Replenishment delivery NL created without reference to STO

Dear All ,
I have noticed in SAP that replenishment delivery ( NL ) is created manually in SAP without referencing to Stock transport Purchase order. Can any one explain how it can be created  or is it a glitch in SAP system .
Looking forward to your valuable suggestions/solutions .
Thanks and regards
Veera

Hi,
This can be done in transaction  VL01NO.
BR

Similar Messages

  • Creation of Delivery Using IDOC without reference to order

    Pls suggest is there is any way to create delivery using idoc without reference to order. This is very urgent.

    Hi
    Design the inbound idoc in such a way that it carries all the essential data needed to create a delivery document namely the material number, no of units to be deilvery, delivering plant, storage location, shipping point, warehouse number(if applicable) etc.
    Pass all these details to the function module  RV_DELIVERY_CREATE while creating delivery in VL01N and pass the document type as LO which is delivery document without reference to order.
    But it is advised to have atleast a pseudo order with which we have to create the delivery document.
    Pls reward points.

  • Find debit and credit memos created without reference

    Hi Experts
    Could you please tell the easy way to find out credit memos and debit memos created without reference to oringinal order.
    Regards,
    Santosh

    hello, friend.
    try a query using table VBFA.  specify the document category in both preceding (sales invoice) and subsequent documents (debit/credit memos).
    this should help you.
    regards.
    p.s.
    in this particular case, in VBFA only credit/debit memos with reference to invoices will be displayed.  this can be compared to VA05.
    Edited by: jonathan y on Mar 27, 2009 1:22 PM

  • Can a 1099 be manually created without reference to an AP Document ?

    Our AP department cut a cheque against a vendor id which included the names of two vendors in the description. They added the second name to the existing vendor in order to meet a requirement that the settlement cheque be made out to both parties.
    E.G.:> Vendor 100 = John Dow & Jane Smith. The tax-id/SSN for vendor 100 belongs to John Dow.
    A seperate vendor code exists for attorney Jane Smith.  E.G.> Vendor 200 = Jane Smith. And the tax-id/SSN for vendor 200 belongs to Jane Smith.
    We can generate the 1099 for this payment document which references vendor 100 and John Dow's tax-id. Can another 1099 be created against the same payment for vendor 200?  And/or is there a manual way to create a 1099 without reference to an AP document?

    The solution we used to create a second 1099 was as follows:
    1: Post an AP item to the 2nd Vendor for the amount that you want to report - FB60.
    -Credit Vendor Account
    -Debit Any account to clear with - We used petty cash
    2: Use the F-51 to Clear
    -Doc type ZV
    -Credit: The account you used to clear with
    -Debit: Select the open item for the vendor
    This will give you a payment document for the vendor for the amount you wish, but nothing paid to the vendor.

  • Contract cannt be created without reference of PR

    Hi,
    Can we put restriction that contract can't be created without Purchase requisition in MK31K transaction code.
    I tried with field selection and combination of field selection and document type , where Purchase requisition is required entry, however system is not restricting it in posting contract.
    Thanks & Regards
    Sudhansu

    Hi,
       I would suggest to use the transaction variant option to achieve the same.
       You may create transaction variant for ME31K in SHD0 transaction. Maintain the following in transaction variant:
    1. While creating transaction variant, maintain the purchase group as "output only" - so that user wont be able to create contract directly without any reference" (ME083 error)
    2. While creating transaction variant, click on "copy" button and then maintain the reference document as output only.
    3. While creating transaction variant, click on "reference to RFQ" button and maintain the reference RFQ details as display only.
    Result:
    1. Purchase group display only: User cant proceed without purchase group (ME083 Error)
    2. Copy document reference display only: User cant Proceed:
    3. Create with ref to RFQ : Ref doc field display only: User cant proceed:
    Now, the user cant create the contract without any reference, he cant copy from another contract, he cant create with reference to RFQ. The only option would be to create with reference to PR.
    Refer the doc: Learning SHD0 with Example
    Please check and revert back.
    Note: In this case, the user would be able able to insert new line item in ME32K without any reference. If you want to restrict the same, you may maintain the account assignment and material code field as display only for ME32K in another transaction variant.
    Regards,
    AKPT

  • Creation of inbound delivery without reference to a PO

    Dear gurus,
    Let's say that a normal inbound flow is something like this:
    PO > Create inbound delivery with reference to PO > inbound shipment > Transfer Order > Confirm Transfer Order > Post Goods Receipt > Putaway
    Issue:
    My client does not want to create the PO because the PO serves no purpose to them. They want the process to start from inbound delivery.
    Question:
    1. Can a standalone inbound delivery be created WITHOUT reference to a PO ? If yes, please tell me the configuration and transaction code involved in order to create this standalone inbound delivery.
    2. Based on standard configuration, can an inbound delivery be created automatically with reference to a material document (for eg MIGO Mvt Type 501). Once again, for this scenario, no PO should be involved. If yes, please tell me the configuration and transaction code involved in order to trigger the creation of this inbound delivery (I'm not looking for the answer of an inbound delivery creation BAPI to being triggered directly after the creation of the Material Document).
    3. Based on standard configuration, can an inbound delivery be created manually with reference to a material document (for eg MIGO Mvt Type 501). Once again, for this scenario, no PO should be involved. If yes, please tell me the configuration and transaction code involved in order to create this inbound delivery.
    Thanks.

