We would like to increase our simultaneous report jobs per Report Job Server.  We currently have 4 CPUs and the Deployment and Configuration Guide says the 'Supported Load' is 5 reports per CPU so we should only run 20 reports simultaneously.  Our CPU usage is very low and we'd like to increase the Maximum Jobs Allowed on the Job Servers, but I don't know what the consequences would be to our servers.  Has anyone gone above the 'Supported Load' numbers for simultaneous report jobs per Report Job Server?  How high could I go without having problems?

Hi Eileen
There is no definite answer on this. The Maximum Jobs Allowed setting depends very much on your environment. If you have reports that run quickly you could increase it. Also, do you have a high concurrency of jobs? The fact that the CPU time is low means either that your Job Server (CR, DeskI) or Web Intelligence Report Server (WebI) is waiting for results from the database OR that there are simply no reports or not even 1 report per Job Server to process at this time. If you run 1 report and you see 25% CPU usage in the task manager on a quad core machine, means that the Job Server uses up the resources on one core fully.
Regards
Roland

Similar Messages

  • OpenDocument and the Webi Job Server

    (Using XI R2 on windows environment)
    I have a Webi report which will be opened using the OpenDocument URL syntax, passing parameters through, with the report set to refresh on open.
    When this report opens and refreshes does this use one of the Webi Job Server "Maximum Jobs Allowed"?
    ie say the server is set to allow 10 simultaneous jobs to run, and these are all being used by scheduled jobs (say at month end) and someone uses the OpenDocument function, will this document wait until there is a job allowed to run on the Job Server or does it refresh immediatley?
    Sorry if this doesn't make sense, its a bit had to explain what I think I mean.
    Cheers

    Hi
    the WebI Job server is not involved  in the workflow you described. The webI Report Server is repsonsible for creating reports on-demand. Calling your openDocument link will trigger the WebI report server. While the report is refreshed and remains open a connection will be opened on this server.
    Regards
    Stratos

  • Crystal Reports Job Server

    What is the maximum number of jobs allowed through a Crystal Reports Job Server?
    We have 4 Crystal Reports Job Servers out of which 1 is not being used. Maximum jobs allowed for the other 3 CR Job Servers are 5-7.
    What is the limit?? Can I increase the number without effecting the system performance?
    Please advice.
    Thanks!

    Which version of BO do you use?
    There is a parameter setting for this that can be set over the CMC. The parameter is called Maximum Concurrent Jobs. If yaou set this to 0 then the number of maximum jobs is calculated automatically. In XI 3.1 you can see the calculated number in the Metrics of the crytsal report job server.
    Increasing the number of maximum concurrent job will affect the performance depending on the number of the submitted jobs. The higher this number the more reports will be processed in parallel and thus the more load your system has to handle.
    Regards,
    Stratos

  • Problem with Crystal Report Job Server Destinations

    I am using Crystal Reports XI Server and I am having problems with scheduling.  I believe that the problem is that I have not enabled any destinations under the Crystal Reports Job Server.  The following is an observation list:
    -Enabled and set up all destinations for other servers, such as the Destination Server.
    -Have been able to use Infoview to directly email, inbox, and file save reports in different formats (I believe the Destination Server controls this, right?)
    -All servers are enabled in the Central Configuration Manager
    -Have been able to go into the Crystal Reports Job Server within the CMC, but I DO NOT FIND ANY destinations to enable (why is this?)
    -Have not been able to schedule an instance of any report (neither email, nor inbox, nor file, ...nothing)
    Could somebody please help me with this?  Is this a limitation to the Crystal Reports XI Server vs the Enterprise edition?  Is there something else I am missing?  I have never been able to successfully schedule a report.

    Thank you for the input, but I have not yet solved my problem.  Please allow me to provide some additional information which may give more hints:
    I have Crystal Reports XI Server R2 installed as 5 named user license (version that comes with developer)
    The following servers are enabled in CMC (which is all of them)
    -Input.DomainNameSQL
    -DomainNameSQL.cacheserver
    -DomainNameSQL.cms
    -DomainNameSQL.destinationjobserver (has all destinations enabled)
    -DomainNameSQL.eventserver
    -DomainNameSQL.ListofValuesJobServer (no destination tab)
    -DomainNameSQL.pageserver
    -DomainNameSQL.programjobserver (has all destinations enabled)
    -DomainNameSQL.RAS
    -DomainNameSQL.reportjobserver (has destinations tab, but there are no destination entries to enable! Object type is: CrystalEnterprise.Report and detail: IDL:omg.org/CORBA/UserException:1.0
    . Details: %2.'
    These are the ONLY two event IDs that appear after I schedule the report instance.  No other events occur.
    Are there any other logs that I can check?  How do I look up what event ID 45387 and 45385 are?
    Thanks!

