enhancement and choose Save.
    4. Set the indicator Enhancement components and choose Change.
    5. Position the cursor on the enhancement component EXIT_SAPLCKAZ_001 and choose Edit -> Use SAP source code.
    6. The system asks whether you want to create ZXCKAU01. Answer Yes.
    7. Maintain the attributes.
    8. Save the program and choose Back.
    9. Position the cursor on the enhancement component EXIT_SAPLCKAZ_002 and choose Edit -> Use SAP source code.
    10. The system asks whether you want to create ZXCKAU02. Answer Yes.
    11. Maintain the attributes.
    12. Save the program and choose Back.
    13. Activate the project.
    14. To display the reports, you must perform costing again.
    Further notes
    Unlike modifications, enhancements are always upgrade-compatible because they are implemented in a name range reserved for the customer rather than in the SAP original.
    The general procedures for creating enhancements can be found in the enhancement transaction CMOD under Goto -> Online Manual. This takes you to the SAP library where you can find detailed information on customer exits.For more information on the above enhancements, see the associated function module documentation.
    Reward if useful...
    Regards
    Karthik D

  • Cost Object in FI document with WBS Settlement

    Hi,
    I'm testing WBS settlement to G/L account which is cost element. I made some substitution rules because I met an error message saying that "Cost Object is needed"
    As a result I can settle WBS to cost elements such as COGS etc. I got a FI document, CO document and PCA document. Everything looked so nice.
    Suddenly I noticed, however, that there is no such a thing like cost object on FI document. When I look up the FI document using FB03, I found that the PS-POSID was empty. Of course, CO documents have Cost Object.
    What I wonder is as follows
    1. Is this standard? Is it natural that FI document with CO doc has no cost object on it?
    2. If I need to use FI document to determine WBS element, what is the best to way? Is it possible to enter Cost Object such as wbs element in FI document during settlement?
    Thank you for your kind advice in advance.
    Message was edited by:
            Namseok Kang

    Kang,
    In the message which you got, the word 'Cost Object' refered to a cost center, or order, or any other cost object.
    However, there is another account assignment object with the name 'Cost Object', which was not filled in the FI document. That is normal.
    Right now I don't have much information in the a/c assignment object 'Cost Object'.
    Regards,
    Vishal.

  • FI Document created during WBS settlement

    Hi Everyone,
    I have an issue regarding the FI document generated while running CJ88 for WBS settlement. We settle a WBS to a Cost Center, after it, three documents are created, an FI document, a CO document and a Profit center Document.
    Logic tells me there shouldnt be an FI document  in this situation since im settleing between two cost objects. For example when we settle internal orders no FI document is generated.
    I've checked many threads in SCN about said FI document and i cant find a definitive reason as for why is this document is generated during the settlemet, many threads about it are not answered and some others are not very conclusive.
    Nevertheless! I can live with the FI document but i'd like to change it from the standard "SA" document to "ZA" for analysis purposes. We created de document type and i've changed the settlement profile to use ZA but still after we settle a WBS an SA document is created.
    Can anyone shine any light on this issue? either pointing me in the right direction to modify the document type or by explaining why is it generated?
    Thank you in advance for your time.
    Pelayo.

    Hello Chauhan,
    My settlement profile is enabeled for Cost Center, Order and Fixed Assets all as optional, however the settlement rule in this specific scenario is from WBS to Ctr. (both elements have a Profit ctr. assigned.
    Under Other parameters i've set Document type as "ZL".
    The system creates an FI document like this.
    50
    5XXXXXXXX1
    123.456,00-
    USD
    PCtr 2
    40
    5XXXXXXXX1
    123.456,00
    USD
    CCtr 1
    PCtr 1

  • WBS Settlement by Line Item

    Hi gurus,
    Can anyone please help me figure out how I can trigger the WBS settlement process to settle by line item and not in summary by assigned cost element?
    please help
    thanks
    Brian

    Brian, 
    Did you ever get this quesiton resolved?  I'd like the answer if you did.
    Thanks,
    Ralph

  • Help required in the last step of SAP Query

    Hi Experts,
    I have walked through all the steps of SAP Query except for the last one.Please tell what to do in the attached screen shot of SAP Query.
    Thanks and regards
    Rajeev Chhabra

    Hi Vinod
    My problem is that
    1.I am not getting the screen Basic List Line structure in the Tcode SQ01 can you tell me how to get that.
    2. In the last step of the SQ01 transaction code Can you please tell what to do on the screen Query layout design(Please give adetailed response)
    Thanks and regards
    Rajeev Chhabra
    Message was edited by: rajeev chhabra

  • Generation of WBS Settlement Rule

    Hi Folks!
    I was wondering if there is any function module that allow me to generate a WBS Settlement Rule for a specific project and for elements on level 3.
    If there is no FM for this, is there any workaround to do this.
    Thx for any advise.
    Regards,
    Gilberto Li