    Hi Peter,
    Actually, my intention is not really to create an inbound delivery based on a goods receipt. Since my client is not keen on the idea of creating a PO, I'm actually trying to provide alternatives and workarounds. From what I have gathered, I already know this much
    -> An inbound delivery must be created with reference to PO unless Handling Unit Management is activated. If Handling Unit Management is activated, the creation of a Material Document will trigger the creation of an inbound delivery (I havent tested this out yet). Therefore, a PO will not be necessary in this case.
    I was kind of expecting answers along this line, unless of course, something better pops up. Maybe someone out there may know something more.
    As for Handling Units, I'm not familiar with it. Hopefully somebody can give me a good configuration guideline on what to do in order to activate it so that I can simulate the scenario of a Material Document triggering the creation of an inbound delivery (I'm not looking for the kind of answers which simply cuts and pastes the SAP HELP URL, 4.6C Handling Unit PDF, Best Practice Document and etc). Hopefully somebody out there can really give me a good guideline on how to do this.
    Thanks..

  • Default billing type for delivery without reference (Delivery Type LO)

    Hi,
    We have copied delivery type LO to ZLO, so by default Copy control got maintained in VTFL.
    But when we do billing for this delivery in VF01 the system is picking F2 as billing type automatically.
    The system is not picking the defined billing type (ZF2- copy of F2) for which we have maintained copy control in VTFL
    The system is accepting ZLO->F2 but not accepting ZLO->ZF2
    Rgs,
    Vipin

    Hi,
    When you have a delivery document created without reference to a sales order, the system uses a defualt order type. Check that in the delivery document type definition ( LO ), the default order type is DL. If you look at the definition of DL in VOV8, the billing document type defined in F2. This is what the system uses as the proposed billing document type. If you want the system to propose ZF2, create a copy of DL and assign that to ZLO as the default order type. Change the billing document type to ZF2 in the sales order definition and you will be able to propose ZF2.
    Hope this helps.

  • Add Item to a delivery without reference to a sales order

    Hello everybody,
    I'm trying to add an item to an existing delivery via VL02n without reference to a sales order but every time the following error message appears: "You cannot add this item to the delivery".
    What settings do i need in order to that? (material type, delivery type, item category group,..etc..)
    Could anyone help me?
    Thank for your attention.
    Regards,
    A.

    Hi!
    Its not feasible to add a new line item without reference, becuase in one of the user exits such a code would have been written to prevent adding line item without refernec.
    This is done to ensure that a standard availabilty check, pricing and infostructure updates are done. Otherwise, after billing the report of Profitabilty will not come correct and will lead to more problems.
    So my suggestion would be not to add the line item withour referencing to the sales order.
    SAP provides the way of unreferincing through a seperate delivery type called LO. So if you want to create a delivery without refernce, you can use delivery type LO or some Z version of it.
    Hope this helps,
    Abhishek

  • How movement type will be determined in Delivery without reference order

    hi gurus,
    i want to know what movement type will be determined in delivery type LO(Without reference of order) . i think in a normal delivery with referance to sales order movement type will be taken from the sales order schedule lines.  Incase of delivery without referencing an order whether system will use any movement type? if yes what movement type and from where the movement type will be picked up?

    When you create a delivery without referring to a preceding document, the system copies the following data into the document from the appropriate master records:
    Data from the customer master record of the ship-to party
    Data from the material master records of the delivery items
    normally schedulelines are determined by item category mrp type and schedule line.
    so it is determined by mrp type of the material

  • With reference to which document Delivery is created in Sub contract

    Hi Friends
    With Reference to  which document delivery document is created in subcontract process .
    through which T code I can see this reference  document .
    Suppose , there are 10 quantity in delivery document , where can I see this 10 numbers  are from in delivery document .
    In delivery ,in subcontract process , from which document , delivery quantities are  copied from . And what should I do in order to avoid over delivery in subcontract process .
    Pala

    Hi,
    Delivery is created with reference to Purchase order for subcontracting, to view  the delivery check  in purchase order history it displays the delivery double click on the delivery.Check in VL02N.
    Delivery quantity are copied from Purchase order,
    To avoid over delivery in subcontract process in material master purchasing view there field called purchase value key which controls this.
    Regards
    Ravi Shankar.