  • Creation of Report Job Server

    I've just installed a new copy of XI R2 running parallel with Crystal Enterprise 10.  My Enterprise 10 has 4 report job servers and I need to have XI R2 configured with 4 too before I start migrating the reports from CE10 to XI - How is this accomplished?

    On the server, launch the CCM (central configuration manager) from the program files\business objects.
    one of the icons looks to be a plus sign, holding the mouse over it would indicate "add server" Do this to add additional job servers. Since there are multiple jop servers insure that you select the crystal reports job server.
    Regards,
    Tim
    Edited by: Tim Ziemba on Jul 15, 2008 10:56 AM

  • Crystal Reports Job Server - Default destinations not available

    Greetings,
    Currently I'm installing Crystal Reports XI onto a new server.
    When scheduling reports they are stuck in a 'pending' status which records the following error in the windows event log:
    Transport System exception for backend plugin DLL type newIJob():: Couldn't get IJob interface: CORBA exception! Object type is: CrystalEnterprise.Report and detail: IDL:omg.org/CORBA/UserException:1.0
    . Details: %2.
    After further investigation I discovered the Crystal reports job server has no defaul destinations, however the servers Destination Job Server and Program Job Server do have the default instances.
    Firstly I assume the error reported in the event log is due to there are no destinations, as the scheduler won't know where to send out to.
    Can anyone help in advising how to ensure the reports server had some default destinations?
    I have restarted the server and rebooted the Crystal reports server too.
    Thanks
    Rob

    Hi RobWhalley,
    Could you provide me which version of Crystal Reports Server XI  you use?
    you could find useful below articles.
    [1202926 - Scheduled reports in Crystal Reports Server XI Release 2 stays in 'Pending' state |http://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/com.sap.km.cm.docs/oss_notes_boj/sdn_oss_boj_bi/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/scn_bosap/notes%7B6163636573733d36393736354636443646363436353344333933393338323636393736354637333631373036453646373436353733354636453735364436323635373233443330333033303331333233303332333933323336%7D.do]
    [1477380 - Crystal Reports in Pending status|http://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/com.sap.km.cm.docs/oss_notes_boj/sdn_oss_boj_bi/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/scn_bosap/notes%7B6163636573733d36393736354636443646363436353344333933393338323636393736354637333631373036453646373436353733354636453735364436323635373233443330333033303331333433373337333333383330%7D.do]
    And please check job server is enabled and under the CMC > Server > Crystal Job Server > RightClick on the server > Destination to File System.
    And you can increase the maximun concurrent job value through CMC>Servers>CrystalReportJobServer>Properties.
    Regards
    Rameez Shaikh

  • Report Job Server goes Offline

    I've had a persistent problem with the Report Job Server in the CMC going offline (BO XI R2).  I try to stop/start but I get a message that the server is already in the requested state (started).
    I've tried disable/enable -- still it is offline and my reports won't run.
    I check the CCM and all the servers are running.  The Event Viewer in Windows shows that the Report Job Server has stopped..."Unable to contact server sccecho2.reportjobserver.jobserver to change its enabled status. Please restart it."
    The only way to get it started again is via a server reboot.  Then the reports will run.
    This problem seems to happen shortly before I have several reports scheduled to run and none of them get sent off due to the Report Job Server being offline.
    Is there something else I can check somewhere or other thoughts as to what is causing this persistent problem?
    Thank you for any help you can send my way.
    kd

