Requested delivery date in Sales order for internally produced products

Dear All,
I'm searching for a solution for the following case:
Customer places a sales order for inhouse produced material, there is no stock for that product and no planned receipts, so ATP check does not confirm anything.
A sales person does not know when product can be produced since thats depended on components availability on stock or confirmed dates of future receipts of needed components.
So at the stage when a sales person inputs a sales order he should somehow calculate the requested delivery date.
He can create a production order (without saving it) for requested good and check components availability inside production order, and based on that figure out a valid date, but thats of course is not convenient at all.
He will need to go through all confirmed dates in ATP (in production order) and figure out the latest date when the latest component is available. Then he will get a start date for production order and as a result a date when requested product will be on stock.
All these activities which could be a workaround are not so convenient for sales persons.
I'm curious, is there any official SAP way how to calculate a day for above described case when product will be produced (like simulation of overall chain) and of course much better to have it in background...
Your ideas and suggestions are very much appreciated.
Best Regards,
Andrey

Hi Andrey
I feel this is more of process issue rather than config problem. Whatever market and productline your client is operating in ,there will be some analysis available regarding the time required to replenish a material from the date requirement is generated and this is even if you don't have SAP.
Generally companies have the approximate time entered in  material master  either in GR processing When material is procured  or in planned delivery time When  produced in house.
So you can still maintain approximate time there and configure availability check to check cumulated confirmed quantities.
change VOV8 to propose the delivery date. this way u get delivery proposal for availability check and then still u can block the delivery as Mr.Sai ; has suggested , OR  have your own checks incorporated in user exits in  RV03VFZZ.
The requirement transfer can be blocked and you can use  user status  or  combination of user status and user exit to control the requirement transfer.
For customer specific manufacturing of sales order stock also ,you need to verify strategy group and planning strategy .that should solve problems rather than changing config. into sales.
So i would suggest that have a second look  at PP ,MRP config and material  master data and then check for changes on SD side. also try using delivery proposal.
Regards
Mandar

Similar Messages

  • User Exit for Requested Delivery Date in Sales Order

    Hi
    Which user exit can be used to change Requested Delivery Date in Sales Order.
    Scenario:  Sales Document Type: OR has Lead Time: 7 days.  System always proposes delivery date after 7 days.  We need to change this Lead Time based on plant.
    Thanks in advance for your support.
    Regards
    Uma

    Hello,
      try with USEREXIT_MOVE_FIELD_TO_VBEP or USEREXIT_SAVE_DOCUMENT_PREPARE, of program MV45AFZZ.
    Hope to be useful.
    Best regards,
    Andrea

  • Changing proposed delivery date in sales order for one specific sales org

    Hi All,
    I want to change proposed delivery date in sales order automatically for one specific sales org only without changing lead time in VOV8.
    For that can I use MV45AFZZ. But it is asking access key to make changes. Is there any other user exit for the same. And how does exactly change it.
    Thanks in advanced.
    Points will be awarded.
    Regards,

    EXIT_SAPFV45E_001 has nothing to do with this - it is meant to update the purchase order from a sales order. It might not even be triggered if the sales order has no link to a purchase order.
    USEREXIT_SAVE_DOCUMENT is not really good for this either, because the delivery date has to be changed before that. If memory serves, it also influences the schedule lines and probably the ATP check and such. I would strongly advise against it. One of the other routines in MV45AFZZ should do just fine, USEREXIT_MOVE_FIELD_TO_VBAK for example.

  • Delivery date in Sales Order for Make to Order Scenario

    Hello,
    We are creating Sales order for MTO ... In that our requirement is to get the delivery date based on Production planning and not from RLT. ie we have configured RLT as 36 days, system calculates delivery date as 36 days from the date of order what ever be the order quantity but considering our plant capacity  this is not possible. In our Production planning we allocate certain numbers per week. so when we give 100 nos order it plans as per the allocation if we see through MD73 it will give clear picture but in our sales order it shows delivery possible date as 36 days from date of PO. How to correct this.. it should calculate from the date of beginning of the production process.
    Can any one help in finding solution for this
    Thanks in Advance

    Hello,
    We are creating Sales order for MTO ... In that our requirement is to get the delivery date based on Production planning and not from RLT. ie we have configured RLT as 36 days, system calculates delivery date as 36 days from the date of order what ever be the order quantity but considering our plant capacity  this is not possible. In our Production planning we allocate certain numbers per week. so when we give 100 nos order it plans as per the allocation if we see through MD73 it will give clear picture but in our sales order it shows delivery possible date as 36 days from date of PO. How to correct this.. it should calculate from the date of beginning of the production process.
    Can any one help in finding solution for this
    Thanks in Advance

  • Change Delivery date in Sales Order

    Hi all
    I want to change Request Delivery Date in Sales Order. But when I changed Request Delivery Date system appear" The default date is not copied into existing schedule lines"
    And Delivery Date didn't change.Could you tell me how to change Delivery Date ?
    I setup Request Delivery Date - September 21th but Availability Date is September 19th. Could you tell me how to setup loading time, picking time, packing time ?
    Thank and Best regards,
    Thang

    Hi,
    When you change the Request Delivery Date, it automatically changes the schedule line date of all the materials, but by default does not change the schedule line date of the ordered material.
    So just check the ordered material schedule line date and change it manually in the order.
    Similarly maintain the same date in all the resp fieldsi in the delivery, wherever you see the date.
    Regards,
    Siddharth.

