Replication of Project Server 2010 databases from Production to Development

HI
We have One Production, One Development and One QA server but the Production data is not matching with the Dev and QA.
Now our client is asking is there any possibility that we can copy the production data bases and replicate in the Dev and QA.
Is there any auto sync method where the production data updates will be updated in Dev and QA automatically.
Our environment is Project Server 2010  4 PWA data bases and 1 config data base and 1 config data base for project sites.
Please suggest a best possible way to solve this issue as i thought to take the the PWA back up frm central admin along with the 4 db back up from pwa--- 6 db back up from sql server---- restore all of them in the Dev and QA---i don't think it is the right
approach.
Thanks
Geetha
Geeth If you feel that the answer which i gave you is Helpful please select it as Answer/helpful.

As per your First post you only want to update the data of DB on regular basis. 
Now you are talking about back up restore Please be clear what you want . 
If you have all the configuration ready on qa and dev then only replication need to be done. 
can i use the replication mechanism for all the 5 databases in PS 2010 at time won't be a problem right
?  YES
other wise 
If i want to copy the PWA configuration part can i use play book or any other steps i need to perform.
YES
We have some workflows on PWA instance. Create workflow on Dev and QA
kirtesh

Similar Messages

  • Renaming Project Server 2010 database server

    Hi all,
    We have Project Server 2010 + SQL Server 2008 R2, but we need to upgrade DB to cluster SQL Server 2012 Enterprise Edition
    SP1 CU7.
    Is it ok if we rename Project Server DB server , for example from DBSER05 to DBSRVCL07\APPDB ?

    As you planning to upgrade SQL server from 2008 r2 to sql server 2012 enterprise edition SP1 CU7.
    In this case you have to create your farm from scratch. You have to Create your APP server and FE server all together from scratch and then you have to give your new DB server name DBSRVCL07\APPDB  while creating farm.Once you run the configuration
    wizard their you have to specify the NEW DB name DBSRVCL07\APPDB it will create Sharepoint config and content.
    then you can restore your current project server DBs on new DB cluster server DBSRVCL07\APPDB  and create project WEB  APP where you can point restored project server DBs.
    It means it would be all together back up and restore on new hardware.
    i am just guessing if you think you will only upgrade Sql server, create cluster and rename proejct server DB server name in the existing farm that will not work.
    Only approach is take back up and restore onto new infrastructure.
    http://azlav.umtblog.com/2011/06/07/project-server-2010-database-restore-part-i/ 
    if we rename Project Server DB server , for example from DBSER05 to DBSRVCL07\APPDB-- If you will only rename project
    server DB server name then it wont work as project server also uses sharepoint config and content DB which are setting on old DB server name(we give db server name while running wizard) and it will throw errors.
    kirtesh

  • Project Server 2010 Migratet from one farm to another farm

    Hi ,
    I need to migrate existing Project server 2010 farm one server to another server.
    Kindly suggest me what is the best way we need to fallow.
    Existing Environment two server:
    1.  App server(SharePoint 2010 +Project Server 2010)- Existing PWA site is running
    2.Database server(with DNS instance name)
    New Environment:
    1.App server (fresh installed SharePoint + project server 2010)
    2.DB server fresh server with sql 2008
    Hasan Jamal Siddiqui(MCTS,MCPD,ITIL@V3),Sharepoint and EPM Consultant,TCS
    |
    | Twitter

    Event viewer Error:
    Failed to provision site PWA with error: Microsoft.Office.Project.Server.Administration.ProvisionException: Membership synchronization failed. ---> System.UnauthorizedAccessException: Access is denied. (Exception from HRESULT: 0x80070005 (E_ACCESSDENIED))
       at Microsoft.SharePoint.Library.SPRequest.RemoveRoleDef(String bstrUrl, Int32 lRoleID)
       at Microsoft.SharePoint.SPRoleDefinitionCollection.Delete(SPRoleDefinition roleDefinition)
       at Microsoft.Office.Project.Server.BusinessLayer.SharePointSecurityHelper.DeleteRoleByName(SPWeb web, String roleName)
       at Microsoft.Office.Project.Server.BusinessLayer.SharePointSecurityHelper.DeleteRoles(SPWeb web)
       at Microsoft.Office.Project.Server.BusinessLayer.SharePointSecurityHelper.ConfigureDefaultPWAWSSSecurityModel(SPSite topSite, SPWeb web)
       at Microsoft.Office.Project.Server.BusinessLayer.Admin.<>c__DisplayClass18.<QueueUpdateUsersAddRemoveStatusOnPwaRootsAndWorkspaces>b__17()
       at Microsoft.SharePoint.SPSecurity.<>c__DisplayClass4.<RunWithElevatedPrivileges>b__2()
       at Microsoft.SharePoint.Utilities.SecurityContext.RunAsProcess(CodeToRunElevated secureCode)
       at Microsoft.SharePoint.SPSecurity.RunWithElevatedPrivileges(WaitCallback secureCode, Object param)
       at Microsoft.SharePoint.SPSecurity.RunWithElevatedPrivileges(CodeToRunElevated secureCode)
       at Microsoft.Office.Project.Server.BusinessLayer.Admin.QueueUpdateUsersAddRemoveStatusOnPwaRootsAndWorkspaces(Dictionary`2 deletedUserUidsLoginNames, Guid[] addedUserUids, Boolean isFullSync, Boolean syncWorkspaces)
       at Microsoft.Office.Project.Server.BusinessLayer.Admin.SynchronizeMembershipForPwaAppRootSite()
       at Microsoft.Office.Project.Server.Administration.PsiServiceApplication.SynchronizePwaMembership(ProjectProvisionSettings provset, ProjectSite projectSite)
       --- End of inner exception stack trace ---
       at Microsoft.Office.Project.Server.Administration.PsiServiceApplication.SynchronizePwaMembership(ProjectProvisionSettings provset, ProjectSite projectSite)
       at Microsoft.Office.Project.Server.Administration.PsiServiceApplication.CreateSite(ProjectProvisionSettings provset
    Hasan Jamal Siddiqui(MCTS,MCPD,ITIL@V3),Sharepoint and EPM Consultant,TCS
    |
    | Twitter

