Hi,all,
After releasing of maintenance order, my client's requirement is not to change any data like operation ,components by anyone.Is there any settings in standard SAP to do this or some user exit to prevent anyone to change the data but again changeable option  should be there to some authorised person only.please suggest .Thanks in advance.
rgds
rajib

I thought PJ had a good solution with the user status, and only giving the authorization to remove the status to authorized users.
Unfortunately, there is nothing in the business transactions to forbid changes like operation changes.
I tried forbidding 'change' and that did nothing.
I was surprised that even the forbid 'change documents' setting didn't prevent me changing the operation control key and the system created the change documents, but then I realized there is a different status profile for operations. So this would require assigning the user status to each operation, and even that would not prevent addition of operations.
Of course, I usually advocate accountability over control. If anyone makes inappropriate changes, the system records who, what and when, so you can see who changed an operation after release.
But in the end, if that's what the customer wants.......
I think the solution would be to use user exit IWO10009 (Checks at order "save")
Check to see if the order is released, if it is then prevent user from saving unless their user ID is in a Ztable that has a maintenance view  for administration. A sort of variation on TVARV.
Hope it helps

Similar Messages

  • BADI during release of Maintenance Order thru IW32

    hi,
    is there any badi maintained at the point of, maintenance order release thru IW32.
    When I trace the logic for the release steps of MO, i can only see AT_SAVE method...i cannot see any AT_RELEASE method...
    Rgds
    lakshmi

    [PM/CS User-Exits|http://pjatkin.users.btopenworld.com/documents/PMCSUserExits.pdf]
    PeteA
    [PJA Consultancy Services|www.pjas.com]

  • Automatic release of plant maintenance order at Plant level

    Dear All
    I would like to release plant maintenance order automatically and would like to enable only for a specific plant.
    Could you please suggest different options for this
    Thanks in advance
    Regards
    Yogesh +48 500287949

    Hi ,
    There is no tcode for automatic release of Maintenance order . You have the below options :
    1. Activate the user exit IWO10009 PM Order: Customer Check for 'Save' Event which checks for specific plant and status of order is not released then it would release automatically ..
    2. Create a programme which runs as a batch job and this programme checks for PM Order and filters specific to plant and then filters the orders which are not released and then auto releases....The proramme should be set up as  a batch job which runs at every 30min or etc..
    this would give you some idea ..
    regrds
    pushpa

  • Don't permit release maintenance orders after Period-End CO

    Hello.
    Is there a standard way in SAP to don't permit the creation or release of maintenance orders after a Period-End CO is established? We had a case the last month when an user created an order after a specific hour and it caused an incongruity in the costs because the period-end was established before.

    Gabriel,
    Release can be easily controlled via user-exit IWO10002 as mentioned above (see transaction SMOD).
    But stopping orders being created is a little different, especially when you consider planned maintenance orders via IP30 as this may lead to inconsistencies in the maintenance plan data.
    We would need to know why this caused issues with period-end-closing??
    PeteA

  • Maintenance Order Settlement Rule Mandatory

    Dear Masters,
    I want to make the settlement rule to be mandatory at the time of releasing a maintenance order,can anybody tell me how to achieve this?
    Hope for a sooner reply. Thanks in advance.
    Chin2

    Hey Shailendra,
    Thanks for your reply, your answer solved my question.
    Thanks a lot once again
    Chin2

  • Do not execute - Maintenance Order ??

