Reposting fixed costs to variable costs
Hi Gurus,
one of our subsidiary company uses target=actual method in the cost center accounting. Sometimes they forget to plan some cost elements during the planning process. If some costs incurred on these unplanned cost elements, SAP put all of these costs to the fixed costs during the period-end closing (activity allocation).
So far so good, but is there any possibility to repost these costs to variable costs on cost center level???
Thx
Thanks a lot for the quick reply.
We know the splitting method but this company don't use it. For this reason I asked about a possibility if it is possible to repost the amounts from fixed to variable costs afterwards.
I would be grateful for an other solution.
Similar Messages
-
Hi All
Can anyone help me to understand what is base cost and what is variable cost. And also from where can I find these both.
Thanks
VaniMayby you mean fixed and variable costs?
Variable costs are expenses that change in proportion to the activity of a business.
For example, a manufacturing firm pays for raw materials. When activity is decreased, less raw material is used, and so the spending for raw materials falls. When activity is increased, more raw material is used and spending therefore rises.
Fixed costs are business expenses that are not dependent on the level of production or sales.
For example, a retailer must pay rent and utility bills irrespective of sales. -
Material cost as variable cost
While viewing the cost analysis of the standard cost estimate of a material after costing run, we find that the material cost is coming as a fixed value. No value in the variable column. Material cost is always a variable cost, right ? But how this is coming ?
Hi ,
Please check wether BOM has a fixed quantity tick on that material .
For that go to BOM , and click on the item and see the details for the material . In Basic Data tab , you have the fixed quantity indicator.
Regards
Sarada -
Product Costs Split is required, that is fixed and Variable costs
Hi All,
In a Sales Order screen (VA03), if we check the Costing, by clicking on EXTRAS -> COSTING, we get Total Costs, Fixed Costs and Variable Costs.
Can someone please help me in getting these costs, I have used Table KEKO,
In KEKO (filtered based on Material, Plant, Sales Document, Item) and executed it, taken the resultant ProdCstgNo (KALNR)
In KEPH used that KALNR, as a result I am getting 4 records, However 2 records are not correct, and 2 are correct.
In correct ones I have to add few costs to get FIXED COSTS and few costs to get VARIABLE COSTS.
My question is, which filter should I use to get the correct record (probably just one record) ?
Can I in some table get the summed up VARIABLE COSTS and FIXED COSTS, rather that I have to add them seperately ?
Please help, will award points promptly. ThanksHi,
In KEKO (filtered based on Material, Plant, Sales Document, Item) and executed it, taken the resultantProdCstgNo (KALNR)
In KEPH used that KALNR, as a result I am getting 4 records, However 2 records are not correct, and 2 are correct.
The table you mentioned CKMLKEPH is used for Material Ledger actual cost components.
Regd,
Khan. -
Fixed & Variable Cost flow to COPA Value fields
Hi All,
I am using the Fixed & Variable Cost option that has to flow to COPA (under which mechanism it will flow to COPA Value fields).
as structure based sample from OKTZ to KE4R
OKTZ
KE4R
01
10
Raw Material
3
Sum of Fixed & Var
ROHST
Raw Material Cost
01
20
Power
1
Fixed Amt
VVPOW
Power
01
30
Labour
1
Fixed Amt
VVLAB
Labour
02
10
Raw Material
3
Sum of Fixed & Var
ROHST
Raw Material Cost
02
20
Power
2
Var Amt
VVPOW
Power
02
30
Labour
2
Var Amt
VVLAB
Labour
While I run Std cost estimate it will show me "Power & Labour" -as per KP26 Fixed & Variable
Power
Fixed Cost
15
Variable Cost
8
Labour
Fixed Cost
10
Variable Cost
5
How it ditribute to COPA Value Fields the below amountsAny replies ...........pls
-
Fixed Cost to be fixed as 40% of Variable Cost
Hi,
We want to fix the fixed cost of all the finished goods of our company to fix 40% to variable cost. Is there any way to make routing.
Presently, what we are doing, we are making several routing to get this result, but this procedure is quite lengthy,
Kindly help me out.
Regards
GRHi G R,
Why Can't fix the Fixed and Variable Cost in KP26, that Prices only will come to Routing?
If it is wrong Please revert back to me -
Fixed Cost & Variable cost in Production Order
Hi ,
I have maintained the fixed cost & Variable cost in KP 26 for the activity type .
for 1 hr
Fixed cost : 1
Variable cost :1
Operation duration is 1 hr , when i check the Planned cost it shows total plan cost is 6.92 ,
Fixed cost as 3.46 and variable cost as 3.46 ,
How the system calculates 6.82 ,
I have maintained the valuation Variant for the activity type is Plan price for the period .