  • Bulk Project Site option isn't working in project server 2010 migrated from PS 2007.

    Hi,
    I am doing a test migration from epm 2007 to epm 2013. 
    So first, i need to migrate the project server 2007 to project server 2010. i have 2 separate environments for EPM 2007 and EPM 2010).
    there is no problem in migration process and i successfully migrate entire PWA 2007 to 2010, except Workspaces (Project sites).
    Bulk project site option is not helping. I have tried 4-5 times with different PWA 2007 databases (PWA1, PWA2...) but this option did not work. and errors in queue are WSSWebDoesNotExist(16405) and GeneralQueueJobFailed(26000).
    Then next time while migrating all over again i kept the same port and same PWA name then bulk project site option worked.
    Question is, Do i need to keep the same PWA name and same port for the new upgraded PWA??,  one more issue regarding this is that if don't keep the same PWA name and i open the project site and click on the "Project web app" back link, it
    redirects me to old PWA site which doesn't exist and give me page not found error (Obviously).
    Below, you can see the both scenarios.
    my previous PWA 2007 site, say  - http://epm2007:2222/PWA
    When  -  migrated PWA 2010 site, say  - http://epm2010:3000/NewPWA    (Bulk project site update just doesn't work)
    When -  migrated PWA 2010 site, say  - http://epm2010:2222/PWA    (Bulk project site update worked)
    Whats the solution of this problem. is there any utility or query to link all project sites correctly?
    Will i face the same problem while migrating PS 2010 to PS 2013??
    Thank you.
    sandeep

    Hi,
    I would say it is easier to keep the same PWA name between 2007 and 2010 (no need to have the same port).
    If you want to move to a new PWA URL maybe you can use stsadm backup/restore as detailed in this article?
    http://technet.microsoft.com/en-gb/library/ee662500(v=office.14).aspx
    Hope this helps
    Paul

  • How to find Project Level Text Custom Fields in Project Server 2010 databases?

    Hello,
    We are using Project Server 2010 SP2 in SEM Mode. We are planning to use Project Level Local Custom fields and we want to pull them in reports using SSRS, so I am wondering which table these "Local" (non enterprise) custom fields are stored in
    database.
    Any suggestions?
    Regards,
    Kishore Dodda
    Kishore Dodda

    Hi,
    Please see this
    similar thread about reading local custom fields though the PSI.
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • Project Server 2010 Task page - An unknown error has occurred

