Request delivery schedule with fixed total delivery qty updated by MRP

Hi Gurus,
Please help on this issue. The issue is since in the "direct Purchase order", the delivery date is fixed & not updated by MRP, seems only delvery schedule line in Scheduling Agreement can be updated by MRP.
Below is the requirement:
1) Use appropriate Purchase Document (like Scheduling Agreement) for subcontracting the in-house production parts when capacity is insufficient, so that delivery schedule qty can be updated by MRP.
2) The Purchase Document will covered partially the requirements of the in-house production parts, the qty covered should be the same as total open qty in the Pur Doc to be delivered (if it's Sch. Agrmnt, should be Target Qty)
3) During MRP run, source of supply should be assigned to the Purchase Doc iteam firstly, afterward assigned to planned order
Thanks a lot!
Jerlyn

Hi,
For all of your queries;
ME01 - Maintain Source List for the materials
Here maintain, Vendor, Plant, Purchase Org, most important input Scheduling Agreement No  in Agreement column and  in "MRP" column, use "2" i.e. Record relevant to MRP. Sched. lines generated automatically
Now run MRP and observe the result, it will consider Scheduling Agreement in MRP.

Similar Messages

  • Delivery schedules with outline purchase agreement

    Can somebody tell me how to automatically result delivery schedules with outline purchase agreement through MRP running?

    Priyanka.P thanks for your reply.
    The following is how I process:
    1.I use auto po indicator at VMR
    2. I tick Auto PO indicator and source list indicator at MMR
    3.I have made schedule agreement(type LP) and assign it in source list as fix vendor(1000) and with the MRP indicator 2(Record relevant to MRP Sched. lines generated automatically)with the proper validity periods in IDES.
    4. In MD03, I use the create schedule as 3
    5.There is Dependent reqmt.
      When I finish my MRP running I find a Purch.Req with Exception 30( Plan process according to schedule (08.11.07/08.11.06)) generated. however I hope a  vendor Delivery schedule.

  • Multiple delivery schedule (with same delivery date) for same PO line item

    Hi All,
    In a STO, for a PO line item say for 10 quantities. I have been receiving 3 delivery schedule with the same day with quantities say 5 3 2. I would like to know the what would be possible reasons for this.
    Regards,
    PSS

    Hi PSS,
    I had the similar issue there is a report which gives you the reason for delivery split
    Please refer to the following thread
    Multiple deliveries created
    Thanks
    Diwakar

  • The delivery schedule lines don't get created automatically on MRP run.

    Hi All,
    The delivery schedule lines don't get created automatically on MRP run for subcontracting material.  I have maintained source list as follow eg.
    Valid from | Valid to | Vendor | Porg | PPI | Agreement | Item | Fix | MRP | MRP area
    02.11.2009 | 31.12.2999| XYZ | XY01|     |AA0000XYZE |10 | X |2 | ABC
    Could you please help me about this issue
    Thanks in advance.

    Hi Amit,
    Please ensure the value of Special procurement key in the MRP2 view for the material. It should be maintained as 30 - subcontracting.
    Thanks and Regards,

  • Scheduling Agreement New Delivery Schedule With & Without Proposal

    Hi Experts!
    I had an issue regarding our scheduling agreements. Issue is below:
    What is the difference between "New Delivery Schedule <b>WITH</b> Proposal" and New Delivery Schedule <b>WITHOUT</b> Proposal"?
    Any responses will be greatly appreciated and points. Thank you for your time!!
    Best Regards,
    WC

    In addition to the above post,
    as you changed the date manually from 2nd to 3rd....
    so there are was no report for 2nd generated ulitmately...and if generated it was changed...right...
    so when you again run the mrp...the system will generate one more pr for the same article....
    this ultimately happens because of the set del dates in the MMR as i told above..
    Hope it helps..
    Regards
    Priyanka.P

  • Is it possible to add new delivery schedule with bapi_change_po?

    Hi all,
    We're able to update PO existing line item and delivery schedule date with BAPI_CHANGE_PO. However we can't find any way to add new delivery date (under delivery schedule tab, in PO) for multiple delivery schedule scenario.
    please advise is it to do so with BAPI_CHANGE_PO or we should try other approach to do it. Thanks.