    Hi Kim,
    Try creating a new Server and check the issue.
    Thanks,
    Anisa

  • Project Server 2013 - Reporting ( Project publish ) Queue Job Error - 24006

    I am trying to publish a project and getting below error
    please provide me a solution your help greatly appreciated
    Reporting ( Project publish ) Queue Job Error - 24006 
    General
    Reporting message processor failed:
    ReportingProjectChangeMessageFailed (24006) - Object reference not set to an instance of an object.. Details: id='24006' name='ReportingProjectChangeMessageFailed' uid='5a10ad83-4736-e311-941a-00155d0c1708' QueueMessageBody='Project
    UID='eaf690a4-5fda-e211-af15-b8ac6f50f278'. PublishType='ProjectPublish'' Error='Object reference not set to an instance of an object.'.
    ReportingProjectChangeMessageFailed (24006) - Object reference not set to an instance of an object.. Details: id='24006' name='ReportingProjectChangeMessageFailed' uid='e412ad83-4736-e311-941a-00155d0c1708' QueueMessageBody='Project
    UID='eaf690a4-5fda-e211-af15-b8ac6f50f278'. PublishType='ProjectPublish'' Error='Object reference not set to an instance of an object.'.
    ReportingProjectChangeMessageFailed (24006) - Object reference not set to an instance of an object.. Details: id='24006' name='ReportingProjectChangeMessageFailed' uid='6e15ad83-4736-e311-941a-00155d0c1708' QueueMessageBody='Project
    UID='eaf690a4-5fda-e211-af15-b8ac6f50f278'. PublishType='ProjectPublish'' Error='Object reference not set to an instance of an object.'.

    If your farm is not updated please update it  from OCT  CU for 2013 project server.
    Please update it as cumulative update is having hotfix for this issue.
    http://www.intersoft.no/blogg/item/33-april-2013s-cumulative-update-for-project-server-2013
    http://www.datazx.cn/Fv7p5a/xw-US/dc6mbbt6-btss-fxi4-s8c4-8jsribt69m8x/nnn.projectserverexpertrs
    As per the 2nd link Oct Cu for 2013 is fix this issue hence i would suggest you to upgrade from OCT CU.
    kirtesh

  • BI 4.x : guideline for "Maximum Concurrent Jobs" in Adaptive Job Server

    Dear all,
    What is the guideline in BI 4.x for the property "Maximum Concurrent Jobs" in the Adaptive Job Server (eg in the Web Intelligence Scheduling Service)
    In the XI-versions it was 5 concurrent jobs per CPU.
    Is that guideline still applicable in BI 4.x ?
    Many thanks
    Hans

    Default value is same for BO 4.0 also. You can adjust based on your requirement.

  • Adaptive Processing Server & Report Job Server Stopped

    Hi!
    I am using BOXI 3.1 on windows server 2003 datacenter and we have a clustered environment.  Our most of the reports are Deski reports (1195) out of which around 56 reports are scheduled.
    Adaptive processing server, Multidimensional Analysis server & report job server got stuck randomly and the only way left is to stop/start them.
    It was happening from last few days and now from today it is not getting started.
    I have restarted SIA several times but of no use. Suddenly after 2 hours they are in running stage. I am very confused with the strange behavior of BOXI servers.
    Do anyone have clue on this.
    This happens always at the time schedule instance start running.
    Thanks & regards,
    Saurabh Gupta

    Adaptive processing server, Multidimensional Analysis server & report job server  are not used in Deski report procesing at all.
    To find out what happens, you need to review Event Viewer logs, enable tracing on this 3 servers.
    Or simply stop and disable them to give more resources to your Deski processing