    Hi All,
    I have searched inside the forum for similar problems but i didn't find any solution.
    We have Project Server 2010 with December CU installed and
    we are
    experiencing
    a serious
    problem with two enterprise resources.
    They can login to pwa succesfully but when they enter in the Task page the following error is raised:
    An unknown error has occurred
    There are no errors reported in the event viewer while in the ULS Log I found only this entry but i don't know if it's related with this issue:
    Detected use of SPRequest for previously closed SPWeb object. Please close SPWeb objects when you are done with all objects obtained from them, but not before. Stack trace:
    at Microsoft.SharePoint.SPWeb.get_CurrentUser()
    at Microsoft.Office.Project.PWA.PJContext.get_RegionalSettings()
    at Microsoft.Office.Project.PWA.PJContext.get_LocaleCulture()
    at Microsoft.Office.Project.PWA.WCFContext.AuthenticateUser(Message message, WCFContext& wcfContext, String userName, Boolean isWindowsUser)
    at Microsoft.Office.Project.PWA.WCFContext.GetContext(Message message, String userName, Boolean isWindowsUser, Boolean newCookie, Uri originalTargetUri)
    at Microsoft.Office.Project.Server.ProjectServerRouter.Microsoft.Office.Project.Server.IProjectServerRouter.ProcessMessage(Message message)
    at SyncInvokeProcessMessage(Object , Object[] , Object[] )
    at System.ServiceModel.Dispatcher.SyncMethodInvoker.Invoke(Object instance, Object[] inputs, Object[]& outputs)
    at System.ServiceModel.Dispatcher.DispatchOperationRuntime.InvokeBegin(MessageRpc& rpc)
    at System.ServiceModel.Dispatcher.ImmutableDispatchRuntime.ProcessMessage5(MessageRpc& rpc)
    at System.ServiceModel.Dispatcher.ImmutableDispatchRuntime.ProcessMessage4(MessageRpc& rpc)
    at System.ServiceModel.Dispatcher.MessageRpc.Process(Boolean isOperationContextSet)
    at System.ServiceModel.Dispatcher.ChannelHandler.DispatchAndReleasePump(RequestContext request, Boolean cleanThread, OperationContext currentOperationContext)
    at System.ServiceModel.Dispatcher.ChannelHandler.HandleRequest(RequestContext request, OperationContext currentOperationContext)
    at System.ServiceModel.Dispatcher.ChannelHandler.AsyncMessagePump(IAsyncResult result)
    at System.ServiceModel.Diagnostics.Utility.AsyncThunk.UnhandledExceptionFrame(IAsyncResult result)
    at System.ServiceModel.AsyncResult.Complete(Boolean completedSynchronously)
    at System.ServiceModel.Channels.InputQueue`1.AsyncQueueReader.Set(Item item)
    at System.ServiceModel.Channels.InputQueue`1.EnqueueAndDispatch(Item item, Boolean canDispatchOnThisThread)
    at System.ServiceModel.Channels.InputQueue`1.EnqueueAndDispatch(T item, ItemDequeuedCallback dequeuedCallback, Boolean canDispatchOnThisThread)
    at System.ServiceModel.Channels.InputQueueChannel`1.EnqueueAndDispatch(TDisposable item, ItemDequeuedCallback dequeuedCallback, Boolean canDispatchOnThisThread)
    at System.ServiceModel.Channels.SingletonChannelAcceptor`3.Enqueue(QueueItemType item, ItemDequeuedCallback dequeuedCallback, Boolean canDispatchOnThisThread)
    at System.ServiceModel.Channels.SingletonChannelAcceptor`3.Enqueue(QueueItemType item, ItemDequeuedCallback dequeuedCallback)
    at System.ServiceModel.Channels.HttpChannelListener.HttpContextReceived(HttpRequestContext context, ItemDequeuedCallback callback)
    at System.ServiceModel.Activation.HostedHttpTransportManager.HttpContextReceived(HostedHttpRequestAsyncResult result)
    at System.ServiceModel.Activation.HostedHttpRequestAsyncResult.BeginRequest()
    at System.ServiceModel.Activation.HostedHttpRequestAsyncResult.OnBeginRequest(Object state)
    at System.ServiceModel.PartialTrustHelpers.PartialTrustInvoke(ContextCallback callback, Object state)
    at System.ServiceModel.Activation.HostedHttpRequestAsyncResult.OnBeginRequestWithFlow(Object state)
    at System.ServiceModel.Channels.IOThreadScheduler.CriticalHelper.WorkItem.Invoke2()
    at System.ServiceModel.Channels.IOThreadScheduler.CriticalHelper.WorkItem.Invoke()
    at System.ServiceModel.Channels.IOThreadScheduler.CriticalHelper.ProcessCallbacks()
    at System.ServiceModel.Channels.IOThreadScheduler.CriticalHelper.CompletionCallback(Object state)
    at System.ServiceModel.Channels.IOThreadScheduler.CriticalHelper.ScheduledOverlapped.IOCallback(UInt32 errorCode, UInt32 numBytes, NativeOverlapped* nativeOverlapped)
    at System.ServiceModel.Diagnostics.Utility.IOCompletionThunk.UnhandledExceptionFrame(UInt32 error, UInt32 bytesRead, NativeOverlapped* nativeOverlapped)
    at System.Threading._IOCompletionCallback.PerformIOCompletionCallback(UInt32 errorCode, UInt32 numBytes, NativeOverlapped* pOVERLAP)
     It's not a task related errors because i have alredy done an analysis of the resorce's assignments.
    I have also verified IIS authentication settings as described in this
    post but all had been alredy correctly configured.
    We have a farm installation with two physical server:
    Application Server with Windows 2008 R2, SharePoint 2010 Enterprise, Project Server 2010
    Database Server with Windows 2008 R2 and SQL Server 2008 SP2
    Any help would be greatly appreciated!
    Thanks in advance.
    Raffaele

    Hi,
    I faced exactly the same problem: some resources try to connect to My Tasks, and get an Unknown error. No error message in ULS or Eventlog.
    I hope I solved the problem, and want to share the experience here.
    First, by reading this article,
    http://www.projectserverexperts.com/ProjectServerFAQKnowledgeBase/Unknown%20Error%20My%20Tasks%20Page.aspx: even if the SQL Query returns me no records, it gives me the idea to delete (unpublish) some tasks (i managed to identify some tasks which raised
    the problem, by assigning a test account on them, and see that the pb happened).
    So I decided to delete my project from the Published Database (and keep it in the Draft of course). Than in Project Pro, I opened and Published: the problem seem to be solved.
    I don't know the root cause of the pb: maybe some SQL data were corrupted for an unknown reason.
    Hope it could help some one ! Don't hesitate to give feedback if you solved this pb with this solution, or workaround.
    Sylvain

  • Project Server 2010 - M(one to another)

    Hi,
    Can anyone send me the steps for migrating project server 2010 from one server to other server?
    Also please let me know some of the known issues during migration.
    Regards,
    K.Gokulraj
    K.Gokulraj

    Hi,
    Since I'm not a DBA, I'm not going into much technical details, but this is quite a common backup/restore procedure which is well documented.
    Please find a few links as reference:
    http://azlav.umtblog.com/2011/06/07/project-server-2010-database-restore-part-i/
    http://azlav.umtblog.com/2011/06/09/project-server-2010-database-restore-part-ii/
    http://technet.microsoft.com/en-us/library/dd207290(v=office.14).aspx
    http://technet.microsoft.com/en-us/library/ff961887(v=office.14).aspx
    Hope
    this helps.
    Guillaume Rouyre - MBA, MCP, MCTS

  • Project Server 2013 reporting database change in Schema from Project Server 2010

    I have a current Project Server 2010 implementation, I am planning to migrate to Project Online.
    We have Customized Reports that consume from the PS 2010 Reporting DB.
    Are there differences in the Reporting DB schema  between PS 2010 and Project Online?
    My Question is: if we migrated to Project Online, will the reports crash?
    Another question is that, is PS 2013 Reporting DB schema the same as Project Online?