    Use the BAPI "BAPI_PO_CHANGE".  New delivery schedule information can be filled in the structures POSCHEDULE & POSCHEDULEX.
    poschedule-po_item = <item_number>
    poschedule-sched_line = <new schedule Line>.
    poschedule-delivery_date = <delivery_date>.
    poschedule-quantity = <schedule quantity>.
    append poschedule.
    poschedulex-po_item = <item_number>
    poschedulex-sched_line = <new schedule Line>.
    poschedulex-po_itemx = 'X'.
    poschedulex-sched_linex = 'X'.
    poschedule-delivery_date = 'X'.
    poschedule-quantity = 'X'.
    append poschedulex.
    Regards
    Vinod
    Edited by: Vinod Kumar on Apr 21, 2010 11:35 AM

  • Schedule Lines - fixed Date and Qty checkbox

    Hi Experts,
    When an order is placed, on the schedule line tab there is a check box for a fixed date and qty. Can this only be set manually or can it be set by customer number.
    Thanks in advance.
    Mike

    Hi,
    When the availability check will happen in that screen you can see fixed date and quantity If you check that it will automatically copied in schedule line .
    If you leave the field blank, the delivery date and confirmed quantity are not fixed. If you are able to expedite either the manufacture or purchase of goods, you may be able to deliver the goods closer to the customer's original request (and sooner than the date the system confirmed).
    Regards,
    Krishna O

  • MRP-Delivery Schedule for Sales order is not updating in Production order

    Dear Experts,
    I have created Sales order and maintained delivery scheduling, Then Run MRP through MD50,
    We received Planned order then through this we have converted to Prodcution order.
    When we observe the delivery schedule for sales order under assignment Tab in Produciton order which is showing zero instead showing line item of Delivery schedule.
    I am able to see Sales order and Line item but i am not abel to get any delivery schedule line item.
    Please suggest where settings are missing.
    Thanks in advance
    Regards
    Don

    Dear Experts,
    Please provide me solution.
    after Running MD50 transaction against Sales order.
    If I maintained different Scheduling Line Item for First Line item of Sales order.
    The Respective Scheduling Lines should update against Each Production order which has converted from Planned order.
    Thanks in advance.
    Regards
    DON

  • Procurement scenario with delivery Schedule

    Hello experts,
    In this case we have a purchase order that count with Delivery Schedule, in this case 4 planned deliveries, every one with this specific delivery date and Quantity.
    Now we going to create an Inbound delivery and the goods receipt, only for the first Delivery Schedule (it means 3 delivery schedules are pending to happen). When we verify in the Purchase order history, only show a partial Goods receipt (in this case corresponding with the first delivery schedule).
    Now we are going to verify in EM (/SAPTRX/EH_LIST) and the event handler show the events as executed complete, but in the reality, we have still pending 3 Delivery schedule to make.
    In this case we have a difference between SAP ECC and SAP EM, because in SAP ECC the system show the event in u201Cpartially executedu201D, and in EM the event itu2019s in status of Closed.
    It represent a problem of visibility cause I can´t see complete, an event that is still in progress.
    An additional question it´s about the visualization in /SAPTRX/EH_LIST transaction, in this case we have the detail at -> Purchase order / position.
    It´s posible to see  -> Purchase order / position / delivery schedule. I mean at delivery schedule level?
    In the following link you can see the description made with images for more clarity:
    http://www.sendspace.com/file/zx3w6o
    I appreciate a lot your help with this issue.
    Best regards,
    Julián.

    Hello Julian,
    if you want to track on schedule line level an option would be create EH also on schedule line level.
    This would be a complete new visibility process.
    Another option is to create an own rule activity fo the status handling. There you could check if all events for the inbound deliveries for the assigned schedules are already received. If not you could create a new status like partially delivered.
    This would need only some enhancements in the rule set.
    Best regards,
    Steffen

  • PO Delivery schedule

    when creating PO item via PR, i find one PO item have several ve delivery schedule item, and each delivery item generate from same PR.
    Example,
    Item 10
    Material A 37 Qty's
    I am getting Delivery schedule with multiple schdule lines with splitting the total Qty's for same Purchase Req
    Can you explain how this happening for One PO item.
    I am getting this for Intra Company STO.
    There is no delivery created for this STO
    With Regards
    Ram.

