Report showing sum of Budget/actual cost of WBS elements from diff proj

Hi,
i need to display consolidated budget/cost report for separate projects. (example PROJ 1 and PROJ 2)
in both projects, they have similar structure of WBS (same descriptions etc..)
in reports i can run both project but the values are summarized for the entire projects.. (results = Total of PROJ 1 + total of PROJ 2).
but i need report showing subtotals of WBS 1.1 of PROJ 1 + WBS 1.1 of PROJ 2 and so on...
i thought i could do it using CJI8 but i cannot filter it by description and do subtotals since it does not have a description column.
is my requirement possible with standard or need to customize a report?
thanks in advance

hi
please try to use Co Object Name field with sub total

Similar Messages

  • Function Module to find Planned Costs and Actual Costs against WBS element

    Dear All,
    We have a requirement where we need to find out the Planned Costs and Actual Costs booked against a WBS element, in a year. The costs can be against all the plan versions or on individual plan version.
    Are there any function modules to retrieve this value?
    Thanks for the help.
    Warm Regards,
    Judith

    Hi,
    The easiest way would be to get the OBJNR for all WBS elements from PRPS and look up RPSCO and summarize for Value type (RPSCO-WRTTP) 1 for planned cost and 4 for Actual cost.
    Please let me know if this helps.
    jibat

  • Report:actual costs:statistical wbs elements and assets assigned to them

    Hi all,
    I would like to run a report that gave me this info:
    WBS Element (all statistical)
    Assets assigned to each WBS
    Actual costs
    It would be perfect CJI3 but it doesn't show assets. In AM I haven't see either any report that shows WBS elements...
    any ideas???

    Thanks for your reply but this is not the question.
    The question is:
    Example:
    I have 100 WBS Elements. Each of them has an average of 5 assets assigned. (what makes 500 assets)
    I post lot of invoices in each asset.
    I would like a report that tells me at once the total actual amount posted in each ASSET and group those costs by each WBS element.
    Thanks and regards,
    Miguel

  • Need a report for actual cost by WBS element by month

    Hello all,
    I am looking for a report that will give me the total costs charged to a series of of WBS elements by month. Does anybody know if such a report can be run and what the transaction number of this report would be?
    Thanks

    Hello Stacy,
    Thank you for your help.
    I tried the S_ALR_87100185 report as you instructed but I cant get it to display as I would like to see it. What I need the report to do is display actuals by month and WBS elemnts from January through August. However the report cuts off at the May period. Does anybody have a workaround so I can see the charges from January through August?
    Thanks

  • PS - Report on Planned v/s actual cost of the project

    Hi,
    I have a client requirement on the above subject. In Report S_ALR_87013542, Under actual cost the system is taking both the Revenue and Actual cost booked on the project. Is there any other report wherein the system shows only the actual cost booked on the project so that planned V/s Actual can be compared.
    Rgds,
    Prasad

    Hi,
    You can also refer the report S_ALR_87013543 - Actual/Plan/Variance Absolute/Variance %. This will give the reports based on cost elements. Morever plan cost Vs actual cost can be obtained from Project Infosystem report (CN41/ CNS41).
    In fact the report S_ALR_87013533 is a hiecherachical report for plan & actual cost of project.
    If the system is calculating wrongly both revenue & actual cost under actual then you need to check Cost elements asignments & value category details.
    Hope this will help you.
    Regards,
    Rakesh Pradhan

  • Report for actual cost of WBS, Profit center wise

    Hi Experts,
    Do we have any standard report that gives the actual cost of WBS/Project with Profit center wise.
    Thanks,
    Krishna

    Hi,
    Thanks for your solutions.
    But I m looking for the Profit center in the report (display screen), not in selection screen.
    My scenario is like, the cost was posted to WBSE with X profit center/cost center in January, now I changed the profit center to Y for the same WBSE and posted.
    Want to see thru which PC I have posted to WBSE and how much. So that I can reversal.
    Thanks again.
    Krishna.
    Edited by: krishna.gujju on Jul 8, 2011 6:56 PM

  • Actual Date in WBS element

    Hi,
      Actually in my WBS elemrnt the actual Date fields are disabled in change mode,  i need to enter the actual dates, How to do...
    Thanks in Advance....