  • How to know if a Sales order item created with or without reference

    Hi,
    I am working on user exit USEREXIT_MOVE_FIELD_TO_VBAP, and I just wanted to know if there is a way to know if a sales order item is created with or without reference to a contract.
    I need to write the code in USEREXIT_MOVE_FIELD_TO_VBAP, however, when an SO line item is created with reference the userexit is being called twice and when the SO line item is created without reference the user exit is being called only once.
    My aim is to check if a SO line item is created with reference to a valid contract. If the item is without reference to a contract or the referenced contract is not valid, then I will have to determine the contract based on the customer contracts.
    Any help on this would be greatly appreciated.
    Best regards,
    Siva

    Hi Vindo,
    The Userexit USEREXIT_MOVE_FIELD_TO_VBAP is called twice when the SO line item is created with reference to contract. The first time the user exit is called there will be no value filled in vbap-vgbel and the second time it comes to the userexit then vbap-vgbel will have a value. I think CVBAK-VBELN will contain the reference if the so line item is created with reference and the value of CVBAK-VBELN contrains blank if the item is not referenced. Anyway thanks for your reply.
    Best regards,
    Siva

  • Delivery and replenishment delivery

    hello all,
    I would like to know the difference between delivery and replenishment delivery. pl. let me know in which scenario replenishment delivery is used and how it is created.
    Thanks,
    Maxx

    Hi,
    Longman online dictionary:
    to put new supplies into something, or to fill something again
    Dictionary.com:
    to make full or complete again, as by supplying what is lacking
    Cambridge online dictionary:
    to fill something up again
    Well, I think in terms of SAP it is used in the same meaning: if you use a material somewhere continually (consume it continually) you need continually supply that material to be able to continue your consumption.
    In SAP you use this expression in connection with
    - storage location MRP scenario
    - fixed bin replenishment
    - KANBAN replenishment
    - generally in connection with material staging
    - etc.
    Please consider that characteristics of this processes: you "continually" produce / consume (e.g. raw) materials and that's why you need "replenishment".
    In connection with certain MTO scenario where certain raw materials are very specific and are used only once maybe there's no point in speaking "replenishment".
    The procurement of these goods seems to be a very simple process (very simple purchasing activity).
    So, I think delivery is delivery and there's no separate "replenishment delivery" type / document, a delivery becomes "replenishment delivery" because it is used for "replenishment".
    (E.g. delivery created with reference to STO can be called replenishment delivery if you provide the raw materials from one plant to another, or from one SLoc to another SLoc).
    Just my ideas..
    Regards,
    Csaba
    Edited by: Csaba Szommer on Jan 27, 2009 9:39 PM
    Edited by: Csaba Szommer on Jan 28, 2009 8:16 AM

  • Stock is available in MMBE but delivery isnt created

    Dear friends,
    Stock for a material is available under unrestricted stock in a plant, as can be seen in MMBE. But at the time of creating a delivery, system throws up an error saying " Required quantity exceeds available stock"
    I feel that some stock might be blocked against some open sale orders. Could this be the reason?
    I also deleted one open sale order, still delivery couldnt be created.
    Kindly advice.
    Regards,
    Ronald

    Dear Ronald
    Please check in VL21 whether any delivery is created without doing PGI for the same material.  In this case also, you wont be able to post the goods issue for another delivery.
    Also go to VA02, input the sale order and ensure that the quantity what you are to do delivery is flowing in confirmed quantity.  If not, do availabillity check and then retry.
    thanks
    G. Lakshmipathi

  • Pricing procedure for Credit Memo request WITHOUT reference

    Dear friends,
    I have come across a requirement where credit memo request has to be created without reference to preceding document. i.e. for just giving some credit to customer may be for over pricing or giving some credit to customer (as to maintain good relation).
    So generally we have different pricing procedure for Cr/Dr process.
    thus i have different pricing procedure for Cr/Dr process than normal sales process.
    here i have copied pricing procedure of normal sales and added extra condition type for manual pricing, which overrides basic pricing condition type.
    but calculate the discount and taxes on the manual price.
    I would like to know whether discounts and taxes condition type's should be used
    in the cr/dr process without reference to preceding document. and suggest me the right condition types to be used in cr/dr pricing procedure without reference.
    Thanks.

    HI,
    Remove all the other condition types from the procedure and keep only those which you need.
    Regards
    Abhilash

  • Delivery get created with one line item from sale ord having two line item

    I have an issue when delivery is created with reference to a sales order.
    The sale order consist of a header with customer group VBKD-KDGRP = '01'. There are two line item for this header with item 10 having customer group '01' and line item '20' having customer group '02'.
    When delivery is created with reference to this sale order the delivery contains only one line item corresponding to line item 10 having customer group '01' of the sale order. But I need to have both the line item in the delivery irrespective of difference in customer group.
    What makes this split up of delivery? Is there any configuration or user exit that need to be applied in order to adress this.
    <REMOVED BY MODERATOR>
    Thanks in advance
    Ramachandran Babu
    Edited by: Alvaro Tejada Galindo on Jun 13, 2008 5:45 PM

    Check if there is any copy routine applied in the copy control from order to delivery - transaction VTLA. The routines themselves can be found in transaction VOFM (Data transfer -> Deliveries). LIKP-ZUKRL field contains the split criteria (by the way, check what's in that field on your deliveries).
    It's possible that there is something in the current routine that is forcing the delivery split. Otherwise you can probably use similar approach to make it stop splitting.
    Hope this helps.