  • How system determine delivery date in sales order

    Hi, sap gurus
    I am new to sdn forum please help me regarding my question
    1) how the system will determine delivery date in sales order
    2) what are factors effects to conform sales order stock
    3) what is different between static check and damanic check in credit mgt
    Thanks and regards
    nishad

    hi,
    Reg question:1 - System determines the Requested Delivery Date based on the Scheduline assigned to the item category of the item in sales order.the schedule line in the order transfers the requirements trhu MRP (can be individual or collective) . If its ruch order , you configure the order type "Deliver Immediately".
    In Detail:
    The TOR depends on the Requirement Type (MMR), Requirement Class(MMR), Checking group(MMR) and the Sc line category (Line Item). For the TOR to happen u need Plant at line item, scheduline category markd for TOR, Requirement Class marked for TOR and Checking group in MMR (Availability check)
    What all stocks need to be checked during Availability check is controlled by using the checking rule.. for example for AV -02 Ind Requirements a checking rule will be assigned and this checking rule- and then what all stocks need to be considered to determine the delivery can be maintained here.
    Rgds
    Sai

  • Required delivery date in sales order shoud not be less than the inhouse pd

    Customer Requested Dates (CRD) entered in orders are often shorter than Product form wise lead time. 
    Logic to be configured in SAP : SAP should capture the CRD as per the lead time of Products or Date entered by sales persons (whichever is later).
    Required delivery date in sales order shoud not be less than the inhouse production lead time.
    Please help.
    Regards

    IMG - Sales and Distribution - Basic Functions - Availability Check and Transfer of Requirements - Availability Check - Availability Check with ATP Logic or Against Planning - Carry Out Control For Availability Check
    Here select the combination of your Availability Check & Checking Rule.
    Under Replenishment Lead TIme, you need to put a Tick Mark in the Check Box of "Check without RLT"
    This will make sure that system considers either the Requested Delivery Date or actual Material Availability Date, which ever is earlier.
    Hope this helps.
    Thanks,
    Jignesh Mehta
    Edited by: Jignesh Mehta on Nov 9, 2011 12:18 PM
    Edited by: Jignesh Mehta on Nov 9, 2011 12:23 PM

  • Automatic delivery dates in sales order.

    Hi all,
    The problem is that, The sales order is taking current date as delivery date , although ther are all config exist for availabiltity chek and Delivery & Transportation scheduling. The goods reciept processing time is 5 days in master record(MRP 2 View).
    so if order is created on 18.04.08 , the delivery dated also been shown as 18.04.08. why?
    Thanks in advance.
    Edited by: Gaurav S on Apr 18, 2008 11:20 AM

    Hi,
    System takes the requested delivery date from the sales doc type settings-
    goto VOV8- choose your sales doc type-details,
    in req.del date/pricing date/po date- maintain the lead time in days field- as desired.
    the above settings you made in material master is to confirm the delivery date in sales order, but not for the requested del date.
    hope it clears.
    *rewards

  • Delivery Date in Sale Order

    Dear All
    Delivery date in sales order should automatically changed or by defalt it should be after 2 days of creating the sales order.
    I have tried with lead time period and the ways given in the forum, but the schedule line/delivery date is by default coming as the day of sale order creation.
    Please guide me how to do it.
    Regards
    SB

    Hi,
    Goto Tcode: VOV8
    select sales document types
    goto request delivery date tab
    remove tick mark or uncheck propose delivery date
    and maintain lead time 2 days.
    thanks.

  • Cant change delivery date on Sales Order posted in prior period

    Hello All,
    Scenario: A sales order which was processed in prior period but since then delivery date had changed due to request from our customer. When we try to go back and change the delivery date, we find it greyed out. To get around this, we have to open the period again, change date and then close the period. Problem is that not all dates get changed, so our late delivery report look bad, shows that 90% of our deliveries are late, when in fact they are on time, the new time which we could not record on the Sales Order. We have similar problem with our purchase Orders.
    Is there anything in Administration we can do to enable us to easily chnage delivery dates on Sales order and purchase orders?