    Entering actual start and finish dates for a WBS element, depends on below
    1. WBS element has been further described using activities
    2. Whether you have already entered actual dates for subordinate WBS elements.
    WBS Elements W Activities
    1. You can always enter actual start.
    2. You can only enter actual finish, if all subordinate WBS element already have an actual finish.
    WBS Elements W/o Activities
    1. You can only maintain the actual start, if all activities that are assigned to WBS element have status "PREL" or "REL".
    2. You can only enter actual finish if all subordinate WBS elements already have an actual finish and all activities for this WBS element have system status "final confirmation".
    Regards
    Sreenivas

  • PLM table for Internal Order budget, Actual Cost and Actual Hrs

    Dear all
    In cProjects version 4.0, we have integration with existing ECC 6.0. We create Internal Order manually and assign it to cProjects.
    One cProject  having one Internal Order.
    Resource Planning part is managed in cProjects while Actual Time keeping(CATS with reference to Internal Order), budgeting of Internal Order, Material and Service Procurement which is done against Internal Order is managed in ECC. ECC and PLM are separate systems.
    We have RFCs established to transfer actual hrs, budget and actual cost data from ECC to PLM.
    Which is the ABAP table in PLM where we get linking of cProject with Internal Order and also actual hrs, budget and actual cost data in PLM system?
    Thanks & Regards
    Ashish

    actual hrs, budget and actual cost data in PLM system?
    Its not there, actual hours can be found in DPR_Task but it needs to be transferred by running a report.
    The planned cost etc is also calculated at runtime and passed on to Costing object in ECC (Int order/PS)
    Actual hours will be in CATSDB in ECC
    needless to say actual cost will also be there in ECC and not in PLM, PLM only displays at runtime based on RFC.
    If you want to try, Break the RFC and try to check the Evaluation..
    Niranjan

  • Report with cost center, Wbs element and cost element

    Dear Experts,
    I am creating Income Statement report with report painter using table CCSS.
    In this report, I need cost centers, cost elements/ GL accounts and WBS elements.
    Report is okay except sales. Because my cost elements for revenue are created with the category "11", it is not showing in the report.
    Please suggest what changes to make to get sales revenues in the report.
    Thanks

    Hi Simi
    Structure CCSS of Report Painter is combination of several tables including COEP
    Even your revenue should have been updated in COEP table...
    May be your report's selection conditions are preventing the revenues from being displayed... Can you check that?/
    Also, you can build this report from FI Structures
    Br, Ajay M

  • Actual cost of the employee from HR  to be  posted in projects

    Hi experts,
    Help needed.
    Scenario:
    Employee fills in time sheet (CATS) against WBS  element  (different for different projects) which is transferred to HR (IT 2002). Overtime hours is also recorded.
    Time evaluation and Payroll is run for the respective months.
    The requirement is to calculate the actual Personnel Cost per Project. When i post results to FI, it is not taking the WBS element. 
    I tried giving IT 27 , but when i try to post to FI, it gives out an error "Required field GL_ACCOUNT was not transferred in parameter ACCOUNTGL"
    How can i transfer the cost from payroll to WBS element? Is it possible??? if so, how?
    Pls help
    Helpful answers will be acknowledged
    regards

    hi,
    Pls check up with your WT list for posting
    If all the desired WTs are posted to expense & Balance sheet accounts with proper Symbolic account
    Check up with the FI team.
    -Also check are you changing any symbolic account or any new GL is attchaed to an existing Wt
    -Delimiting  the wage type chekc View: V_T52EZ.
    Regards
    Hemant V. Mahale