  • SQL Server Agent Jobs error for Slowly changing dimension

    Hi,
    I have implemented Slowly changing dimension in 5 of my packages for lookup insert/update.
    All the packages are running good in SSDT. And when i deployed the project to SSISDB and run the packages all are running successfully. But when i created a job out of that and run the packages, then 3 packages ran successfully and 2 packages failed. 
    When i opened All Execution Report. I found the following error:
    Message
    Message Source Name
    Subcomponent Name
    Process Provider:Error: SSIS Error Code DTS_E_OLEDBERROR.  An OLE DB error has occurred. Error code: 0x80004005. An OLE DB record is available.  Source: "Microsoft SQL Server Native Client 10.0"  Hresult: 0x80004005  Description:
    "Login timeout expired". An OLE DB record is available.  Source: "Microsoft SQL Server Native Client 10.0"  Hresult: 0x80004005  Description: "A network-related or instance-specific error has occurred while establishing
    a connection to SQL Server. Server is not found or not accessible. Check if instance name is correct and if SQL Server is configured to allow remote connections. For more information see SQL Server Books Online.". An OLE DB record is available. 
    Source: "Microsoft SQL Server Native Client 10.0"  Hresult: 0x80004005  Description: "Named Pipes Provider: Could not open a connection to SQL Server [53]. ".
    Process Provider
    Slowly Changing Dimension [212]
    Then i opened Provider package in SSDT and changed the source reading record limit from 4,00,000 to 15,000 in source query and deployed again and run, then the job succeeded. more than 15,000 failed.
    And in the 2nd experiment, I removed slowly changing dimension task and implemented normal lookup for insert/update, and set the source reading limit again to 4,00,000 and deployed again and run, then the job succeeded.
    Now i am not able to figure out, what exactly is the problem with Slowly changing dimension task for more than 15,00 records in SQL Server  Agent Job run?
    Can anybody pls help me out.
    Thanks
    Bikram

    Hi Vikash,
    As i have mentioned in the above post, below 2 scenarios: 
    "Then i opened Provider package in SSDT and changed the source reading record limit from 4,00,000 to 15,000 in source
    query and deployed again and run, then the job succeeded. more than 15,000 failed.
    And in the 2nd experiment, I removed slowly changing dimension task and implemented normal lookup for insert/update, and set the source reading limit again to 4,00,000 and deployed again and run, then the job succeeded."
    That means i am able to connect to sql server.
    But if i change the 1st scenario and read 4,00,000 records, the job fails and shows the above mentioned error.
    Similarly in the 2nd scenario, if i implement SCD look up,  the job fails and shows the above mentioned error.
    And i am consistently reproducing this.
    Thanks
    Bikram

  • Java.Lang.nullpointerexception issue only isolated to a repository on the job server

    I am having the
    "Java.Lang.nullpointerexception" error message issue only isolated to a repository on the job server.
    This error message appearing when i try to execute or create a new schedule for a job on mgmt console.
    I have few other repositories in the same server, with those repositories i am not having any issues, in terms of executing a job or creating a new schedule.
    Does any one had the similar issue, and know how to resolve it.
    Thanks a lot for the helpful info.