As per my understanding system has to calculate the Planned cost as 2 (1 for fixed + 1 for Variable )
Can anybody explain me why the system calculated the price as 6.82 ...
Thanks in Advance ...Dear,
Please check the following :
1.Goto CR02-Slect the Costing tab -Check the Formula Key assinged in the Work Centre costing tab .??
2.Please note that variable cost is dependant on quantity, where as fixed cost is independent of quantity.
For example, if you have updated Rs.300 in variable and Rs.200 in Fixed cost fields and you quanity of activity type consumed is 100 minutes.Your fixed cost will be Rs.200 and variable cost will Rs.300/minute * 100 = Rs.30000
3.What s the currency in Controlling area ??
Regards
JH -
Experts,
What is the Variable Cost tab in Landed Cost, Cost meant for?
I only have the Fixed Cost that is active, the Variable Cost is not active. How do I get this active?
Thanks,
MarliHere is the answer:
The tab consists of two subtabs: Fixed Costs and Variable Costs. If your company manages a perpetual inventory system, the Variable Costs subtab is disabled. -
Apportionment of semi variable cost
Dear SAP Gurus,
We define the cost components in the cost component structure (OKTZ) with attributes as variable or fixed and variable costs.
Suppose if we define one component with attribute as fixed and variable - where do we maintain the settings as to how much is fixed and how much portion goes to variable - Please clarify.
Please provide example as to how KP06 and KP26 differentiates fixed and variable costs and how it is displayed in the output of CK13N.
Please explain.
Regards
Rajya LakshmiHi,
Thanks for the reply.
My client requirement is to show the costs under variable costs. For which I have defined the cost component as variable and planned them in KP06 and KP26.
Still while performing KSS2 and KSSI system is showing values under control costs fixed.
I need the solution as to what shall I do to show them under the variable control costs alone.
Please Help ASAP.
Regards
Rajya Lakshmi -
Fixed and variable cost component break up in PCA
Hi,
Is it possible to get fixed and variable cost component break up and contribution report in PCA at each product group level and lower level of node. I think this requires development. As my client requires the report to have cost break up into fixed and variable in PCA at each line item level. Can anyone solve thisHello
You can get the report by using the report painter, no development will be required.
Regards
Madhav -
Activity Allocation - Split of costs between variable and fixed costs
Hi,
The business is very keen on contribution analysis. Therefore all costs (cost elements) are broken up as fixed and variable.
I have a utility cost center (boiler) which incurs both fixed and variable costs. The cost center produces STEAM (created as an activity type). The steam consumption at the process order level cannot be entered. Therefore the production cost centers contain only MHR (machine hour) as their activity. Morover because the business wants to look at costs by production process each production cost center provides a different MHR activity type.
When I compute the activity rate at the boiler cost center for steam, the system correctly breaks up the rate as fixed and variable. Now, when I try to do an activity allocation (KSCB) from boiler to the production cost centers, the entire costs are being treated as fixed.Hi,
check SAPNET note 541858, this describes the system behaviour regarding fix/variable cost when KSCB is executed.
Best regards, Christian -
Fixed and variable cost element's cost
hi,
i would like to clarify. need your kind advice.
1) can direct cost has both fixed and variable cost? can have example?
2) can indirect cost has both fixed and variable cost? can have example?
3) direct cost only happens in direct cost center and indirect cost only happens in indirect cost center?
4) can direct cost center assign to fixed cost element and variable cost element? Likewise, indirect cost center assign to fixed cost element and variable cost element?
thanksHi,
As per my understanding
Direct cost to a department could be variable or fixed.
Example: A supervisor in the X department would be a direct cost to the Dept A department. Since the X salary is likely to be the same amount each month regardless of the quantity of products manufactured, it is a fixed cost to the department. The supplies furnished to the X department will be a direct cost to the department, but will be a variable cost to the department if the total amount of supplies used in the department increases as the volume or activity in the department increases.
Indirect cost is the Power used to operate a production machine.
Example: The cost of the Power is variable because the total Power used is greater when more products are manufactured on the machine. Depreciation on the production machine is also an indirect product cost, except it is usually a fixed cost. That is, the machineu2019s total depreciation expense is the same each year regardless of volume produced on the machine.