  • Exchange rate diff. influencing the available cost of WBS-element

    Hi all,
    here is a intricate problem I need help to solve. I am not so very experienced withon CO/PS, my main competence is within PM. This issue involves PM/MM/PS and CO so I am not sure if this is the correct group to post to, but I give it a try..
    In PM (Plant Maintenance) workorders the u201DPlanned Costu201D is calculated.  Exchange rate type for the u201DPlanned costu201D is picked from the CO Cost Version u201D0u201D that uses exchange rate type u201DPu201D. This is a exchange rate type that have one yearly fixed exchange rate. The actual costs are posted with exchange rate type M, which is daily updated.
    The Planned cost in the workorder is a part of the u201DAssigned Costu201D that are influencing the available budget on the WBS-element. u201DRemaining/Residual order planu201D.
    In cases where the PRQ/PO are created in other currency than the Company code currency we have a problem:
    The difference in exchange rate are causing the u201DAvailable budgetu201D to be too low u2013 and the only workaround I have found is to decrease the planned cost in the WO to release the available cost for the Budget. (make the available cost higher )
    Does anyone have an idea how to solve this?
    - I have thought of setting the exchange rate type for the planned cost to be the same as for the actual costs u2013 but it is not recommended to change the exchange rate type in CO for cost version u201D0u201D and not a good ide to change the exchange rate type for actual cost eather. This will also not solve the problem of exchange rate difference caused by PRQ/PO beeing created for a whole year for varying exchange rates.
    - Is there a way to exclude the u201D Remaining/Residual order planu201D from the u201DAssigned Costu201D? And what consequences will this have? Only cost from PRQ/PO will appear? (Since internal material (reservations) and internal hours not triggers a PRQ/PO)? I see there is a transaction CJE5 where you can exclude the u201D Remaining/Residual order planu201D from the u201DAssigned costu201D u2013 but I think this will only exclude it from beeing shown in the report S_ALR_87013558?- not from the calculation of available cost at the WBS-element?  which is what I need. (see Note 668240)
    -Is there any u201DExchange rate differenceu201D setting in the customizing u2013 how exchange rate difference are treated for PM orders? And will this help my problem?
    Best regards
    Ellen

    Hi ,
    try this way...
    Go to T-code>CJE0>Enter CO Area-->and execute the report 12KST1A  ->in the selection screen -->
    go to menu -->system -->status check the program name and ...copy
    next go to se38 and copy yhe above program name and execute and use submit report with selections,,,,
    Prabhudsa

  • Function modules or BAPI for posting plan costs for WBS Element

    Hi all,
    Does anyone know, whether there exists a function module or BAPI for posting plan costs to a WBS Element? K_COSTS_PLAN_PS does not work, because RKP1 is not allowed.
    Greetings

    check
    BAPI_COSTACTPLN_POSTACTINPUT   Activity Input Planning: Posting                
    BAPI_COSTACTPLN_POSTACTOUTPUT  Activity/Price Planning: Posting                
    BAPI_COSTACTPLN_POSTKEYFIGURE  Stat. Key Figure Planning: Postings             
    BAPI_COSTACTPLN_POSTPRIMCOST   Primary Cost Planning: Postings                 
    BAPI_PDTRANSCO_POSTPRIMCOST    Transfer of Planning Data: Post Primary Costs   
    K40C                           CO Actual Postings, Manual                      
    BAPI_ACC_PRIMARY_COSTS_POST    Accounting: Post Primary Costs                  
    BAPI_COPAACTUALS_POSTCOSTDATA  BAPI Operating Concern: Post Costing-Based Actua
    BAPI_PRIM_COST_CHECK_AND_POST  Primary Costs: Formal Parameter Check           
    S@meer

  • Input help for cost center & WBS element not working

    Hi ALL
    We are using SRM 4.0 with backend ECC 5.0.
    Input help for attributes cost center (CNT), WBS element (PRO) are not functioning.
    When tried to search for input help (F4) on the above attributes, I am getting message "Display not possible (Inconsistency in the input help)".
    I even applied SAP note 746788 for cost center search help.
    Can you tell me if I have missed any config settings?
    Thanks in advance
    Jagdish

    Hi,
    Did you managed the transactional RFC destination in the customizing (where you define all your log. systems it is an additional field in the table control).
    Regards.
    Vadim

  • Cost Center & WBS Element

    Dear All,
    My client wants to use WBS elements instead of Cost Center.  Can WBS elements can be mapped under Profit Centers ?
    Business Areas, Profit Centers, Cost Centers, Plants, WBS elements - can we use all or some to be eliminated ?
    Thanks,
    JEERI
    Moderator: Please, avoid asking basic questions

    Hi Jeeri,
    the answer is yes to both questions.
    Please see SAP notes 41103 and 106968 explaining in detail the CO account assignment
    logic.
    br, Guido

  • BOOKING TRAVEL COST TO WBS ELEMENT

    Hi there,
    Can anyone tell me how i can book travel expenses to a WBS element.
    From pr05 i can select the WBS but when i post it to FI its getting posted to the cost center (and the profit center) and not to the WBS although the correct GL account is being updated.

    Hi,
    The problem is at your wage type and symbolic account settings. Remove the tick for "w/o CO receiver".
    Path: SPRO>Financial Accounting (New)>Travel Management>Integration of Travel management and payroll>wage types>define assignment of wage type to symbolic account.
    Settle a trip with WBS to FI, whatever the CO assignment you maintain in the trip will flow to FI.
    Thanks,
    Sharif

Maybe you are looking for