    Hello George / Viacheslav, thks to both for responding.
    BODS is based on 4.0 never was migrated from 3.2
    Under this repository almost 30 jobs currently running with no issues, which were created and scheduled before this error started.
    THis error message started just two months ago, since then it is not allowing any new jobs to be executed or creating any new schedules.
    But all prior jobs are running fine no issues.
    FRom designer i am able to execute with no problem, This issue is only happening on Mgmt console and only in this repository.
    Repository name has no apostrophe, all repsositories have the same style naming convention.
    "BODS_THENAME"
    Here i am pasting the block from viewsoure, where the error is:
     <span nowrap class="viewContext">Repository: BODS_JBROOK</span><table class="viewcontrollerarea" style="height:1"><COLGROUP><COL width="100%"/></COLGROUP><tr><td class="viewcontrollerheaderspacer"></td></tr><tr><td class="viewcontrollerheadertabarea"><table class="viewcontrollertabs"><tr class="viewcontrollertabs"><td class="viewcontrollertabs"><img border=0  src="../images/tab_sel_left.gif"></td><td class="selectedTab" nowrap background="../images/tab_sel_center.gif" ><a class="selectedTab"  href="/DataServices/servlet/AwBatchJobExecute?REPOSITORY_NAME=BODS_JBROOK&GUID=7cb34824-6d1f-42cc-9968-6c69d006ee87&NAME=Job_TestRaghuRepo&HISTORY=%2FDataServices%2Fservlet%2FAwBatchJobHistory%3FREPOSITORY_NAME%3DBODS_JBROOK%26SHOWREPO%3D2%26ACTIVE_VIEW%3DBatch%2BJob%2BConfiguration&ACTIVE_VIEW=Execute+Batch+Job">Execute Batch Job</a></td><td class="viewcontrollertabs"><img border=0  src="../images/tab_sel_right.gif"></td></tr></table></td></tr><tr bgcolor="#7997CD" ><td height="2px" class="viewfont" VALIGN=CENTER width="100%"></td></tr><tr><td class="viewcontrollermain"><div id="tipDiv" class="tipdiv"></div><span class="viewMessage">java.lang.NullPointerException</span><br><span class="viewMessage"> <!-- </span><br><span class="viewMessage">java.lang.NullPointerException at com.acta.repo.AwJobCommandOptions.getDBServerName(AwJobCommandOptions.java:322) at com.acta.repo.AwJobCommandOptions.getConnectionCmd(AwJobCommandOptions.java:388) at com.acta.repo.AwJobCommandOptions.getConnectionCmd(AwJobCommandOptions.java:379) at com.acta.repo.AwJobCommandOptions.validateConnectionInformation(AwJobCommandOptions.java:296) at com.acta.repo.AwJobCommandOptions.init(AwJobCommandOptions.java:168) at com.acta.repo.AwJobCommandOptions.<init>(AwJobCommandOptions.java:91) at com.acta.webapp.admin.report.AwExecuteBatchJobPage.submitAction(AwExecuteBatchJobPage.java:586) at com.acta.webapp.mdreport.common.DIView.doAction(DIView.java:564) at com.acta.webapp.mdreport.common.DIView.PrintReport(DIView.java:406) at com.acta.webapp.mdreport.common.DIViewController.PrintReport(DIViewController.java:84) at com.acta.webapp.mdreport.reportframework.JCActaGenericSection.PrintReport(JCActaGenericSection.java:112) at com.acta.webapp.mdreport.common.DIFrame.PrintReport(DIFrame.java:67) at com.acta.webapp.mdreport.common.DIMainFrame.PrintReport(DIMainFrame.java:98) at com.acta.webapp.mdreport.common.DIBaseReport.PrintMainFrame(DIBaseReport.java:233) at com.acta.webapp.mdreport.common.DIBaseReport.PrintReportImpl(DIBaseReport.java:158) at com.acta.webapp.mdreport.common.DIBaseReport.PrintReport(DIBaseReport.java:269) at com.acta.webapp.admin.servlet.AwBatchJobExecuteServlet.doPostSafe(AwBatchJobExecuteServlet.java:30) at com.acta.webapp.mdreport.reportframework.JSActaHttpServlet.doPost(JSActaHttpServlet.java:359) at javax.servlet.http.HttpServlet.service(HttpServlet.java:637) at javax.servlet.http.HttpServlet.service(HttpServlet.java:717) at org.apache.catalina.core.ApplicationFilterChain.internalDoFilter(ApplicationFilterChain.java:290) at org.apache.catalina.core.ApplicationFilterChain.doFilter(ApplicationFilterChain.java:206) at com.acta.webapp.mdreport.servlet.JSFilter.doFilter(JSFilter.java:71) at org.apache.catalina.core.ApplicationFilterChain.internalDoFilter(ApplicationFilterChain.java:235) at org.apache.catalina.core.ApplicationFilterChain.doFilter(ApplicationFilterChain.java:206) at com.acta.webapp.mdreport.servlet.EscapeFilter.doFilter(EscapeFilter.java:52) at org.apache.catalina.core.ApplicationFilterChain.internalDoFilter(ApplicationFilterChain.java:235) at org.apache.catalina.core.ApplicationFilterChain.doFilter(ApplicationFilterChain.java:206) at org.apache.catalina.core.StandardWrapperValve.invoke(StandardWrapperValve.java:233) at org.apache.catalina.core.StandardContextValve.invoke(StandardContextValve.java:191) at org.apache.catalina.core.StandardHostValve.invoke(StandardHostValve.java:127) at org.apache.catalina.valves.ErrorReportValve.invoke(ErrorReportValve.java:102) at org.apache.catalina.core.StandardEngineValve.invoke(StandardEngineValve.java:109) at org.apache.catalina.connector.CoyoteAdapter.service(CoyoteAdapter.java:298) at org.apache.coyote.http11.Http11Processor.process(Http11Processor.java:852) at org.apache.coyote.http11.Http11Protocol$Http11ConnectionHandler.process(Http11Protocol.java:588) at org.apache.tomcat.util.net.JIoEndpoint$Worker.run(JIoEndpoint.java:489) at java.lang.Thread.run(Thread.java:619)</span><br><span class="viewMessage"> --></span><br>

  • What is the Diffrence between Adaptive and Webi Job Server

    Hello,
    What is the diffrence between Adaptive Job server and Webi Job server?
    In my BO server we didn't have Webi Job server but we are able to schedule the webi reports successfully.
    Any Idea on this.
    Thanks,
    Nimesh.