As you can see, costs can be direct and indirect depending on the cost object: product, department. The cost is fixed if the total amount of the cost does not change as volume changes. If the total cost does change in proportion to the change in the activity or volume, it is a variable cost. -
Fixed & Variable cost of the Material at CK11N
Hello Experts,
Before posting this thread, i have gone through several threads about my query. Still I have a doubt.
Material Cost always should be Variable. Cost Component Structure OKTZ also the Inventory Valuation would be Variable Cost as per as Std SAP.
But where as the Raw Material Price control would be "S" & the Cost Component Structure of OKTZ having Inventory Valuation Fixed + Variable Cost then what would be the effect..?
I have run a SCE for a Material & both Material having standard price 140.6 & 1.09. Then how come the Fixed Value shows here as 10.37 & 0.9 & How can it be divided into Total & Fixed Value..?
Regards
RajDear Raj,
Please check the following settings in OKTZ:
Materials are of 3 types:
Finished: Valuation (Fixed + Variable)
Semi Finished:Valuation (Fixed + Variable)
Raw Materials: Variable
Why Inventory Valuation (Fixed + Variable) for Finished Goods:
It contains material price as well as overheads.
Overheads may contain fixed portion also in addition to variable nature.
So Finished goods valuation should be (Fixed + Variable).
For Raw materials valuation should always variable:
You can make the settings in OKTZ as mentioned below:
Please check these settings and change the settings accordingly.
Hope this will helps you.
Regards,
Pavan Kumar Arvapally -
Hi,
Could anyone show me how fixed and variable cost are treated in SAP
In case commercial enterprise, (not implementing Product costing sub-module), how to take care fixed and variable cost ?
If it possible, could you show me the documents relevant my concern!
Thanks very much for any help!Thanks Ashok,
Yes, I am clear what you mean now.
But My concern is mixed-cost (semi-fixed or semi-variable), how the system dealt with this?
For example:
salary of sales man: Cost element 627000
fixed salary: 500
If he sells more than 20 product a month, he will receive 10 for each addition one.
So 500 is fixed cost, and the bonus is variable.
This CE 627000 is called mixed cost element.
In many cases, the accountant can not know which part is fixed, which one is variable as my example.
So at the end of period, she will use some ways to calculate
And, another problem i care: except drawing statement , what more can SAP do about fixed & variable?
Thanks very much Ashok! -
Definition of fixed and variable costs
Hi,
where do I define if a an expense account is a fixed or variable cost element? Do I have to set up separte expense accounts in the Chart of Accounts for fixed and variable?
Can you give me some info of how this is done.
Thanks
PaulHi Paul,
You can use the features of Cost Element Attributes and Cost Element Attributes Mix for this.
Pls check OKA4 and OKEC transaction codes for this. IMG -- CO -- CE Accounting -- Master Data -- Cost Elements
Once you create the Attribute Mix, you can populate it in the Cost Element Master Data.
You can describe a cost element with a maximum of eight attributes, independent of the chart of accounts. You can use these attributes for evaluations in reporting.
You can store a valid combination of permitted attributes:
--In the cost element's master data
--In cost center planning for the combination cost center/cost element
Pls revert back for further explanation...
Srikanth Munnaluri
Maybe you are looking for
-
"An error occurred in the idisk quota" - A fix.
Hi all. I am another one of us that has seen this error whilst publishing. Here is my fix, hopefully it will work for others: Make a temporary folder. (I'll call it Temp and put it on the desktop) Navigate to ~/Library/Application Support/iWeb and th
-
Hi, How do i include an external .js(JavaScript) file into a JSP file?My .js file is located in some package(lets say abc.jar). Below is my application structure:- jsp | ->MyJsp.jsp lib | | abc.jar | | ->com.abc.test
-
Other problems with loading Captivate files into Flash AS3 project
I have a Captivate file done with Captivate 3, published to Flash player 9 that is being loaded into Flash AS3. The captivate is a simple recording of some mouse clicks in a browser. I am displaying the playbar along the bottom, and its buttons all w
-
How to make use of ALEAUD for receiving acknowledgement
In a IDOC-->XI--> file scenario, how to get the acknwledgement of the message received by the Receiver Business System, by making use of ALEAUD in Partner Profile ?
-
I cannot send or receive group messages when one or more member of the group is not on iMessage. I have group messaging turned on in settings and send as SMS or MMS as well. This problem is on my iPhone and on my Mac. Does anyone have any suggestion