    Hi Atia,
    IN project server 2013 we have only one database instead of 4, it means draft, archive, published and reporting with in one database.Project Server 2013 reporting database schema tool that can be downloaded.
    http://blogs.msdn.com/b/project_programmability/archive/2013/01/28/project-server-2013-reporting-database-rdb-schema-reference.aspx
    There are differences in reporting of on-premises vs. Project Online
    The Project Server 2013 reporting schema includes three new tables, 27 new views, and a total of 33 tables and views that include new fields.
    Answer-1 : Yes there are some differences between PS 2010 and project Online.
    Answer-2 : Reports will crash as In Project Online you have to use ODATA to create report. You can not query project online data for reporting directly you have to have use ODATA. 
    http://msdn.microsoft.com/en-us/library/jj163015.aspx
    Answer-3 : NO, PS 2013 Schema and Project online Schema is different. 
    kirtesh

  • How to query Process Status from database in Project Server 2010

    Hello All,
    I am using Project Server 2010. 
    I need to query Process Status  from SQL. 
    where can I find Process Status in Database. 
    Thanks,
    Rohit

    Hi Rohit,
    you will not be able to find this information in reporting DB - the only database queries are supported.
    If you really want to go for an unsupported solution, you should be able to find related tables and how to join them in stored proc "MSP_WEB_SP_QRY_Statusing_ReadStatus" in published database.
    Regards
    Barbara
    To increase the value of this forum, please mark the replies that helped to solve your issue as answer. If you find answers to questions from other forum participants to be helpful, please mark them as helpful. Your participation will help others to find
    an appropriate solution faster. Thanks for your support!

  • Project Server 2010 failover environment with Database SQL Mirroring

     
    Hello,
    We have prod and failover environment. Failover environment created by using farm backup and restore of prod.
    my question is : Can we do SQL Mirroring (from prod to failover) of 5 databases (4 PS databases and content db) to keep both the environment in sync. Will this process work in the case of Project
    Server 2010. i am in doubt due to timestamp and GUID in config DB.
    Also will this process is supportable.
    Any help much appreciated.
    Thanks

    Hello MOhit2020,
    I haven't done this type of failover, but I think you would need to setup all your SharePoint  and project databases to use a SQL Alias to point to your production databases.  When and if your production databases failed, you would update
    your SQL Alias to point to the mirror location.
    The other nice feature about having SQL Alias setup in SharePoint, is that in the future, if you switch to another SQL Server, the SQL alias makes it easier to handle.
    Cheers!
    Michael Wharton, MVP, MBA, PMP, MCT, MCTS, MCSD, MCSE+I, MCDBA
    Website http://www.WhartonComputer.com
    Blog http://MyProjectExpert.com contains my field notes and SQL queries

  • Unable open Project details or a project from PWA Project server 2010 with Alias name

    Hi,
    I am unable to open the Projects from Project center with the Alias name with the server name i am able to open the projects, version is  project server 2010,
    My system is ABC.DC.IN  alias name i have given is DEF.AD.COM  
    With the system name i can able access PWA and all are working fine.
    As i have observed with alias name i can able to login to  pwa and all the server  setting approval center all are working fine but only in the project center i am not able to open the projects (http://DEF.AD.COM/pwa/ProjectDrillDown.aspx .xxxx)
    its is coming in the below of the ie. 
    But with Alias name these are the issues i am facing,
    1.when longing with alias name its asking two times for user name and password
    2.when i click on a project from project center its taking some time and asking for user name and password after i enter user name and password "PAGE cannot displayed" error i am getting.
    can any one Help me. 
    vijay kommireddi

    Hi Eric,
    Thanks for your Reply.
    As you said i have added in Manged Path as  (Testpwa/projects.aspx as <Wildcard inclusion>) But still problem is there it is asking user
    name password again if click on any project in project center and  and showing page cannot be displayed error. 
    This is url its is showing in the below of the IE ( http://def.ad.com/testpwa/projectdrilldown.aspx?ProjUid=e28c6d43-85b6-478d-9542-2961cc81a69e)
    I have observed one more thing if click on Project
    details then only this issue  is coming project schedule and project information
    is also opening with Alias name.
    My farm version is 14.0.7015.1000
    Vijay Kommireddi

  • Email Notifications from Project 2013 has Project Server 2010 in the subject

    When Project 2013 sends out task reminders it has "Task reminders - Microsoft Project Server 2010
    notification service" in the subject line.  Anyone know how or where this can be changed from 2010 to 2013. 
    New On premise installation of Project 2013 sp1