    I believe the Adaptive Job Server is on a generic shell server that behave as a Webi Job Server when it processes webi reports, as a program job server when it processes program object etc.

  • Destination disabled. []: [CrystalEnterprise.Ftp]. Please note the name of the job server used for your request and contact your system administrator to make sure the specified destination is enabled. (FWB 00031)

    Hi
    In BO 4.0 SP 9 when a administrator tries to schedule a report via CMC there is no error
    But when a user schedules a report and the destination is FTP location -> Use default settings he gets following error
    Destination disabled. []: [CrystalEnterprise.Ftp]. Please note the name of the job server used for your request and contact your system administrator to make sure the specified destination is enabled. (FWB 00031)
    There is only one Job Server and the destinations are enabled in it
    There is no Job server for Crystal Reports Job Server
    Do i need to create it and how.

    Please check if you have proper rights to schedule to FTP. You can create a new job server, whenever you schedule it, there are multiple job servers, it will handle based on the load. But it is not mandatory, depends on the load.

  • How to configure the crystalreports job server

    hi everyone,
    we are having crystal reports itself in our cmc .
    i am having a scenario where the  reports are stored in cmc i am showing you the folder hierarchy how the reports r stored in cmc( daily/eod/ak or fl or az), i am having the  specific crystal reports for that particular state in that folder. i want to schedule these crystal reports fro every day. i select file-system as destination for these crystal reports. my scenario is these reports need to be stored on the  server(i mean the location of the file-system)  under different directories  like
    /abcd/xyz/crystalreports/daily/eod/ak or
    /abcd/xyz/crystalreports/daily/eod/az.
    but i am unable to do that, i can see just to point all the crystal reports to one location i.e /abcd/xyz/crystalreports
    i did changes to my crystal reports job server by adding file-system to the destination and specified the path were i want to store the  reports but i cannot see how to store these crystal reports for different states in different directories on the server(i mean abcd/xyz/crystalreports/daily/eod/az)
    we r having boe xi 3.1 sp3 on solaris
    we want to schedule crystal reports thats the reason i asked for crystalreports job server
    Edited by: richa123 on Jan 13, 2011 7:41 PM
    Edited by: richa123 on Jan 13, 2011 7:44 PM

    Hi,
    If you are talking unmanaged reports (network location) then yes you can do this but if you are talking managed reports (reports stay in CMC) then you can not specify the folder path for the successful instance. The destination will be default enterprise and it will be same folder where the parent report resides, to keep the relationship intact.
    I hope this helps.
    Thanks,
    Muhammad

Maybe you are looking for

  • Ipod playlists/podcast automatic updates

    Hi, I have subscribed to some podcasts. Is there any way that my iPod can automatically update with the episodes I have not listened to-or with each new days episodes- without me dragging and dropping each episode I want every day, and erasing the ep

  • Help: Airport Remote Speakers No Longer Showing in iTunes

    Hello! After 2 years of streaming music to my remote speakers via iTunes and Airport Express (AX), I've had my first real issue. I have not been able to figure this out, and am at my last strand of sanity. My AX is connected to a pair of speakers in

  • Subcontract PO/PR does not generate PR for non stock component

    Hello, I need help on above topic. SAP Version is ERP Central Component 5.0. My problem is that PR is not being generated for non stock component in PR/PO of higher/parent material. I notice that in component overview screen the item cat for this non

  • Acrobat X Pro - Digital Signatures

    Good Morning! I am trying to add a digital signature field in Adobe Pro X.  It seems fine when I'm doing the editing and preview, but when I save as .pdf, the form doesn't allow it to be signed.  If I click on the form in that field nothing happens.

  • IChat Crashes

    So, I have the white MacBook, the kind that was improved when leopard came out. (bought in jan. 08) I had just had my hard drive replaced and I had heard that snow leopard was a good investment, so I bought it, and put it on my computer when I got it