    Check whether is there any maximum order qty maintained in the material master or in the info-record

  • Schedule Line(Delivery Schedule) generation stopped

    Dear Experts,
    We are using Scheduling Agreeements to procure materials from Vendor.We are using MRP(type PD) to generate our requirements.We have noticed that ,for a Schedule Agreement- MRP generates Delivery Schedules accordingly,but if user will try to interven the process by entering a manual schedule line with some quantity,and Fix Indicator is getting fixed,after that MRP is not able to generate Schedule Lines,henceforth.
    We had done the same things earlier,but MRP was able to generate Schedule Lines even after manual intervention by user.We have not maintained Fix indicator in Source List also and the particular material and the Agreement both have been marked as MRP relevant against that Vendor in Source List.
    If we will remove the open delivery schedules having Fix indicator fixed ,after that we run MRP,then the Schedule Lines are getting generated,but for those Schedule Lines(Manual or thorough MRP) having Fixed Indicator fixed and have GRN transaction completed,we would not be able to delete those and also MRP will not be able to generate Delivery Schedules.Please advice what is the reason behind this and share the full concept of Fixed Indicator against the same?
    Regards,
    Soumick

    It looks we encountered very similar problem,one item line in our Scheduling Agreeements can't be driven by MRP MD02/MD41,but if we add another same line item under this SA, this new line can be driven by MD02,and generated delivery schedule line.
    I don't know why. Please give me some light! Thanks!

  • Delivery schedule ME38

    hello Gurus,
    When we are maintaing delivery schedule with ME38 t code there is a button fixed which can be ticked or unticked please let me know the use of this.
    I have already seen F1 Help documentation
    helpful answers will be rewarded
    regards
    suresh

    Hi,
    Schedule lines for a Scheduling Agreement can be created in following 2 ways;
    1. Manual (In ME38)
    2. Automatic via MRP Run (MD01 / MD02)
    1. If you create Schedule lines manullay in ME38, these will get fixed by default since you know the requirment and entering by yourself.
    2. When Schedule lines are generated via MRP Run (MD01 / MD02), then system creates these as per the MRP Parameters which may not provide the correct results always and you might make some chnages in these schedule lines so these type of Schedule lines will not have "Fixed" indicator ON by default after creation.
    If you go to ME38 and make any chnages in date or quantity of schedule lines as per your requirement then "Fixed" indicator will get activated for this Schedule line and will not be affected by MRP Run for 2nd time onwards and will get changed only via ME38.
    To generate Schedule lines via MRP, maintain Sourcel Iist for material in ME01, here assign the Scheduling Agreement and also Put MRP Indicator as;
    1   Record relevant to MRP OR
    2   Record relevant to MRP. Sched. lines generated automatically

  • Zreports for vendor wise Delivery schedule release

    hi ,
    Can some one help me with codes for  the reports for the Delivery Schedule Release vendor wise. which shows vendor details , on titles, Schedule agreement Nos and then the material listed with the qty and targetted date.
    Kindly help
    regards
    Kim

    How to release directly from ME38 ?
    I tried in the path  delivery sche > Edit > generate Forc Sche
    but the msg below:
    Error generating release against scheduling agreement  (cause 2)
    Message no. 06857
    Diagnosis
    The function module for generating a scheduling agreement release (forecast delivery schedule or JIT delivery schedule) has run up against an error, causing processing to be terminated.
    In this case the cause of the error is 2.
    *System Response*
    The error may involve one of the following situations:
    1: The nature of the error cannot be specified precisely.
    2: The forecast delivery schedule or the JIT delivery schedule was generated but no message record could be generated.
    3: A document type for which the functions "Generate forecast delivery schedule" or "Generate JIT delivery schedule" are not defined may be involved.
    4: A material for which the function "Generate JIT delivery schedule" is not defined may be involved.
    5: A scheduling agreement that has not yet been released by all persons responsible may be involved.
    6: The factory calendar has not been maintained correctly.