    I think it is a known bug, not sure if it has been corrected in the latest CU. Contact MS, they should help you with a script:
    https://social.technet.microsoft.com/Forums/en-US/6441b337-785e-48a6-a40a-6406a141001d/task-reminder-emails-for-project-server-2013-have-subject-line-task-reminders-microsoft-project?forum=projectserver2010general
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • Problem with the% deviation from Project Server 2010 field

    hello
    I have a problem with the% deviation from Project Server 2010 field.
    Within a file or project, this project contains tasks.
    Each task has completed the field% deviation.
    Within the row "Summary" in the field of% deviation does not perform the sum of all fields of tasks.
    Only occurs on certain projects, these projects have the view of PR Progress Report
    Anyone know happens?
    thank you very much

    Hi
    Sorry, I'll be more specific now.
    Within the field% deviation. Your settings in PWA is:
    The formula for field% Deviation:
    Str (IIf ([Job baseline] = 0; IIf ([Working] = 0, 0, 100); IIf ([Working] = 0; -100; Int (100 * ([Job] - [Work Online base]) / [Working baseline])))) + "%"
    Under the heading rows Calculation Summary:
    > Use formula.
    Within the field Allocation Calculation of rows:
    > It is labeled the "Apply unless you manually specify".
    The field [Job] and field [Job baseline] are fields Pack project server.
    The error is in project, in the list of tasks.
    In the top row, this row summary makes the sum of the ranks of the tasks of the file.
    But in my case only in the summary field the same value appears in the tasks.
    In all the cells in column% deviation appears the same value.
    I hope it helps.
    thank you very much

  • Problem: Task completion sync back from Exchange 2010 to Project Server 2010

    I have new installation of PS 2010 and Exchange 2010 (one server holds all roles including CAS).
    For sync between PS and EX 2010, I following the technet article Configure Project Server 2010 to work with Exchange Server 2010 at http://technet.microsoft.com/en-us/library/ff468700%28office.14%29.aspx (yes I read the second part on Impersonation, too).
    Basically I followed the video and opted for "Impersonation for all users".
    I got tasks appear in resources outlook "Tasks" folder no problem. They appeared instantly after project is published. But when the resource update the completion in outlook, it failed to update the Project server.
    The applog on Exchange server has the following events:
    A notification for subscription [IABmaWxiZXJ0Lm1zYy5hbHR1cmFzYW5hbHl0aWNzLmNvbRAAAABpsVspLo+TSpth0iMukr+TjiFq73wS0Qg=] against endpoint [http://MyPSserver/PWA/_vti_bin/PSI/ExchangeSync.asmx] couldn't be sent. (Send attempts: 2) Details: WebException:
    The remote server returned an error: (500) Internal Server Error. StatusCode: InternalServerError Internal Server Error    at System.Net.HttpWebRequest.EndGetResponse(IAsyncResult asyncResult)
       at Microsoft.Exchange.Services.Core.NotificationServiceClient.HandleResponse(IAsyncResult responseAsyncResult)
    After 8 unsuccessful attempts to send a notification for subscription [IABmaWxiZXJ0Lm1zYy5hbHR1cmFzYW5hbHl0aWNzLmNvbRAAAABaEEJ+4ahFSY6IVGcSZ7/m4kLgKCES0Qg=] against endpoint [http://MyPSserver/PWA/_vti_bin/PSI/ExchangeSync.asmx], the subscription has