    Hi,
    Welcome you to post on the forum. What is your B1 version and PL?
    Thanks,
    Gordon

  • Two Delivery dates in Sale Order against one item

    Dear All
    I need two delivery dates in sale order. one is default at the time of creation sale order. second i need actual delivery date which will be confirmed by production planning department after analysis the order whether material can be ready on that delivery date or it need to change. Actual delivery date may vary from original delivery date and both need to preserve in system. kindly provide solution. best regards.
    Manjit

    You need to select the Availability & Transfer of Req. check box in Schedule Line Configuration.It will transfer the req. to PP.So while creating the sale order , schedule Lines will be confirmed as per the Available Stock.
    System will give you the Default Delivery Date as the Date added after Lead Time in days in the Configuration.Else system will give the Current Date.
    Best regards,
    Ankur

  • How to syatem determine delivery date in sales order

    hi sap gurus
    how to syatem determine delivery date in sales order
    Thanks and regards
    ram

    Hi Friend,
    There are many things which determines the delivery dates.
    01. PICK TIME+ PACK TIME +LOADING TIME
    02. LEAD TIME in days (VOV8)
    03. Shipping point
    04. Scheduling line
    05. Kind of availblity check
    06. If the above things are maintained as blank then the current date will be the delivery date
    However whether it must be proposed by the system or not is determined by one check box there find in VOV8 in requesteed delivery date determination tab.

  • Delivery date and sales order creation date

    Dear all
    Can you please explain the relation between delivery date and sales order date. In my case i can create delivery with delivery date as before the sales order date... how it is possible that i can create delivery before the sales order date.??
    Please explain.........
    Warm Regards
    Inder Pal

    Hi,
    Sales order date: Date on which the customer officially places an order to your company.
    All the commitment and product allocation counting starts with reference to this date.
    e.g. customer says that the goods are required from 20 days of placing order, then from this date the calculation starts.
    Delivery date: Date on which after the system goes through material availability date, replenishment time, calculates the date on which physically the goods can be delivered to the customer.
    e.g. customer orders 100 qty of material X in 15 days, you will hve to check this delivery date through availability check which can be done in sales order and also delivery.
    payment date is based on this delivery date.
    regards,
    Siddharth.

  • Invoice request based on multiple sales order for same customer

    Hi Team,
    I just wanted to know if we can create manual invoice request based on multiple sales order for same customer?
    For project based invoice request i have create based on single invoice request.
    Appreciate your input here.
    Thanks,
    Nitin

    Dear Ratish,
    Thanks for yr reply.
    I already did that but it is not serving business purpose.
    Comm payment  - comes diff time than sales payment.
    so ,I will post one entry customer will get hit with total amount Sales + commission
    like below
    Let say 10, 000 is the sales value and 500 is the commission
    So , This entry will get posted
    Customer Db- 10,500
    Sales Cr- 10,000
    Comm Income Cr- 500
    But, As I said sales amt will be paid before so We need to clear it partially and some time customer pays also diff amount due to some defect.
    So, We wont be knowing for which case we have or havnet received the payment against commission.
    As , Customer account is got hit with total amount( Sales+ Comm..value).
    Pls advise how to solve this.
    Regards,
    Sukh

  • Price Determination in Sales Order - for a Standard product & Custom Produc

    Hi,
    The price information is not displaying at Item Level in Sales Order for my own product 'SalesProduct1' and to my custom Sales order (z-TA). However, for standard products (Ht-1000, HT-1010, HT-1100 etc.) the price information is getting displayed successfully in z-TA.
    Also, in standard sales Order transaction (TA: Sales process). The price information is getting displayed successfully for both Standard products (Ht-1000, HT-1010, HT-1100 etc.) and for my own product (salesproduct1).
    Could you please help me out, how to rectify this problem ie. How can I diplay the price information for salesproduct1 in Z-TA?
    I tried to duplicate all the information that is there in standard products like category, sales Area etc, except PR00 price condition to my custom salesproduct1. However, in the place of PR00, I have added 0PR0 price condition and price information.
    Still the price information is not reflecting in my custom sales order (z-TA) for my salesproduct1.
    I also verifed that the SalesAreas are same for BP, Product org, Product price condition, Sales Order org info.
    I also checked that BP the Customer pricing procedure is Standard and for Doc. pricing procedure in Z-TA, TA is Standard.
    I also confirmed that in price procudere determination there exists a record that mathces with these salesarea, cust pp, doc. pp.

    Hi,
    in order to get closer to the root cause of the issue, you might want to make use of the pricing analysis / price trace. Set the user parameter PRC_TRACE = X via transaction SU3. Create an order in SAP GUI and navigate to the item level conditions tab. You should find the button accesses. In the accesses screen you will find details on condition determination and why it failed / succeeded.
    Best Regards,
    Michael