    Hi,
    There is an option before Release of MAintenance order called 'Do not execute ' , can we click that option if anyone have generated wrong maintenance order by change or by doing worng scheduling of Maintenance Plan. I think this option is for the same.
    Any suggestions.
    Thanks
    DM

    Hi,
    Yes, you could use that option.
    You just need to be aware that the function cannot be reversed.
    -Paul

  • Reservation against maintenance order and MMBE

    Dear Experts,
    As per my knowledge the reservation which are created through maintenance order will be reflected in MMBE as we save the order, without specific to status of maintenance order.But here in my client it is not happening, instead of this it is getting reflected only after releasing the maintenance order. Reserved quantity of material is getting updated only after releasing the maintenance order.However if I select plant and check for reservation details there it shows all the reservations. But the quantity in Reseved column is getting updated only after releasing the maintenance order.
    Please tell me where is the setting for this type of system. Please correct me if I am wrong anywhere.
    I wanted the reservation quantity should get updated in MMBE at the moment I save the order. please do the needful.
    Thanks & Best regards,
    Praveen
    Edited by: Praveen kumar on Nov 28, 2008 4:23 PM

    hi praveen ,
    in MO itself in operation tab the last field you will find... Reservation/PR  with immediate,from release ,never ... u can control from here itself while creating MO .... or you can set this thru config --- Function and settings for order types --- Define collective Requsitions.. here you can find the same setting and ... better to grey out that field for MOs through field selections in operation detail screen in config.
    regrds
    pushpa

  • Maintenance order release cancel

    Hi...Experts
    Can we cancel or unrelease  maintenance order ?
    if yes then pls suggest how  ?
    Regards
    Lokesh

    Greetings Lokesh,
    The System Status REL is not reversible. Once an Order is released, it becomes possible to book actual cost to that order, make confirmations, goods receipts etc. This Orders should then follow on to the status TECO, and then to CLSD.
    A work-around if you wanted to prevent certain actions on a released Order, or to signify that an Order was released, but then pulled back and might not be executed, would be to create a User Status with some business transaction control in OIBS.
    Note that as Maria Terence mentions above, locking the Order is also a good work around that prevents posting costs to Order, among other things.

  • Maintenance order release

    Dear Gurus;
    I am facing a problem, when I am trying to release maintenance order (of a specific order type)- system gives me following error.
    Quote;
    "You cannot use asset class 4001 for capital-investment measures
    Message no. AY106
    Diagnosis
    You have selected the asset class 4001 for automatically creating an asset under construction for a capital investment measure. Asset class 4001 cannot be used for this function.
    Procedure
    Choose an asset class that is marked for capital investment measures, or set the appropriate indicator in the master record for the asset class."
    Unquote.
    How do I fix this problem? Pls. guide.
    Points assured.
    Thanx & regards
    Hemant

    HI
         Change the asset class to Capital invest measure as per configured(ex: 9100)
    Get the asset class from  FI/CO
    Regards
    Seenu
    reward points if it useful

  • Order release on maintenance plan level

    Hi,
    Is it possible to have preventive maintenance order release on maintenance plan level instead of order type level?
    Br,
    Shrithar

    In ECC 6.0 EHP 4 version, you have the option the setting release based on Maintenance plan.
    http://help.sap.com/ERP2005_EHP_04/helpdata/EN/86/429EA7A6E945E18A09EE75D566E789/frameset.htm
    From above link:
    Maintenance plan not immediately released
    You can set an indicator in the maintenance plan item to define that any orders created from the maintenance plan during scheduling are not released immediately. This overrides the "Set released status immediately" indicator in Customizing for the order type, if this indicator is set in Customizing.

  • Revoke release of Plant maintenance order after change is done to the order

    Hi
    I need to know if thorugh some configuration I could enable the feature which revokes the release of a plant maintenance order after certain change is done to the order. Please help.
    Thanks,
    Ankbat

    hi
    you cannot revoke the status of released after changing the order. you can explore the use of user status profile
    regards
    thyagarajan

  • Release of break down maintenance order

    Hi,
    In Configuration ,I have put flagg in "release immediately" check box  for Breakdown Maintenance order ,my requirement is to release this breakdown order immediately while creating the order, which is not happening but in case of preventive maintenance order(system generated order), it is happening. Can anybody please tell me what extra settings ,I need to do to get break down order in release mode at the time of saving??thanks in advance.
    rgds
    rajib