    been removed. Details: WebException: The remote server returned an error: (500) Internal Server Error. StatusCode: InternalServerError Internal Server Error    at System.Net.HttpWebRequest.EndGetResponse(IAsyncResult asyncResult)
       at Microsoft.Exchange.Services.Core.NotificationServiceClient.HandleResponse(IAsyncResult responseAsyncResult
    The W3C log on PS app server has the following related entries (401 and 500 errors. 10.0.0.76 is Exch server. 10.0.0.77 is the PS app server):
    2014-03-20 18:12:39 10.0.0.77 POST /PWA/_vti_bin/PSI/ExchangeSync.asmx - 80 - 10.0.0.76 - 401 2 5 0
    2014-03-20 18:12:39 10.0.0.77 POST /PWA/_vti_bin/PSI/ExchangeSync.asmx - 80 - 10.0.0.76 - 401 1 2148074254 15
    2014-03-20 18:12:39 10.0.0.77 POST /_vti_bin/PSI/ExchangeSync.asmx - 80 MyDomain\MyExchServer$ 10.0.0.76 - 500 0 0 31
    2014-03-20 18:12:39 10.0.0.77 POST /PWA/_vti_bin/PSI/ExchangeSync.asmx - 80 - 10.0.0.76 - 401 2 5 0
    2014-03-20 18:12:39 10.0.0.77 POST /PWA/_vti_bin/PSI/ExchangeSync.asmx - 80 - 10.0.0.76 - 401 1 2148074254 0
    2014-03-20 18:12:39 10.0.0.77 POST /_vti_bin/PSI/ExchangeSync.asmx - 80 MyDomain\MyExchServer$ 10.0.0.76 - 500 0 0 31
    2014-03-20 18:12:39 10.0.0.77 POST /PWA/_vti_bin/PSI/ExchangeSync.asmx - 80 - 10.0.0.76 - 401 2 5 0
    2014-03-20 18:12:39 10.0.0.77 POST /PWA/_vti_bin/PSI/ExchangeSync.asmx - 80 - 10.0.0.76 - 401 1 2148074254 0
    2014-03-20 18:12:39 10.0.0.77 POST /_vti_bin/PSI/ExchangeSync.asmx - 80 MyDomain\MyExchServer$ 10.0.0.76 - 500 0 0 31
    2014-03-20 18:12:41 10.0.0.77 POST /PWA/_vti_bin/PSI/ExchangeSync.asmx - 80 - 10.0.0.76 - 401 2 5 0
    2014-03-20 18:12:41 10.0.0.77 POST /PWA/_vti_bin/PSI/ExchangeSync.asmx - 80 - 10.0.0.76 - 401 1 2148074254 0
    2014-03-20 18:12:41 10.0.0.77 POST /_vti_bin/PSI/ExchangeSync.asmx - 80 MyDomain\MyExchServer$ 10.0.0.76 - 500 0 0 62
    2014-03-20 18:28:39 10.0.0.77 POST /PWA/_vti_bin/PSI/ExchangeSync.asmx - 80 - 10.0.0.76 - 401 2 5 15
    2014-03-20 18:28:39 10.0.0.77 POST /PWA/_vti_bin/PSI/ExchangeSync.asmx - 80 - 10.0.0.76 - 401 1 2148074254 0
    2014-03-20 18:28:39 10.0.0.77 POST /_vti_bin/PSI/ExchangeSync.asmx - 80 MyDomain\MyExchServer$ 10.0.0.76 - 500 0 0 46
    2014-03-20 18:28:39 10.0.0.77 POST /PWA/_vti_bin/PSI/ExchangeSync.asmx - 80 - 10.0.0.76 - 401 2 5 15
    2014-03-20 18:28:39 10.0.0.77 POST /PWA/_vti_bin/PSI/ExchangeSync.asmx - 80 - 10.0.0.76 - 401 1 2148074254 0
    2014-03-20 18:28:39 10.0.0.77 POST /_vti_bin/PSI/ExchangeSync.asmx - 80 MyDomain\MyExchServer$ 10.0.0.76 - 500 0 0 31
    2014-03-20 18:28:39 10.0.0.77 POST /PWA/_vti_bin/PSI/ExchangeSync.asmx - 80 - 10.0.0.76 - 401 2 5 0
    2014-03-20 18:28:39 10.0.0.77 POST /PWA/_vti_bin/PSI/ExchangeSync.asmx - 80 - 10.0.0.76 - 401 1 2148074254 0
    2014-03-20 18:28:39 10.0.0.77 POST /_vti_bin/PSI/ExchangeSync.asmx - 80 MyDomain\MyExchServer$ 10.0.0.76 - 500 0 0 15
    2014-03-20 18:28:41 10.0.0.77 POST /PWA/_vti_bin/PSI/ExchangeSync.asmx - 80 - 10.0.0.76 - 401 2 5 15
    2014-03-20 18:28:41 10.0.0.77 POST /PWA/_vti_bin/PSI/ExchangeSync.asmx - 80 - 10.0.0.76 - 401 1 2148074254 0
    2014-03-20 18:28:41 10.0.0.77 POST /_vti_bin/PSI/ExchangeSync.asmx - 80 MyDomain\MyExchServer$ 10.0.0.76 - 500 0 0 15
    I am new to PS 2010. Help is appreciated. Thanks.