  • System problem in the delivery schedules of a purchase order ?

    hello to all,
    I am creating a purchase order and displaying it (in smart form). what i am noticing is the system does not keep that entry of the delivery schedule(with itself) that has the same audit quantity and delivered quantity. why is this so and how to display that entry ?
    suppose following r thr delivery schedules entries(against a material), while creating a purchase order..
    PO Quantity of Material is  4
    Delivery Schedules are:
    Deliv Date  SL Qty    Stat Del Date  GR Qty   Open Qty
    01.03.2006    1        01.03.2006      1          
    03.03.2006    2        03.03.2006      1           1
    04.03.2006    1        04.03.2006                  1
    where,i believe, 'SL Qty' = Audit Quantity and 'GR Qty' is the Delievered Qty.
    Now when i display these delivery schedules(thru a smart form) the first entry in the deliveryschedules does not get displayed.
    Deliv Date  SL Qty   GR Qty  
    03.03.2006    2        1  
    04.03.2006    1        0  
    why does system deletes the entry whose audit qty is equal to the deliv qty ??
    hope u all got it... Thanks for yur time..

    Hello,
    Refreshin this thread ... can sumone anwser to my query ?

  • MRP creating multiple delivery schedule lines in PR

    Hi,
    We have activated MRP (type PD) where Purchase requiesition is auto created by system for requirement quantity. We require to optimize delivery schedule in such a way that entire PR quantity is broken into various delivery schedule based on planned delivery time and requirement.  Scenario can be further explained with following example.
    Material Requirement for a month is say 1,25,000 units
    Closing Stock say 25,000 units
    PR Generated by system for 1,00,000 units. The entire quantity is schdulled with only one delivery schedule line as per planned delivery time. 
    The requirement is to generate multiple delivery schedule lines automatically in Purchase requisition based on planned delivery time so that Purchase orders can be placed with system generated delivery schedule lines.
    How can it be achieved ?
    Regards,
    Nirav Kinkhabwala

    Dear
    Are you dealing with Single vendor  where you want Multiple Schedule Line item through single PR  which should be generated through MRP run ??
    What you will have to do is to set up the Outline Agreement or Info Record for your vendor and material and then create the source record for this vendor- material relationship and make sure that this source record is set as MRP relevant. Once MRP is run, the vendor is automatically defaulted to your PRs. If in your material master, you have defined the same purchasing group for various material numbers, then with Transaction ME59, it is feasible that you can combine various PRs of the same purchasing group by flagging onto the 'Per Purchasing Group' indicator checkbox. Make a trial test and let me know how it goes.
    Or you can use Qouta arrabgement in that case for different vendor .Please refer : Multiple Requisition  line itme for Quota arrangement
    Just check and revert
    regards
    JH
    Edited by: Jiaul Haque on Dec 25, 2010 1:52 PM

Maybe you are looking for

  • Scheduled Web Intelligence report fails with ORA-01013 and WIS 10901

    Hi,         the environment I'm working in is BOXI R2 SP4 on a Solaris 10 server using WebLogic running against Oracle 9i database. I have a report written by one of the users. In SQL Viewer the SQL detailed is two joined Select statements. Each time

  • Money transfer

    I would like to transfer my skype credit from one account to another. How can I do this?

  • Supervisor desktop:- Display current skill

    Hi All, In supervisor desktop application, i would like to know, when an agent is in talking mode, the current skill to which he is actually mapped to. a sample code for the same would be of great appreciation. Regards Suhas

  • Quicktime Export Issue

    On my MacPro have a sequence shot in 720p60 with an HVX200 and when I try to "Export using Quicktime Conversion" and converting to H.264 at 50% (ie. 640x360) the resulting quicktime file is 960x720? I can startup my MacPro in target firewire mode and

  • Part-time labview job

    Hello , I am looking for a part-time labview job, remotely. Have 6 years labview experience, participated on different projects. Main qualifications - large scale software architecture,costum hardware IO, signal processing. Recently  started to work