    Rajib,
    If you read the help-text behind the field it tells you that it will only release orders if they are generated in the background e.g. from a maintenance plan or sales order.
    If you manually create an order, then this flag has no effect.
    If you want auto-release manually created orders, then you will need to utilise user-exit IWO10009 (at save event) setting the RELEASE_ORDER parameter.
    PeteA
    [www.pjas.com]

  • Run MRP for production order/maintenance order has been release

    Hi all,
    please tell me how to configure for running mrp for production order/maintenance order has been release. as you know, i want production order has not release will not appear in MD04. I think that is the way for running mrp will not take care about this production order has not release
    Thanks all

    Hi Hoai,
    It is impossible to exclude production order from net requirement calculation in MRP run. You may take a look at the online documentation under the PP-MRP area.
    Material Requirements Planning (PP-MRP)
       Planning Process
         Net Requirements Calculation
           Net Requirements Calculation for MRP
    But there is a way to temporarily exclude production order from MRP. That is you can set the 'delivery completed' indicator in 'Goods receipt' Tab in in production order. Please note that this order will not appear in MD04. Actually to some degree, this order could be considered as completed because ticking the indicator could set status 'DLV' for the order. But you still can execute confirmation, goods issue and goods receipt activities. This way is just a workaround. You may
    consider it.
    Or maybe you can consider the useage of BADI: MD_CHANGE_MRP_DATA to change the MRP run data to see if this could fulfill your requirement.
    Regards,
    Rachel

  • How to block maintenance order from releasing if cost is high

    Hi Experts
    If cost of maintenance order is more than Rs.100000(e.g); it should not release and if less than this value then it can be released.
    Plz help me can i do this in SAP PM and how ?
    Regards
    Pooja

    Hi ,
    In SAP PM there is a functionality known as Permits.You can create a Functional Permit and assign it your order type to acheive the requirement.Create a characteristics with currency format(data type) in the additional field give table name CSEVPERMIT and field name  PKOSTEN.Create a class type 049 and assign the characteristics created to the class.Give this class in the permit create (Tcode IPMD).Assign the range of the values by clicking on the classification sequence like > 50000Rs etc.In the order release option choose 2Permit must be issued else error message.
    assign this permit to the order type or the Technical object.
    Check it out and let know.
    Manisha

  • Operations in Preventive maintenance order has to release then only order has to TECO

    Hi,Friends
    is there any standard in R/3 that as soon as i am not releasing Operations in Preventive maintenance order, order should not be TECO
    when ever i have released Operations then only Preventive Maint order has to be TECO
    Your response is highly appriciated
    Regards,
    Kumar

    Kumar,
    I'm still confused...
    When you release the order header (REL), then all operations are also set to released (REL). You cannot individually release operations using the system status.
    However, you can set user statuses for each operation which are configured in the IMG.
    Please give more details.
    PeteA

Maybe you are looking for

  • How does this work: Long.parseLong(String)

    I am passing a string: "MM/DD/YYYY HH:MM:SS:MM" into the method Long.parseLong and it correctly gives me the epoch time as a long. Is this suppose to do this, or is this a freak thing? Does parseLong know that this is formatted as a date and correctl

  • Process Context changes (.XSD) are not refreshed in the Task Mapping

    Hello, I'm adding new attributes to the .XSD but the changes are not refreshed in the mapping section of the tasks. How can I refreshed these changes? Best Regards SU

  • Integration of Delivery header and item into a single ods

    Hi Nagesh, The reason why i have started a new thread is to award you some more points as i cannot assing you any more points in the prvious thread. I ahve a question though....... you want me to add hdr data to sales document number right.... bue my

  • CMD_EI_API Documentation

    Is there any documentation of the api CMD_EI_API to create/modify/update clients? I'm having a trouble when i update the phone number, it's deleting info that i have at the same level like fax, smtp (and i'm not marking it to update). Thanks.

  • Webi report link to other webi report opening blank page

    I have put the hyperlink to link to the other webi report. But once I click on the links. It open the report with blank page. I have tried it in View mode or Edit mode, the browser will open up another blank page. Following is my links: <a href="http