    Here are the errors found in Project Queues:
    ExchangeSyncExchangeSubscriptionUpdateForUserFailed (40511). Details: id='40511' name='ExchangeSyncExchangeSubscriptionUpdateForUserFailed' uid='ef501cc2-9305-47b5-92b3-021e3b41d1b5' teamMemberUid='b8f2e0cd-9882-4677-be61-b2780b32bae5' exception='System.NullReferenceException:
    Object reference not set to an instance of an object. at Microsoft.Office.Project.Server.ExchangeSync.ExchangeSyncUtil.UpdateExchangeSubscription(Guid resourceUid, SubscriptionContext context) at Microsoft.Office.Project.Server.ExchangeSync.ExchangeSyncUtil.UpdateExchangeSubscription(Guid
    resourceUid) at Microsoft.Office.Project.Server.ExchangeSync.ExchangeSubscriptionRefreshProcessor.Refresh(PlatformContext ctx)'.
    ReportingProjectChangeMessageFailed (24006) - The INSERT statement conflicted with the FOREIGN KEY constraint "FK_MSP_EpmAssignment_ResourceOwnerUID". The conflict occurred in database "ProjectServer_Reporting", table "dbo.MSP_EpmResource", column 'ResourceUID'.
    The statement has been terminated.. Details: id='24006' name='ReportingProjectChangeMessageFailed' uid='ef4e51a1-8cb2-4ec2-bfc4-530f1f34cd8c' QueueMessageBody='Project UID='2668bb26-5c23-42ce-843a-fa49feadba05'. PublishType='ProjectPublish'' Error='The INSERT
    statement conflicted with the FOREIGN KEY constraint "FK_MSP_EpmAssignment_ResourceOwnerUID". The conflict occurred in database "ProjectServer_Reporting", table "dbo.MSP_EpmResource", column 'ResourceUID'. The statement has been terminated.'.
    ReportingProjectChangeMessageFailed (24006) - The INSERT statement conflicted with the FOREIGN KEY constraint "FK_MSP_EpmAssignment_ResourceOwnerUID". The conflict occurred in database "ProjectServer_Reporting", table "dbo.MSP_EpmResource", column 'ResourceUID'.
    The statement has been terminated.. Details: id='24006' name='ReportingProjectChangeMessageFailed' uid='0b88178b-2e45-41af-a85f-8c5590e9c3e7' QueueMessageBody='Project UID='2668bb26-5c23-42ce-843a-fa49feadba05'. PublishType='ProjectPublish'' Error='The INSERT
    statement conflicted with the FOREIGN KEY constraint "FK_MSP_EpmAssignment_ResourceOwnerUID". The conflict occurred in database "ProjectServer_Reporting", table "dbo.MSP_EpmResource", column 'ResourceUID'. The statement has been terminated.'.
    ReportingProjectChangeMessageFailed (24006) - The INSERT statement conflicted with the FOREIGN KEY constraint "FK_MSP_EpmAssignment_ResourceOwnerUID". The conflict occurred in database "ProjectServer_Reporting", table "dbo.MSP_EpmResource", column 'ResourceUID'.
    The statement has been terminated.. Details: id='24006' name='ReportingProjectChangeMessageFailed' uid='0d7421f6-2579-4656-b956-d50ecc7f5f1c' QueueMessageBody='Project UID='2668bb26-5c23-42ce-843a-fa49feadba05'. PublishType='ProjectPublish'' Error='The INSERT
    statement conflicted with the FOREIGN KEY constraint "FK_MSP_EpmAssignment_ResourceOwnerUID". The conflict occurred in database "ProjectServer_Reporting", table "dbo.MSP_EpmResource", column 'ResourceUID'. The statement has been terminated.'.
    ReportingProjectChangeMessageFailed (24006) - The INSERT statement conflicted with the FOREIGN KEY constraint "FK_MSP_EpmAssignment_ResourceOwnerUID". The conflict occurred in database "ProjectServer_Reporting", table "dbo.MSP_EpmResource", column 'ResourceUID'.
    The statement has been terminated.. Details: id='24006' name='ReportingProjectChangeMessageFailed' uid='3456b70e-fe16-4b3a-ab66-f2a5237fbaeb' QueueMessageBody='Project UID='2668bb26-5c23-42ce-843a-fa49feadba05'. PublishType='ProjectPublish'' Error='The INSERT
    statement conflicted with the FOREIGN KEY constraint "FK_MSP_EpmAssignment_ResourceOwnerUID". The conflict occurred in database "ProjectServer_Reporting", table "dbo.MSP_EpmResource", column 'ResourceUID'. The statement has been terminated.'.
    ReportingProjectChangeMessageFailed (24006) - The INSERT statement conflicted with the FOREIGN KEY constraint "FK_MSP_EpmAssignment_ResourceOwnerUID". The conflict occurred in database "ProjectServer_Reporting", table "dbo.MSP_EpmResource", column 'ResourceUID'.
    The statement has been terminated.. Details: id='24006' name='ReportingProjectChangeMessageFailed' uid='fc78474a-bf5c-422c-a209-cb79e3201e38' QueueMessageBody='Project UID='2668bb26-5c23-42ce-843a-fa49feadba05'. PublishType='ProjectPublish'' Error='The INSERT
    statement conflicted with the FOREIGN KEY constraint "FK_MSP_EpmAssignment_ResourceOwnerUID". The conflict occurred in database "ProjectServer_Reporting", table "dbo.MSP_EpmResource", column 'ResourceUID'. The statement has been terminated.'.
    ReportingProjectChangeMessageFailed (24006) - The INSERT statement conflicted with the FOREIGN KEY constraint "FK_MSP_EpmAssignment_ResourceOwnerUID". The conflict occurred in database "ProjectServer_Reporting", table "dbo.MSP_EpmResource", column 'ResourceUID'.
    The statement has been terminated.. Details: id='24006' name='ReportingProjectChangeMessageFailed' uid='d2f4b313-0c21-4a2c-b8a7-f6bd7aef13fe' QueueMessageBody='Project UID='2668bb26-5c23-42ce-843a-fa49feadba05'. PublishType='ProjectPublish'' Error='The INSERT
    statement conflicted with the FOREIGN KEY constraint "FK_MSP_EpmAssignment_ResourceOwnerUID". The conflict occurred in database "ProjectServer_Reporting", table "dbo.MSP_EpmResource", column 'ResourceUID'. The statement has been terminated.