    Hi Gilberto,
    Hm, not a question that has a simple answer. Settlement rules are first of all defined in customizing how the should be behave and secondly lies the question how to update a CO cost object with this settlement rule.
    Let us first assume that customizing is done with a settlement profile named ZZ_PROF for instance. This is defined in customizing like path (from R/3 4.7): Trans SPRO -> Project System -> Costs -> Automatic and Periodic Allocations -> Settlement -> Settlement Profile -> Create Settlement Profile.
    My first advice would be to use the "automatic settlement derivation feature" that can be setup in customizing alike. Trans SPRO -> Project System -> Costs -> Automatic and Periodic Allocations -> Settlement -> Settlement Rule for Work Breakdown Structure Element. Read the docu for this node (right click and choose Display documentation) to understand what possibilities and limitations this functionality has. Below this node you have the possibility to define a "settlement strategy" and allocate this to a project profile. There is also an option to define a BADi whereby you you can somewhat influence the automatic generation of settlement rules. You must "obey" the rules in the "settlement strategy" but can do some filtering of SD orders influence and derive a "settlement strategy" baseed on some coding logic of your choice.
    To execute these settings on operative projects you run trans CJB1 (collective processing) or CJB2 (indicidual processing).
    All in all: This is good functionality but maybe not what you are looking for due to the built in "restrictions" in the "settlement strategy" profile.
    My second advice would be: What I did in the past was to write a batch input program that was run just before period end closing (that is before settlement - of course) that did read all relevant WBS elements without a settlement rule and derived a new settlement rule. Finally, updated the setttlement coding block with this info. Processing of the BDC is then done via trans SM35 the normal way.
    I also did a check for trans CJB2: In include LKAZBF15 there is the "magic" call to the update FM with name KSRG_GENERATE_RULE. One option could be to set a break point here and run the trans to see what parameters has to be filled. This implies that the customizing is done before, of course. I have a feeling that this is NOT the easist solution to use - to fill the parameters correctly may be difficult
    I hope this helps you in deciding what action to take.
    Sometimes a simple BDC will do the trick although it may not be a "good" solution.
    Disclaimer: There might be some other relevant FM to solve your problem as I am not aware of. If you find one for WBS elements then I would certainly be interested in any findings.
    Regards, Johan

  • IM-PS  top WBS settle to AUC

    Dear all experts,
    could you help me on the following issue?
    i am working on a capital project. IM and PS modules are used.
    my key users want to settle lower WBS to the superior WBS and the top WBS to one AUC when they do the monthly settlement.
    i delete the IM profile in the lower WBS, and maintain the settlement rule of them.
    when i do the settle i found that lower WBS settle to the superior WBS but the top WBS doesn't settle to AUC
    could you tell me what's the problem.
    Judy

    sorry, i didn't mean to close the question, as the problem is still there.
    here is what i am.
    AUC is created automatically when i release the project.
    if i didn't delete the IM profile, all the WBS including the top one will be settled to AUC individually.
    but if i delete the IM profile of lower WBS and maintain the settlement rule manually, the lower WBS will be settled to the top WBS. but the top one will not be settled to AUC that is created automatically.
    the settlement type is not AUC,but GES.
    i don't think it is correct.
    could someone offer me some help or suggestions?
    did someone meet the same problem?
    thanks in advance.
    Judy

  • WBS settlement wiht AUC

    Hello,
    Can anybody help to do the configuration for wbs settlement with AUC other than below mentioned configuration.
    1. New Asset class creation with line iteme settlement.
    2. Allocaiton structure added settlement with FXA.
    3. New settlement profile created with default object type FXA,document type AA and amount settlement check box activated.
    but based on above mentioned configuration i am not moving forward, kindly suggest any more configuration need for this requirement.
    Thanks for your advance help.
    Regards,
    Lakshmi.

    Hi,
    Please follow above mentioned points
    Allocation structure added settlement with FXA. -- Path - SPRO - IMG - Investment Management - Projects as Investment Measures - Settlement  -- Maintain Allocation Structures  -create on Allocation structure - and assignment - 010 -- Material & service cost -- and select - click on - source - give Cost elements - from - to
    and click on settlement cost element  - give receiver category -- FXA  - check box for By cost element -- and save it ,
    2.Maintain Settlement Profiles -- Define Settlement Profile -- XX - WBSE Settlement Profile
        select radio button - to be settled in full , give allocated structure ,
         Default object type  FXA  Asset
         select all indicators -- and give other parameter -- Document type -- AA or as per requirement
         and Assign Settlement Profile to Project Profile
    3.New Asset class creation with line items settlement     --   Investment Management  -- Projects as Investment Measures -- Master Data  --Assets under Construction  --Define Asset Classes  ==
          give- Account determination -- asset class , scr layout rule -- capital investment measure ,
    give number range  --whichever is created
    status of AuC -- select radio button -- Investment Measure
    Save it ,
    Now you can create Project -   Run -- CJ88 for settlement
    Thanking you
    Regards
    Mahesh

  • WBS Settlement  reversal

    An FI document was created and entries were posted on WBS "X" for period 03.2008 and the WBS "X" was settled in period 03.2008. In the settlement rule of WBS "X",   WBS"Y" was maintained and customer "Y" was maintained.
    Hence the setlltement went to WBS"Y" and customer "Y" for period 03.2008
    The settlement rule for period 04.2008 was rectified and maintained with WBS "X" and customer "X".
    Now if we do the reversal for WBS "X" settled for period 03.22008, would the reversal take place so in such a manner the settlemnt effect in march 03.2008is negatived. Wht would be the reversal effect.

    Hi ,
    WBS X has been settled  to WBS Y bcoz of mistake in WBS settl rule.
    The settlement happened in 03.2008.
    Now in April month this settlement has to be reversed for period 03.2008.
    If i do reverse settlement in April month for period 03.2008, will the new settlement rule created in 04.2008 take effect or the old settlement rule for 03.2008 will be taken to effect while doing the reverse settlement.
    Regards, Samir