  • Project Server 2010 PWA Provisioning Error - System.UnauthorizedAccessException: Access is denied.

    Hi,
    When migrating from a Prod Environment to a Test Environment using the Project Server 2010 5 Database backup and restore process (actually 6 DB's with the Project Sites DB), upon encountering a failure during provisioning the PWA Instance, we get the errors listed
    at the base of this posting in our Event Logs.
    To clarify what we have done already, we have:
    1. Backed up the 6 databases from the Source Environment.
    2. Removed the existing PWA_Content and PWS_Content (Project Sites) databases from the Target Environment Farm.
    3. Restored the 6 databases in the Target Environment.
    4. Given the SP Farm Service Account 'db_owner' rights to each of the 6 restored databases.
    5. Added the PWA_Content and PWS_Content databases  (exact same names) to the Target Environment.
    6. Locked down (offline/stopped), all of the SharePoint Content databases in the Farm except for the PWA_Content database.
    7. Run the PWA Provisioning process from the 'Project Server' SharePoint Service in Central Admin.
    It is during the PWA provisioning that we encounter these errors.
    As the Target Environment is for Test/Dev purposes, the SP Farm Service Account is setup to support all of the SharePoint Farm Services, is in the Local Admin Group of each of the Servers (App, WFE and DB), and is actually in the sysadmin
    role on the DB Server.
    Any suggestions on what is causing this denied access situation would be most appreciated.
    Cheers,
    Wayne
    Event Log Entries:
    ============================================
    Log Name:      Application
    Source:        Microsoft-SharePoint Products-Project Server
    Date:          1/22/2014 2:47:34 PM
    Event ID:      6971
    Task Category: Provisioning
    Level:         Error
    Keywords:     
    User:          ACCOUNTS\svc_psfarm
    Computer:      SERVER.accounts.domain.com
    Description:
    Failed to provision site PWA with error: Microsoft.Office.Project.Server.Administration.ProvisionException: Membership synchronization failed. ---> System.UnauthorizedAccessException: Access is denied. (Exception from HRESULT: 0x80070005 (E_ACCESSDENIED))
       at Microsoft.SharePoint.Library.SPRequest.AddRoleDef(String bstrUrl, String bstrName, String bstrDescription, Boolean bHidden, Int32 lRoleOrder, UInt64 iPermMask, Byte iType, Int32 lRoleDefID)
       at Microsoft.SharePoint.SPRoleDefinitionCollection.AddCore(SPRoleDefinition role)
    etc....
    Failed to create the Report Center web (Exception: PSI Entry Point:
    Project User: DOMAIN\svc_psfarm Correlation Id: c0a30b18-46e4-4447-b469-f8fd3bb1490a
    PWA Site URL: http://pstest2010/PWA
    SSP Name: Project Server
    PSError: NoError (0))
    Failed to grant 'DOMAIN\svc_psfarm' access to web application 'SPWebApplication Name=Portal'.
    Error: System.Security.SecurityException: Access denied.  Only machine administrators are allowed to create administration service job definitions of type: Microsoft.SharePoint.Administration.SPUpdateWorkerProcessGroup, Microsoft.SharePoint, Version=14.0.0.0,
    Culture=neutral, PublicKeyToken=71e9bce111e9429c.
       at Microsoft.SharePoint.Administration.SPAdministrationServiceJobDefinition..ctor(String name, SPService service, SPServer server, SPJobLockType lockType)
       at Microsoft.SharePoint.Administration.SPUpdateWorkerProcessGroup..ctor(SPTimerService timerService, String[] loginsToAdd, String[] loginsToRemove)
       at Microsoft.SharePoint.Administration.SPWebApplication.GrantAccessToProcessIdentity(String username, SPPolicyRoleType policyRole)
       at Microsoft.Office.Project.Server.Administration.PsiServiceApplication.GrantAccessToWebApp(List`1 webApps, String userName) The Zone of the assembly that failed was: MyComputer

    Is the Test and Production in the same domain. If they are not, then the SIDs associated with the SQL accounts may look the same but they are not.  At times, I have had to recreated accounts when in different domains.
    I would also use PowerShell cmdlets and see if it finds any issues, such as Test-SPContentDatase.. Validate the SharePoint content databases, because if not setup properly the Provisioning will fail.
    Also check these properties.
    $web=get-spweb http://prodproj01/pwa
    $Web.AllProperties[“PWAURL”] ### see what the value is.. you may have to blank it out, specially if it is pointing to a different URL
    Here is how to fix.
    $Web.AllProperties[“PWAURL”]=””
    $web.Update()
    Michael Wharton, MVP, MBA, PMP, MCT, MCTS, MCSD, MCSE+I, MCDBA
    Website http://www.WhartonComputer.com
    Blog http://MyProjectExpert.com contains my field notes and SQL queries

Maybe you are looking for

  • Exception Class

    Hi, What is exception class . What is local exception class what is global exception class. Thanks, Medha.

  • Running Process Chains via abap

    Hi all, I have scenario in loading text file to cube via chains using abap, here the step: Start from abap code to check the file, if exist run the Process chains <b>Process Chains</b> a. <b>start</b> b. <b>load data</b>   c. <b>updt from PSA</b> d.

  • Can MacbookPro7, 1 Version 10.6.8 get an 10.7.5 upgrade?

    I have a MacbookPro 7, 1 purchased in Summer of 2010 that I would like to get the 10.7.5 update.  I bought a game and it only works on operating systems 10.7.5 or higher.  I did all the software updates possible on my macbook and it is still at a 10.

  • Use EJBs in Webdynpro

    Dear All, We have the following scenareio to be achieved, Use Database of the WAS Java engine and table creation using NWDS. - this can be done using data dictionary Use EJBs Data Updation - we have created a EJB project. One ear project which can be

  • Reader X will not read comment enabled PDF

    My computer was recently upgraded to Windows 7. After the up upgrade, I installed Acrobat Reader X and quickly discovered that not all PDF files were readable. I found that if I create a PDF file from CS5 InDesign, the file reads just fine. If I enab